CN102837978A - Shipment method combining large constructional element rolling and floating crane - Google Patents

Shipment method combining large constructional element rolling and floating crane Download PDF

Info

Publication number
CN102837978A
CN102837978A CN2012103650816A CN201210365081A CN102837978A CN 102837978 A CN102837978 A CN 102837978A CN 2012103650816 A CN2012103650816 A CN 2012103650816A CN 201210365081 A CN201210365081 A CN 201210365081A CN 102837978 A CN102837978 A CN 102837978A
Authority
CN
China
Prior art keywords
harbour
ship
special
constructional element
shipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012103650816A
Other languages
Chinese (zh)
Other versions
CN102837978B (en
Inventor
宿有为
杨阳
韩鹏飞
朱小明
李守阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu xinzhongtai Bridge Steel Structure Engineering Co. Ltd.
Original Assignee
JIANGSU ZHONGTAI BRIDGE STEEL STRUCTURE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU ZHONGTAI BRIDGE STEEL STRUCTURE CO Ltd filed Critical JIANGSU ZHONGTAI BRIDGE STEEL STRUCTURE CO Ltd
Priority to CN201210365081.6A priority Critical patent/CN102837978B/en
Publication of CN102837978A publication Critical patent/CN102837978A/en
Application granted granted Critical
Publication of CN102837978B publication Critical patent/CN102837978B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The invention relates to a shipment method combining large constructional element rolling and floating crane, mainly relates to a rolling and floating crane combined technology during shipment, and belongs to the technical field of building material transportation. The shipment method adopts the following steps of: stopping a special beam carrying ship in a wharf, taking a large constructional element, and utilizing two large flatcars to carry the large constructional element to the wharf; selecting an appropriate tidal level, arranging two parallel overlapping platforms on the special beam carrying ship, and paving two rows of rails which are mutually parallel between the overlapping platforms; loading the special large flatcars for loading the large constructional element to a ship in a rolling way through rails, using the floating crane to lift, slowly moving to the frontage of a transport ship wharf, stopping a steel lagging box, and carrying out colligation; and transporting to the special beam carrying ship; and enabling a transport ship to move to the wharf, stopping the constructional element, and carrying out colligation and fixation. According to the invention, the large constructional element can be safely and smoothly stopped on the transport ship, the operation is easy, the shipment safety is guaranteed, the construction cost is reduced, and the existing wharfs, ships and floating cranes are fully utilized.

Description

A kind of big member rolls dress and ties shipment method mutually with crane barge
Technical field
The present invention relates to a kind of big member and roll dress and tie shipment method mutually with crane barge, the technology that relates generally to that rolling in the shipment process adorned and crane barge combines belongs to building materials transportation technology field.
Background technology
Big member stock size is big, and total amount is big, and the shipment shipping is proposed very high requirement; Prior art is for this type of big member; General adopt roll dress, or directly go on board with the large-scale floating crane lifting, these two kinds shipment technology to the hanger of harbour, ships that transport, crane barge and member be provided with all require very high.Because the restriction of crane barge length of boom requires the stage of growing up to need the along the coastline lateral arrangement, need call the very big crane barge in position of squatting; Expense is very high, and rolls when dress is vertical loads onto ship, receives the restriction of morning and evening tides condition to a great extent again; When the sections shipping, run into simultaneously the camp site sometimes and have the obstacle that to remove or to cross over; Cause on the bank steel case beam movement track to get on the right track and dock, therefore adopt mono-shipment mode, cause loading onto ship that difficulty is big, expense is high with ship.
Summary of the invention
The objective of the invention is to overcome above-mentioned deficiency, provide a kind of big member to roll dress and tie shipment method mutually with crane barge, this shipment method easy operating guarantees shipment safety, and can reduce executive cost.
According to technical scheme provided by the invention, a kind of big member rolls dress and ties shipment method mutually with crane barge, and step is:
(1) shipping is prepared: the beam ship is transported in special use rested on the harbour, be overlapped with trestle on the harbour, harbour the place ahead is provided with and puts pier, and makes stern rest preceding the putting on the pier of harbour; Get big member, be transported to harbour, and carry out the inspection before the shipping with two iant flat trucks;
(2) roll-on-roll-off ship oceangoing ship and crane barge are in place: select suitable tidal level, boats and ships are when the tidal level of 2 ~ 3m, and the deck is concordant with harbour; The beam section is gone on board and must carried out at the incoming tide, and to require at duration of tide be 40 ~ 60min, so that iant flat truck is gone on board smoothly and gone ashore;
By the location of casting anchor, the position that designs in advance; On the horizontal direction of along the coastline, on special use fortune beam ship, arrange two parallel overlap joint platforms, and between the overlap joint platform, lay two rows track parallel to each other;
(3) member rolls and takes on board: the special-purpose iant flat truck that loads big member rolls through track and takes on board, and in rolling process of assembling, through the cabin water of the special-purpose fortune of row pressure beam ship, makes special-purpose fortune beam ship keep concordant with harbour;
(4) crane barge: carrier rests in raises boat landing; Iant flat truck rolls and is filled to special-purpose fortune beam ship, and rolling dress length is 50 ~ 60m, should try one's best and lean on forward, makes casing near operator's compartment; With the crane barge lifting, slowly move to carrier harbour the place ahead, bold and generous, the colligation of steel bushing case; Be transported on the special-purpose fortune beam ship, hang send finish after, special-purpose fortune beam ship withdraws from harbour, carrier drives harbour into, member is bold and generous, colligation is fixed.
The present invention has following advantage: big member safety and steady ground is bold and generous to carrier, and easy operating guarantees shipment safety, and can reduce executive cost; Existing harbour, boats and ships, crane barge have been made full use of.
Description of drawings
Fig. 1 the present invention transports the preparation front view.
Fig. 2 the present invention transports diagrammatic top view.
The specific embodiment
1 one kinds of big members of embodiment roll dress and tie shipment method mutually with crane barge, and step is:
(1) shipping is prepared: the beam ship is transported in special use rested on the harbour 3, be overlapped with trestle 2 on the harbour 3, harbour 3 the place aheads are provided with and put pier 1, and make stern rest harbour 3 preceding putting on the pier 1; Get big member, be transported to harbour 3, and carry out the inspection before the shipping with two iant flat trucks;
(2) roll-on-roll-off ship oceangoing ship and crane barge are in place: select suitable tidal level, boats and ships are when the tidal level of 2m, and the deck is concordant with harbour; The beam section is gone on board and must carried out at the incoming tide, and to require at duration of tide be 40min, so that iant flat truck is gone on board smoothly and gone ashore;
By the location of casting anchor, the position that designs in advance; On the horizontal direction of along the coastline, on special use fortune beam ship, arrange two parallel overlap joint platforms, and between the overlap joint platform, lay two rows track parallel to each other;
(3) member rolls and takes on board: the special-purpose iant flat truck that loads big member rolls through track and takes on board, and in rolling process of assembling, through the cabin water of the special-purpose fortune of row pressure beam ship, makes special-purpose fortune beam ship keep concordant with harbour;
(4) crane barge: carrier rests in raises boat landing; Iant flat truck rolls and is filled to special-purpose fortune beam ship, and rolling dress length is 50m, should try one's best and lean on forward, makes casing near operator's compartment; With the crane barge lifting, slowly move to carrier harbour the place ahead, bold and generous, the colligation of steel bushing case; Be transported on the special-purpose fortune beam ship, hang send finish after, special-purpose fortune beam ship withdraws from harbour, carrier drives harbour into, member is bold and generous, colligation is fixed.
2 one kinds of big members of embodiment roll dress and tie shipment method mutually with crane barge, and step is:
(1) shipping is prepared: the beam ship is transported in special use rested on the harbour 3, be overlapped with trestle 2 on the harbour 3, harbour 3 the place aheads are provided with and put pier 1, and make stern rest harbour 3 preceding putting on the pier 1; Get big member, be transported to harbour 3, and carry out the inspection before the shipping with two iant flat trucks;
(2) roll-on-roll-off ship oceangoing ship and crane barge are in place: select suitable tidal level, boats and ships are when the tidal level of 3m, and the deck is concordant with harbour; The beam section is gone on board and must carried out at the incoming tide, and to require at duration of tide be 60min, so that iant flat truck is gone on board smoothly and gone ashore;
By the location of casting anchor, the position that designs in advance; On the horizontal direction of along the coastline, on special use fortune beam ship, arrange two parallel overlap joint platforms, and between the overlap joint platform, lay two rows track parallel to each other;
(3) member rolls and takes on board: the special-purpose iant flat truck that loads big member rolls through track and takes on board, and in rolling process of assembling, through the cabin water of the special-purpose fortune of row pressure beam ship, makes special-purpose fortune beam ship keep concordant with harbour;
(4) crane barge: carrier rests in raises boat landing; Iant flat truck rolls and is filled to special-purpose fortune beam ship, and rolling dress length is 60m, should try one's best and lean on forward, makes casing near operator's compartment; With the crane barge lifting, slowly move to carrier harbour the place ahead, bold and generous, the colligation of steel bushing case; Be transported on the special-purpose fortune beam ship, hang send finish after, special-purpose fortune beam ship withdraws from harbour, carrier drives harbour into, member is bold and generous, colligation is fixed.
3 one kinds of big members of embodiment roll dress and tie shipment method mutually with crane barge, and step is:
(1) shipping is prepared: the beam ship is transported in special use rested on the harbour 3, be overlapped with trestle 2 on the harbour 3, harbour 3 the place aheads are provided with and put pier 1, and make stern rest harbour 3 preceding putting on the pier 1; Get big member, be transported to harbour 3, and carry out the inspection before the shipping with two iant flat trucks;
(2) roll-on-roll-off ship oceangoing ship and crane barge are in place: select suitable tidal level, boats and ships are when the tidal level of 2.63m, and the deck is concordant with harbour; The beam section is gone on board and must carried out at the incoming tide, and to require at duration of tide be 45min, so that iant flat truck is gone on board smoothly and gone ashore;
By the location of casting anchor, the position that designs in advance; On the horizontal direction of along the coastline, on special use fortune beam ship, arrange two parallel overlap joint platforms, and between the overlap joint platform, lay two rows track parallel to each other;
(3) member rolls and takes on board: the special-purpose iant flat truck that loads big member rolls through track and takes on board, and in rolling process of assembling, through the cabin water of the special-purpose fortune of row pressure beam ship, makes special-purpose fortune beam ship keep concordant with harbour;
(4) crane barge: carrier rests in raises boat landing; Iant flat truck rolls and is filled to special-purpose fortune beam ship, and rolling dress length is 55m, should try one's best and lean on forward, makes casing near operator's compartment; With the crane barge lifting, slowly move to carrier harbour the place ahead, bold and generous, the colligation of steel bushing case; Be transported on the special-purpose fortune beam ship, hang send finish after, special-purpose fortune beam ship withdraws from harbour, carrier drives harbour into, member is bold and generous, colligation is fixed.

Claims (1)

1. a big member rolls dress and ties shipment method mutually with crane barge, it is characterized in that: adopt following steps:
(1) shipping is prepared: the beam ship is transported in special use rested on the harbour (3), be overlapped with trestle (2) on the harbour (3), harbour (3) the place ahead is provided with and puts pier (1), and makes stern rest preceding the putting on the pier (1) of harbour (3); Get big member, be transported to harbour (3), and carry out the inspection before the shipping with two iant flat trucks;
(2) roll-on-roll-off ship oceangoing ship and crane barge are in place: select suitable tidal level, boats and ships are when the tidal level of 2~3m, and the deck is concordant with harbour; The beam section is gone on board and must carried out at the incoming tide, and to require at duration of tide be 40~60min, so that iant flat truck is gone on board smoothly and gone ashore;
(3) by the location of casting anchor, the position that designs in advance; On the horizontal direction of along the coastline, on special use fortune beam ship, arrange two parallel overlap joint platforms, and between the overlap joint platform, lay two rows track parallel to each other;
(4) member rolls and takes on board: the special-purpose iant flat truck that loads big member rolls through track and takes on board, and in rolling process of assembling, through the cabin water of the special-purpose fortune of row pressure beam ship, makes special-purpose fortune beam ship keep concordant with harbour;
(5) crane barge: carrier rests in raises boat landing; Iant flat truck rolls and is filled to special-purpose fortune beam ship, and rolling dress length is 50~60m, should try one's best and lean on forward, makes casing near operator's compartment; With the crane barge lifting, slowly move to carrier harbour the place ahead, bold and generous, the colligation of steel bushing case; Be transported on the special-purpose fortune beam ship, hang send finish after, special-purpose fortune beam ship withdraws from harbour, carrier drives harbour into, member is bold and generous, colligation is fixed.
CN201210365081.6A 2012-09-26 2012-09-26 Shipment method combining large constructional element rolling and floating crane Expired - Fee Related CN102837978B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210365081.6A CN102837978B (en) 2012-09-26 2012-09-26 Shipment method combining large constructional element rolling and floating crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210365081.6A CN102837978B (en) 2012-09-26 2012-09-26 Shipment method combining large constructional element rolling and floating crane

Publications (2)

Publication Number Publication Date
CN102837978A true CN102837978A (en) 2012-12-26
CN102837978B CN102837978B (en) 2014-12-24

Family

ID=47365753

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210365081.6A Expired - Fee Related CN102837978B (en) 2012-09-26 2012-09-26 Shipment method combining large constructional element rolling and floating crane

Country Status (1)

Country Link
CN (1) CN102837978B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106275287A (en) * 2016-09-05 2017-01-04 江苏中铁山桥重工有限公司 A kind of large-scale truss whole sections shipment method
CN107628201A (en) * 2017-08-25 2018-01-26 中国海洋石油总公司 The technics of shipment of large-sized deep water piling bar

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2615042Y (en) * 2003-04-25 2004-05-12 中铁大桥局集团有限公司 Special crane ship for transporting & erecting bridges on sea
KR20090022045A (en) * 2007-08-29 2009-03-04 에스티엑스조선주식회사 Method to load big size block to floating dock and rendezvous on the sea for erection using the same
CN101774422A (en) * 2009-12-30 2010-07-14 天津市海王星海上工程技术有限公司 Novel offshore installation construction resource-combined type pontoon barge

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2615042Y (en) * 2003-04-25 2004-05-12 中铁大桥局集团有限公司 Special crane ship for transporting & erecting bridges on sea
KR20090022045A (en) * 2007-08-29 2009-03-04 에스티엑스조선주식회사 Method to load big size block to floating dock and rendezvous on the sea for erection using the same
CN101774422A (en) * 2009-12-30 2010-07-14 天津市海王星海上工程技术有限公司 Novel offshore installation construction resource-combined type pontoon barge

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宿有为: "崇启大桥大节段滚装上船技术研究", 《2011全国钢结构学术年会论文集》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106275287A (en) * 2016-09-05 2017-01-04 江苏中铁山桥重工有限公司 A kind of large-scale truss whole sections shipment method
CN107628201A (en) * 2017-08-25 2018-01-26 中国海洋石油总公司 The technics of shipment of large-sized deep water piling bar

Also Published As

Publication number Publication date
CN102837978B (en) 2014-12-24

Similar Documents

Publication Publication Date Title
CN102556691B (en) Roll-on/roll-off shipping method for long large steel box girder segment across obstacles
US6802684B2 (en) Container tranfer terminal system and method
CN102337736B (en) Installation process of upper module on offshore oil platform
CN203866772U (en) Multipurpose shipping dock capable of being adapted to tidal level change
CN101597896B (en) Method for building riprap levee island wall of offshore artificial island by large box barge
CN207045637U (en) A kind of floating ship terminals
CN102660923A (en) Assembly construction process of prefabricated 40m T-beam in intertidal zone of open sea
CN206288202U (en) LNG tank formula container loading and unloading ship
CN107856819A (en) Floating shipyard and floating type warship maintenance and method of construction
CN101941510A (en) Method for improving ship handling efficiency of containers (or bulk cargo) and equipment thereof
CN115893042A (en) Method for sliding wind power pipe pile onto ship
CN101781887A (en) Overhang installation method for upper structure of offshore platform
CN102837978B (en) Shipment method combining large constructional element rolling and floating crane
CN104060592B (en) Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles
CN103640909B (en) Large component roll-roll shipment
CN208882038U (en) Semi-submersible type loads and unloads ship
CN202642027U (en) Floating fitting-out device
CN204979163U (en) A overhang slope multilane rolls adorns landing stage for inland river
CN201587808U (en) Track system for moving ship unloaders
KR101166718B1 (en) Stabilized Container Crane With Improved Legs
CA3224947A1 (en) Method for preparing an integrated production complex on a gravity-based structure (gbs)
WO2015136086A1 (en) A quay structure, a quay arrangement and a method of installing such structure
CN214001992U (en) Self-propelled transportation flat top barge with excavator
CN105926466A (en) Device and construction method for steel truss bridge integral transporting
CN207228045U (en) All-weather wharf structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170929

Address after: 214521 Jiangsu city of Wuxi province Jingjiang Jiangyin economic development zone with Kang Road No. 15

Patentee after: Jiangsu xinzhongtai Bridge Steel Structure Engineering Co. Ltd.

Address before: 214521 Jiangsu city of Taizhou province Jingjiang city Jingjiang park with Kang Road No. 15

Patentee before: Jiangsu Zhongtai Bridge Steel Structure Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141224

Termination date: 20180926