CN103031845A - 一种预应力静压管桩施工工艺 - Google Patents

一种预应力静压管桩施工工艺 Download PDF

Info

Publication number
CN103031845A
CN103031845A CN 201110301192 CN201110301192A CN103031845A CN 103031845 A CN103031845 A CN 103031845A CN 201110301192 CN201110301192 CN 201110301192 CN 201110301192 A CN201110301192 A CN 201110301192A CN 103031845 A CN103031845 A CN 103031845A
Authority
CN
China
Prior art keywords
pile
construction
stake
pipe pile
controlled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201110301192
Other languages
English (en)
Inventor
马静蓓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 201110301192 priority Critical patent/CN103031845A/zh
Publication of CN103031845A publication Critical patent/CN103031845A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及基础处理工程技术,具体为一种预应力静压管桩施工工艺。其特征在于:施工时,桩机的压桩力应不小于单桩竖向极限承载力标准值的1.2倍,成桩的偏位控制在2~5mm,桩身垂直度控制在±3mm,接桩焊接层数不少于2层,自然冷却约8~10分钟,两桩桩心的错位偏差不宜大于2mm。该方法有益效果在于通过静力压桩机的压桩机构自重和桩架上的配重作反力将预制桩压入土中,而减小了对周围建筑环境及地下管线的影响,也克服了过大的压桩力(夹持力)易将管桩桩身夹破夹碎,或使管桩出现纵向裂缝的问题,并能在地下障碍物或孤石较多的场地施工。

Description

一种预应力静压管桩施工工艺
技术领域
本发明涉及基础处理工程技术,具体为一种预应力静压管桩施工工艺。
背景技术
随着我国经济发展,建筑工程项目不断增多,预应力静压管桩在基础处理工程上由于其具有施工工期短、单位承载力及造价较低等优点,得到了发展及推广应用。同时由于锤击法施工在环保等方面的缺点日益突出,故而静压法施工越来越普遍,由此而引发的许多关于静压管桩的质量安全技术问题也倍受人们的关注。目前主要存在的问题是:(1)仍然具有挤土效应,对周围建筑环境及地下管线有一定的影响,要求边桩中心到相邻建筑物的间距较大;(2)施工场地的地耐力要求较高,在新填土、淤泥土及积水浸泡过的场地施工易陷机;(3)过大的压桩力(夹持力)易将管桩桩身夹破夹碎,或使管桩出现纵向裂缝;(4)不宜在地下障碍物或孤石较多的场地施工。根据施工中遇到的问题,本发明采用新的施工方法提高了工程质量与效益。
发明内容
本发明的目的在于采用一种预应力静压管桩施工工艺,通过静力压桩机的压桩机构自重和桩架上的配重作反力将预制桩压入土中,而减小了对周围建筑环境及地下管线的影响,也克服了过大的压桩力(夹持力)易将管桩桩身夹破夹碎,或使管桩出现纵向裂缝的问题,并能在地下障碍物或孤石较多的场地施工。
为了实现上述目的,本发明采用的具体施工工艺如下:
一、桩机的选择:必须根据具体工程的地质资料和设计的单桩承载力要求,准确地选择压桩机。桩机的压桩力应不小于单桩竖向极限承载力标准值的1.2倍。
二、底桩的定点:每个桩位的桩心,控制桩不偏离桩心,使成桩的偏位在2~5mm范围内。
三、桩身的控制:当桩在两个方向都已经垂直的情况下方可允许压桩,而且在压桩过程中要检查桩身垂直度,使桩身垂直度控制在±3mm。
四、接桩的控制:两桩桩心的错位偏差不宜大于2mm(宜设置接桩导向箍)。焊接层数不少于2层,自然冷却约8~10分钟(严禁用水冷却或焊完即压),防止高温的焊缝遇水变脆而被压坏。
本发明一种预应力静压管桩施工工艺的有益效果在于(1)低噪声、无振动、无污染,可以24小时连续施工,缩短建设工期,创造时间效益,从而降低工程造价;(2)施工速度很快,同时场地整洁、施工文明程度高;(3)由于送桩器与工程桩桩头的接触面吻合较好,送桩器在送桩过程中不会左右晃动和上下跳动,因而可以送桩较深,基础开挖后的截去量少;(4)施工中由于压桩引起的应力较小,且桩身在施工过程中不会出现拉应力,桩头一般都完好无损,复压较为容易。
具体实施方式
实例一、结合某工地静压桩施工作具体的说明
(一)压桩前的准备工作
1、桩机的选择:必须根据具体工程的地质资料和设计的单桩承载力要求,准确地选择压桩机。如果压桩机吨位过小,可能出现桩压不下的情况,因而无法达到设计承载力要求;反之,如果压桩机吨位过大,易发生陷机情况。所以应该会同各有关部门合理地选择桩机,尽量采用超载施工。一般情况下,桩机的压桩力应不小于单桩竖向极限承载力标准值的1.2倍。
2、施工放线与定桩位:由于放线的准确与否直接影响建筑物的位置是否符合“规划”要求,而桩位的准确与否又直接影响着整个工程的结构,因此,这两个工序的重要性不容忽视。项目技术管理人员应该对已定好的轴线位进行复核,根据建筑物与结构桩位图逐位校核,发现不符合要求的及时纠正。
3、桩尖、桩身质量检查:首先必须对桩尖进行查验、测量,按照管桩有关规范对于桩尖的构造要求和设计图纸要求,对所有到场的桩尖进行测量,不满足设计和管桩规范要求的,责令其更换;对所有到场的管桩进行仔细认真地查验,测量管桩的外径、壁厚、桩身、长度、桩身弯曲度等有关尺寸,并详细记录。特别是管壁厚度,由于静压法施工中的夹持力较大,壁厚不够很容易把桩夹碎。同时应对桩身外观质量进行仔细地查验,检查桩身是否粘皮麻面、内外表面是否露筋、表面是否有裂缝、是否断头脱头、桩套箍是否凹陷、表面砼是否坍落等情况,不符合管桩规范要求的,责令厂家退回。
(二)压桩施工工艺
1.底桩的定点
虽然在放线与定桩位时已经核查过,但是经验不足或技术水平不高的施工技术人员往往在放底桩时偏离原定的桩位,从而导致成桩的偏位。建议在每个桩位处用石灰或贝灰以原定的桩心为圆心、以该桩的桩径为直径画一圆圈,压底桩时以此圆圈为准,控制桩不偏离该圆圈,使成桩的偏位控制在2~5mm范围内。
2.桩身垂直度的控制
由于静压管桩桩机驾驶室内一般会悬挂一吊有重锤的绳线,由开机员以此线为准控制桩一个方向的垂直度,因而另一方向的垂直度必须另外控制,方法就是在垂直于桩与此绳线连接的地方(即另一正交方向)另设一吊重锤的绳线(视线要通透),以这两条绳线来控制桩的垂直度。当桩在两个方向都已经垂直的情况下方允许压桩,而且在压桩过程中要经常检查桩身,垂直度控制在±3mm。
3.接桩及焊缝控制
接桩前,应保证上下两节桩的顺直,而且两桩桩心的错位偏差不宜大于2mm(宜设置接桩导向箍)。管桩施工中主要采用焊接接桩法,在焊接前应该把两节桩的端头板用钢刷清刷干净,直至坡口露出金属光泽,而且应该保证上节桩已经垂直后方能焊接。焊接时最好两个焊工同时进行,先在坡口圆周上对称点焊4-6点,焊接层数不少于2层,每层焊渣必须清理干净,保证焊缝连续饱满,自然冷却约8~10分钟(严禁用水冷却或焊完即压),防止高温的焊缝遇水变脆而被压坏。

Claims (2)

1.一种预应力静压管桩施工工艺,其特征在于:桩机的压桩力应不小于单桩竖向极限承载力标准值的1.2倍,成桩的偏位控制在2~5mm,桩身垂直度控制在±3mm,接桩焊接层数不少于2层,自然冷却约8~10分钟,两桩桩心的错位偏差不宜大于2mm。
2.如权利要求1所述一种预应力静压管桩施工工艺,其特征在于:所述接桩焊接须自然冷却,严禁用水冷却或焊完即压,防止高温的焊缝遇水变脆而被压坏。
CN 201110301192 2011-09-30 2011-09-30 一种预应力静压管桩施工工艺 Pending CN103031845A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110301192 CN103031845A (zh) 2011-09-30 2011-09-30 一种预应力静压管桩施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110301192 CN103031845A (zh) 2011-09-30 2011-09-30 一种预应力静压管桩施工工艺

Publications (1)

Publication Number Publication Date
CN103031845A true CN103031845A (zh) 2013-04-10

Family

ID=48019204

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110301192 Pending CN103031845A (zh) 2011-09-30 2011-09-30 一种预应力静压管桩施工工艺

Country Status (1)

Country Link
CN (1) CN103031845A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437357A (zh) * 2013-08-28 2013-12-11 华南理工大学 一种用于提高非挤土桩复合地基承载力的方法
CN103953041A (zh) * 2014-04-30 2014-07-30 王利华 一种提高已施工的基桩单桩承载力的方法
CN104452754A (zh) * 2014-11-28 2015-03-25 中铁二十三局集团有限公司 预应力混凝土管桩施工方法

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437357A (zh) * 2013-08-28 2013-12-11 华南理工大学 一种用于提高非挤土桩复合地基承载力的方法
CN103437357B (zh) * 2013-08-28 2015-08-26 华南理工大学 一种用于提高非挤土桩复合地基承载力的方法
CN103953041A (zh) * 2014-04-30 2014-07-30 王利华 一种提高已施工的基桩单桩承载力的方法
CN104452754A (zh) * 2014-11-28 2015-03-25 中铁二十三局集团有限公司 预应力混凝土管桩施工方法

Similar Documents

Publication Publication Date Title
CN103603358B (zh) 一种多平台围护结构及施工方法
JP5932124B1 (ja) 鋼管杭の施工方法
JP4643364B2 (ja) 杭頭部の補強方法
CN101429768B (zh) 预应力高强砼管桩静压施工方法
CN101220593A (zh) 一种预应力管桩施工后处理该管桩断裂的加固方法
CN104452754A (zh) 预应力混凝土管桩施工方法
CN101775807A (zh) 软土地基深基坑支护结构
CN107816170A (zh) 一种大直径超长钢筋笼及其施工方法
CN102425166A (zh) 地基施工处理的新型打桩方法及其设备
CN107587508A (zh) Phc管桩锤击施工方法
CN202202326U (zh) 一种高强度混凝土预制管桩接桩构造
CN107642041A (zh) 超大直径空心群桩锚碇
CN105421474A (zh) 用于岩石地层低桩承台的植桩围堰平台一体化施工方法
CN107938666B (zh) 带桩靴管桩桩端内锤击沉桩及同步端测注浆结构及工艺
CN103031845A (zh) 一种预应力静压管桩施工工艺
CN103806451B (zh) 一种锚碇型基坑加固结构及其施工方法
CN103603357B (zh) 一种多平台无内支撑自防水基坑围护结构及其施工方法
CN111428304A (zh) 基坑开挖下带有抗浮锚杆盾构隧道的位移变形预测方法
CN108677930A (zh) 一种孔桩钢筋笼的防锈蚀对中结构及其应用
CN202247878U (zh) 地基施工处理的新型打桩设备
CN105200994A (zh) 预留盾构穿越复合式基坑围护装置的施工工法
CN206034437U (zh) 垫片型二次张拉预应力锚具
CN106284366A (zh) 外拉式拉森钢板桩加固方法
CN103628481A (zh) 一种预应力静压管桩施工工艺
CN208701659U (zh) 一种孔桩钢筋笼的防锈蚀对中结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130410