CN102720211A - Wedge type bottom-end deviation fine-rectifying system for immersed pipe and rectifying process of wedge type bottom-end deviation fine-rectifying system - Google Patents

Wedge type bottom-end deviation fine-rectifying system for immersed pipe and rectifying process of wedge type bottom-end deviation fine-rectifying system Download PDF

Info

Publication number
CN102720211A
CN102720211A CN2012101871212A CN201210187121A CN102720211A CN 102720211 A CN102720211 A CN 102720211A CN 2012101871212 A CN2012101871212 A CN 2012101871212A CN 201210187121 A CN201210187121 A CN 201210187121A CN 102720211 A CN102720211 A CN 102720211A
Authority
CN
China
Prior art keywords
jack
immersed tube
carve
rectifying
body piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101871212A
Other languages
Chinese (zh)
Other versions
CN102720211B (en
Inventor
曲俐俐
刘德进
冯海暴
杨瑞亮
李德钊
苏长玺
陆连洲
付大伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ENGINEERING Co Ltd OF CCCC FIRST HARBOR ENGINEERING CO LTD
No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority to CN201210187121.2A priority Critical patent/CN102720211B/en
Publication of CN102720211A publication Critical patent/CN102720211A/en
Application granted granted Critical
Publication of CN102720211B publication Critical patent/CN102720211B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a wedge type bottom-end deviation fine-rectifying system for an immersed pipe and a rectifying process of the wedge type bottom-end deviation fine-rectifying system. The wedge type bottom-end deviation fine-rectifying system comprises a control system and a mechanical system. The mechanical system comprises a hydraulic pump station, a weight box and a rail. A horizontal positioning mechanism is arranged on the rail and comprises a bottom plate and a horizontal positioning jack. A slide groove and a horizontal transversely-moving jack are mounted on the bottom plate, a jacking deviation rectifying box is disposed in the slide groove, and a perpendicular jacking mechanism is arranged in the jacking deviation rectifying box and comprises a jacking jack, a lower wedge and an upper wedge. One end of the jacking jack is fixed on the jacking deviation rectifying box, the other end of the jacking jack is connected with the lower wedge, and the upper wedge is mounted on the lower wedge and can move upwards perpendicularly along with the lower wedge. The wedge type bottom-end deviation fine-rectifying system is simple in structure, can automatically jack and rectify deviation of the immersed pipe to be mounted by the aid of the jacking jack, the upper wedge, the lower wedge and the horizontal transversely-moving jack, is timesaving and laborsaving and accurate in mounting and is slightly affected by natural conditions such as waves, water flow and wind, and high in stability.

Description

The immersed tube bottom is carved body formula correction accurate adjustment system and is regulated technology
Technical field
The present invention relates to the immersed tube tunnel construction technology, specifically, relates to immersed tube correction bottom regulating system and adjusting technology thereof in a kind of immersed tube tunnel work progress.
Background technology
Immersed tunnelling method is a kind of job practices in the building tunnel at the bottom.Immersed tube tunnel be exactly with several prefabricated section respectively transportation by driving to the sea (river surface) scene, and sink to put one by one and be installed in the foundation trench of having dredged, the submerged tunnel of building with the method.At present, in the immersed tube tunnel work progress, in order to improve the planarization of trench bottom surfaces, the subaqueous tunnel that the overwhelming majority builds up all adopts the method for leveling up.Wherein, The early stage method of leveling up that adopts mostly be a kind of pipeline section is heavy put before first sanding masonry be the first shop method of bed course; It is through hoist engine and the special shop machine of scraping or the steel plough of cable control on operation ship; Guide rail that be provided with, that have the regulation absolute altitude and the gradient is back and forth wipeed the bedding and padding that put down off along the trench bottom surfaces both sides, and this method shortcoming is more; The method that another kind is leveled up is filled out method after being; Promptly elder generation sinks pipeline section and is placed on the temporary support on the trench bottom, and (preset hydraulic jack can be pushed up to bearing when locating in the pipeline section base plate to make the pipe end form certain space; Regulate the pipeline section elevation), use the course filling closely knit subsequently.In above-mentioned two kinds of methods; Handling heavy purpose of putting the pipeline section basis is to make trench bottom surfaces smooth, rather than in order to improve the bearing capacity of ground, the groove that excavates under water; Its bottom surface is uneven; As do not flatten, pipeline section is heavy can to cause local failure because of the ground discontinuity after putting, or ftractures because of differential settlement.
The essential condition that is suitable for the immersed tunnelling method construction is: water channel stabilization of river bed and current are not too urgent.Big in the depth of water, when the immersed tube aspect ratio is big; Need obviously to increase the jack configuration; Usually adopt heavy putting to refute auxiliary providing to the power of hanging oneself reducing immersed tube to bedding frictional force, through heavy put refute auxiliary install wave height is required relatively stricter, general job wave height requirement≤0.4m.At present, adopt the heavy case of refuting auxiliary installation of putting to have only Pusan-huge Ji immersed tube tunnel and Oresund immersed tube tunnel, wherein, Pusan-huge Ji immersed tube tunnel is to operation wave height requirement≤0.4m; In the immersed tube tunnel construction of Oresund, can find out that from map formed shielding around the job site, sea situation is better.And when requiring greater than 0.4m,, adopt heavy putting when refuting auxiliary the installation owing to receive the influence of natural conditions such as wave, current, wind for wave height; The power amplitude of variation of hanging is very big, and bigger to the installation and control influence, jack thrust is big; The control difficulty; And installation accuracy is inaccurate, needs the time to adjust, and wastes time and energy.
Summary of the invention
The present invention is directed to and have the problems referred to above such as the thrust that existed by effect of natural conditions such as wave, current, wind when immersed tube is installed in the immersed tube tunnel work progress is big, control is difficult, waste time and energy now; Provide a kind of immersed tube bottom to carve body formula correction accurate adjustment system and adjusting technology thereof; This system is positioned at immersed tube afterbody to be installed bottom when using; Function with autonomous rectifying by jack up, the immersed tube correction when being applicable to the immersed tube tunnel construction.
Technical scheme of the present invention is: body formula correction accurate adjustment system is carved in a kind of immersed tube bottom; This system comprises control system and mechanical system; Mechanical system comprises hydraulic power unit, ballast box and is installed in the track of ballast box one side; Track be provided with can be Orbiting horizontal location mechanism, this horizontal location mechanism comprises the base plate that is installed in orbit and is installed in the horizontal location jack on the base plate that one end of horizontal location jack is connected with ballast box; The traversing jack of chute and level is installed on the base plate, is placed with the rectifying by jack up case in the chute, be provided with vertical lifting body in this rectifying by jack up case, traversing jack one end of level is fixed on the base plate, and the other end is connected with the rectifying by jack up case; Vertical lifting body comprise the pushing tow jack, down carve the body piece and on carve the body piece; Pushing tow jack one end is fixed on the rectifying by jack up case; The other end with under carve the body piece and be connected, on carve the body piece and be installed in down and carve on the body piece, and can move with carving moving vertically upward of body piece down.
Preferably, the upper surface of carving down the body piece is provided with chute, on carve the body piece soffit be provided with and the corresponding slide block of chute, on carve the body piece and can in the chute of carving the body piece down, move through slide block.
Preferably, the sidewall of rectifying by jack up case is provided with vertical stopper slot, on carve the body piece both sides be provided with and the corresponding spacing block set of vertical stopper slot.
Preferably, base plate is provided with column, and traversing jack one end of level is fixed on the column, and the other end is connected with the rectifying by jack up case.
Preferably, the upper surface of carving the body piece on all is set to ramp structure with the following soffit of carving the body piece.
Another object of the present invention is to provide a kind of immersed tube bottom correction technology, adopt the immersed tube bottom to carve body formula correction accurate adjustment system and rectify a deviation, its correction processing step is:
(1) basis requires: hydraulic power unit and control system that body formula correction accurate adjustment system is carved in the immersed tube bottom all are positioned on the diving crane ship; This system mechanics system-based need be with immersed tube afterbody rubble to be installed basis than the low 70cm of base bed flattening absolute altitude; Axial length is 5m; The mechanical system entering immersed tube bottom part height that body formula correction accurate adjustment system is carved in the immersed tube bottom is 56cm, and it is in place to be convenient to mechanical system.
(2) axis repetition measurement: after the crimping of immersed tube waterpower is accomplished, open the steel measured hole of sealing up a door and carry out holing through survey.
(3) heavyly put, in place: the immersed tube bottom is carved heavy the putting through suspension bracket of mechanical system of body formula correction accurate adjustment system and is fixed, suspension bracket length 25m, heavy set level can contact with the passage abutment wall when moving spacing; During heavy putting; Through being installed in the distance between measuring instrument on the mechanical system is measured and steel is sealed up a door; When apart from 2m place, immersed tube end implantation, and then sling apart from bedding 1m, the mechanical system of carving body formula correction accurate adjustment system through the wire rope pulling immersed tube bottom that is preset in the immersed tube end is adjacent to the immersed tube end; And then fall implantation, it is in place to utilize the immersed tube bottom to carve the horizontal location jack pushing tow rectifying by jack up case of mechanical system self of body formula correction accurate adjustment system.
(4) immersed tube jacking: through carving body piece 0.4m under the pushing tow jack pushing tow, on carve the jacking of body piece and raise 0.1m, carve body piece and immersed tube gap in the elimination, make and carve the body piece and closely contact with the immersed tube bottom; The pushing tow jack continues to carve the body piece to 0.9m under the pushing tow, on carve the body piece and raised 0.2m by jacking, immersed tube is raised by jacking, at this moment, immersed tube reaches 600t to carving body piece gross pressure, on carve body piece and immersed tube generation frictional force can reach 360t.
(5) immersed tube correction: carve down the body piece through pushing tow jack pushing tow spacing after, the traversing jack pushing tow of level rectifying by jack up case correction immersed tube 100mm realizes immersed tube correction operation.
(6) monitoring in real time: the operating period of rectifying a deviation utilizes total powerstation to pass through measured hole observation immersed tube tail end correction situation and tail end top lifting height.
(7) equipment shifts out: after correction put in place, the traversing jack of locking level was through carving the body piece under the pulling of pushing tow jack; Make and carve the decline of body piece; Immersed tube decline implantation is accomplished correction, at this moment; The mechanical system that body formula correction accurate adjustment system is carved in the immersed tube bottom withdraws from the immersed tube bottom, and the mechanical system of utilizing crane gear that body formula correction accurate adjustment system is carved in the immersed tube bottom winches to assigned address.
Preferably, in the step (3), heavy putting when in place; The rectifying by jack up case state that mediates; Before jacking, through the traversing jack of level the rectifying by jack up case is pushed to an end of correction, the traversing jack correction of maintenance level amount can repeat above-mentioned steps between 10-20cm.
The invention has the beneficial effects as follows: the present invention carves body formula correction accurate adjustment system architecture advantages of simple, easy to use, adopts the horizontal location jack in place, through the pushing tow jack, on carve the body piece, carve the rectifying by jack up function that the traversing jack of body piece and level is realized immersed tube to be installed down; And be provided with the control system; Whole process is accomplished automatically, and is time saving and energy saving, and control is convenient; Installation accuracy is accurate, receives effect of natural conditions such as wave, current, wind little; After correction is accomplished, can directly unload and carve body formula correction accurate adjustment system, stability is high.
Description of drawings
Accompanying drawing 1 is put the original state structural representation when in place for specific embodiment of the invention mechanical system is heavy.
Status architecture sketch map when accompanying drawing 2 is the correction of specific embodiment of the invention mechanical system jacking immersed tube.
Accompanying drawing 3 is the following body block structure sketch map of carving of specific embodiment of the invention mechanical system.
Accompanying drawing 4 is for carving body block structure sketch map on the specific embodiment of the invention mechanical system.
The specific embodiment
Below in conjunction with accompanying drawing the present invention is described further.
Body formula correction accurate adjustment system is carved in a kind of immersed tube bottom; This system comprises control system and mechanical system; Mechanical system comprises hydraulic power unit, ballast box 1 and is installed in the track of ballast box 1 one sides; Track be provided with can be Orbiting horizontal location mechanism, this horizontal location mechanism comprises the base plate 2 that is installed in orbit and is installed in the horizontal location jack 3 on the base plate 2 that an end of horizontal location jack 3 is connected with ballast box 1; The traversing jack 4 of chute and level is installed on the base plate 2; Be placed with rectifying by jack up case 5 in the chute; Be provided with vertical lifting body in this rectifying by jack up case 5, traversing jack 4 one ends of level are fixed on the column 12 that is arranged on the base plate 2, and the other end is connected with rectifying by jack up case 5; Vertical lifting body comprise pushing tow jack 6, down carve body piece 7 and on carve body piece 8, on carve the upper surface of body piece 8 and all be set to ramp structure with the soffit of carving body piece 7 down.Pushing tow jack 6 one ends are fixed on the rectifying by jack up case 5, the other end with under carve body piece 7 and be connected, on carve body piece 8 and be installed in down and carve on the body piece 7, and can move with carving moving vertically upward of body piece 7 down.The upper surface of carving body piece 7 down is provided with chute 9, on carve body piece 8 soffit be provided with and chute 9 corresponding slide blocks 10, on carve body piece 8 and can in the chute 9 of carving body piece 7 down, move through slide block 10.The sidewall of rectifying by jack up case 5 is provided with vertical stopper slot, on carve body piece 8 both sides be provided with and the corresponding spacing block set 11 of vertical stopper slot.
Its correction processing step is following:
(1) basis requires: hydraulic power unit and control system that body formula correction accurate adjustment system is carved in the immersed tube bottom all are positioned on the diving crane ship; This system mechanics system-based need be with immersed tube afterbody rubble to be installed basis than the low 70cm of base bed flattening absolute altitude; Axial length is 5m; The mechanical system entering immersed tube bottom part height that body formula correction accurate adjustment system is carved in the immersed tube bottom is 56cm, and it is in place to be convenient to mechanical system.
(2) axis repetition measurement: after the crimping of immersed tube waterpower is accomplished, open the steel measured hole of sealing up a door and carry out holing through survey.
(3) heavyly put, in place: the immersed tube bottom is carved heavy the putting through suspension bracket of mechanical system of body formula correction accurate adjustment system and is fixed, suspension bracket length 25m, heavy set level can contact with the passage abutment wall when moving spacing; During heavy putting; Through being installed in the distance between measuring instrument on the mechanical system is measured and steel is sealed up a door; When apart from 2m place, immersed tube end implantation, and then sling apart from bedding 1m, the mechanical system of carving body formula correction accurate adjustment system through the wire rope pulling immersed tube bottom that is preset in the immersed tube end is adjacent to the immersed tube end; And then fall implantation, it is in place to utilize the immersed tube bottom to carve the horizontal location jack pushing tow rectifying by jack up case of mechanical system self of body formula correction accurate adjustment system; Heavy putting when in place, the rectifying by jack up case state that mediates is pushed to an end of correction through the traversing jack of level with the rectifying by jack up case before jacking, the traversing jack correction of maintenance level amount is between 10-20cm.
(4) immersed tube jacking: through carving body piece 0.4m under the pushing tow jack pushing tow, on carve the jacking of body piece and raise 0.1m, carve body piece and immersed tube gap in the elimination, make and carve the body piece and closely contact with the immersed tube bottom; The pushing tow jack continues to carve the body piece to 0.9m under the pushing tow, on carve the body piece and raised 0.2m by jacking, immersed tube is raised by jacking, at this moment, immersed tube reaches 600t to carving body piece gross pressure, on carve body piece and immersed tube generation frictional force can reach 360t.
(5) immersed tube correction: carve down the body piece through pushing tow jack pushing tow spacing after, the traversing jack pushing tow of level rectifying by jack up case correction immersed tube 100mm realizes immersed tube correction operation.
(6) monitoring in real time: the operating period of rectifying a deviation utilizes total powerstation to pass through measured hole observation immersed tube tail end correction situation and tail end top lifting height.
(7) equipment shifts out: after correction put in place, the traversing jack of locking level was through carving the body piece under the pulling of pushing tow jack; Make and carve the decline of body piece; Immersed tube decline implantation is accomplished correction, at this moment; The mechanical system that body formula correction accurate adjustment system is carved in the immersed tube bottom withdraws from the immersed tube bottom, and the mechanical system of utilizing crane gear that body formula correction accurate adjustment system is carved in the immersed tube bottom winches to assigned address.
Above specific embodiment is only unrestricted in order to technical scheme of the present invention to be described; Although the present invention is specified with reference to preferred embodiment; Those of ordinary skill in the art is to be understood that; Can make amendment or be equal to replacement technical scheme of the present invention, and not break away from the spirit and the scope of technical scheme of the present invention, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (7)

1. body formula correction accurate adjustment system is carved in an immersed tube bottom; It is characterized in that: this system comprises control system and mechanical system; Mechanical system comprises hydraulic power unit, ballast box and is installed in the track of ballast box one side; Track be provided with can be Orbiting horizontal location mechanism, this horizontal location mechanism comprises the base plate that is installed in orbit and is installed in the horizontal location jack on the base plate that one end of horizontal location jack is connected with ballast box; The traversing jack of chute and level is installed on the base plate, is placed with the rectifying by jack up case in the chute, be provided with vertical lifting body in this rectifying by jack up case, traversing jack one end of level is fixed on the base plate, and the other end is connected with the rectifying by jack up case; Vertical lifting body comprise the pushing tow jack, down carve the body piece and on carve the body piece; Pushing tow jack one end is fixed on the rectifying by jack up case; The other end with under carve the body piece and be connected, on carve the body piece and be installed in down and carve on the body piece, and can move with carving moving vertically upward of body piece down.
2. body formula correction accurate adjustment system is carved in immersed tube as claimed in claim 1 bottom; It is characterized in that: the upper surface of carving the body piece down is provided with chute; On carve the body piece soffit be provided with and the corresponding slide block of chute, on carve the body piece and can in the chute of carving the body piece down, move through slide block.
3. body formula correction accurate adjustment system is carved in immersed tube as claimed in claim 1 bottom, and it is characterized in that: the sidewall of rectifying by jack up case is provided with vertical stopper slot, on carve the body piece both sides be provided with and the corresponding spacing block set of vertical stopper slot.
4. body formula correction accurate adjustment system is carved in immersed tube as claimed in claim 1 bottom, and it is characterized in that: base plate is provided with column, and traversing jack one end of level is fixed on the column, and the other end is connected with the rectifying by jack up case.
5. carve body formula correction accurate adjustment system like any described immersed tube bottom of claim 1 to 4, it is characterized in that: on carve the upper surface of body piece and all be set to ramp structure with the soffit of carving the body piece down.
6. immersed tube bottom correction technology is characterized in that: adopt the immersed tube bottom to carve body formula correction accurate adjustment system and rectify a deviation, its correction processing step is:
(1) basis requires: hydraulic power unit and control system that body formula correction accurate adjustment system is carved in the immersed tube bottom all are positioned on the diving crane ship; This system mechanics system-based needs will wait to pacify immersed tube afterbody rubble basis than the low 70cm of base bed flattening absolute altitude; Axial length is 5m; The mechanical system entering immersed tube bottom part height that body formula correction accurate adjustment system is carved in the immersed tube bottom is 56cm, and it is in place to be convenient to mechanical system;
(2) axis repetition measurement: after the crimping of immersed tube waterpower is accomplished, open the steel measured hole of sealing up a door and carry out holing through survey;
(3) heavyly put, in place: the immersed tube bottom is carved heavy the putting through suspension bracket of mechanical system of body formula correction accurate adjustment system and is fixed, suspension bracket length 25m, heavy set level can contact with the passage abutment wall when moving spacing; During heavy putting; Through being installed in the distance between measuring instrument on the mechanical system is measured and steel is sealed up a door; When apart from 2m place, immersed tube end implantation, and then sling apart from bedding 1m, the mechanical system of carving body formula correction accurate adjustment system through the wire rope pulling immersed tube bottom that is preset in the immersed tube end is adjacent to the immersed tube end; And then fall implantation, it is in place to utilize the immersed tube bottom to carve the horizontal location jack pushing tow rectifying by jack up case of mechanical system self of body formula correction accurate adjustment system;
(4) immersed tube jacking: through carving body piece 0.4m under the pushing tow jack pushing tow, on carve the jacking of body piece and raise 0.1m, carve body piece and immersed tube gap in the elimination, make and carve the body piece and closely contact with the immersed tube bottom; The pushing tow jack continues to carve the body piece to 0.8m under the pushing tow, on carve the body piece and raised 0.2m by jacking, immersed tube is raised by jacking, at this moment, immersed tube reaches 600t to carving body piece gross pressure, on carve body piece and immersed tube generation frictional force can reach 360t;
(5) immersed tube correction: carve down the body piece through pushing tow jack pushing tow spacing after, the traversing jack pushing tow of level rectifying by jack up case correction immersed tube 100mm realizes immersed tube correction operation;
(6) monitoring in real time: the operating period of rectifying a deviation utilizes total powerstation to pass through measured hole observation immersed tube tail end correction situation and tail end top lifting height;
(7) equipment shifts out: after correction put in place, the traversing jack of locking level was through carving the body piece under the pulling of pushing tow jack; Make and carve the decline of body piece; Immersed tube decline implantation is accomplished correction, at this moment; The mechanical system that body formula correction accurate adjustment system is carved in the immersed tube bottom withdraws from the immersed tube bottom, and the mechanical system of utilizing crane gear that body formula correction accurate adjustment system is carved in the immersed tube bottom winches to assigned address.
7. immersed tube as claimed in claim 6 bottom correction technology; It is characterized in that: in the step (3); Heavy putting when in place, the rectifying by jack up case state that mediates is pushed to the rectifying by jack up case through the traversing jack of level one end of correction before jacking; The traversing jack correction of maintenance level amount can repeat above-mentioned steps between 10-20cm.
CN201210187121.2A 2012-05-29 2012-05-29 Wedge type bottom-end deviation fine-rectifying system for immersed pipe and rectifying process of wedge type bottom-end deviation fine-rectifying system Active CN102720211B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210187121.2A CN102720211B (en) 2012-05-29 2012-05-29 Wedge type bottom-end deviation fine-rectifying system for immersed pipe and rectifying process of wedge type bottom-end deviation fine-rectifying system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210187121.2A CN102720211B (en) 2012-05-29 2012-05-29 Wedge type bottom-end deviation fine-rectifying system for immersed pipe and rectifying process of wedge type bottom-end deviation fine-rectifying system

Publications (2)

Publication Number Publication Date
CN102720211A true CN102720211A (en) 2012-10-10
CN102720211B CN102720211B (en) 2014-10-15

Family

ID=46946066

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210187121.2A Active CN102720211B (en) 2012-05-29 2012-05-29 Wedge type bottom-end deviation fine-rectifying system for immersed pipe and rectifying process of wedge type bottom-end deviation fine-rectifying system

Country Status (1)

Country Link
CN (1) CN102720211B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105253351A (en) * 2015-10-23 2016-01-20 东莞市锦顺包装机械有限公司 Automatic paperboard packaging machine
CN108660952A (en) * 2018-05-21 2018-10-16 南通路桥工程有限公司 A kind of Incremental Launching Method that the prefabricated car case of assembly concrete is logical
CN108951326A (en) * 2018-06-28 2018-12-07 安徽东方钢结构有限公司 A kind of track girder slope conditioning
CN111395397A (en) * 2020-03-20 2020-07-10 华侨大学 Bending type immersed tube anti-deformation structure and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003049441A (en) * 2001-08-03 2003-02-21 Toyo Constr Co Ltd Direction correcting device and method for submerged caisson
CN1696415A (en) * 2004-05-12 2005-11-16 布伊古公共工程公司 Process and apparatus for producing an immersed tunnel on subsea ground
CN101586342A (en) * 2009-06-15 2009-11-25 中交一航局第二工程有限公司 Caisson adopts jack to move horizontally the roof process of jacking
CN202787315U (en) * 2012-05-29 2013-03-13 中交一航局第二工程有限公司 Immersed tube bottom end carving body type rectifying and fine adjusting system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003049441A (en) * 2001-08-03 2003-02-21 Toyo Constr Co Ltd Direction correcting device and method for submerged caisson
CN1696415A (en) * 2004-05-12 2005-11-16 布伊古公共工程公司 Process and apparatus for producing an immersed tunnel on subsea ground
CN101586342A (en) * 2009-06-15 2009-11-25 中交一航局第二工程有限公司 Caisson adopts jack to move horizontally the roof process of jacking
CN202787315U (en) * 2012-05-29 2013-03-13 中交一航局第二工程有限公司 Immersed tube bottom end carving body type rectifying and fine adjusting system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105253351A (en) * 2015-10-23 2016-01-20 东莞市锦顺包装机械有限公司 Automatic paperboard packaging machine
CN108660952A (en) * 2018-05-21 2018-10-16 南通路桥工程有限公司 A kind of Incremental Launching Method that the prefabricated car case of assembly concrete is logical
CN108660952B (en) * 2018-05-21 2020-07-21 南通路桥工程有限公司 Pushing installation method of prefabricated concrete automobile box
CN108951326A (en) * 2018-06-28 2018-12-07 安徽东方钢结构有限公司 A kind of track girder slope conditioning
CN111395397A (en) * 2020-03-20 2020-07-10 华侨大学 Bending type immersed tube anti-deformation structure and construction method
CN111395397B (en) * 2020-03-20 2021-11-30 华侨大学 Construction method of bending type immersed tube anti-deformation structure

Also Published As

Publication number Publication date
CN102720211B (en) 2014-10-15

Similar Documents

Publication Publication Date Title
CN102251530B (en) Construction process of double-wall steel cofferdam for construction of pier bearing platform in main river water of Yellow River
CN102691314B (en) Internal deviation correcting fine adjusting system and adjusting technology for immersed tubes
CN109487822B (en) Method for installing and adjusting steel pipe column in reverse construction and control device
CN102720222A (en) Tail-end deviation rectifying process for immersed pipe
CN104929144A (en) Deepwater suction type barrel-shaped foundation intermittent penetration equipment and installation method
CN110185044B (en) Foundation pit side wall stress adjustment system for deep unstable stratum
CN102720211B (en) Wedge type bottom-end deviation fine-rectifying system for immersed pipe and rectifying process of wedge type bottom-end deviation fine-rectifying system
CN102704512B (en) Immersed tube bottom jack type deviation rectifying fine adjusting system and adjusting technology
CN112301991B (en) Deformation automatic monitoring and early warning method capable of being used for high-fill and soft foundation engineering
CN103423093B (en) Platform floating type wind driven generator provided with suction caissons and used for sea surface of deep sea
CN105804041A (en) Large-area ultra-soft foundation settlement monitoring device and method
CN109610308B (en) The device and method of bridge settlement is avoided suitable for tunnel underbridge beam work progress
CN103669383B (en) A kind of method of installation and leveling caisson on ground, seabed
CN202530464U (en) Road drainage foundation-pit supporting structure for auxiliary steel sheet pile construction of dewatering wells
CN102704508B (en) Immersed tube bottom end fork truck type deviation correcting fine adjusting system and regulating process of system
CN202913431U (en) Immersed tube bottom end jack type deviation-rectifying accurate adjustment system
CN112647533A (en) Construction system and construction method for preventing slurry leakage in jacket foundation pile by pile-first method
GB2493023A (en) Wind turbine foundation with pontoons
CN202787314U (en) Immersed tube bottom end forklift-type rectifying and fine adjusting system
CN202787315U (en) Immersed tube bottom end carving body type rectifying and fine adjusting system
CN102691313B (en) Immersed tube bottom capsule water filling fine adjusting system and adjusting technology
CN204461907U (en) There is the waters vane shear test platform on tub truss basis
CN202913427U (en) Immersed tube bottom end capsule water-filling type accurate adjustment system
CN203238663U (en) Immersed tube top end three-dimensional fine tuning system
CN202787339U (en) Immersed tube inner portion rectifying and adjusting system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: CCCC FIRST HARBOR ENGINEERING COMPANY LTD.

Effective date: 20121019

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Lin Ming

Inventor after: Fu Dawei

Inventor after: Qu Lili

Inventor after: Liu Dejin

Inventor after: Feng Haibao

Inventor after: Li Zengjun

Inventor after: Yang Ruiliang

Inventor after: Li Dezhao

Inventor after: Su Changxi

Inventor after: Lu Lianzhou

Inventor before: Qu Lili

Inventor before: Liu Dejin

Inventor before: Feng Haibao

Inventor before: Yang Ruiliang

Inventor before: Li Dezhao

Inventor before: Su Changxi

Inventor before: Lu Lianzhou

Inventor before: Fu Dawei

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: QU LILI LIU DEJIN FENG HAIBAO YANG RUILIANG LI DEZHAO SU CHANGXI LU LIANZHOU FU DAWEI TO: LIN MING QU LILI LIU DEJIN FENG HAIBAO LI ZENGJUN YANG RUILIANG LI DEZHAO SU CHANGXI LU LIANZHOU FU DAWEI

TA01 Transfer of patent application right

Effective date of registration: 20121019

Address after: 266071 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong

Applicant after: The Second Engineering Co. of CCCC First Harbor Engineering Co., Ltd.

Applicant after: ENGINEERING COMPANY LTD. OF CCCC FIRST HARBOR ENGINEERING CO.,LTD.

Address before: 266071 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong

Applicant before: The Second Engineering Co. of CCCC First Harbor Engineering Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CI01 Publication of corrected invention patent application

Correction item: Applicant

Correct: CCCC Second Highway Engineering Co. Ltd.| 266071 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong|CCCC First Harbor Engineering Co., Ltd.

False: CCCC Second Highway Engineering Co. Ltd.| 266071 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong|ENGINEERING COMPANY LTD. OF CCCC FIRST HARBOR ENGINEERING CO.,LTD.

Number: 47

Volume: 28

ERR Gazette correction

Free format text: CORRECT: APPLICANT; FROM: THE SECOND ENGINEERING CO. OF CCCC FIRST HARBOR ENGINEERING CO., LTD.:266071 QINGDAO, SHANDONG PROVINCE; CCCC FIRST HARBOR ENGINEERING COMPANY LTD. TO: THE SECOND ENGINEERING CO. OF CCCC FIRST HARBOR ENGINEERING CO., LTD.:266071 QINGDAO, SHANDONG PROVINCE; CCCC FIRST HARBOR ENGINEERING CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant