CN102756218A - Benzene hydrogenation engineering heat resistant steel pipeline welding method - Google Patents

Benzene hydrogenation engineering heat resistant steel pipeline welding method Download PDF

Info

Publication number
CN102756218A
CN102756218A CN2011101064327A CN201110106432A CN102756218A CN 102756218 A CN102756218 A CN 102756218A CN 2011101064327 A CN2011101064327 A CN 2011101064327A CN 201110106432 A CN201110106432 A CN 201110106432A CN 102756218 A CN102756218 A CN 102756218A
Authority
CN
China
Prior art keywords
welding
weld
benzene hydrogenation
resisting steel
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011101064327A
Other languages
Chinese (zh)
Other versions
CN102756218B (en
Inventor
廖兴银
陈和平
寇大伟
冯娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201110106432.7A priority Critical patent/CN102756218B/en
Publication of CN102756218A publication Critical patent/CN102756218A/en
Application granted granted Critical
Publication of CN102756218B publication Critical patent/CN102756218B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a benzene hydrogenation engineering heat resistant steel pipeline welding method. By using a TIG pulsating welder, a pearlite heat resistant steel with a band number of 12 Cr2Mo is welded through manual argon tungsten-arc welding; the supply state of the heat resistant steel is that the heat resistant steel is annealed at 730-750 DEG C; and the welding method is characterized by comprising the following steps: (a) pipe section cutting and groove preparation, (b) providing an argon shield device, (c) preheating before welding, (d) welding and (e) heat treatment after welding. The benzene hydrogenation engineering heat resistant steel pipeline welding method provided by the invention has the advantages of reasonable construction step design, simplicity in operation and safe and reliable welding quality, and the engineering construction cost is reduced.

Description

Benzene hydrogenation engineering heat resisting steel pipeline welding method
Technical field
The present invention relates to a kind of method for welding pipeline, specifically, is a kind of benzene hydrogenation engineering heat resisting steel pipeline welding method.
Background technology
The technology of benzene hydrogenation device is more special, its system complex, and equipment is many, and the pressure of system own, temperature are higher, and pumping unit does not allow idle running.The benzene hydrogenation engineering mainly is divided into the affiliated facility of central control room and electric substation, refining plant, water supply and sewage work, air compression station, storage and handling facility (tank field and pump house), the power supply of full factory and the illumination of full factory, torch and engineering; Lightning protection, fire prevention, explosion-proof specific (special) requirements are arranged in the electric installation of these facilities; Wherein benzene hydrogenation engineering process medium pipeline is and carries high temperature, high pressure, inflammable, explosive medium; Whole special material pipeline construction technology quality standard is high; Require sternly, the welding of benzene hydrogenation engineering heat resisting steel pipeline is the important component part of whole engineering.At present domesticly built or still be in the stage lack of standardization building, existed much not science, irrational place, manufacturing process is numerous and diverse, manufacturing cost is high.
Therefore known benzene hydrogenation engineering heat resisting steel pipeline welding exists above-mentioned all inconvenience and problem.
Summary of the invention
The object of the invention is to propose a kind of safe and reliable benzene hydrogenation engineering heat resisting steel pipeline welding method.
For realizing above-mentioned purpose, technical solution of the present invention is:
A kind of benzene hydrogenation engineering heat resisting steel pipeline welding method, with GTAW welding 12Cr2Mo trade mark pearlite heatproof steel, the supply of material state of said heat resisting steel is 730~750 ℃ of tempering, it is characterized in that may further comprise the steps with the TIG pulsating welder:
A, pipeline section cutting and groove processing
Adopt plasma arc or flame cutting pipeline section, and notch portion leaves machine-finish allowance, so that remove quench-hardened case and over-heat metal;
B, argon protective device is provided
Expand in the adopting protective device of applying argon gas in the centering rubber seal ring perhaps adopts on the flange protective device of local applying argon gas in the blind plate and pipe;
C, weld preheating
Adopt oxy-acetylene flame local heat preheating method, the width of preheating is the center with the weld seam, and every hem width degree is 3 times of pipeline wall thickness, and is not less than 100mm; During duct wall thickness >=6mm, preheat temperature is 250~350oC, adopts the TIG bottoming, can reduce the 50oC preheating by lower limit; Less than 60mm, wall thickness is less than the pipe of 6mm for external diameter, and when adopting TIG, preheat temperature is 50~100oC;
D, welding comprise the following step:
(1) preweld cleaning: adopt steel wire emery wheel or wire brush that groove and nearly seam district 30mm both side surface dirt are removed to pipe joint, keep the argon protective device cleaning;
(2) the weld bond assembling is not taked to force the counterpart tack welding, avoids the residual stress of toe of the weld;
(3) the disposable welding of per pass weld bond finishes, and carries out the interlayer cleaning before the second layer welding; The second layer welding point 20~30mm that will stagger keeps interlayer temperature to be not less than preheat temperature in the welding process; The thickness of every layer of deposited metal is 3mm during multi-pass welding;
When (4) under low temperature environment, carrying out the argon arc welding welding, need welding protection gas is adjusted to more than 15 seconds lag time, must not weld one and finish to move at once welding gun;
E, post weld heat treatment
(1) after welding job stops, carrying out post weld heat treatment immediately; If can not carry out post weld heat treatment immediately, carry out after heat, the width when its width of heating is not less than preheating; Wherein:, adopt the pipe welding port of full argon arc welding and weld preheating and postweld heat preservation measure can not do post weld heat treatment to the pipeline of 45 * 4mm; 108 * 5mm and 159 * 6mm pipeline will be done post weld heat treatment;
(2) pearlite heatproof steel post weld heat treatment temperature is 715 ℃;
(3) the post weld heat treatment temperature of weld bond is 715 ± 15 ℃;
When (4) welding point is heat-treated,, be heated to the dangerous temperature district and will be rapidly heated after more than 500 ℃, avoid in the dangerous temperature district temperature retention time long as far as possible in slowly heating below 500 ℃;
(5) when temperature drops to 300 ℃, directly air cooling.
Benzene hydrogenation engineering heat resisting steel pipeline welding method of the present invention can also adopt following technical measures further to realize.
Aforesaid method, among the wherein said step a, the diameter of welding pipeline section is 32~273mm, and pipe thickness is 3mm~7mm.
Aforesaid method, among the wherein said step a, the above pipe joint of the pipe thickness 3mm of pipeline section adopts machined finished edge, α=30+5 °, p=0, b=2.0mm~2.4mm.
Aforesaid method, among the wherein said step a, the above arm pipe joint of the pipe thickness 3mm of pipeline section adopts machined finished edge, α=45+5 °, p=0, b=2.0mm~2.4mm.
Aforesaid method, in the wherein said steps d, the TIG welding parameter of pearlite heatproof steel is during welding:
Figure 415707DEST_PATH_IMAGE002
Aforesaid method in the wherein said steps d, is used purity >=99.99% argon gas, to prevent the pollution of gaseous impurity to welding region during welding.
Aforesaid method in the wherein said steps d, is led to argon gas a period of time before the weldering in advance, on the heat-resisting steel sheet and plate testpieces, carries out test weld, and adjustment welding gun argon flow amount.
Aforesaid method, in the wherein said steps d, the welding wire termination can not break away from the arc protection zone in the welding process, and the phenomenon of finding welding wire termination aerobicization cuts off immediately and could continue to weld.
Aforesaid method, in the wherein said steps d, welding current is got the lower limit of applicable norm in the welding process, reduces the scope of welding heat affected zone as far as possible.
Aforesaid method, in the wherein said steps d, hysteresis gas transferred to more than 15 seconds in the welding process, must not weld an end, moved welding gun at once.
Aforesaid method, wherein said steps d in (2), must not impact with iron hammer on the pipe test specimen in the assembling tack welding process.
Aforesaid method, wherein said step e, in (3), the post weld heat treatment programming rate is: 6250/ δ, unit ℃/h, δ is a pipe thickness; Temperature retention time: 0.75h; Cooling rate is: 6250/ δ, δ are pipe thickness, unit ℃/h.
After adopting technique scheme, benzene hydrogenation engineering heat resisting steel pipeline welding method of the present invention has the following advantages:
1, construction procedure is reasonable in design, simple to operate;
2, welding quality is safe and reliable;
3, reduce the engineering construction cost.
Description of drawings
Fig. 1 is the tube and tube banjo fixing butt jointing divided edge structure sketch map of the embodiment of the invention;
Fig. 2 is the tube and tube banjo fixing butt jointing bevel angle sketch map of the embodiment of the invention;
Fig. 3 is the pipe and the bump joint bevel angle sketch map of the embodiment of the invention;
Fig. 4 is the interior protective device sketch map of the tube and tube banjo fixing butt jointing pipeline of the embodiment of the invention;
Fig. 5 is the pipe of the embodiment of the invention is connected weld bond with flange a protective device sketch map;
Fig. 6 is the post weld heat treatment curve map of the embodiment of the invention.
Among the figure: 1 rubber seal ring, 2 clamping plate, 3 joints, 4 air guide steel pipes, 5 argon gas air admission holes, 6 rubber gasket sheets, 7 blind plates.
The specific embodiment
Below further specify the present invention through specific embodiment and accompanying drawing thereof.
Embodiment 1
Benzene hydrogenation engineering heat resisting steel pipeline welding method of the present invention, with GTAW welding 12Cr2Mo trade mark pearlite heatproof steel, the supply of material state of said heat resisting steel is 730~750 ℃ of tempering, it is characterized in that may further comprise the steps with the TIG pulsating welder:
Fig. 1 is the tube and tube banjo fixing butt jointing divided edge structure sketch map of the embodiment of the invention, and Fig. 2 is the tube and tube banjo fixing butt jointing bevel angle sketch map of the embodiment of the invention, carries out the tube and tube banjo fixing butt jointing welding of heat resisting steel pipeline.
A, pipeline section cutting and groove processing
Adopt plasma arc or flame cutting pipeline section, and notch portion leaves machine-finish allowance, so that remove quench-hardened case and over-heat metal; The diameter of welding pipeline section is 32~273mm, and pipe thickness is 3mm~7mm; The above pipe joint of the pipe thickness 3mm of pipeline section adopts machined finished edge, α=30+5 °, p=0, b=2.0mm~2.4mm; The above arm pipe joint of the pipe thickness 3mm of pipeline section adopts machined finished edge, α=45+5 °, p=0, b=2.0mm~2.4mm.
B, argon protective device is provided
Fig. 4 is the interior protective device sketch map of the tube and tube banjo fixing butt jointing pipeline of the embodiment of the invention, the protective device of the interior applying argon gas of centering rubber seal ring that expands in adopting.
C, weld preheating
Weld preheating: consider site environment, preheating method adopts the oxy-acetylene flame local heat, and the width of preheating is the center with the weld seam, and every hem width degree is 3 times of pipeline wall thickness, and is not less than 100mm; During duct wall thickness >=6mm, preheat temperature is 250~350oC, according to the site operation situation, adopts the TIG bottoming, can reduce the 50oC preheating by lower limit; Less than 60mm, wall thickness is less than the pipe of 6mm for external diameter, and when adopting TIG, preheat temperature is 50~100oC;
D, welding comprise the following step:
(1) preweld cleaning: adopt steel wire emery wheel or wire brush that groove and nearly seam district 30mm both side surface dirt are removed to pipe joint, keep the argon protective device cleaning;
(2) the weld bond assembling does not take to force counterpart tack welding (being preferably free state), avoids the residual stress of toe of the weld;
(3) the disposable welding of per pass weld bond finishes, and carries out the interlayer cleaning before the second layer welding, and the second layer welding point 20~30mm that will stagger keeps interlayer temperature to be not less than preheat temperature in the welding process; The thickness of every layer of deposited metal is 3mm during multi-pass welding;
When (4) under low temperature environment, carrying out the argon arc welding welding, need welding protection gas is adjusted to more than 15 seconds lag time, must not weld an end, move welding gun at once;
The TIG of pearlite heatproof steel weldering standard parameter is during welding:
Figure 332847DEST_PATH_IMAGE004
Use purity >=99.99% argon gas during welding, to prevent the pollution of gaseous impurity to welding region; Lead to argon gas a period of time in advance before the weldering, on the heat-resisting steel sheet and plate testpieces, carry out test weld, and adjustment welding gun argon flow amount; The welding wire termination can not break away from the arc protection zone in the welding process, and the phenomenon of finding welding wire termination aerobicization cuts off immediately and could continue to weld; Welding current is got the lower limit of applicable norm in the welding process, reduces the scope of welding heat affected zone as far as possible; Hysteresis gas transferred to more than 15 seconds in the welding process, must not weld an end, moved welding gun at once; Must not on the pipe test specimen, impact in the assembling tack welding process with iron hammer.
E, post weld heat treatment
Fig. 6 is the post weld heat treatment curve map of the embodiment of the invention, and concrete heat treatment step is following:
(1) after welding job stops, carrying out post weld heat treatment immediately; If can not carry out post weld heat treatment immediately, carry out after heat, the width when its width of heating is not less than preheating; Wherein:,, can not do post weld heat treatment if adopt the pipe welding port of full argon arc welding and weld preheating and postweld heat preservation measure to the pipeline of 45 * 4mm; To 108 * 5mm and 159 * 6mm pipeline, do post weld heat treatment;
(2) pearlite heatproof steel post weld heat treatment temperature is 715 ℃;
(3) the post weld heat treatment temperature of weld bond is 715 ± 15 ℃, and intensification, insulation, cooling form are seen heat treatment cycle curve Fig. 6.The heat treatment programming rate is: 6250/ δ, and 6250/ δ, unit ℃/h, δ is a pipe thickness; Temperature retention time: 0.75h; Cooling rate is: 6250/ δ, δ are pipe thickness, unit ℃/h;
When (4) welding point is heat-treated,, be heated to the dangerous temperature district and will be rapidly heated after more than 500 ℃, avoid in the dangerous temperature district temperature retention time long as far as possible in slowly heating below 500 ℃;
(5) when temperature drops to 300 ℃, directly air cooling.
Embodiment 2
Fig. 3 is the pipe and the bump joint bevel angle sketch map of the embodiment of the invention, carries out the pipe and the welding of bump joint straddling type joint of heat resisting steel pipeline.Adopt plasma arc or machine cuts, bevel for welding and nearly seam district adopt mechanical means to remove the oxidation stain layer; The above arm pipe joint of pipe thickness 3mm adopts α=45+5 ° of machined finished edge, p=0, b=2.0~2.4mm.
Fig. 5 is the pipe of the embodiment of the invention is connected weld bond with flange a protective device sketch map, provides with bump joint and adopts on the flange protective device of local applying argon gas in the blind plate and pipe.Present embodiment other technologies characteristic is identical with embodiment 1.
Above embodiment only supplies to explain the present invention's usefulness, but not limitation of the present invention, the technical staff in relevant technologies field under the situation that does not break away from the spirit and scope of the present invention, can also make various conversion or variation.Therefore, all technical schemes that are equal to also should belong to category of the present invention, should be limited each claim.

Claims (12)

1. a benzene hydrogenation engineering heat resisting steel pipeline welding method is welded 12Cr2Mo trade mark pearlite heatproof steel with the TIG pulsating welder with GTAW, and the supply of material state of said heat resisting steel is 730~750 ℃ of tempering, it is characterized in that may further comprise the steps:
A, pipeline section cutting and groove processing
Adopt plasma arc or flame cutting pipeline section, and notch portion leaves machine-finish allowance, so that remove quench-hardened case and over-heat metal;
B, argon protective device is provided
Expand in the adopting protective device of applying argon gas in the centering rubber seal ring perhaps adopts on the flange protective device of local applying argon gas in the blind plate and pipe;
C, weld preheating
Adopt oxy-acetylene flame local heat preheating method, the width of preheating is the center with the weld seam, and every hem width degree is 3 times of pipeline wall thickness, and is not less than 100mm; During duct wall thickness >=6mm, preheat temperature is 250~350oC, adopts the TIG bottoming, can reduce the 50oC preheating by lower limit; Less than 60mm, wall thickness is less than the pipe of 6mm for external diameter, and when adopting TIG, preheat temperature is 50~100oC;
D, welding comprise the following step:
(1) preweld cleaning: adopt steel wire emery wheel or wire brush that groove and nearly seam district 30mm both side surface dirt are removed to pipe joint, keep the argon protective device cleaning;
(2) the weld bond assembling is not taked to force the counterpart tack welding, avoids the residual stress of toe of the weld;
(3) the disposable welding of per pass weld bond finishes, and carries out the interlayer cleaning before the second layer welding; The second layer welding point 20~30mm that will stagger keeps interlayer temperature to be not less than preheat temperature in the welding process; The thickness of every layer of deposited metal is 3mm during multi-pass welding;
When (4) under low temperature environment, carrying out the argon arc welding welding, need welding protection gas is adjusted to more than 15 seconds lag time, must not weld one and finish to move at once welding gun;
E, post weld heat treatment
(1) after welding job stops, carrying out post weld heat treatment immediately; If can not carry out post weld heat treatment immediately, carry out after heat, the width when its width of heating is not less than preheating; Wherein:, adopt the pipe welding port of full argon arc welding and weld preheating and postweld heat preservation measure can not do post weld heat treatment to the pipeline of 45 * 4mm; 108 * 5mm and 159 * 6mm pipeline will be done post weld heat treatment;
(2) pearlite heatproof steel post weld heat treatment temperature is 715 ℃;
(3) the post weld heat treatment temperature of weld bond is 715 ± 15 ℃;
When (4) welding point is heat-treated,, be heated to the dangerous temperature district and will be rapidly heated after more than 500 ℃, avoid in the dangerous temperature district temperature retention time long as far as possible in slowly heating below 500 ℃;
(5) when temperature drops to 300 ℃, directly air cooling.
2. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that, among the said step a, the diameter of welding pipeline section is 32~273mm, and pipe thickness is 3mm~7mm.
3. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that, among the said step a, the above pipe joint of the pipe thickness 3mm of pipeline section adopts machined finished edge, α=30+5 °, p=0, b=2.0mm~2.4mm.
4. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that, among the said step a, the above arm pipe joint of the pipe thickness 3mm of pipeline section adopts machined finished edge, α=45+5 °, p=0, b=2.0mm~2.4mm.
5. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that in the said steps d, the TIG welding parameter of pearlite heatproof steel is during welding:
Figure 2011101064327100001DEST_PATH_IMAGE001
6. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that, in the said steps d, uses purity >=99.99% argon gas during welding, to prevent the pollution of gaseous impurity to welding region.
7. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that, in the said steps d, leads to argon gas a period of time in advance before the weldering, on the heat-resisting steel sheet and plate testpieces, carries out test weld, and adjustment welding gun argon flow amount.
8. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that in the said steps d, the welding wire termination can not break away from the arc protection zone in the welding process, and the phenomenon of finding welding wire termination aerobicization cuts off immediately and could continue to weld.
9. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that in the said steps d, welding current is got the lower limit of applicable norm in the welding process, reduces the scope of welding heat affected zone as far as possible.
10. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that in the said steps d, hysteresis gas transferred to more than 15 seconds in the welding process, must not weld an end, moves welding gun at once.
11. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that, said steps d in (2), must not impact with iron hammer on the pipe test specimen in the assembling tack welding process.
12. benzene hydrogenation engineering heat resisting steel pipeline welding method as claimed in claim 1 is characterized in that, said step e, and in (3), the post weld heat treatment programming rate is: 6250/ δ, unit ℃/h, δ is a pipe thickness; Temperature retention time: 0.75h; Cooling rate is: 6250/ δ, δ are pipe thickness, unit ℃/h.
CN201110106432.7A 2011-04-27 2011-04-27 Benzene hydrogenation engineering heat resisting steel method for welding pipeline Active CN102756218B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110106432.7A CN102756218B (en) 2011-04-27 2011-04-27 Benzene hydrogenation engineering heat resisting steel method for welding pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110106432.7A CN102756218B (en) 2011-04-27 2011-04-27 Benzene hydrogenation engineering heat resisting steel method for welding pipeline

Publications (2)

Publication Number Publication Date
CN102756218A true CN102756218A (en) 2012-10-31
CN102756218B CN102756218B (en) 2016-01-27

Family

ID=47050992

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110106432.7A Active CN102756218B (en) 2011-04-27 2011-04-27 Benzene hydrogenation engineering heat resisting steel method for welding pipeline

Country Status (1)

Country Link
CN (1) CN102756218B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102962557A (en) * 2012-11-06 2013-03-13 哈尔滨汽轮机厂有限责任公司 Method for welding balancing air leakage pipe of medium-high pressure outer cylinder in turbine
CN103624378A (en) * 2013-12-02 2014-03-12 昆山华恒焊接股份有限公司 Pipeline butt joint hot wire TIG welding method
CN103990895A (en) * 2014-05-14 2014-08-20 攀钢集团攀枝花钢铁研究院有限公司 Welding method for high-strength seamless steel tube
CN104874937A (en) * 2015-06-15 2015-09-02 唐山师范学院 Welding technology for bainite heat-resistant steel 12Cr2MoWVTiB
CN105033415A (en) * 2015-07-09 2015-11-11 安徽金阳金属结构工程有限公司 15CrMo steel welding process
CN107009100A (en) * 2017-05-11 2017-08-04 山东电力建设第工程公司 A kind of new big footpath skew T preparation method
CN107214427A (en) * 2017-05-16 2017-09-29 合肥市瀚坤机械有限公司 One kind takes door frame welding procedure
CN107795721A (en) * 2017-10-27 2018-03-13 四川精控阀门制造有限公司 The valve rod neck inserting type welding structure and manufacture method of all-welded ball valve
CN107891216A (en) * 2017-11-14 2018-04-10 宝鸡中铁宝桥天元实业发展有限公司 High-strength steel thick plates stress concentration prevention method
CN108098204A (en) * 2017-12-29 2018-06-01 东方电气集团东方锅炉股份有限公司 Girth welding oxygen-proof protecting device and its header stack shell welding method
CN108817610A (en) * 2018-09-07 2018-11-16 中国能源建设集团安徽电力建设第工程有限公司 A kind of 12Cr1MoVG path Thick Wall Tube Welding method
CN110091030A (en) * 2019-05-24 2019-08-06 江苏格兰环境科技有限公司 The welding procedure of heating furnace pipeline steel alloy
CN111618400A (en) * 2020-03-13 2020-09-04 中国电建集团山东电力建设第一工程有限公司 Tower type photo-thermal power generation fused salt pipeline welding process in alpine region

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6478678A (en) * 1987-09-19 1989-03-24 Ishikawajima Harima Heavy Ind Welding method for austenitic heat resistant alloy tube
CN1814387A (en) * 2006-02-24 2006-08-09 中国有色金属工业第六冶金建设公司金属结构厂 12Cr1MoV alloy steel pipe welding method
CN1935438A (en) * 2006-06-09 2007-03-28 浙江省火电建设公司 P92 steel welding process
CN201394704Y (en) * 2009-05-09 2010-02-03 中国石油兰州石油化工公司 Argon-filling welding protective cover
CN101791746A (en) * 2010-03-29 2010-08-04 中冶实久建设有限公司 Large high-temperature refractory steel pipeline welding process
CN101850460A (en) * 2010-05-21 2010-10-06 中国石化集团第五建设公司 Welding process of 12Cr1MoV high-pressure pipeline CO2 semiautomatic or automatic gas shielded welding

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6478678A (en) * 1987-09-19 1989-03-24 Ishikawajima Harima Heavy Ind Welding method for austenitic heat resistant alloy tube
CN1814387A (en) * 2006-02-24 2006-08-09 中国有色金属工业第六冶金建设公司金属结构厂 12Cr1MoV alloy steel pipe welding method
CN1935438A (en) * 2006-06-09 2007-03-28 浙江省火电建设公司 P92 steel welding process
CN201394704Y (en) * 2009-05-09 2010-02-03 中国石油兰州石油化工公司 Argon-filling welding protective cover
CN101791746A (en) * 2010-03-29 2010-08-04 中冶实久建设有限公司 Large high-temperature refractory steel pipeline welding process
CN101850460A (en) * 2010-05-21 2010-10-06 中国石化集团第五建设公司 Welding process of 12Cr1MoV high-pressure pipeline CO2 semiautomatic or automatic gas shielded welding

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张建利 等: ""珠光体耐热钢12Cr1MoV的焊接实践", 《安装》, no. 7, 31 July 2006 (2006-07-31) *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102962557A (en) * 2012-11-06 2013-03-13 哈尔滨汽轮机厂有限责任公司 Method for welding balancing air leakage pipe of medium-high pressure outer cylinder in turbine
CN103624378A (en) * 2013-12-02 2014-03-12 昆山华恒焊接股份有限公司 Pipeline butt joint hot wire TIG welding method
CN103990895A (en) * 2014-05-14 2014-08-20 攀钢集团攀枝花钢铁研究院有限公司 Welding method for high-strength seamless steel tube
CN104874937A (en) * 2015-06-15 2015-09-02 唐山师范学院 Welding technology for bainite heat-resistant steel 12Cr2MoWVTiB
CN105033415A (en) * 2015-07-09 2015-11-11 安徽金阳金属结构工程有限公司 15CrMo steel welding process
CN107009100B (en) * 2017-05-11 2019-10-11 山东电力建设第一工程公司 A kind of novel major diameter skew T production method
CN107009100A (en) * 2017-05-11 2017-08-04 山东电力建设第工程公司 A kind of new big footpath skew T preparation method
CN107214427A (en) * 2017-05-16 2017-09-29 合肥市瀚坤机械有限公司 One kind takes door frame welding procedure
CN107795721A (en) * 2017-10-27 2018-03-13 四川精控阀门制造有限公司 The valve rod neck inserting type welding structure and manufacture method of all-welded ball valve
CN107891216A (en) * 2017-11-14 2018-04-10 宝鸡中铁宝桥天元实业发展有限公司 High-strength steel thick plates stress concentration prevention method
CN108098204A (en) * 2017-12-29 2018-06-01 东方电气集团东方锅炉股份有限公司 Girth welding oxygen-proof protecting device and its header stack shell welding method
CN108817610A (en) * 2018-09-07 2018-11-16 中国能源建设集团安徽电力建设第工程有限公司 A kind of 12Cr1MoVG path Thick Wall Tube Welding method
CN110091030A (en) * 2019-05-24 2019-08-06 江苏格兰环境科技有限公司 The welding procedure of heating furnace pipeline steel alloy
CN111618400A (en) * 2020-03-13 2020-09-04 中国电建集团山东电力建设第一工程有限公司 Tower type photo-thermal power generation fused salt pipeline welding process in alpine region
CN111618400B (en) * 2020-03-13 2022-02-11 中国电建集团山东电力建设第一工程有限公司 Tower type photo-thermal power generation fused salt pipeline welding process in alpine region

Also Published As

Publication number Publication date
CN102756218B (en) 2016-01-27

Similar Documents

Publication Publication Date Title
CN102756218A (en) Benzene hydrogenation engineering heat resistant steel pipeline welding method
CN102756199A (en) Welding method for stainless steel pipeline in benzene hydrogenation engineering
CN104416292A (en) Gas pressure welding procedure for reinforcing steel bar
CN102231357B (en) Construction method for controlling cleanliness of electronic-grade multicrystal-silicon process pipe
CN102601490A (en) Welding process of P92/T92 steel pipe and heating device
WO2015147684A1 (en) Method for welding pipelines from high-strength pipes with controllable heat input
CN109794668B (en) Method for welding closure seam of martensite heat-resistant steel container
CN105397319A (en) Welding process for steel bridge structure
CN105312742A (en) Welding technology
CN110814560A (en) Large-caliber G115 pipeline on-site welding method
CN107150161A (en) A kind of T91 steel welding technologies
CN103322364A (en) Connecting device and connecting method of internal and external anti-corrosion plastic-steel composite pipe
CN105728893A (en) Manual arc welding process for pipeline
CN106334888A (en) Multi-pipe diameter movable lifting type pipeline welding preheating device
EP2855064B1 (en) Method of applying a protective cladding, particularly to gas-tight membranes of energy boilers
CN108620716B (en) Welding process of reformer pipeline
CN109794666B (en) Vertical annular full-automatic welding process
CN116275401A (en) Large-caliber pipe dissimilar steel welding process applied to advanced ultra-supercritical boiler material
CN110695495A (en) Welding process of water wall pipe for tower boiler field installation
CN209773771U (en) Preheating device before marine riser girth welding
CN111014900A (en) Method for preventing aluminum steel dissimilar metal transition pipe joint from assembling and welding cracks
CN204209270U (en) A kind of Flame Heating Temperature compensator for the long weld seam welding of steel plate
CN219787258U (en) Preheating section feeding U-shaped groove body cracking welding device on electric furnace
CN105598561A (en) A steel pressure bearing pipeline welding process
KR102567066B1 (en) Welding machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant