CN102943526A - Building combined pendant, building structure and construction method - Google Patents

Building combined pendant, building structure and construction method Download PDF

Info

Publication number
CN102943526A
CN102943526A CN2012104667227A CN201210466722A CN102943526A CN 102943526 A CN102943526 A CN 102943526A CN 2012104667227 A CN2012104667227 A CN 2012104667227A CN 201210466722 A CN201210466722 A CN 201210466722A CN 102943526 A CN102943526 A CN 102943526A
Authority
CN
China
Prior art keywords
structural beams
wallboard
hanging part
mount pad
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104667227A
Other languages
Chinese (zh)
Other versions
CN102943526B (en
Inventor
王睿敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Lijiu Construction Robot Co., Ltd.
Original Assignee
王睿敏
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 王睿敏 filed Critical 王睿敏
Priority to CN201210466722.7A priority Critical patent/CN102943526B/en
Publication of CN102943526A publication Critical patent/CN102943526A/en
Application granted granted Critical
Publication of CN102943526B publication Critical patent/CN102943526B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention aims at providing a building combined pendant, a building structure, which are simple in structure, convenient to construct, safe and firm and further provides a construction method. The building combined pendant comprises an upper hanging connecting piece and a lower hanging connecting piece, wherein the upper hanging connecting piece and the lower hanging connecting piece are buckled together, the lower hanging connecting piece comprises a transition piece and an installing base, the installing base is provided with an installing surface and an extruded surface, and an installing hole is arranged on the installing surface. The building structure comprises a wallboard, an upper structural beam and a lower structural beam, wherein the upper part of the wallboard is connected with the upper structural beam into a whole by the building combined pendant, and the lower part of the wallboard is connected with the lower structural beam into a whole by the building combined pendant. The construction method of the building structure comprises the following steps of: 1, prefabricating the wallboard, the upper hanging connecting piece and the lower hanging connecting piece; 2, installing the lower hanging connecting piece on the upper structural beam by an embedded part; 3, connecting the upper hanging connecting piece with the prefabricated wallboard into a whole, and buckling the upper hanging connecting piece with the lower hanging connecting piece into a whole; and 4, grouting into an installing gap to be sealed.

Description

Building Combined hanger and building structure and job practices
Technical field
The present invention relates to building field, be specifically related to a kind ofly build Combined hanger and by the building building structure that consists of of Combined hanger and the job practices of described building structure.
Background technology
Prior art wallboard and structural beams be connected that the link plate thickness that adopts is thick, rigidity is little, use is inconvenient.
Exist a kind of energy-saving heat-preserving board to comprise outer panels, wainscot and the central layer between outer panels, wainscot in the market.When installing, this heat preservation plate material need to bore a hole at warming plate, then will by connectors such as configuration screws in perforation the two be coupled together between heat preservation plate material and the building girder, install inconveniently, and waste time and energy, cause long construction period, materials are many, cost is high.
Summary of the invention
The object of the invention provides a kind of building Combined hanger and building structure and job practices, simple in structure, easy construction and firm safely.
To achieve these goals, the present invention is by the following technical solutions:
A kind of building Combined hanger, be used for connecting wallboard and structural beams, comprise one or more upper hanging parts and a lower hanging part, upper hanging part and lower hanging part snap together mutually, upper hanging part is used for connecting wallboard, and lower hanging part is used for the syndeton beam, and lower hanging part comprises transition piece and the mount pad that connects as one, mount pad has more than one the installed surface that is used for the syndeton beam and the evagination face of protrusion and installed surface, and installed surface is provided with one or more installing holes.
Further, upper hanging part comprises a side plate that is used for the junction plate that links to each other with wallboard and is positioned at the junction plate both sides, and junction plate is provided with connecting hole, and the side plate lower end has side cut; Transition piece is the plate body that bends to factory's font, and the inclined plane of transition piece is consistent with the gradient of side cut, and transition piece inner surface and mount pad fasten and be integrated, and mount pad is the broken line type plate body.
Further, mount pad has installed surface and the evagination face that the interval arranges, and installed surface be the horizontal plane parallel with the structural beams surface, and the evagination face comprises two side plate bodies and a middle connecting plate, corner cut on the side plate, and with horizontal plane between become the obtuse angle.
Further, upper hanging part has downward bending part, and the transition piece longitudinal section is L shaped, and mount pad has installed surface and the evagination face that the interval arranges, and the cross section of installed surface and evagination face is arcuate structure.
A kind of building structure, comprise wallboard, upper structural beams and lower structural beams, connect as one by the building Combined hanger between wallboard top and the upper structural beams, connect as one by the building Combined hanger between wallboard bottom and the lower structural beams, upper hanging part is arranged in the wallboard through the bolt and nut pair, mount pad links to each other with upper structural beams or lower structural beams through built-in fitting, built-in fitting comprises channel-section steel and a plurality of bolt and nut component, channel-section steel is embedded in upper structural beams or the lower structural beams through a plurality of rivets, bolt and nut component comprises tommyhead bolt and nut, the bolt head of tommyhead bolt arranges in the groove of channel-section steel, and the end of tommyhead bolt passes installing hole and is connected with mount pad through nut.
A kind of building structure, comprise wallboard, upper structural beams and lower structural beams, connect as one by the building Combined hanger between wallboard top and the upper structural beams, the building Combined hanger connects as one between wallboard bottom and the lower structural beams, upper hanging part end is arranged in the wallboard, mount pad links to each other with upper structural beams or lower structural beams through built-in fitting, built-in fitting comprises channel-section steel and a plurality of bolt and nut component, channel-section steel is embedded in upper structural beams or the lower structural beams through a plurality of rivets, bolt and nut component comprises tommyhead bolt and nut, the bolt head of tommyhead bolt arranges in the groove of channel-section steel, and the end of tommyhead bolt passes installing hole and is connected with mount pad through nut.
Further, be embedded with the screw thread lock tube in the wallboard, upper hanging part is terminal to be integrated through being threaded with the screw thread lock tube.
Further, the wallboard top is embedded with a plurality of screw thread lock tubes.
Further, the wallboard top is embedded with a plurality of screw thread lock tubes.
A kind of job practices of building structure may further comprise the steps:
1) prefabricated panel, upper hanging part and lower hanging part are transported to the job site;
2) on the structural beams under installation of embedded parts hanging part;
3) upper hanging part and prefabricated panel are connected as one, upper hanging part and lower hanging part are fastened be integrated, and level pushes away and installs to the position;
4) grouting sealing in the slit is installed.
Beneficial effect of the present invention: the building Combined hanger adopts and is fastened and connected, and utilizes thinner sheet material to make the suspension member of larger rigidity, has improved the degree of safety that structure connects; Building structure is to adopt building unit that wallboard and beam are connected as one, and overall structure is simple, easy construction and firm safely.
Description of drawings
Fig. 1 is the schematic perspective view of embodiment 1 building structure.
Fig. 2 is that the mount pad master looks schematic diagram among the embodiment 1.
Fig. 3 is the schematic top plan view of mount pad among the embodiment 1.
Fig. 4 is the schematic side view of mount pad among the embodiment 1.
Fig. 5 is that the master of transition piece among the embodiment 1 looks schematic diagram.
Fig. 6 is the schematic side view of transition piece among the embodiment 1.
Fig. 7 is the schematic top plan view of transition piece among the embodiment 1.
Fig. 8 is that other parts make up schematic diagrames after removing wallboard and structural beams among the embodiment 1.
Fig. 9 is that the master of upper hanging part among the embodiment 2 looks schematic diagram.
Figure 10 is the schematic side view of upper hanging part among the embodiment 2.
Figure 11 is the schematic top plan view of upper hanging part among the embodiment 2.
Figure 12 is that other parts make up schematic diagrames after removing wallboard and structural beams among the embodiment 2.
Figure 13 is the schematic perspective view of embodiment 3 building structure.
Figure 14 is that the mount pad master looks schematic diagram among the embodiment 3.
Figure 15 is the schematic top plan view of mount pad among the embodiment 3.
Figure 16 is the schematic side view of mount pad among the embodiment 3.
Figure 17 is that other parts make up schematic diagrames after removing wallboard and structural beams among the embodiment 3.
Among the figure 1, the screw thread lock tube, 2, upper hanging part, 3, transition piece, 4, mount pad, 5, wallboard, 6, upper structural beams, 7, channel-section steel, 8, bolt and nut component, 9, rivet, 10, lower structural beams, 12, installed surface, 13, the evagination face, 14, installing hole, 15, connecting hole, 16, junction plate, 17, side plate, 19, cut edge 20, bolt and nut is secondary, 81, tommyhead bolt, 82, nut, 131, the side plate body, 132, middle connecting plate.
The specific embodiment
Understand for the ease of those skilled in the art, below in conjunction with the drawings and specific embodiments the present invention is described in further detail.
Embodiment 1
With reference to the accompanying drawings 1, a kind of building structure comprises wallboard 5, upper structural beams 6 and lower structural beams 10, all connects as one by building Combined hanger between between wallboard 5 tops and the upper structural beams 6 and wallboard 5 bottoms and the lower structural beams 10.
The building Combined hanger comprises a upper hanging part 2 and lower hanging part that mutually snaps together, upper hanging part 2 ends are arranged in the wallboard 5, lower hanging part comprises transition piece 3 and the mount pad 4 that connects as one, mount pad 4 links to each other with upper structural beams 6 or lower structural beams 10 through built-in fitting, mount pad 4 has more than one the installed surface 12 that is used for the syndeton beam and the evagination face 13 of protrusion and installed surface, and installed surface is provided with one or more installing holes 14.
With reference to the accompanying drawings 1.8, upper hanging part 2 has downward bending part, upper hanging part 2 terminal be embedded in wallboard in the screw thread lock tube be integrated through being threaded; 2.3.4 with reference to the accompanying drawings, in the reality, mount pad 4 is the broken line type plate body, mount pad 4 has installed surface 12 and the evagination face 13 that the interval arranges, and installed surface 12 is the horizontal plane parallel with the structural beams surface, and evagination face 13 comprises two side plate bodies 131 and a middle connecting plate 132, side plate body 131 upper end corner cuts, and with become obtuse angle a between the horizontal plane, for erection bolt nut assembly 8, installed surface 12 is provided with the installing hole 14 of strip; 8.9.10 with reference to the accompanying drawings, transition piece 3 is for bending to the plate body of factory's font, and the bending part inner surface of transition piece 3 external surfaces and upper hanging part 2 is bonded to each other, and transition piece 3 inner surfaces and mount pad 4 fastenings are integrated.
In the present embodiment, built-in fitting comprises the channel-section steel 7 that is embedded in 10 li of upper structural beams 6 or lower structural beams through a plurality of rivets 9, channel-section steel 7 is connected with mount pad 4 through bolt and nut component 8, bolt and nut component 8 comprises tommyhead bolt 81 and nut 82, the bolt head of tommyhead bolt 81 arranges in the groove of channel-section steel 7, and the end of tommyhead bolt 81 passes installing hole and is connected with mount pad 4 through nut 82.
Embodiment 2
The present embodiment is compared the difference part and is with embodiment 1: upper hanging part 2 is for a plurality of, the upper hanging part of 9.10.11.12 comprises that one is used for the junction plate 16 that links to each other with wallboard and the side plate 17 that is positioned at junction plate 16 both sides with reference to the accompanying drawings, junction plate is provided with the connecting hole 15 of strip, and side plate 17 lower ends have cuts edge 19; Transition piece 3 is for bending to the plate body of factory's font, and the inclined plane of transition piece 3 is consistent with the gradient of side cut 19.
Be connected by bolt and nut secondary 20 between upper hanging part and the wallboard, during installation in the bolt and nut component bolt one end be arranged in the wallboard 5, the other end passes the connecting hole 15 of hanging part 2 and fixes through nut.
Embodiment 3
The present embodiment is compared the difference part and is with embodiment 1: with reference to the accompanying drawings 13.17, upper hanging part 2 has downward bending part, upper hanging part 2 terminal be embedded in wallboard in screw thread lock tube 1 be integrated through being threaded; The second installed part 3 longitudinal sections are L shaped; 14.15.16 with reference to the accompanying drawings, mount pad have installed surface 12 and the evagination face 13 that the interval arranges, and the cross section of installed surface 12 and evagination face 13 is arcuate structure, and mount pad 4 surfaces are provided with circular installing hole 14.
Above-mentioned each examples of implementation, wallboard 5 tops are embedded with a plurality of screw thread lock tubes 1, can make things convenient for mobile wallboard 5 in the installation process.
The job practices of building structure among the above-mentioned individual various embodiment may further comprise the steps:
1) prefabricated panel, upper hanging part and lower hanging part are transported to the job site;
2) on the structural beams under installation of embedded parts hanging part;
3) upper hanging part and prefabricated panel are connected as one, upper hanging part and lower hanging part are fastened be integrated, and level pushes away and installs to the position;
4) slit grouting sealing is installed.
Above embodiment only is used for illustrating that technical scheme of the present invention is not intended to limit; although by embodiment the present invention is had been described in detail; under the field personnel should make amendment or the part technical characterictic is equal to replacement with reference to concrete mode of the present invention; but under the spirit that does not break away from technical solution of the present invention, above-mentioned change or be equal to replacement and should belong in the technical scheme scope that the present invention asks for protection.

Claims (10)

1. build Combined hanger for one kind, be used for connecting wallboard and structural beams, it is characterized in that: comprise one or more upper hanging parts and a lower hanging part, upper hanging part and lower hanging part snap together mutually, upper hanging part is used for connecting wallboard, and lower hanging part is used for the syndeton beam, and lower hanging part comprises transition piece and the mount pad that connects as one, mount pad has more than one the installed surface that is used for the syndeton beam and the evagination face of protrusion and installed surface, and installed surface is provided with one or more installing holes.
2. described building Combined hanger according to claim 1, it is characterized in that: upper hanging part comprises a side plate that is used for the junction plate that links to each other with wallboard and is positioned at the junction plate both sides, and junction plate is provided with connecting hole, and the side plate lower end has side cut; Transition piece is the plate body that bends to factory's font, and the inclined plane of transition piece is consistent with the gradient of side cut, and transition piece inner surface and mount pad fasten and be integrated, and mount pad is the broken line type plate body.
3. described building Combined hanger according to claim 2, it is characterized in that: mount pad has installed surface and the evagination face that the interval arranges, installed surface is the horizontal plane parallel with the structural beams surface, the evagination face comprises two side plate bodies and a middle connecting plate, side plate upper end corner cut, and with horizontal plane between become the obtuse angle.
4. described building Combined hanger according to claim 1, it is characterized in that: upper hanging part has downward bending part, and the transition piece longitudinal section is L shaped, and mount pad has installed surface and the evagination face that the interval arranges, and the cross section of installed surface and evagination face is arcuate structure.
5. building structure, it is characterized in that: comprise wallboard, upper structural beams and lower structural beams, connect as one by claim 1 or 2 or 3 building Combined hangers between wallboard top and the upper structural beams, connect as one by claim 1 or 2 or 3 building Combined hangers between wallboard bottom and the lower structural beams, upper hanging part is arranged in the wallboard through the bolt and nut pair, mount pad links to each other with upper structural beams or lower structural beams through built-in fitting, built-in fitting comprises channel-section steel and a plurality of bolt and nut component, channel-section steel is embedded in upper structural beams or the lower structural beams through a plurality of rivets, bolt and nut component comprises tommyhead bolt and nut, the bolt head of tommyhead bolt arranges in the groove of channel-section steel, and the end of tommyhead bolt passes installing hole and is connected with mount pad through nut.
6. building structure, it is characterized in that: comprise wallboard, upper structural beams and lower structural beams, connect as one by claim 4 building Combined hanger between wallboard top and the upper structural beams, connect as one by claim 4 building Combined hanger between wallboard bottom and the lower structural beams, upper hanging part end is arranged in the wallboard, mount pad links to each other with upper structural beams or lower structural beams through built-in fitting, built-in fitting comprises channel-section steel and a plurality of bolt and nut component, channel-section steel is embedded in upper structural beams or the lower structural beams through a plurality of rivets, bolt and nut component comprises tommyhead bolt and nut, the bolt head of tommyhead bolt arranges in the groove of channel-section steel, and the end of tommyhead bolt passes installing hole and is connected with mount pad through nut.
7. according to claim 6 described building structure is characterized in that: be embedded with the screw thread lock tube in the wallboard, upper hanging part is terminal to be integrated through being threaded with the screw thread lock tube.
8. according to claim 5 described building structure is characterized in that: the wallboard top is embedded with a plurality of screw thread lock tubes.
9. according to claim 6 or 7 described building structure, it is characterized in that: the wallboard top is embedded with a plurality of screw thread lock tubes.
10. the job practices of a building structure is characterized in that, may further comprise the steps:
1) prefabricated panel, upper hanging part and lower hanging part are transported to the job site;
2) upper hanging part and prefabricated panel are connected as one, on the structural beams under installation of embedded parts hanging part;
3) prefabricated panel lifting is put in place, hanging part and lower hanging part are fastened be integrated, and level pushes away and installs to the position;
4) grouting sealing in the slit is installed.
CN201210466722.7A 2012-11-19 2012-11-19 Building combined pendant, building structure and construction method Active CN102943526B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210466722.7A CN102943526B (en) 2012-11-19 2012-11-19 Building combined pendant, building structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210466722.7A CN102943526B (en) 2012-11-19 2012-11-19 Building combined pendant, building structure and construction method

Publications (2)

Publication Number Publication Date
CN102943526A true CN102943526A (en) 2013-02-27
CN102943526B CN102943526B (en) 2014-10-29

Family

ID=47726506

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210466722.7A Active CN102943526B (en) 2012-11-19 2012-11-19 Building combined pendant, building structure and construction method

Country Status (1)

Country Link
CN (1) CN102943526B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741802A (en) * 2013-12-30 2014-04-23 王东彬 Connecting structure of combined wall body and steel girder
CN103741803A (en) * 2013-12-30 2014-04-23 王东彬 Connecting structure of combined wall body and concrete beam

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1077740A (en) * 1996-09-04 1998-03-24 Sekisui House Ltd Hanging metal fitting for outside wall and its hanging structure
CN101649657A (en) * 2009-07-17 2010-02-17 浙江太阳岛建筑陶土板有限公司 Mounting structure of clay plate hanging piece
CN202055377U (en) * 2011-04-02 2011-11-30 广州江河幕墙系统工程有限公司 Slotted stone curtain wall unit
CN202299035U (en) * 2011-10-20 2012-07-04 沈阳远大铝业工程有限公司 Air-pressure resisting connecting piece of unit curtain wall
CN102605897A (en) * 2012-03-27 2012-07-25 王睿敏 Rainproof outer wall board and construction method of rainproof outer wall
CN202899303U (en) * 2012-11-19 2013-04-24 王睿敏 Building combined hanging piece and building structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1077740A (en) * 1996-09-04 1998-03-24 Sekisui House Ltd Hanging metal fitting for outside wall and its hanging structure
CN101649657A (en) * 2009-07-17 2010-02-17 浙江太阳岛建筑陶土板有限公司 Mounting structure of clay plate hanging piece
CN202055377U (en) * 2011-04-02 2011-11-30 广州江河幕墙系统工程有限公司 Slotted stone curtain wall unit
CN202299035U (en) * 2011-10-20 2012-07-04 沈阳远大铝业工程有限公司 Air-pressure resisting connecting piece of unit curtain wall
CN102605897A (en) * 2012-03-27 2012-07-25 王睿敏 Rainproof outer wall board and construction method of rainproof outer wall
CN202899303U (en) * 2012-11-19 2013-04-24 王睿敏 Building combined hanging piece and building structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741802A (en) * 2013-12-30 2014-04-23 王东彬 Connecting structure of combined wall body and steel girder
CN103741803A (en) * 2013-12-30 2014-04-23 王东彬 Connecting structure of combined wall body and concrete beam
CN103741803B (en) * 2013-12-30 2016-01-20 王东彬 The syndeton of a kind of combined body of wall and concrete beam
CN103741802B (en) * 2013-12-30 2016-01-20 王东彬 The syndeton of a kind of combined body of wall and girder steel

Also Published As

Publication number Publication date
CN102943526B (en) 2014-10-29

Similar Documents

Publication Publication Date Title
CN106801473B (en) Aluminum alloy structure house
CN202899303U (en) Building combined hanging piece and building structure
CN107724588B (en) Integrated curved surface suspended ceiling structure and construction method thereof
CN102943526B (en) Building combined pendant, building structure and construction method
CN106894625B (en) Modularized external hanging scaffold
CN203347100U (en) Composite wallboard, hanging connection unit between composite wallboard and cross beam and connecting structure between composite wallboard and cross beam
KR101275932B1 (en) Method for installing ALC panel to concrete slab
CN207332045U (en) A kind of twin spans Glass Rib curtain wall wind load span centre bearing
CN206385723U (en) A kind of container house roof beam
CN108797857B (en) Back bolt dry-hanging assembly and back bolt dry-hanging system
CN204662804U (en) A kind of assembled steel structure stair
CN206256537U (en) Big across steel vestibule with railing
CN202899295U (en) B type beam column fixing component used for door-window lintel
CN202509642U (en) Energy-saving insulated plate convenient to install
CN109208850B (en) Composite wallboard mounting method and assembly component thereof
CN204356958U (en) A kind of fixing floor spiced benefit roof beam structure
CN103334539B (en) Combined wall board, combined wall board and crossbeam mount unit and combined wall board and beam connecting structure
CN205637265U (en) Xenogenesis profiled sheet fixing device on strength nature roof beam
EP2662901A1 (en) System for butt jointing photovoltaic modules, and roof-covering created with photovoltaic modules joined by means of jointing systems of this type
CN205276530U (en) Economical removable antidetonation power consumption node
CN204959980U (en) Simple to operate's floor connection structure
CN220247367U (en) Steel construction assembled building heat preservation side fascia
CN204590650U (en) The flexible reinforcing construction of steam-pressing aero-concrete wall body door or window hole
CN210032459U (en) Anchor subassembly and anchor structure of decorative board
CN211080841U (en) A heat preservation wallboard for assembled

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANDONG LIJIU BUILDING TECHNOLOGY CO., LTD.

Free format text: FORMER OWNER: WANG RUIMIN

Effective date: 20150114

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 250001 JINAN, SHANDONG PROVINCE TO: 250101 JINAN, SHANDONG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20150114

Address after: High tech Zone of Ji'nan City Industrial Road, No. 59 in Shandong province 250101 Expo International Building 1 unit 1301 room 6

Patentee after: Shandong Lijiu Building Technology Co., Ltd.

Address before: 250001 Jianshe Road Century Park, Ji'nan City, Shandong province 15-2-1103

Patentee before: Wang Ruimin

ASS Succession or assignment of patent right

Owner name: WANG RUIMIN

Free format text: FORMER OWNER: SHANDONG LIJIU BUILDING TECHNOLOGY CO., LTD.

Effective date: 20150615

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150615

Address after: 250001 Jianshe Road Century Park, Ji'nan City, Shandong province 15-2-1103

Patentee after: Wang Ruimin

Address before: High tech Zone of Ji'nan City Industrial Road, No. 59 in Shandong province 250101 Expo International Building 1 unit 1301 room 6

Patentee before: Shandong Lijiu Building Technology Co., Ltd.

TR01 Transfer of patent right

Effective date of registration: 20191212

Address after: Room 601, block B, Olympic Tiantai Plaza, 5777 jingshidong Road, high tech Zone, Jinan City, Shandong Province, 250000

Patentee after: Shandong Lijiu Construction Robot Co., Ltd.

Address before: 250001 Jianshe Road century Jiayuan 15-2-1103, Shizhong District, Shandong City, Ji'nan Province

Patentee before: Wang Ruimin

TR01 Transfer of patent right