CN102910079B - Subway train pantograph control method based on train network system - Google Patents

Subway train pantograph control method based on train network system Download PDF

Info

Publication number
CN102910079B
CN102910079B CN201210353502.3A CN201210353502A CN102910079B CN 102910079 B CN102910079 B CN 102910079B CN 201210353502 A CN201210353502 A CN 201210353502A CN 102910079 B CN102910079 B CN 102910079B
Authority
CN
China
Prior art keywords
train
bow
network system
pantograph
instruction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210353502.3A
Other languages
Chinese (zh)
Other versions
CN102910079A (en
Inventor
张军贤
陈美霞
奚华峰
夏益韬
黄苏平
黄涛
吕红强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRRC Nanjing Puzhen Co Ltd
Original Assignee
CSR Nanjing Puzhen Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CSR Nanjing Puzhen Co Ltd filed Critical CSR Nanjing Puzhen Co Ltd
Priority to CN201210353502.3A priority Critical patent/CN102910079B/en
Publication of CN102910079A publication Critical patent/CN102910079A/en
Application granted granted Critical
Publication of CN102910079B publication Critical patent/CN102910079B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Train Traffic Observation, Control, And Security (AREA)
  • Electric Propulsion And Braking For Vehicles (AREA)

Abstract

The invention relates to a subway train pantograph control method based on a train network system. A pantograph hoisting instruction can be sent through a pantograph control switch on a driver display or a driver platform, the instruction is transmitted to a central control unit of the train network system through a driver display unit (when an operation is carried out on the driver display unit) or a remote input and output module (when the operation is carried out at the driver platform), the central control unit performs logic diagnosis by combining with states of relative system equipment and the like, and then sends a corresponding control instruction to a dragging assistant system and a pantograph control system, and then hoisting of the pantograph is controlled. By the subway train pantograph control method based on the train network system, a network system software is used for controlling the hoisting of the pantograph, manufacturing cost of a train is saved, and a trouble brought about by wiring is reduced. The subway train pantograph control method based on the train network system has the characteristics of high technical reliability, low equipment cost and simpleness in implementation and the like.

Description

Subway train pantograph control method based on train network system
Technical field
The present invention relates to a kind of subway train pantograph control method based on train network system.
Background technology
Mostly current subway train is the battery-driven car group adopting, the subway train of typical 6 joint marshallings is made up of 4 motor-cars and two trailers, the subway train of 6 joint marshallings is divided into two unit (three of every unit car) conventionally, on motor-car in the middle of each unit, there is a set of pantograph, for train high powered.At present, what the current collecting bow lifting control system on subway train adopted is the train rigid line that runs through full train, adopts train rigid line can strengthen train manufacturing cost, also can cause the puzzlement in wiring simultaneously and strengthen the weight of train.Along with developing rapidly and the continuous maturation of Train Control and monitored control system of network communication field, the lifting that obviously utilizes train network system controlling software to control pantograph has been a kind of trend and will have become main flow in the future.
Summary of the invention
Technical matters to be solved by this invention is, overcomes the above-mentioned deficiency of prior art, and a kind of subway train pantograph control method based on train network system is provided.
In order to solve above technical matters, the subway train pantograph control method based on train network system provided by the invention, is characterized in that train network system remote input/output module is connected with pantograph control system, and the control method of pantograph is as follows:
The first step, receive the operational order of current collecting bow lifting when train network system Central Processing Unit (CPU), if now train network system Central Processing Unit (CPU) regulation does not participate in the control of lifting bow, transmit this instruction to pantograph control system by the remote input output module of train network system, judge voluntarily and carry out lifting bow by pantograph control system; Otherwise go to second step;
If any is activated in second step emergency stop button or train sleep relay or workshop power supply, all pantographs of time delay 2s mandatory down notify all tractor equipments and all accessory equipments; If all do not activated, go to the 3rd step;
If bow falls in the 3rd step this locality, instruction activates, time delay 2s carries out this locality and falls and bend and notify local tractor equipment, judge that far-end falls bow instruction and whether activates simultaneously, if bow falls in far-end, instruction also activates, time delay 2s execution far-end falls and bends and notify all accessory equipments, if bow falls in far-end, instruction does not activate, and does not carry out the operation of lifting bow, if instruction does not activate if bow falls in this locality, this locality, go to the 4th step;
If the local rising bow instruction of the 4th step does not activate, do not carry out the operation of lifting bow; If local rising bow instruction activates, go to the 5th step;
If all train accessory equipment AC contactor all do not have closure on the 5th step train, carry out local rising bow operation; If have any one train accessory equipment AC contactor closure, go to the 6th step;
If the 6th step train has high pressure to exist, carry out local rising bow operation; If train does not have high pressure, do not carry out local rising bow operation, and driver display unit carries out corresponding prompting.
The present invention further improves and is:
1,, in described the 6th step, if train does not have high pressure, driver display unit shows the information about " may with carry a rising bow ".
2, the operational order of described current collecting bow lifting is sent to train network system Central Processing Unit (CPU) by the corresponding button on driver operation driving position or click driver display unit.
Sending of current collecting bow lifting instruction of the present invention can be by the pantograph master cock on driver's read-out or on driving position, then instruction is transferred to the Central Processing Unit (CPU) of train network system by driver display unit (while operation on driver display unit) or remote input output module (while operation on driving position), Central Processing Unit (CPU) carries out sending corresponding control command to traction ancillary system and pantograph control system after logistic diagnosis in conjunction with states such as related system equipment, controls the lifting of pantograph.
The present invention utilizes the lifting of network system software control pantograph, the trouble that can reduce train manufacturing cost, connects up and bring.This method possesses skills, and reliability is high, equipment cost is low, realize the features such as simple.
Brief description of the drawings
Fig. 1 is the inventive method diagram of circuit.
Detailed description of the invention
For making object, technical scheme and the advantage of the embodiment of the present invention clearer, below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described.
Be illustrated in figure 1 the inventive method diagram of circuit.The subway train pantograph control method of the embodiment of the present invention based on train network system, hardware aspect, train network system remote input/output module is connected with pantograph control system, and the control method of pantograph is as follows:
The first step, receive the operational order (operational order of this current collecting bow lifting by driver operation driving position or click the corresponding button on driver display unit be sent to train network system Central Processing Unit (CPU)) of current collecting bow lifting when train network system Central Processing Unit (CPU) (VCU), if now train network system Central Processing Unit (CPU) regulation does not participate in the control of lifting bow, transmit this instruction to pantograph control system by the remote input output module of train network system, judge voluntarily and carry out lifting bow by pantograph control system; Otherwise go to second step;
If any is activated in second step emergency stop button or train sleep relay or workshop power supply, all pantographs of time delay 2s mandatory down notify all tractor equipments and all accessory equipments; If all do not activated, go to the 3rd step;
If bow falls in the 3rd step this locality, instruction activates, time delay 2s carries out this locality and falls and bend and notify local tractor equipment, judge that far-end falls bow instruction and whether activates simultaneously, if bow falls in far-end, instruction also activates, time delay 2s execution far-end falls and bends and notify all accessory equipments, if bow falls in far-end, instruction does not activate, and does not carry out the operation of lifting bow, if instruction does not activate if bow falls in this locality, this locality, go to the 4th step;
If the local rising bow instruction of the 4th step does not activate, do not carry out the operation of lifting bow; If local rising bow instruction activates, go to the 5th step;
If all train accessory equipment AC contactor all do not have closure on the 5th step train, carry out local rising bow operation; If have any one train accessory equipment AC contactor closure, go to the 6th step;
If the 6th step train has high pressure to exist, carry out local rising bow operation; If train does not have high pressure, do not carry out local rising bow operation, and driver display unit carries out corresponding prompting.In this step, if train does not have high pressure, driver display unit shows the information about " may with carry a rising bow ".
Lifting far-end bow is identical with the control logic of the local bow of lifting described above, specifically referring to logic control block diagram.
Above control logic contains following functions module in software: the transmission of pantograph instruction, mandatory down bow, rise singly to bend and fall other bow and (be included in current collecting bow lifting control command, derive from the operation of driving position pantograph master cock or driver display unit), whether be with and carry rising bow diagnosis and an elevating control logic, above functional module is interrelated in logic, but in Software for Design, be standalone module, can carry out choice for use according to disparity items demand, to realize the different control functional requirements such as mandatory down bow, lifting/lowering list/bouble-bow.
In addition to the implementation, the present invention can also have other embodiments.All employings are equal to the technical scheme of replacement or equivalent transformation formation, all drop on the protection domain of requirement of the present invention.

Claims (3)

1. the subway train pantograph control method based on train network system, is characterized in that train network system remote input/output module is connected with pantograph control system, and the control method of pantograph is as follows:
The first step, receive the operational order of current collecting bow lifting when train network system Central Processing Unit (CPU), if now train network system Central Processing Unit (CPU) regulation does not participate in the control of lifting bow, transmit this operational order to pantograph control system by the remote input output module of train network system, judge voluntarily and carry out lifting bow by pantograph control system; Otherwise go to second step;
If any is activated in second step emergency stop button or train sleep relay or workshop power supply, all pantographs of time delay 2s mandatory down notify all tractor equipments and all accessory equipments; If all do not activated, go to the 3rd step;
If bow falls in the 3rd step this locality, instruction activates, time delay 2s carries out this locality and falls and bend and notify local tractor equipment, judge that far-end falls bow instruction and whether activates simultaneously, if bow falls in far-end, instruction also activates, time delay 2s execution far-end falls and bends and notify all accessory equipments, if bow falls in far-end, instruction does not activate, and does not carry out the operation of lifting bow, if bow falls in this locality, instruction does not activate, and goes to the 4th step;
If the local rising bow instruction of the 4th step does not activate, do not carry out the operation of lifting bow; If local rising bow instruction activates, go to the 5th step;
If all train accessory equipment AC contactor all do not have closure on the 5th step train, carry out local rising bow operation; If have any one train accessory equipment AC contactor closure, go to the 6th step;
If the 6th step train has high pressure to exist, carry out local rising bow operation; If train does not have high pressure, do not carry out local rising bow operation, and driver display unit carries out corresponding prompting.
2. the subway train pantograph control method based on train network system according to claim 1, is characterized in that: in described the 6th step, if train does not have high pressure, driver display unit shows the information about " may with carry a rising bow ".
3. the subway train pantograph control method based on train network system according to claim 1, is characterized in that: the operational order of described current collecting bow lifting is sent to train network system Central Processing Unit (CPU) by the corresponding button on driver operation driving position or click driver display unit.
CN201210353502.3A 2012-09-20 2012-09-20 Subway train pantograph control method based on train network system Active CN102910079B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210353502.3A CN102910079B (en) 2012-09-20 2012-09-20 Subway train pantograph control method based on train network system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210353502.3A CN102910079B (en) 2012-09-20 2012-09-20 Subway train pantograph control method based on train network system

Publications (2)

Publication Number Publication Date
CN102910079A CN102910079A (en) 2013-02-06
CN102910079B true CN102910079B (en) 2014-11-19

Family

ID=47608741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210353502.3A Active CN102910079B (en) 2012-09-20 2012-09-20 Subway train pantograph control method based on train network system

Country Status (1)

Country Link
CN (1) CN102910079B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103273929B (en) * 2013-06-19 2016-03-09 南车株洲电力机车有限公司 A kind of control system of motor train unit and method
CN103434536B (en) * 2013-08-30 2015-09-02 南车南京浦镇车辆有限公司 Train network parameter tracking method
CN104670026B (en) * 2015-03-18 2017-03-01 南车株洲电力机车有限公司 A kind of rail vehicles and its fall bow circuit and fall bow control method
CN106627162B (en) * 2016-12-12 2019-04-30 中国神华能源股份有限公司 A kind of motorcycle pantograph control method and system and alternating current-direct current shuffling locomotive
CN109383560A (en) * 2017-08-14 2019-02-26 株洲中车时代电气股份有限公司 A kind of train high-tension apparatus control method and system
CN107902551A (en) * 2017-12-12 2018-04-13 上海浦东国际集装箱码头有限公司 Overhead oil changes electric tyre crane trolley pole remote control and draws extension two-dimensional micromotion system
CN110456686B (en) * 2019-07-18 2020-11-17 株洲长河电力机车科技有限公司 Full-load traction starting control method for special manned tramcar

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19729479A1 (en) * 1997-07-10 1999-01-14 Abb Daimler Benz Transp Pulse width modulation method for inverters connected in series
CN101487873A (en) * 2008-01-15 2009-07-22 中国神华能源股份有限公司 Wireless video automatic monitoring system for pantograph of locomotive
CN201439348U (en) * 2009-05-21 2010-04-21 中国北车集团大同电力机车有限责任公司 Control system used in a track vehicle and device
CN102050034A (en) * 2009-11-05 2011-05-11 陆中源 Trackless electric automobile and road surface power supply contact line thereof
GB2477166A (en) * 2010-01-26 2011-07-27 Responsiveload Ltd Transport responsive load system
CN202066623U (en) * 2010-12-27 2011-12-07 北京赛德高科铁道电气科技有限责任公司 Pantograph static pressure detection terminal, controller and detection system

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003284201A (en) * 2002-03-26 2003-10-03 Maeda Corp Transportation system for engineering work
WO2009133608A1 (en) * 2008-04-30 2009-11-05 三菱電機株式会社 Electric railway system
JP2011142763A (en) * 2010-01-08 2011-07-21 Panasonic Corp Radio power transfer device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19729479A1 (en) * 1997-07-10 1999-01-14 Abb Daimler Benz Transp Pulse width modulation method for inverters connected in series
CN101487873A (en) * 2008-01-15 2009-07-22 中国神华能源股份有限公司 Wireless video automatic monitoring system for pantograph of locomotive
CN201439348U (en) * 2009-05-21 2010-04-21 中国北车集团大同电力机车有限责任公司 Control system used in a track vehicle and device
CN102050034A (en) * 2009-11-05 2011-05-11 陆中源 Trackless electric automobile and road surface power supply contact line thereof
GB2477166A (en) * 2010-01-26 2011-07-27 Responsiveload Ltd Transport responsive load system
CN202066623U (en) * 2010-12-27 2011-12-07 北京赛德高科铁道电气科技有限责任公司 Pantograph static pressure detection terminal, controller and detection system

Also Published As

Publication number Publication date
CN102910079A (en) 2013-02-06

Similar Documents

Publication Publication Date Title
CN102910079B (en) Subway train pantograph control method based on train network system
CN102081402B (en) Vehicle-mounted control and diagnosis system for medium-low speed maglev train
CN106740572A (en) A kind of automobile line traffic control drive device, system and automobile
CN201193041Y (en) Traction control system based on TCN network
CN104260731B (en) Train as well as train operation control method and system
CN204156887U (en) For the locomotive communicating system of fixed-interlock train
CN102874280A (en) Train speed limitation control method based on train network system
CN103648826A (en) Train information management device and train information management method
WO2017005214A1 (en) Brake instruction conversion and control circuit for multiple unit
CN104192154A (en) Method for controlling traction braking force by TCMS
CN203005423U (en) System for realizing locomotive multiple-connection pantograph control
CN104554347A (en) Interconnection method for rail vehicles
CN102935810B (en) System and method for controlling pantograph of multi-locomotive
CN110362066A (en) Fortune control system and fortune prosecutor method under a kind of pilot steering mode based on magnetic floating system
CN108466578B (en) The deliverance apparatus and its control method of vehicle
CN109501788A (en) Tramcar traction braking force control method based on train network control system
CN109501597A (en) A kind of control method of automatic lifting pantograph
CN102019919A (en) Control application mode for air-braking small brake of multi- locomotive
CN205292326U (en) System and vehicle of control electric drive annex
CN107554539B (en) A kind of detection vehicle and its detection vehicle group
CN107458227B (en) The power concentration motor train unit train method for controlling power supply flexibly organized into groups
CN206358097U (en) A kind of automobile line traffic control drive device, system and automobile
CN207020520U (en) Mine motor vehicle radio joins synchronous control system again
CN103324167B (en) Driver display unit of rapid passenger transport electric locomotive
CN207292035U (en) Long-range isolation circuit and the brake fault shielding system for crewless train

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 210031 Nanjing province high tech Industrial Development Zone, Taishan Park, North Pearl Road, No. 68

Patentee after: CRRC NANJING PUZHEN CO., LTD.

Address before: 210031 Nanjing province high tech Industrial Development Zone, Taishan Park, North Pearl Road, No. 68

Patentee before: CSR NANJING PUZHEN Vehicles Co., Ltd.