CN102900058A - 一种宽河床坝式水电站导流施工方法 - Google Patents

一种宽河床坝式水电站导流施工方法 Download PDF

Info

Publication number
CN102900058A
CN102900058A CN2012104495998A CN201210449599A CN102900058A CN 102900058 A CN102900058 A CN 102900058A CN 2012104495998 A CN2012104495998 A CN 2012104495998A CN 201210449599 A CN201210449599 A CN 201210449599A CN 102900058 A CN102900058 A CN 102900058A
Authority
CN
China
Prior art keywords
cofferdam
diversion
construction
master
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104495998A
Other languages
English (en)
Other versions
CN102900058B (zh
Inventor
陈义军
叶建群
任金明
吕国轩
董宝顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN201210449599.8A priority Critical patent/CN102900058B/zh
Publication of CN102900058A publication Critical patent/CN102900058A/zh
Application granted granted Critical
Publication of CN102900058B publication Critical patent/CN102900058B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

本发明涉及一种宽河床坝式水电站导流施工方法。本发明的目的是提供一种宽河床坝式水电站导流施工方法,缩短水电枢纽工程的总工期。本发明的技术方案是:步骤如下:a、在河道一侧先修筑导流建筑物;b、修建导流建筑物同时,在河道另一侧河床进行临时围堰施工;c、待临时围堰施工完成后,临时围堰与河岸围成基坑抽排水,进行大坝的施工;d、导流建筑物具备过流条件后,延伸临时围堰上游段和下游段至河道对岸,形成上游主围堰和下游主围堰;e、对上游主围堰和下游主围堰之间基坑进行抽排水形成干地施工环境;f、上游主围堰和下游主围堰之间进行大坝或厂房的全面施工。本发明适用于宽河床坝式水电站采用分期导流方式布置的枢纽布置设计及施工。

Description

一种宽河床坝式水电站导流施工方法
技术领域
发明涉及一种宽河床坝式水电站导流施工方法。适用于宽河床坝式水电站采用分期导流方式布置的枢纽布置设计及施工。
背景技术
在宽河床布置坝式水电站时,当施工导流选择分期导流方式时,常规施工是在时间上将导流分为若干期,并在空间上用围堰将水工建筑物分为若干段,逐期逐段将枢纽工程修建完成。按常规施工导流方式布置的枢纽工程,一期导流通常修建导流建筑物,而控制工程总工期的关键项目一般放在二期或三期导流中实施,这种常规导流方式布置使得工程总工期或发电工期持续时间相对较长。如何缩短水电枢纽工程的总工期或发电工期是要在枢纽布置设计及工程施工导流布置中需要考虑的问题。
发明内容
本发明要解决的技术问题是:针对上述存在的问题,提供一种施工便捷、成本相对较低的宽河床坝式水电站导流施工方法,可有效缩短水电枢纽工程的总工期或发电工期,使电站达到提前受益的目的。
本发明所采用的技术方案是:一种宽河床坝式水电站导流施工方法,其特征在于包括步骤如下:
a、在河道一侧先修筑导流建筑物,即先在导流建筑物的上、下游位置分别施工进口围堰和出口围堰,待进口围堰和出口围堰施工完成后,开始修建导流建筑物;
b、在修建导流建筑物的同时,在河道另一侧河床进行临时围堰施工,该临时围堰呈U型,分为上游段、中间连接段和下游段,所述上游段和下游段均沿二期导流上、下游主围堰的轴线修筑,临时围堰的开口端与该侧河岸相连;
c、待临时围堰施工完成后,对U型临时围堰与河岸围成的基坑进行抽排水,形成干地施工环境,而后开始进行部分大坝或厂房的施工;
d、在导流建筑物建成或具备过流条件后,拆除导流建筑物的进口围堰和出口围堰,并对河床进行截流,沿二期导流主围堰轴线延伸临时围堰的上游段和下游段至河道对岸,分别形成上游主围堰和下游主围堰;
e、对上游主围堰和下游主围堰之间的基坑进行抽排水形成干地施工环境,然后拆除临时围堰的中间连接段;
f、在上游主围堰和下游主围堰之间进行大坝或厂房的全面施工。
所述导流建筑物为导流明渠或导流隧洞。 
本发明的有益效果是:本发明中工程的关键项目(如大坝的部分坝段或厂房的部分机组)在截流前的导流建筑物施工期间就可实施,有效地缩短了水电枢纽工程的总工期或发电工期,从而使电站提前受益;本发明中在上游主围堰和下游主围堰施工时,结合部分临时围堰,降低了截流后上、下游主围堰的施工强度,同时也为截流时机提供了较大的选择性。
附图说明
图1为本发明实施例中导流建筑物施工阶段的布置示意图。
图2为本发明实施例中大坝或厂房全面施工阶段的布置示意图。
具体实施方式
本实施例为一种宽河床坝式水电站导流施工方式,在水电站枢纽工程一期导流阶段,在河道左、右岸均布置导流建筑物,即除了在导流建筑物7(如导流明渠或导流隧洞)的上下游布置进、出口围堰外,同时在关键项目(如大坝或厂房)四周结合二期导流的上、下游主围堰提前实施部分围堰,这样就可在施工导流建筑物7(如导流明渠或导流隧洞)的同时,提前施工工程关键项目(如大坝或厂房2)的部分项目,为水电工程的关键项目提前施工创造了有利条件。
本实施例的具体施工方法如下:
a、如图1所示,在河道一侧先修筑导流建筑物7,即先在导流建筑物的上、下游位置分别施工进口围堰5和出口围堰6,待进口围堰5和出口围堰6施工完成后,开始修建导流建筑物7;
b、在修建导流建筑物7的同时,在河道另一侧,在工程的关键项目(如大坝的部分坝段或厂房的部分机组)四周施工临时围堰1,该临时围堰呈U型,临时围堰的开口端与该侧河岸相连,该临时围堰分为上游段1-1和下游段1-3,以及连接上游段1-1和下游段1-3的中间连接段1-2,其中上游段1-1和下游段1-3分别沿着工程关键项目的上、下游主围堰轴线布置,并可与上、下游主围堰相结合,成为上、下游主围堰的一部分;
c、待临时围堰1施工完成后,对U型临时围堰1与河岸围成的基坑进行抽排水,形成干地施工环境,而后进行部分大坝或厂房2的施工;
d、等到导流建筑物7建成或具备过流条件后,拆除导流建筑物7的进口围堰5和出口围堰6,并对河床进行截流,延伸临时围堰1的上游段1-1和下游段1-3至河道对岸,经完善和加高后分别形成二期导流的上游主围堰3和下游主围堰4;
e、对上游主围堰3和下游主围堰4之间的基坑进行抽排水形成干地施工环境,然后拆除临时围堰1的中间连接段1-2;
f、在上游主围堰3和下游主围堰4之间进行大坝或厂房2的全面施工。

Claims (2)

1.一种宽河床坝式水电站导流施工方法,其特征在于包括步骤如下:
a、在河道一侧先修筑导流建筑物(7),即先在导流建筑物的上、下游位置分别施工进口围堰(5)和出口围堰(6),待进口围堰(5)和出口围堰(6)施工完成后,开始修建导流建筑物(7);
b、在修建导流建筑物(7)的同时,在河道另一侧河床进行临时围堰(1)施工,该临时围堰呈U型,分为上游段(1-1)、中间连接段(1-2)和下游段(1-3),所述上游段(1-1)和下游段(1-3)均沿二期导流上、下游主围堰的轴线修筑,临时围堰(1)的开口端与该侧河岸相连;
c、待临时围堰(1)施工完成后,对U型临时围堰(1)与河岸围成的基坑进行抽排水,形成干地施工环境,而后开始进行部分大坝或厂房(2)的施工;
d、在导流建筑物(7)建成或具备过流条件后,拆除导流建筑物的进口围堰(5)和出口围堰(6),并对河床进行截流,沿二期导流主围堰轴线延伸临时围堰(1)的上游段(1-1)和下游段(1-3)至河道对岸,分别形成上游主围堰(3)和下游主围堰(4);
e、对上游主围堰(3)和下游主围堰(4)之间的基坑进行抽排水形成干地施工环境,然后拆除临时围堰(1)的中间连接段(1-2);
f、在上游主围堰(3)和下游主围堰(4)之间进行大坝或厂房(2)的全面施工。
2.根据权利要求1所述的宽河床坝式水电站导流施工方法,其特征在于:所述导流建筑物(7)为导流明渠或导流隧洞。
CN201210449599.8A 2012-11-12 2012-11-12 一种宽河床坝式水电站导流施工方法 Active CN102900058B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210449599.8A CN102900058B (zh) 2012-11-12 2012-11-12 一种宽河床坝式水电站导流施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210449599.8A CN102900058B (zh) 2012-11-12 2012-11-12 一种宽河床坝式水电站导流施工方法

Publications (2)

Publication Number Publication Date
CN102900058A true CN102900058A (zh) 2013-01-30
CN102900058B CN102900058B (zh) 2015-01-07

Family

ID=47572525

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210449599.8A Active CN102900058B (zh) 2012-11-12 2012-11-12 一种宽河床坝式水电站导流施工方法

Country Status (1)

Country Link
CN (1) CN102900058B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032714A (zh) * 2014-06-25 2014-09-10 中国电建集团华东勘测设计研究院有限公司 一次拦断与分期拦断组合的坝式水电站施工导流方法
CN108411865A (zh) * 2018-04-02 2018-08-17 中国电建集团中南勘测设计研究院有限公司 一种导流泄水建筑物的施工方法
CN108677880A (zh) * 2018-07-27 2018-10-19 中国电建集团成都勘测设计研究院有限公司 用于复杂地质条件下的桩林坝
CN110629771A (zh) * 2019-09-02 2019-12-31 中国水利水电第五工程局有限公司 一种多岔河多河心岛围堰施工方法
CN111305141A (zh) * 2019-11-29 2020-06-19 中国一冶集团有限公司 一种地下综合管廊穿枯水期河渠的引流方法
CN111851427A (zh) * 2020-07-22 2020-10-30 桂林生 一种水电站新型截流及围堰坝体以及坝体施工方法
CN112663642A (zh) * 2020-12-18 2021-04-16 贵州天然气管网有限责任公司 一种天然气管道穿越采用二次围堰导流法的施工方法
CN113529761A (zh) * 2020-04-22 2021-10-22 中国电建集团华东勘测设计研究院有限公司 一种具有折线式土石围堰的围堰群结构及施工方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2413050C1 (ru) * 2009-10-23 2011-02-27 Денис Владимирович Кашарин Мобильное гидроэнергетическое сооружение рукавного типа

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2413050C1 (ru) * 2009-10-23 2011-02-27 Денис Владимирович Кашарин Мобильное гидроэнергетическое сооружение рукавного типа

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
冉统军: "连麓一级水电站枢纽导流设计", 《甘肃冶金》, vol. 30, no. 6, 31 December 2008 (2008-12-31) *
宋亦农: "龙滩水电站导流设计与施工", 《水力发电》, no. 10, 31 October 2003 (2003-10-31), pages 51 - 53 *
李克礼: "铜街子水电站施工导流中围堰工程施工技术的回顾", 《四川水力发电》, vol. 21, no. 4, 31 December 2002 (2002-12-31) *
陶涛: "滩坑水电站的施工导流设计", 《水电站设计》, vol. 24, no. 2, 30 June 2008 (2008-06-30), pages 40 - 43 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032714A (zh) * 2014-06-25 2014-09-10 中国电建集团华东勘测设计研究院有限公司 一次拦断与分期拦断组合的坝式水电站施工导流方法
CN108411865A (zh) * 2018-04-02 2018-08-17 中国电建集团中南勘测设计研究院有限公司 一种导流泄水建筑物的施工方法
CN108677880A (zh) * 2018-07-27 2018-10-19 中国电建集团成都勘测设计研究院有限公司 用于复杂地质条件下的桩林坝
CN108677880B (zh) * 2018-07-27 2024-03-19 中国电建集团成都勘测设计研究院有限公司 用于复杂地质条件下的桩林坝
CN110629771A (zh) * 2019-09-02 2019-12-31 中国水利水电第五工程局有限公司 一种多岔河多河心岛围堰施工方法
CN110629771B (zh) * 2019-09-02 2021-06-18 中国水利水电第五工程局有限公司 一种多岔河多河心岛围堰施工方法
CN111305141A (zh) * 2019-11-29 2020-06-19 中国一冶集团有限公司 一种地下综合管廊穿枯水期河渠的引流方法
CN111305141B (zh) * 2019-11-29 2021-11-26 中国一冶集团有限公司 一种地下综合管廊穿枯水期河渠的引流方法
CN113529761A (zh) * 2020-04-22 2021-10-22 中国电建集团华东勘测设计研究院有限公司 一种具有折线式土石围堰的围堰群结构及施工方法
CN113529761B (zh) * 2020-04-22 2023-08-18 中国电建集团华东勘测设计研究院有限公司 一种具有折线式土石围堰的围堰群结构及施工方法
CN111851427A (zh) * 2020-07-22 2020-10-30 桂林生 一种水电站新型截流及围堰坝体以及坝体施工方法
CN112663642A (zh) * 2020-12-18 2021-04-16 贵州天然气管网有限责任公司 一种天然气管道穿越采用二次围堰导流法的施工方法

Also Published As

Publication number Publication date
CN102900058B (zh) 2015-01-07

Similar Documents

Publication Publication Date Title
CN102900058B (zh) 一种宽河床坝式水电站导流施工方法
CN104032714B (zh) 一次拦断与分期拦断组合的坝式水电站施工导流方法
CN101775788B (zh) 一种块石-钢筋混凝土排桩复合型丁坝护岸结构
CN204898614U (zh) 用于泥石流河道防护的拦挡坝
CN103195015B (zh) 基于围湖造河技术综合开发利用湖泊湿地的方法
CN103953003A (zh) 一种用于围海造地的促淤堤坝及促淤方法
CN106560560B (zh) 卷席截流水电站建筑方法
CN107858990B (zh) 峡谷区高坝沟水处理工程的布置结构的导流施工方法
CN203113359U (zh) 土石围堰结构
CN104164858B (zh) 实现高拱坝蓄水期下游不断流的导流隧洞分序封堵方法
CN109371914B (zh) 一种便于后期改建的泄水渠结构
CN105002863A (zh) 一种基于下游水库调度的生态流量保障方法
CN204608736U (zh) 一种布置在溶洞内的发电厂房
CN210482182U (zh) 一种用于构建生态循环水系的双河道结构
CN102352617B (zh) 灯泡贯流式水电站厂房导流的施工方法
CN102505670B (zh) 密集建造水利发电站的方法及可密集建造的水利发电站
CN205152918U (zh) 一种导流洞和泄洪洞结合的结构
CN210086195U (zh) 水电站竖井式尾水渠
CN206529746U (zh) 一种过流拱坝免拆除的混凝土坝施工布置结构
CN204753536U (zh) 一种具有交通功能的导流洞结构
CN208899441U (zh) 用于水利发电工程的发电厂房布置结构
CN105386426A (zh) 导流隧洞改建为弧形闸门控制的生态放水洞及方法
CN204644994U (zh) 一种泄水建筑物结构
CN205688412U (zh) 一种水电站厂房尾水渠导墙布置结构
CN205088684U (zh) 河床部位地质缺陷处临时灌浆廊道

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant