- CN102814485A CN102814485A CN2012102784870A CN201210278487A CN102814485A CN 102814485 A CN102814485 A CN 102814485A CN 2012102784870 A CN2012102784870 A CN 2012102784870A CN 201210278487 A CN201210278487 A CN 201210278487A CN 102814485 A CN102814485 A CN 102814485A
- Authority
- CN
- China
- Prior art keywords
- mould
- molten steel
- steel
- circular
- make
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The invention discloses an anchor ring manufacturing method which is characterized by consisting of the following steps that (a) waste steel is heated to 1700DEG C until that the steel is fully molten; (b) metal element ingredients are additionally arranged in the molten steel by a certain ratio; (c) the molten steel is poured into a mould, the molten steel is initially extruded after being cooled down to 1100DEG C and cold set, so that the tissue of the molten steel is changed; (d) an inner hole is extruded after a blank is fully cooled, so that the whole blank is hardened and formed; and (e) surface treatment and sand blast for oxidation treatment are carried out. The invention provides the improved anchor ring manufacturing method, so that a traditional process is changed without round steel or heat treatment, procedures are reduced and the cost is reduced. Meanwhile, the invention has the advantages of waste utilization and good mechanical properties.
Description
Technical field
The invention belongs to anchor circle manufacture field, specifically is a kind of to anchor circle preparation method and processing mold.
Background technology
The anchor circle belongs to bridge member prestressing force product; Such as positive 9 hole circle anchor circle materials is 45 steel or 40Cr steel; Use amount is big; 9 hole circle anchor circle conventional production process are that machined is shaped, and production process is: blanking → face work, cylindrical → brill straight hole (hinge taper hole) → modified → hinge taper hole → check → zinc-plated → warehouse-in.Many and the dense distribution owing to the hole, the lost time of holing, ream is more, and cutter consumption is big, and cost is higher, and the making of anchor circle is very loaded down with trivial details, expense is high, so need improve so this method of use is carried out.
Summary of the invention
The objective of the invention is to overcome above-mentioned defective provides a kind of anchor circle processing and fabricating method of being convenient to operate at this, utilizes that refuse, operation reduce, production cost is low.
The present invention is achieved in that a kind of anchor circle preparation method of structure, it is characterized in that: may further comprise the steps:
A, be heated to 1600-1700 ℃ to steel scrap it is melted fully;
B, fusing molten steel add the metallic element batching in the 0.1-0.2% ratio;
C, molten steel is poured in the mould, treated that molten steel cools to 1000-1100 ℃ of condensation carry out just squeezing after solid, make it change its tissue and size;
D, treat to push endoporus again after blank cools off fully, make its whole hardened forming;
E, it is carried out surface treatment, surface sand-blasting carries out oxidation processes.
According to a kind of anchor circle preparation method according to the invention, it is characterized in that: zinc-plated again as protective layer after surface sand-blasting is carried out oxidation processes.
According to a kind of anchor circle preparation method according to the invention, it is characterized in that: institute adds metallic element batching for violent, silicon etc.
A kind of mould of realizing said method is characterized in that: mould is provided with a circular pedestal, fixedly is formed with a plurality of circular pillars in this circle pedestal.
According to a kind of mould of the present invention, it is characterized in that: be fixed with 4 said circular pillars in the circular pedestal
According to a kind of mould of the present invention, it is characterized in that: be fixed with 9 said circular pillars in the circular pedestal.
The invention has the beneficial effects as follows: the present invention provides an Artenkreis processing and fabricating method through improvement, without heat treatment, changes conventional machining process without round steel, saves cost, operation reduction.Advantage such as twice laid simultaneously,, mechanical property are good.
Description of drawings
Fig. 1 is a schematic flow sheet of the present invention.
Fig. 2 is mould embodiment 1 structural representation according to the invention.
Fig. 3 is mould embodiment 2 structural representations according to the invention.
Fig. 4 is 4 hole anchor circle sketch mapes.
Among the figure: 101, circular pedestal, 102, circular pillar.
The specific embodiment
Below in conjunction with accompanying drawing the present invention is made detailed description:
Embodiment 1: a kind of anchor circle preparation method specifically comprises:
A, be heated to 1700 ℃ to steel scrap it is melted fully;
B, fusing molten steel add metallic element manganese in 0.1% ratio;
C, molten steel is poured in the mould, treated that molten steel cools to 1100 ℃ condensation carries out just squeezing after solid, make it change its tissue;
D, treat to push endoporus again after blank cools off fully, make its whole hardened forming;
E, it is carried out surface treatment, surface sand-blasting carries out oxidation processes.
Embodiment 2: a kind of anchor circle preparation method specifically comprises:
A, be heated to 1600 ℃ to steel scrap it is melted fully;
B, fusing molten steel add metallic element manganese in 0.2% ratio;
C, molten steel is poured in the mould, treated that molten steel cools to 1000 ℃ condensation carries out just squeezing after solid, make it change its tissue;
D, treat to push endoporus again after molten steel cools off fully, make its whole hardened forming;
E, it is carried out surface treatment, surface sand-blasting carries out oxidation processes;
F, zinc-plated again as protective layer after surface sand-blasting is carried out oxidation processes, only zinc-plated, in other words not zinc-plated at the endoporus of workpiece (moulding anchor circle) at said workpiece outer surface.
Embodiment 3: a kind of anchor circle preparation method specifically comprises:
A, be heated to 1650 ℃ to steel scrap it is melted fully;
B, fusing molten steel add metallic element silicon in 0.2% ratio;
C, molten steel is poured in the mould, treated that molten steel cools to 1050 ℃ condensation carries out just squeezing after solid, make it change its tissue;
D, treat to push endoporus again after blank cools off fully, make its whole hardened forming;
E, it is carried out surface treatment, surface sand-blasting carries out oxidation processes.
Embodiment 4: a kind of anchor circle preparation method specifically comprises:
A, be heated to 1700 ℃ to steel scrap it is melted fully;
B, fusing molten steel add metallic element silicon in 0.1% ratio;
C, molten steel is poured in the mould, treated that molten steel cools to 1100 ℃ condensation carries out just squeezing after solid, make it change its tissue;
D, treat to push endoporus again after molten steel cools off fully, make its whole hardened forming;
E, it is carried out surface treatment, surface sand-blasting carries out oxidation processes;
F, zinc-plated again as protective layer after surface sand-blasting is carried out oxidation processes, only zinc-plated, in other words not zinc-plated at the endoporus of workpiece (moulding anchor circle) at said workpiece outer surface.
At this a kind of mould of realizing said method is provided, mould is provided with a circular pedestal 101, fixedly is formed with a plurality of circular pillars 102 in this circle pedestal 101.
A kind of embodiment of mould is fixed with 4 said circular pillars 102 in the said circular pedestal 101.
The another kind of embodiment of mould is fixed with 9 said circular pillars 102 in the circular pedestal 101.
Claims (6)
1. anchor circle preparation method is characterized in that: may further comprise the steps:
A, be heated to 1600-1700 ℃ to steel scrap and make its fusing;
B, fusing molten steel are by middle adding metallic element batching;
C, molten steel is poured in the mould, treated that molten steel cools to 1000-1100 ℃ of condensation carry out just squeezing after solid, make it change its tissue and size;
D, treat to push endoporus again after blank cools off fully, make its whole hardened forming;
E, it is carried out surface treatment, surface sand-blasting carries out oxidation processes.
2. according to the said a kind of anchor circle preparation method of claim 1, it is characterized in that: zinc-plated again as protective layer after surface sand-blasting is carried out oxidation processes.
3. according to the said a kind of anchor circle preparation method of claim 1, it is characterized in that: institute adds metallic element batching for violent, silicon etc.
4. mould of realizing the said method of claim 1, it is characterized in that: mould is provided with a circular pedestal (101), fixedly is formed with a plurality of circular pillars (102) in this circle pedestal (101).
5. a kind of mould according to claim 4 is characterized in that: be fixed with 4 said circular pillars (102) in the circular pedestal (101).
6. a kind of mould according to claim 4 is characterized in that: be fixed with 9 said circular pillars (102) in the circular pedestal (101).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210278487.0A CN102814485B (en) | 2012-08-07 | 2012-08-07 | A kind of anchor circle preparation method and mould |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210278487.0A CN102814485B (en) | 2012-08-07 | 2012-08-07 | A kind of anchor circle preparation method and mould |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102814485A true CN102814485A (en) | 2012-12-12 |
CN102814485B CN102814485B (en) | 2015-08-26 |
Family
ID=47299131
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210278487.0A Active CN102814485B (en) | 2012-08-07 | 2012-08-07 | A kind of anchor circle preparation method and mould |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102814485B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1613599A (en) * | 2004-11-26 | 2005-05-11 | 刘志文 | Casting and rolling machining process for circular steel structure |
CN1864915A (en) * | 2006-06-13 | 2006-11-22 | 中北大学 | A labor-saving automobile hub forming method and device |
EP1927415A1 (en) * | 2006-12-01 | 2008-06-04 | Sintokogio, Ltd. | Casting process, upeer mold assembly and method of securing core to upper mold |
CN101435205A (en) * | 2007-11-14 | 2009-05-20 | 陈志成 | Hole cap and manufacturing method thereof |
CN202114223U (en) * | 2011-06-11 | 2012-01-18 | 芜湖奥凯金属科技有限公司 | Special die for casting aluminum barrels |
-
2012
- 2012-08-07 CN CN201210278487.0A patent/CN102814485B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1613599A (en) * | 2004-11-26 | 2005-05-11 | 刘志文 | Casting and rolling machining process for circular steel structure |
CN1864915A (en) * | 2006-06-13 | 2006-11-22 | 中北大学 | A labor-saving automobile hub forming method and device |
EP1927415A1 (en) * | 2006-12-01 | 2008-06-04 | Sintokogio, Ltd. | Casting process, upeer mold assembly and method of securing core to upper mold |
CN101435205A (en) * | 2007-11-14 | 2009-05-20 | 陈志成 | Hole cap and manufacturing method thereof |
CN202114223U (en) * | 2011-06-11 | 2012-01-18 | 芜湖奥凯金属科技有限公司 | Special die for casting aluminum barrels |
Also Published As
Publication number | Publication date |
---|---|
CN102814485B (en) | 2015-08-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102699635B (en) | Liquid die-forging and rolling composite forming method for bearing ring piece | |
CN101804450B (en) | 20/321H corrosion-resisting double-metal composite tube and manufacturing process thereof | |
CN204583887U (en) | A kind of reciprocating extrusion device preparing block body ultrafine grain metal material | |
CN103624502A (en) | Cold-forging plastic molding technology of brake piston | |
CN103100829A (en) | Preparation method for cold rolls of super hardness wide width light gauge aluminum foils | |
CN104959564A (en) | Method for manufacturing bimetallic seamless plastic insert casting piece | |
CN104907452A (en) | Extrusion manufacturing method of high-pressure air bottle and opening shrinkage mold used in method | |
CN104690514A (en) | Process for manufacturing tube plate by using hollow steel ingot | |
CN102909527B (en) | The technological process of progressive forming is rolled in the casting of 42CrMo steel loop part | |
CN102814485A (en) | Anchor ring manufacturing method and mould | |
CN102773485B (en) | Method for manufacturing check valve core by powder metallurgy | |
CN103659161A (en) | Forming process of conical roller bearing inner ring large flange groove | |
CN102962293B (en) | A kind of pipe die manufacture method using steel ingot big diameter-reducing formation blank | |
CN102615473A (en) | Manufacturing method of vacuum machine screw rotor | |
CN205362520U (en) | Steel ball multistation forming die for bearing | |
CN103750607A (en) | Gold jewelry and processing method thereof | |
CN203863025U (en) | Rocking-rolling mold for making iron-copper dual-metal sealing nut | |
CN102689155A (en) | Liquid die forging and rolling compound formation method for aluminum alloy irregular-section large ring piece | |
CN201848503U (en) | Blade guide frame casting forming die | |
CN106670364A (en) | Variable-section thin-wall stainless steel hemisphere seal forming method | |
CN201482894U (en) | Novel combined type rolling roller | |
CN104227362A (en) | Manufacturing method of clutch shaft | |
CN201889849U (en) | Ultra-wear-resisting core bar of brick-making machine | |
CN102699634B (en) | Mould steel different cross section large ring liquid forging Rolling compund manufacturing process | |
CN215508367U (en) | Wire drawing die |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |