CN102720141A - Construction method integrating pilot rope river-crossing and traction system - Google Patents

Construction method integrating pilot rope river-crossing and traction system Download PDF

Info

Publication number
CN102720141A
CN102720141A CN2012102422441A CN201210242244A CN102720141A CN 102720141 A CN102720141 A CN 102720141A CN 2012102422441 A CN2012102422441 A CN 2012102422441A CN 201210242244 A CN201210242244 A CN 201210242244A CN 102720141 A CN102720141 A CN 102720141A
Authority
CN
China
Prior art keywords
dragline
bank
rope
traction
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012102422441A
Other languages
Chinese (zh)
Other versions
CN102720141B (en
Inventor
谭立心
刘宏波
罗超云
冯炳生
吴聪
程建阳
李斌
詹元林
鄢生全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Changda Highway Engineering Co Ltd
Original Assignee
Guangdong Changda Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Changda Highway Engineering Co Ltd filed Critical Guangdong Changda Highway Engineering Co Ltd
Priority to CN201210242244.1A priority Critical patent/CN102720141B/en
Publication of CN102720141A publication Critical patent/CN102720141A/en
Application granted granted Critical
Publication of CN102720141B publication Critical patent/CN102720141B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Ropes Or Cables (AREA)

Abstract

The invention discloses a construction method integrating pilot rope river-crossing and traction system by building bridge cat ways and mounting main cables. The construction method comprises the following steps of: A construction preparation, building tower bodies, pilot rope winches, concrete anchors and main winches on two constructional banks; B, building pilot ropes; C, building traction ropes, respectively drawing one ends of the transition ropes of the main winches arranged on two banks to tops of towers, drawing one end of the traction rope arranged on the top of the tower on one bank to the top of the tower on the opposite bank through the pilot ropes, and enabling end heads of the two traction ropes to be connected; and starting the main winches on two banks, enabling the main winch on one bank to wind and the main winch at the other end to unwind until the traction ropes are built. The method has the advantages of being fast and convenient in mounting, safe in construction, short in navigation channel closure period, short in construction period, guaranteed in quality, convenient in operation and the like.

Description

Elder generation's dragline is crossed river and the incorporate job practices of traction system
Technical field
The present invention relates to the construction method of installation of the traction system that a kind of bridge cat road sets up, main push-towing rope is installed.
Background technology
Trailer system sets up core and is that first dragline crosses the river; Normally cross the river earlier with thinner wire rope earlier; Utilize its first dragline to guide river (wire rope from carefully to thick) in the air again; Main method has: lay under water that method, free suspension method, crane barge are set up method, helicopter sets up method and balloon suspension method etc., transfers the haulage cable of anchor road track cable or main cable strand at last to.Trailer system normally relies on the transition elder generation dragline that sets up in advance to carry out installation.
Sun patrol bridge adopt first dragline under water the method for laying drew the river; Its main feature is after accomplishing first dragline connection; The drag cable of its trailer system sets up at Mao Dao need set up drag cable again; Many, iceound times of aerial work are long, operation is loaded down with trivial details, difficulty of construction is high, and safety is difficult to be guaranteed.
Summary of the invention
In order to overcome above-mentioned deficiency, the object of the present invention is to provide a kind of bridge cat road to set up and first dragline that main push-towing rope can effectively be installed trailer system when installing is crossed river and the incorporate job practices of traction system.That this method has is quick for installation, construction safety, the iceound time weak point in navigation channel, duration weak point, quality assurance, characteristics such as easy to operate.
To achieve these goals, the technical scheme of the present invention's employing is:
Elder generation's dragline is crossed river and the incorporate job practices of traction system, may further comprise the steps: A, preparation of construction: in the two sides of construction, every bank is all established tower body, first dragline hoist engine, anchorage and main winch; B, erecting guide rope; C, set up drag cable: an end of the drag cable on the main winch of two sides is caused cat head respectively, utilize first dragline that one end of the drag cable of the top of tower of one bank is drawn to the top of tower on opposite bank, the termination of two drag cables is connected; Start the main winch of two sides, the main winch rolling of a bank, the main winch of the other end is put rope, to setting up completion to drag cable.
The step of said step B comprises: 1. stride on the first dragline hoist engine on the side assistance platform on tower base, two sides; Be involved in first dragline respectively; Guide's rustling sound head is promoted to cat head,, transfers a side near a river to tower through the cat head roller steering; At the bottom of respectively guide's rustling sound head being temporarily fixed at tower, prepare to be connected with tugboat; 2. to can the part navigation channel carry out iceound, the iceound district in the part, tugboat, barge, that control vessel arrives assigned address is in place, the location barge is in the predetermined point location of casting anchor; 3. utilize tugboat to draw bank elder generation dragline to station keeping ship, be connected on the station keeping ship temporarily, first dragline hoist engine imposes suitable counter-force to first dragline in this process, keeps rope not get in the water; 4. all iceound, utilize tugboat that two sides elder generations dragline is led to station keeping ship and connect temporarily, connect two sides elder generation dragline, remove respectively and being connected of station keeping ship; 5. start two sides elder generation dragline hoist engine, promote first dragline and cross the river, one receives one puts, and through cat head, the adjustment sag is beaten tip anchoring temporarily one bank elder generation dragline to the absolute altitude of opening the navigation or air flight at two cats head, removes bank elder generation dragline until two sides elder generation dragline connector; 6. remove iceoundly, accomplish setting up of first dragline.
The step of said step C comprises: the 1# drag cable is set up at a bank in (1): 1. the 1# drag cable is involved in traction main winch rope roll, lays the interim support roller of drag cable; 2. start main rack winch and put rope, utilize first dragline hoist engine, the 1# drag cable is linked to each other with first dragline hoist engine wire rope, draw to the tower root through directive wheel, first dragline hoist engine tractive promotes 1# traction rustling sound head to cat head, is connected with opposite bank guide's rustling sound head; 3. start earlier the traction main winch make end bay dragline tension force with in stride basic identical; Remove dragline at two cat head place temporary consolidations, start opposite bank elder generation dragline hoist engine, be involved in opposite bank elder generation dragline; The traction of 1# drag cable is walked around cat head, played the temporary fixed 1# traction of tip drag cable at cat head.In the distraction procedure, main rack winch applies suitable counter-force, prevents the drag cable bounce-back, and the drag cable of 1# adjustment at any time sag, guarantees headway; 4. meanwhile, carry out the 2# drag cable on the opposite bank and set up, on the main rack winch of this bank; Arrange 2# traction rustling sound dish; The 2# drag cable is involved in the main rack winch rope roll, 2# is drawn the rustling sound head cause this bank top of tower, pull device in the top of tower utilization of this bank the 1# rope is linked to each other with the 2# rope; 5. start both sides master's rack winch, remove the cat head temporary consolidation, the adjustment drag cable forms the reciprocating type trailer system of single line to design height.
The diameter of said 1# drag cable and 2# drag cable is 36mm; The diameter of said first dragline is 24mm.
Said first dragline hoist engine adopts the hoist engine of 20T, and said main winch adopts the hoist engine of 25T.
Beneficial effect of the present invention: its working procedure is reasonable, ancillary method is few, and construction efficiency is high, the time is short, safety is controlled, practice thrift cost, and integrated have with characteristics under the structure:
(1) the integrated plant equipment of utilizing trailer system does not increase other big ancillary method, promptly adopts rack winch, main push-towing rope to pull hoist engine, pulls device;
(2) integrated installation trailer system one-shot forming, make working procedure rationally, guarantee safety.Promptly under the situation of short iceound time, accomplish, the installation of the transition traction of minimizing reaches carries out the installation of pull rope under innavigable situation;
(3) upstream and downstream is independently laid, and reduces aerial erection construction step, has reduced a large amount of construction ancillary methods;
(4) short construction period, work efficiency are high, security performance is high.
Description of drawings
Below in conjunction with accompanying drawing the present invention is done further detailed description.
Fig. 1 is the structural representation of preparation of construction of the present invention;
Fig. 2 and Fig. 3 are first dragline working drawing of the present invention;
Fig. 4 is the sketch map after the present invention elder generation dragline sets up completion;
Fig. 5 is the erection construction figure of drag cable;
Fig. 6 is the sketch map after the completion that sets up of drag cable.
Among the figure: 1, tower body; 2, first dragline hoist engine; 3, anchorage; 4, main winch; 5, first dragline; 6, tugboat; 7, station keeping ship; 8,1# drag cable; 9,2# drag cable.
The specific embodiment
Elder generation's dragline is crossed river and the incorporate job practices of traction system, may further comprise the steps:
1, preparation of construction: as shown in Figure 1, in the two sides of construction, every bank is all established the main winch 4 of first dragline hoist engine 2, anchorage 3 and the 25T of tower body 1,20T.
In addition, before first dragline is crossed the river, hitching machinery equipment, material arrangements are put in place, apply in advance with port prison, harbour affairs, navigation channel department, the sealing of distraction procedure midchannel is guaranteed in distribution navigation ban announcement.Should carry out detailed technology before the traction, tell somebody what one's real intentions are safely, carry out careful construction organization, meet the standard of zero tolerance.
2, erecting guide rope
1. as shown in Figure 2, stride on the fixing first dragline hoist engine of side assistance platform on tower base, two sides, be involved in first dragline 5 respectively; Guide's rustling sound head is promoted to cat head,, transfers a side near a river to tower through the cat head roller steering; At the bottom of respectively guide's rustling sound head being temporarily fixed at tower, prepare to be connected with tugboat 6.
2. to can the part navigation channel carry out iceound, the iceound district in the part, tugboat 6, barge, that control vessel arrives assigned address is in place, the location barge is in the predetermined point location of casting anchor.
3. as shown in Figure 3, utilize tugboat 6 tractions one bank elder generation dragline to station keeping ship 7, be connected on the station keeping ship 7 temporarily, first dragline hoist engine imposes suitable counter-force to first dragline in this process, keeps rope not get in the water;
4. all iceound, utilize tugboat that two sides elder generations dragline is led to station keeping ship and connect temporarily, connect two sides elder generation dragline, remove respectively and being connected of station keeping ship 7.
5. start two sides elder generation dragline hoist engine, promote first dragline and cross the river, one receives one puts, and through cat head, the adjustment sag is beaten tip anchoring temporarily one bank elder generation dragline to the absolute altitude of opening the navigation or air flight at two cats head, removes bank elder generation dragline until two sides elder generation dragline connector.
6. as shown in Figure 4, remove iceoundly, accomplish setting up of first dragline.
3, dragline is crossed the iceound scheme in river
Should forbid when dragline is crossed a river that all ships open the navigation or air flight at main channel, specifically the scheme of opening the navigation or air flight should be formulated with maritime sector jointly.At first should in news media, issue the announcement in concrete iceound time, iceound waters in advance; Secondly certain distance is provided with construction guardship, iceound announcement ship respectively in upstream and downstream, iceound waters.
4, setting up of trailer system: as shown in Figure 5, in this programme, drag cable is to be that the 1# drag cable 8 of 36mm constitutes with 2# drag cable 9 by diameter, and concrete steps are following:
1. main rack winch is installed and is arranged traction rustling sound dish, the 1# drag cable is involved in traction main winch rope roll, lay the interim support roller of drag cable.
2. start main rack winch and put rope, utilize first dragline hoist engine, the 1# drag cable is linked to each other with first dragline hoist engine wire rope, draw to the tower root through directive wheel, first dragline hoist engine tractive promotes 1# traction rustling sound head to cat head, is connected with opposite bank guide's rustling sound head.
3. start earlier the traction main winch make end bay dragline tension force with in stride basic identical; Remove dragline at two cat head place temporary consolidations, start opposite bank elder generation dragline hoist engine, be involved in opposite bank elder generation dragline; The traction of 1# drag cable is walked around cat head, played the temporary fixed 1# traction of tip drag cable at cat head.In the distraction procedure, main rack winch applies suitable counter-force, prevents the drag cable bounce-back, and the drag cable of 1# adjustment at any time sag, guarantees headway.
4. meanwhile, carry out the 2# drag cable on the opposite bank and set up, on the main rack winch of this bank; Arrange 2# traction rustling sound dish; The 2# drag cable is involved in the main rack winch rope roll, 2# is drawn the rustling sound head cause this bank top of tower, pull device in the top of tower utilization of this bank the 1# rope is linked to each other with the 2# rope;
5. as shown in Figure 6, start both sides master's rack winch, remove the cat head temporary consolidation, the adjustment drag cable forms the reciprocating type trailer system of single line to design height.
The above is a preferred implementation of the present invention, can not limit the present invention's interest field certainly with this.Should be pointed out that for those skilled in the art, technical scheme of the present invention is made amendment or is equal to replacement, do not break away from protection scope of the present invention.

Claims (5)

1. a first dragline is crossed river and the incorporate job practices of traction system, it is characterized in that: may further comprise the steps: A, preparation of construction: in the two sides of construction, every bank is all established tower body, first dragline hoist engine, anchorage and main winch; B, erecting guide rope; C, set up drag cable: an end of the drag cable on the main winch of two sides is caused cat head respectively, utilize first dragline that one end of the drag cable of the top of tower of one bank is drawn to the top of tower on opposite bank, the termination of two drag cables is connected; Start the main winch of two sides, the main winch rolling of a bank, the main winch of the other end is put rope, to setting up completion to drag cable.
2. cross river and the incorporate construction method of traction system based on the described first dragline of claim 1; It is characterized in that: the step of said step B comprises: 1. stride on the first dragline hoist engine on the side assistance platform on tower base, two sides, be involved in first dragline respectively, guide's rustling sound head is promoted to cat head; Through the cat head roller steering; Transfer a side near a river, respectively guide's rustling sound head is temporarily fixed at the bottom of the tower, prepare to be connected with tugboat to tower; 2. to can the part navigation channel carry out iceound, the iceound district in the part, tugboat, barge, that control vessel arrives assigned address is in place, the location barge is in the predetermined point location of casting anchor; 3. utilize tugboat to draw bank elder generation dragline to station keeping ship, be connected on the station keeping ship temporarily, first dragline hoist engine imposes suitable counter-force to first dragline in this process, keeps rope not get in the water; 4. all iceound, utilize tugboat that two sides elder generations dragline is led to station keeping ship and connect temporarily, connect two sides elder generation dragline, remove respectively and being connected of station keeping ship; 5. start two sides elder generation dragline hoist engine, promote first dragline and cross the river, one receives one puts, and through cat head, the adjustment sag is beaten tip anchoring temporarily one bank elder generation dragline to the absolute altitude of opening the navigation or air flight at two cats head, removes bank elder generation dragline until two sides elder generation dragline connector; 6. remove iceoundly, accomplish setting up of first dragline.
3. cross river and the incorporate construction method of traction system based on the described first dragline of claim 1; It is characterized in that: the step of said step C comprises: the 1# hauling rope is set up at a bank in (1): 1. the 1# hauling rope is involved in traction main winch rope roll, lays the interim support roller of hauling rope; 2. start main rack winch and put rope, utilize first dragline hoist engine, the 1# hauling rope is linked to each other with first dragline hoist engine steel wire rope, draw to the tower root through directive wheel, first dragline hoist engine tractive promotes 1# traction rustling sound head to cat head, is connected with opposite bank guide's rustling sound head; 3. start earlier the traction main winch make end bay dragline tension force with in stride basic identically, remove dragline at two cat head place temporary consolidations, start opposite bank elder generation dragline hoist engine; Be involved in opposite bank elder generation dragline, the traction of 1# hauling rope is walked around cat head, play the temporary fixed 1# traction of tip hauling rope at cat head; In the distraction procedure, main rack winch applies suitable counter-force, prevents the hauling rope bounce-back; And the hauling rope of 1# adjustment at any time sag, guarantee headway; 4. meanwhile, carry out the 2# hauling rope on the opposite bank and set up, on the main rack winch of this bank; Arrange 2# traction rustling sound dish; The 2# hauling rope is involved in the main rack winch rope roll, 2# is drawn the rustling sound head cause this bank top of tower, pull device in the top of tower utilization of this bank the 1# rope is linked to each other with the 2# rope; 5. start both sides master's rack winch, remove the cat head temporary consolidation, the adjustment hauling rope forms the reciprocating type trailer system of single line to design height.
4. first dragline according to claim 3 is crossed river and the incorporate job practices of traction system, it is characterized in that: the diameter of said 1# drag cable and 2# drag cable is 36mm; The diameter of said first dragline is 24mm.
5. first dragline according to claim 1 is crossed river and the incorporate job practices of traction system, it is characterized in that: said first dragline hoist engine adopts the hoist engine of 20T, and said main winch adopts the hoist engine of 25T.
CN201210242244.1A 2012-07-13 2012-07-13 Guide cable crosses the river construction method integrated with Traction sysytem Active CN102720141B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210242244.1A CN102720141B (en) 2012-07-13 2012-07-13 Guide cable crosses the river construction method integrated with Traction sysytem

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210242244.1A CN102720141B (en) 2012-07-13 2012-07-13 Guide cable crosses the river construction method integrated with Traction sysytem

Publications (2)

Publication Number Publication Date
CN102720141A true CN102720141A (en) 2012-10-10
CN102720141B CN102720141B (en) 2015-08-19

Family

ID=46945996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210242244.1A Active CN102720141B (en) 2012-07-13 2012-07-13 Guide cable crosses the river construction method integrated with Traction sysytem

Country Status (1)

Country Link
CN (1) CN102720141B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105256724A (en) * 2015-09-28 2016-01-20 中交二公局第二工程有限公司 Method of drawing pilot rope by unmanned aerial vehicle for river-crossing construction
CN105113414B (en) * 2015-09-11 2016-09-21 中铁八局集团桥梁工程有限责任公司 A kind of suspension bridge main rope fast erecting method
CN106379765A (en) * 2016-10-21 2017-02-08 长江勘测规划设计研究有限责任公司 Clamp resetting structure and method for reclaiming main cable of cable crane
CN108018844A (en) * 2017-12-01 2018-05-11 大连汇洋船务工程配套有限公司 A kind of floatable port security door
CN108018778A (en) * 2017-11-14 2018-05-11 中铁大桥局集团第六工程有限公司 The cat road rope in navigable waters does not set up trailer system and cat road rope fast erecting method
CN110306433A (en) * 2019-04-29 2019-10-08 中铁大桥局集团有限公司 A kind of turbulent flow waters guide cable is quick to cross river method
CN111441594A (en) * 2020-04-21 2020-07-24 中铁大桥局第七工程有限公司 Construction method of multilayer sectional type main cable
CN111622111A (en) * 2020-05-04 2020-09-04 中交第四公路工程局有限公司 Pilot cable construction method for erecting main cable of cable crane in ultra-deep valley
CN114182633A (en) * 2021-10-22 2022-03-15 中交第二航务工程局有限公司 Suspension bridge catwalk whole span frame management method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1936189A (en) * 2006-10-13 2007-03-28 浙江省舟山连岛工程建设指挥部 Method for erecting guide-cable in suspension cable bridge traction system
US7415746B2 (en) * 2005-12-01 2008-08-26 Sc Solutions Method for constructing a self anchored suspension bridge
CN101476293A (en) * 2009-01-16 2009-07-08 广东省长大公路工程有限公司 Non-stand construction method for large bridge arch rib
CN102277833A (en) * 2011-04-29 2011-12-14 中交第一公路工程局有限公司 Guide cable installing method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7415746B2 (en) * 2005-12-01 2008-08-26 Sc Solutions Method for constructing a self anchored suspension bridge
CN1936189A (en) * 2006-10-13 2007-03-28 浙江省舟山连岛工程建设指挥部 Method for erecting guide-cable in suspension cable bridge traction system
CN101476293A (en) * 2009-01-16 2009-07-08 广东省长大公路工程有限公司 Non-stand construction method for large bridge arch rib
CN102277833A (en) * 2011-04-29 2011-12-14 中交第一公路工程局有限公司 Guide cable installing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周昌栋 等: "一种先导索过江法及空中横渡等综合技术的实践", 《公路》, no. 10, 31 October 2000 (2000-10-31) *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113414B (en) * 2015-09-11 2016-09-21 中铁八局集团桥梁工程有限责任公司 A kind of suspension bridge main rope fast erecting method
CN105256724A (en) * 2015-09-28 2016-01-20 中交二公局第二工程有限公司 Method of drawing pilot rope by unmanned aerial vehicle for river-crossing construction
CN106379765A (en) * 2016-10-21 2017-02-08 长江勘测规划设计研究有限责任公司 Clamp resetting structure and method for reclaiming main cable of cable crane
CN108018778A (en) * 2017-11-14 2018-05-11 中铁大桥局集团第六工程有限公司 The cat road rope in navigable waters does not set up trailer system and cat road rope fast erecting method
CN108018778B (en) * 2017-11-14 2023-11-07 中铁大桥局集团第六工程有限公司 Catwalk cable erection traction system and catwalk cable rapid erection method for non-navigable water area
CN108018844B (en) * 2017-12-01 2023-06-16 大连汇洋船务工程配套有限公司 Sinking-floating port safety door
CN108018844A (en) * 2017-12-01 2018-05-11 大连汇洋船务工程配套有限公司 A kind of floatable port security door
CN110306433A (en) * 2019-04-29 2019-10-08 中铁大桥局集团有限公司 A kind of turbulent flow waters guide cable is quick to cross river method
CN111441594A (en) * 2020-04-21 2020-07-24 中铁大桥局第七工程有限公司 Construction method of multilayer sectional type main cable
CN111441594B (en) * 2020-04-21 2021-10-26 中铁大桥局第七工程有限公司 Construction method of multilayer sectional type main cable
CN111622111A (en) * 2020-05-04 2020-09-04 中交第四公路工程局有限公司 Pilot cable construction method for erecting main cable of cable crane in ultra-deep valley
CN114182633A (en) * 2021-10-22 2022-03-15 中交第二航务工程局有限公司 Suspension bridge catwalk whole span frame management method
CN114182633B (en) * 2021-10-22 2023-04-28 中交第二航务工程局有限公司 Suspension bridge catwalk span-setting method

Also Published As

Publication number Publication date
CN102720141B (en) 2015-08-19

Similar Documents

Publication Publication Date Title
CN102720141B (en) Guide cable crosses the river construction method integrated with Traction sysytem
CN1160844C (en) Method for laying electrical cables for first offshore wind power plant to second offshore wind powder plant
CA2777282C (en) Vessel and method for transporting and hoisting the offshore wind turbine generator system
CN201447665U (en) Cable releasing device pulled by guide cable on water surface in wide-span suspension bridge construction
CN1936189B (en) Method for erecting guide-cable in suspension cable bridge traction system
CN109159860B (en) Traction system of cable laying ship
CN203129178U (en) Ultra-large type immersed tube stranded cable undock system
WO2016140892A4 (en) Reduced profile wind tower system for land-based and offshore applications
CN105256724A (en) Method of drawing pilot rope by unmanned aerial vehicle for river-crossing construction
CN112728211B (en) Construction method for carrying sewage sea area sea drainage pipe to put water in place and carry at sea in place
CN105604093A (en) Floating transportation construction method of immersed tube method tunnel pipe joint along foundation trench under high-flow-speed condition
CN110217346B (en) Method for towing offshore wind power installation vessel based on multi-point anchoring and positioning system
CN111252196B (en) Anti-collision warning system of underwater cable-stayed suspension tunnel
CN102787561B (en) Construction method of airship hauling pilot rope technology
CN106428429B (en) The method of floating production storage offloading's long pull
CN102277833A (en) Guide cable installing method
CN108018778B (en) Catwalk cable erection traction system and catwalk cable rapid erection method for non-navigable water area
CN208121573U (en) A kind of suspension bridge cat road rope water surface floating crosses erection construction system
CN105711746A (en) Ship dragging method and dragging tool
CN109901273B (en) Construction method for laying optical cable junction boxes on sea in ultra-deep water
JP2018039475A (en) Method for extension of mooring cable, method for mooring floating body structure and method for construction of floating body type offshore wind power generation facility
CN102361315B (en) Three synchronous laying construction method of underground cable in sea area
KR20180038700A (en) Ship mooring system with turning mooring post and mooring method using it
CN113605230A (en) Main cable traction system and method suitable for suspension bridge two-bank tunnel anchor
CN109163144A (en) Submarine pipeline terminates the repositioning method of submarine pipeline terminal when being laid with

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant