CN102888856A - Basement wall plate and containment support changing system and construction method - Google Patents

Basement wall plate and containment support changing system and construction method Download PDF

Info

Publication number
CN102888856A
CN102888856A CN2012104149158A CN201210414915A CN102888856A CN 102888856 A CN102888856 A CN 102888856A CN 2012104149158 A CN2012104149158 A CN 2012104149158A CN 201210414915 A CN201210414915 A CN 201210414915A CN 102888856 A CN102888856 A CN 102888856A
Authority
CN
China
Prior art keywords
support
wall plate
basement
underground
guard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012104149158A
Other languages
Chinese (zh)
Inventor
陈国烽
叶敏
顾靖
王巍
张铭
甘澍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 4 Group Co Ltd
Original Assignee
Shanghai Construction No 4 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 4 Group Co Ltd filed Critical Shanghai Construction No 4 Group Co Ltd
Priority to CN2012104149158A priority Critical patent/CN102888856A/en
Publication of CN102888856A publication Critical patent/CN102888856A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to a basement wall plate and containment support changing system and a construction method. The system comprises a latticed column, a foundation bottom plate, a first path concrete support and an underground two-layered top plate, wherein the foundation bottom plate is connected with the first path concrete support through the latticed column in a supporting manner; and an underground two-layered wall plate is supported by containment at the two sides; and a bentonite waterproof carpet and an extruding polyphenyl plate heat-preservation layer are paved between the containment and the underground two-layered wall plate. The basement wall plate and containment support changing system is a novel support changing system which combines a basement structure outer wall plate to form a framework type combined support to commonly resist lateral force of the structure. The basement wall plate and containment support changing system adopts a basement structure outer wall plate so that the working amount of the backfilling construction of a foundation pit is reduced and the removing construction period of a template of an outer wall plate structure is saved. The basement structure outer wall plate and the newly-established support are combined to be stressed so that the rigidity and the stability of support changing are enhanced.

Description

Double support-replacing system and the job practices gone along with sb. to guard him of basement wallboard
Technical field
The present invention relates to a kind of job practices that adopts the basement wall to replace support-replacing system, be applicable to the closely spaced support replacement construction of core city foundation pit system and underground space structure.
Background technology
During conventional Underground Construction, because floor lacks less, spatial extent is little, only can satisfy the support replacement requirement at corresponding site construction reinforced bar concrete beam or section steel beam.In underground large spatial structure construction; structure floor disappearance area is large, story height is high, spatial extent is large; common beam type support replacement all is difficult to guarantee the reasonable stressed and construction safety of support replacement from intensity, rigidity and stable equal angles; and underground space structure and pit maintenance soil system spacing are little, and trouble, construction period prolongation but also cost are high if construction beam type support replacement is not only constructed.Support replacement belongs to temporary support structure, if can adopt novel support-replacing system, guaranteeing prerequisite decline low cost, the quickening progress of construction safety, then can create good economic benefit.
Summary of the invention
The present invention need to solve the underground large spatial structure construction stage, can't constructing technology problem because of original beam type support replacement, the support-replacing system that provides a kind of employing to have sufficient intensity, rigidity and stability guarantees that underground structure can resist double support-replacing system and the job practices gone along with sb. to guard him of basement wallboard of the lateral force that water and soil applies voluntarily at fininshing step not.
Technical scheme of the present invention is: the double support-replacing system of going along with sb. to guard him of a kind of basement wallboard, comprise that lattice column, sole plate, first concrete support, underground two layers of top board, between supporting, sole plate and first concrete pass through the lattice column support and connection, two sides are with going along with sb. to guard him the underground two layers of wallboard of support replacement, and go along with sb. to guard him and underground two layers of wallboard between lay GCL and extruded polystyrene board insulation layer.
The double job practices of going along with sb. to guard him support-replacing system of a kind of basement wallboard, concrete steps are:
1) reaches in the designing requirement situation in sole plate intensity, remove the second concrete and support the paving of extruded polystyrene board insulation layer;
2) after the paving of extruded polystyrene board insulation layer is finished, underground two layers of exterior wall GCL construction;
3) underground two layers of wallboard and go along with sb. to guard him support replacement construction;
4) repeating step 1) and step 2) and step 3), until form the double support-replacing system of going along with sb. to guard him of basement wallboard.
The invention has the beneficial effects as follows:
The present invention adopts novel support-replacing system cancellation previous level to support and job practices, the thickening of basement structure outer wall plate is extended to foundation pit system consist of firm space frame system, opposing side direction horizontal power.
Double rigidity and the stability that support-replacing system has increased support-replacing system greatly, the more reasonable stress gone along with sb. to guard him of basement wallboard; Save time and the cost of support replacement construction, reduce engineering quantity and the cost of pit backfill soil, have extraordinary economic benefit.
Description of drawings
Fig. 1 is extruded polystyrene board insulation layer paving construction schematic diagram;
Fig. 2 is underground two layers of exterior wall GCL construction schematic diagram;
Fig. 3 is structure of the present invention and underground two layers of wallboard and goes along with sb. to guard him support replacement construction schematic diagram.
The specific embodiment
As shown in Figure 3, the double support-replacing system of going along with sb. to guard him of basement wallboard of the present invention comprises that lattice column 1, sole plate 2, first concrete support 3, go along with sb. to guard him 6, underground two layers of top board 7, GCL 5 and extruded polystyrene board insulation layer 4.
By lattice column 1 support and connection, two sides were with going along with sb. to guard him the underground two layers of wallboard of 6 support replacements between sole plate 2 and first concrete supported 3, and go along with sb. to guard him 6 and underground two layers of wallboard between laying GCL 5 and extruded polystyrene board insulation layer 4.
The double job practices of going along with sb. to guard him support-replacing system of basement wallboard, concrete steps are:
1) reaches in the designing requirement situation in sole plate 2 intensity, remove the second concrete and support 8, paving extruded polystyrene board insulation layer 4(Fig. 1 `);
2) after 4 pavings of extruded polystyrene board insulation layer are finished, underground two layers of exterior wall GCL, 5 constructions (Fig. 2);
3) underground two layers of wallboard and go along with sb. to guard him 6 support replacements construction (Fig. 3);
4) repeating step 1) and step 2) and step 3), until form the double support-replacing system of going along with sb. to guard him of basement wallboard.
The double support-replacing system of going along with sb. to guard him of basement wallboard is a kind of newly-built support replacement forms the common resisting structure lateral force of frame type combined support in conjunction with the basement structure side fascia novel support-replacing system.Its utilized the basement structure outer wall plate, not only reduced pit backfill construction working amount, but also saved the dismounting external wall panel structure form removable construction period.The basement structure outer wall plate is combined stressed with newly-built support, increased again rigidity and the stability of support replacement.

Claims (2)

1. double support-replacing system of going along with sb. to guard him of basement wallboard, comprise that lattice column (1), sole plate (2), first concrete support (3), underground two layers of top board (7), it is characterized in that: described sole plate (2) and first concrete support between (3) by lattice column (1) support and connection, two sides are with going along with sb. to guard him the underground two layers of wallboard of (6) support replacement, and lay GCL (5) and extruded polystyrene board insulation layer (4) going along with sb. to guard him between (6) and the underground two layers of wallboard.
2. the double job practices of going along with sb. to guard him support-replacing system of basement wallboard is characterized in that, concrete steps are:
1) reaches in the designing requirement situation in sole plate (2) intensity, remove the second concrete and support (8), paving extruded polystyrene board insulation layer (4);
2) after extruded polystyrene board insulation layer (4) paving is finished, underground two layers of exterior wall GCL (5) construction;
3) underground two layers of wallboard and go along with sb. to guard him (6) support replacement construction;
4) repeating step 1) and step 2) and step 3), until form the double support-replacing system of going along with sb. to guard him of basement wallboard.
CN2012104149158A 2012-10-26 2012-10-26 Basement wall plate and containment support changing system and construction method Pending CN102888856A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012104149158A CN102888856A (en) 2012-10-26 2012-10-26 Basement wall plate and containment support changing system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012104149158A CN102888856A (en) 2012-10-26 2012-10-26 Basement wall plate and containment support changing system and construction method

Publications (1)

Publication Number Publication Date
CN102888856A true CN102888856A (en) 2013-01-23

Family

ID=47532523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012104149158A Pending CN102888856A (en) 2012-10-26 2012-10-26 Basement wall plate and containment support changing system and construction method

Country Status (1)

Country Link
CN (1) CN102888856A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103912134A (en) * 2014-03-21 2014-07-09 上海建工四建集团有限公司 Construction in-situ underground space structure and construction method
CN105089064A (en) * 2015-09-14 2015-11-25 上海建工二建集团有限公司 Support replacing construction structure and method for rapidly demounting first support of large foundation trench

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2525663A1 (en) * 1982-04-27 1983-10-28 Roux Paul LOCAL BURNER, AS IN PARTICULAR A CELLAR, AND METHOD FOR THE DEVELOPMENT THEREOF
CN201746839U (en) * 2010-06-13 2011-02-16 中建三局建设工程股份有限公司 Low-environment-disturbance device for removing supports from foundation pit
CN201972155U (en) * 2011-01-28 2011-09-14 东南大学 Topdown-construction-method foundation pit supporting structure of steel plate pile
CN102505696A (en) * 2011-10-28 2012-06-20 上海建瓴工程咨询有限公司 Support system of rear support removing type section steel-concrete double-enclosing-purlin foundation pit and construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2525663A1 (en) * 1982-04-27 1983-10-28 Roux Paul LOCAL BURNER, AS IN PARTICULAR A CELLAR, AND METHOD FOR THE DEVELOPMENT THEREOF
CN201746839U (en) * 2010-06-13 2011-02-16 中建三局建设工程股份有限公司 Low-environment-disturbance device for removing supports from foundation pit
CN201972155U (en) * 2011-01-28 2011-09-14 东南大学 Topdown-construction-method foundation pit supporting structure of steel plate pile
CN102505696A (en) * 2011-10-28 2012-06-20 上海建瓴工程咨询有限公司 Support system of rear support removing type section steel-concrete double-enclosing-purlin foundation pit and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103912134A (en) * 2014-03-21 2014-07-09 上海建工四建集团有限公司 Construction in-situ underground space structure and construction method
CN105089064A (en) * 2015-09-14 2015-11-25 上海建工二建集团有限公司 Support replacing construction structure and method for rapidly demounting first support of large foundation trench

Similar Documents

Publication Publication Date Title
CN103469733B (en) A kind of from falling molding box joist steel Guan Beilei door opening support and bearing method thereof
CN103195085B (en) Downward story-adding basement and construction method thereof
CN105625566B (en) Assembly concrete orthogonal-diagonal lattice space lattice box structure tube-in-tube structure
CN203296038U (en) High embankment chair-type sheet-pile retaining wall structure
CN105155549A (en) Partition support system for large-area deep foundation pit under forward and backward working condition, and construction method thereof
CN204510467U (en) A kind of cap node for basement flat slab structure
CN102031785A (en) Foundation pit supporting technique for replacing temporary enclosing purlin by using plate belt of permanent structure
CN201981552U (en) Underground garage structure system with large-span prestressed reinforced concrete frame
CN102926408B (en) A kind of base isolation structure and underpin processing method
CN204715366U (en) A kind of large-area deep foundation pit subregion is along the support system under inverse operating mode
CN102953385A (en) Construction method for changing support of foundation pit at irregular place of rampway
CN102733619B (en) Strengthening method for reinforced concrete frame structure
CN102888856A (en) Basement wall plate and containment support changing system and construction method
CN103015432A (en) Construction method for changing steel pipe supports of ramp foundation pit
CN107313551A (en) A kind of concrete prefabricated wallboard of steel bar girder and structural system and its construction method
CN204001705U (en) Outer wall of basement single surface formwork constructing structure based on earth anchor truss
CN106436721A (en) Underground diaphragm wall embedded steel enclosing purlin plug system and construction method thereof
CN102828616A (en) High-formwork support system for roof
CN207376945U (en) A kind of concrete prefabricated wallboard of steel bar girder and structural system
CN203429661U (en) Basement with additional downward layers
CN202925552U (en) Foundation pit steel pipe brace replacing and construction structure for ramp
CN108412036A (en) Assembled H profile steel column-isolated footing-concrete collar tie beam cross connecting node
CN201169781Y (en) Cap digging pit structure
CN108625491A (en) Assembled H profile steel column-isolated footing-concrete collar tie beam L-shaped connecting node
CN210141143U (en) Pipe curtain undercut multilayer suspension pull stand braced system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130123