CN102946144A - 基于三级网络架构的变电站直流电源信息管理系统 - Google Patents

基于三级网络架构的变电站直流电源信息管理系统 Download PDF

Info

Publication number
CN102946144A
CN102946144A CN2012104827226A CN201210482722A CN102946144A CN 102946144 A CN102946144 A CN 102946144A CN 2012104827226 A CN2012104827226 A CN 2012104827226A CN 201210482722 A CN201210482722 A CN 201210482722A CN 102946144 A CN102946144 A CN 102946144A
Authority
CN
China
Prior art keywords
power supply
information management
management system
system based
transforming plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104827226A
Other languages
English (en)
Other versions
CN102946144B (zh
Inventor
刘颂菊
咸日常
王兴照
刘延华
王爱华
翟滢
张万征
徐传伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Zhiyang Electric Co ltd
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
SHANDONG ZHIYANG ELECTRIC CO Ltd
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG ZHIYANG ELECTRIC CO Ltd, Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical SHANDONG ZHIYANG ELECTRIC CO Ltd
Priority to CN201210482722.6A priority Critical patent/CN102946144B/zh
Publication of CN102946144A publication Critical patent/CN102946144A/zh
Application granted granted Critical
Publication of CN102946144B publication Critical patent/CN102946144B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/20Smart grids as enabling technology in buildings sector

Landscapes

  • Secondary Cells (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

本发明涉及一种基于三级网络架构的变电站直流电源信息管理系统。本系统中包括变电站直流电源系统,电源系统的蓄电池组和直流开关电源通过直流电源监控终端连接网络数据传输系统进而与远程监控平台通信连接。本发明为变电站直流电源提供了一种使用高效、方便的检测手段。

Description

基于三级网络架构的变电站直流电源信息管理系统
技术领域
本发明涉及一种基于三级网络架构的变电站直流电源信息管理系统。
背景技术
电网公司近几年的规模,无论在售电量、变电站数量、规模的建设都得到了迅猛发展。变电站无人值班化、自动化、智能化发展很快。但直流系统的运行、维护的自动化水平却远远滞后。华北电网各直属单位的直流运行维护班组人员非常缺乏,对变电站的蓄电池巡检、蓄电池定期核对性充放电工作,疲于应对,往往每年不好完成相关规定要完成的指标。
造成直流系统的运行隐患的原因主要有:
远程控制技术不完善。现场使用的技术主要以监测为主、缺乏控制部分,特别是以蓄电池远程充放电为核心的远程控制技术还需要进一步完善,以切实保证现场安全可靠的运行。
缺少统一标准。不同生产厂家技术标准不一致,实现形式五花八门;同时对于该设备的运行维护也缺乏相应标准。
缺少检测手段。直流远程监控设备缺少性能检测依据和方法,质量无法得到保证。
发明内容
根据以上现有技术中的不足,本发明要解决的技术问题是:提供一种使用方便、有效的基于三级网络架构的变电站直流电源信息管理系统。
本发明所提供的基于三级网络架构的变电站直流电源信息管理系统,包括变电站直流电源系统,电源系统的蓄电池组和直流开关电源通过直流电源监控终端连接网络数据传输系统进而与远程监控平台通信连接。网络数据传输系统主要为TCP/IP网络数据传输系统。
直流电源监控终端内含有内阻测试单元、蓄电池状态控制装置、开关量采集模块、电压采集模块、遥控输出模块、蓄电池充放电模块、绝缘监察单元和开关电源监控器,内阻测试单元、电压采集模块、遥控输出模块、开关量采集模块和蓄电池充放电模块与蓄电池组连接后与蓄电池状态控制装置通信连接;开关电源监控器连接直流开关电源;蓄电池状态控制装置、开关电源监控器、上位信息采集终端通信。利用这些单元在线自动监测单体电池电压、电池内阻、电流、环境温度、开关状态、充电机参数、绝缘状况。遥控输出模块主要接受外部无线信号使蓄电池状态控制装置控制蓄电池充放电模块进行远程的充放电操作。
内阻测试单元为循环放电内阻测试单元。
电压采集模块内的芯片固化电压系数,并且电压采集模块采用5PPM基准源。
蓄电池充放电模块与蓄电池组的每个母线联络开关、母线进线开关、充电开关和放电开关均通过电动开关机构连接。
远程监控平台为远程PC机、网络短信服务器中的一种或这两种的结合。
本发明所具有的有益效果是:
(一)实现蓄电池组内阻在线监测:
本发明采用分组直流大电流瞬间放电测试法,实现了蓄电池内阻的自动在线检测。直流瞬间放电测量内阻方法,是由蓄电池组瞬间向一个负载放电,通过负载接通时的瞬间电压降和断开负载时的瞬间电压恢复计算相应的内阻。分组法是将整个蓄电池组分为不同的测试组,每次只测试其中的一个分组,最大程度的减轻了瞬间放电对直流母线电压的影响。
(二)建立蓄电池组健康状况模型,为状态检修提供依据:
本发明将采集到的变电站直流电源信息自动上传,通过远程监控平台进行数据分析、数据存储。并定期对蓄电池组进行内阻测试,实时监测蓄电池组电压、单体电压、蓄电池室温度等参数,通过通信网络将数据发送到监控中心,建立蓄电池运行数据库,系统对数据进行综合分析,建立蓄电池组健康状况模型,实现蓄电池健康状况的提前预警,为状态检修提供依据,确保直流系统的安全运行。
系统分析蓄电池的运行数据,综合单体电压和内阻的长期变化趋势,当数据超过设定的限值时,系统提出蓄电池维护或更换的建议,把蓄电池的定期维护转变为状态维护,从而节约大量的人力物力,大大减轻了直流维护人员的工作量。
(三)建立远程核对性放电的安全防护体系:
本发明实时监测蓄电池组的运行参数,通过蓄电池组充放电模块实现对直流系统运行方式的转换,实现蓄电池组的远程核对性放电,并建立了远程核对性放电的一整套安全防护体系。首先,远程操作电动开关机构按次序开端;确保蓄电池组远程放电的安全进行。
(四)建立基于物联网技术的直流电源远程监控系统,实现直流系统一体化监控平台:
本发明采用物联网技术将变电站监控设备分成若干智能单元,包括就地监控单元、充电机监控模块、绝缘监察模块、蓄电池电压监测模块、内阻测试模块、远程放电负载模块等,各模块通过现场网络连接在一起,实现对直流系统运行参数的实时监测。
本发明基于三级网络架构,即通过内部局域网实现了直流系统一体化监控平台,在电科院建立网公司直流系统监测中心,对网内变电站直流系统的运行状况进行监视;在各地区建立直流系统监控中心,对变电站直流系统进行监控,包括直流母线电压、充电机运行数据、直流系统绝缘状况、蓄电池组运行状况等。系统分析充电机的输出电压判断充电机的运行状况;分析绝缘监察数据,根据绝缘电阻的变化趋势预知直流系统的绝缘状况;根据蓄电池单体内阻和电压数据,预警蓄电池的健康状况。
(五)技术规范:
本发明遵守有关对直流远程监控系统的技术规范。规范规定了直流远程监控系统的使用环境条件,系统基本组成,技术要求,技术参数,电气和安全性要求以及检验规则和检验方法。
(六)运行管理规范:
本发明遵守华北电网有限公司对直流远程监控系统的运行管理规范。规定了直流电源系统设备检修涉及直流电源远程监控系统运行维护的基本要求、检修前的准备、检测项目、故障处理、检修项目及质量要求、试验项目及要求、检修报告的编写以及验收投运等内容。
附图说明
图1是本发明方框原理图;
具体实施方式
下面结合附图对本发明的实施例做进一步描述:
如图1所示的基于三级网络架构的变电站直流电源信息管理系统,包括变电站直流电源系统,电源系统的蓄电池组和直流开关电源通过直流电源监控终端连接网络数据传输系统进而与远程监控平台通信连接。
直流电源监控终端内含有内阻测试单元、蓄电池状态控制装置、开关量采集模块、电压采集模块、遥控输出模块、蓄电池充放电模块、绝缘监察单元和开关电源监控器,内阻测试单元、电压采集模块、遥控输出模块、开关量采集模块和蓄电池充放电模块与蓄电池组连接后与蓄电池状态控制装置通信连接;开关电源监控器连接直流开关电源;蓄电池状态控制装置、开关电源监控器、上位信息采集终端通信。利用这些单元在线自动监测单体电池电压、电池内阻、电流、环境温度、开关状态、充电机参数、绝缘状况。绝缘监察单元用于检测各个部件之间的绝缘状态,保证使用安全。
内阻测试单元为循环放电内阻测试单元。即将一组蓄电池组分成多个循环组,每次测量内阻时先对第一个循环进行放电,结束后再对第二个循环进行放电,直至最后一个循环。在放电的同时,系统高速采集每节电池的放电曲线,取得压降后测出每节电池的内阻。
电压采集模块内的芯片固化电压系数,并且电压采集模块采用5PPM基准源。在此基础上还可利用高输入主抗技术,共同来确保电压采集的高精确度及高稳定度。
蓄电池充放电模块与蓄电池组的每个母线联络开关、母线进线开关、充电开关和放电开关均通过电动开关机构连接。同时其放电负载采用恒流负载,确保电压变化时每次放电的电流不变。所述的电动开关机构主要指继电器等可完成自动化开断的电动开关。
远程监控平台为远程PC机、网络短信服务器中的一种或这两种的结合。实时接收各变电站直流监控装置的数据,并对数据加以分析处理,保存到数据库中,提供IE浏览功能,利用各种图表显示运行数据,提高实时性和准确性,以便及时维护和处理,保障直流系统的安全。另外,远程监控平台可选择网络短信服务器,报警信息可以通过短信实时转移到值班人员手机。

Claims (6)

1.一种基于三级网络架构的变电站直流电源信息管理系统,包括变电站直流电源系统,其特征是,电源系统的蓄电池组和直流开关电源通过直流电源监控终端连接网络数据传输系统进而与远程监控平台通信连接。
2.根据权利要求1所述的基于三极网络架构的变电站直流电源信息管理系统,其特征是,所述的直流电源监控终端内含有内阻测试单元、蓄电池状态控制装置、开关量采集模块、电压采集模块、遥控输出模块、蓄电池充放电模块、绝缘监察单元和开关电源监控器,内阻测试单元、电压采集模块、遥控输出模块、开关量采集模块和蓄电池充放电模块与蓄电池组连接后与蓄电池状态控制装置通信连接;开关电源监控器连接直流开关电源;蓄电池状态控制装置、开关电源监控器、上位信息采集终端通信。
3.根据权利要求2所述的基于三极网络架构的变电站直流电源信息管理系统,其特征是,所述的内阻测试单元为循环放电内阻测试单元。
4.根据权利要求2所述的基于三极网络架构的变电站直流电源信息管理系统,其特征是,所述的电压采集模块内的芯片固化电压系数,并且电压采集模块采用5PPM基准源。
5.根据权利要求2所述的基于三极网络架构的变电站直流电源信息管理系统,其特征是,所述的蓄电池充放电模块与蓄电池组的每个母线联络开关、母线进线开关、充电开关和放电开关均通过电动开关机构连接。
6.根据权利要求1所述的基于三极网络架构的变电站直流电源信息管理系统,其特征是,所述的远程监控平台为远程PC机、网络短信服务器中的一种或这两种的结合。
CN201210482722.6A 2012-11-25 2012-11-25 基于三级网络架构的变电站直流电源信息管理系统 Expired - Fee Related CN102946144B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210482722.6A CN102946144B (zh) 2012-11-25 2012-11-25 基于三级网络架构的变电站直流电源信息管理系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210482722.6A CN102946144B (zh) 2012-11-25 2012-11-25 基于三级网络架构的变电站直流电源信息管理系统

Publications (2)

Publication Number Publication Date
CN102946144A true CN102946144A (zh) 2013-02-27
CN102946144B CN102946144B (zh) 2016-01-20

Family

ID=47729062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210482722.6A Expired - Fee Related CN102946144B (zh) 2012-11-25 2012-11-25 基于三级网络架构的变电站直流电源信息管理系统

Country Status (1)

Country Link
CN (1) CN102946144B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104158287A (zh) * 2014-07-20 2014-11-19 国家电网公司 一种变电站蓄电池远程维护系统
CN104682563A (zh) * 2015-03-13 2015-06-03 河北超创电子科技有限公司 交直流系统运维一体化管理平台
CN106549501A (zh) * 2016-12-09 2017-03-29 国网安徽省电力公司池州供电公司 用于通信电源的智能管理监控单元和变电站通信电源系统
CN107069948A (zh) * 2016-11-28 2017-08-18 国网浙江省电力公司紧水滩水力发电厂 一种直流电源系统的远程检测监测系统及检测方法
CN107430171A (zh) * 2015-03-04 2017-12-01 江森自控科技公司 电池测试报告系统和方法
CN107748333A (zh) * 2017-10-09 2018-03-02 杭州华塑加达网络科技有限公司 蓄电池剩余容量估算方法及系统
CN108693800A (zh) * 2018-03-29 2018-10-23 国家电网公司 一种智能变电站电源云监护系统
CN110058583A (zh) * 2019-05-13 2019-07-26 广东电网有限责任公司 一种可自由控制干预的变电站自动化设备远程测试系统
CN116953533A (zh) * 2023-06-29 2023-10-27 国网江苏省电力有限公司泰州供电分公司 一种基于物联网的蓄电池远程核容监测系统

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201444191U (zh) * 2009-08-07 2010-04-28 淄博智洋电气有限公司 直流电源在线监测系统
CN101706558A (zh) * 2009-07-20 2010-05-12 深圳市普禄科智能检测设备有限公司 一种直流电源及蓄电池在线监测系统
CN201583631U (zh) * 2009-07-17 2010-09-15 淄博智洋电气有限公司 一种蓄电池在线监测装置及系统
CN102570597A (zh) * 2010-12-27 2012-07-11 华北电力科学研究院有限责任公司 直流电源远程监控系统
CN202978428U (zh) * 2012-11-25 2013-06-05 山东电力集团公司淄博供电公司 基于三级网络架构的变电站直流电源信息管理系统

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201583631U (zh) * 2009-07-17 2010-09-15 淄博智洋电气有限公司 一种蓄电池在线监测装置及系统
CN101706558A (zh) * 2009-07-20 2010-05-12 深圳市普禄科智能检测设备有限公司 一种直流电源及蓄电池在线监测系统
CN201444191U (zh) * 2009-08-07 2010-04-28 淄博智洋电气有限公司 直流电源在线监测系统
CN102570597A (zh) * 2010-12-27 2012-07-11 华北电力科学研究院有限责任公司 直流电源远程监控系统
CN202978428U (zh) * 2012-11-25 2013-06-05 山东电力集团公司淄博供电公司 基于三级网络架构的变电站直流电源信息管理系统

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李潮勤: "浅淡变电站高频开关电源直流监控系统", 《东北电力技术》 *
黄海宏等: "直流操作电源监控装置设计", 《现代电子技术》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104158287A (zh) * 2014-07-20 2014-11-19 国家电网公司 一种变电站蓄电池远程维护系统
CN104158287B (zh) * 2014-07-20 2017-09-01 国家电网公司 一种变电站蓄电池远程维护系统
CN107430171A (zh) * 2015-03-04 2017-12-01 江森自控科技公司 电池测试报告系统和方法
CN104682563A (zh) * 2015-03-13 2015-06-03 河北超创电子科技有限公司 交直流系统运维一体化管理平台
CN107069948A (zh) * 2016-11-28 2017-08-18 国网浙江省电力公司紧水滩水力发电厂 一种直流电源系统的远程检测监测系统及检测方法
CN106549501A (zh) * 2016-12-09 2017-03-29 国网安徽省电力公司池州供电公司 用于通信电源的智能管理监控单元和变电站通信电源系统
CN106549501B (zh) * 2016-12-09 2023-05-16 国网安徽省电力公司池州供电公司 用于通信电源的智能管理监控单元和变电站通信电源系统
CN107748333A (zh) * 2017-10-09 2018-03-02 杭州华塑加达网络科技有限公司 蓄电池剩余容量估算方法及系统
CN107748333B (zh) * 2017-10-09 2020-07-03 杭州华塑加达网络科技有限公司 蓄电池剩余容量估算方法及系统
CN108693800A (zh) * 2018-03-29 2018-10-23 国家电网公司 一种智能变电站电源云监护系统
CN110058583A (zh) * 2019-05-13 2019-07-26 广东电网有限责任公司 一种可自由控制干预的变电站自动化设备远程测试系统
CN116953533A (zh) * 2023-06-29 2023-10-27 国网江苏省电力有限公司泰州供电分公司 一种基于物联网的蓄电池远程核容监测系统

Also Published As

Publication number Publication date
CN102946144B (zh) 2016-01-20

Similar Documents

Publication Publication Date Title
CN102946144B (zh) 基于三级网络架构的变电站直流电源信息管理系统
CN106340968B (zh) 一种面向配电网管控的一体化支撑系统及方法
CN109633310B (zh) 面向电动汽车充电设施的互联互通检测云平台
CN202978428U (zh) 基于三级网络架构的变电站直流电源信息管理系统
CN202634082U (zh) 变电所直流设备在线监测预警系统
CN101577438B (zh) 基于远程监控平台的大容量后备电源的维护方法所用设备
KR101198194B1 (ko) 독립형 발전시스템의 감시?제어시스템
CN211790784U (zh) 一种光储充一体化充电站
CN102435871A (zh) 一种基于gps同步的电力避雷器数据采集在线监测系统
CN105205232A (zh) 基于rtds的微网系统稳定性仿真测试平台
CN202975282U (zh) 一种直流电源系统中蓄电池设备的实时监测控制系统
WO2012068774A1 (zh) 基于铁锂电池的变电站直流电源应急系统
CN202602375U (zh) 风力发电箱式变压器云终端
CN214201710U (zh) 一种新型蓄电池远程维护系统
CN101446618A (zh) 配网架空线故障实时监测系统
CN101539612A (zh) 蓄电池运行质量在线监测系统
CN111722124A (zh) 一种蓄电池在线状态监测系统和监测方法
CN203135572U (zh) 变电站直流装置状态监测系统
CN109274182A (zh) 直流电源远程一体化监测平台
CN104009268A (zh) 一种智慧电池、智慧电池监测系统及监测方法
CN205333828U (zh) 一种风力发电机蓄电池在线监测系统
CN101762788A (zh) 蓄电池运行监测系统
CN204928219U (zh) 一种铅酸蓄电池系统及智能系统
CN109980305A (zh) 通信电源智能维护装置
CN112816896A (zh) 双电源直流系统电池组远程核容控制系统及控制方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: ZIBO POWER SUPPLY COMPANY OF SHANDONG ELECTRIC POW

Free format text: FORMER OWNER: SHANDONG ZHIYANG ELECTRIC CO., LTD.

Effective date: 20131015

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: ZIBO POWER SUPPLY COMPANY OF SHANDONG ELECTRIC POWER CORPORATION

Effective date: 20131015

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: STATE GRID ZIBO POWER SUPPLY COMPANY OF SHANDONG PROVINCE

Applicant after: SHANDONG ZHIYANG ELECTRIC Co.,Ltd.

Address before: 100031 Xicheng District, Chang'an Avenue, No. 86,

Applicant before: State Grid Corporation of China

Applicant before: Zibo Power Supply Company of Shandong Electric Power Corp.

Applicant before: SHANDONG ZHIYANG ELECTRIC Co.,Ltd.

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 255000 ZIBO, SHANDONG PROVINCE TO: 100031 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20131015

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Zibo Power Supply Company of Shandong Electric Power Corp.

Applicant after: SHANDONG ZHIYANG ELECTRIC Co.,Ltd.

Address before: 255000 No. 61 West Village Road, Zhangdian District, Shandong, Zibo

Applicant before: Zibo Power Supply Company of Shandong Electric Power Corp.

Applicant before: SHANDONG ZHIYANG ELECTRIC Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 100031 Xicheng District, Chang'an Avenue, No. 86,

Patentee after: State Grid Corporation of China

Patentee after: STATE GRID ZIBO POWER SUPPLY COMPANY OF SHANDONG PROVINCE

Patentee after: SHANDONG ZHIYANG ELECTRIC Co.,Ltd.

Address before: 100031 Xicheng District, Chang'an Avenue, No. 86,

Patentee before: State Grid Corporation of China

Patentee before: STATE GRID ZIBO POWER SUPPLY COMPANY OF SHANDONG PROVINCE

Patentee before: SHANDONG ZHIYANG ELECTRIC Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160120

Termination date: 20171125