CN102704396A - Anchorage method for main cable of suspension bridge - Google Patents

Anchorage method for main cable of suspension bridge Download PDF

Info

Publication number
CN102704396A
CN102704396A CN201210213669XA CN201210213669A CN102704396A CN 102704396 A CN102704396 A CN 102704396A CN 201210213669X A CN201210213669X A CN 201210213669XA CN 201210213669 A CN201210213669 A CN 201210213669A CN 102704396 A CN102704396 A CN 102704396A
Authority
CN
China
Prior art keywords
anchor
suspension bridge
pull bar
anchorage
main rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210213669XA
Other languages
Chinese (zh)
Inventor
赵鹏贤
刘昌华
陈远林
杨芙蓉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN TIANYUAN MECHANICAL ENGINEERING CO LTD
Original Assignee
SICHUAN TIANYUAN MECHANICAL ENGINEERING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN TIANYUAN MECHANICAL ENGINEERING CO LTD filed Critical SICHUAN TIANYUAN MECHANICAL ENGINEERING CO LTD
Priority to CN201210213669XA priority Critical patent/CN102704396A/en
Publication of CN102704396A publication Critical patent/CN102704396A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides an anchorage method for a main cable of a suspension bridge. Anchor heads are arranged on the two ends of the main cable of the suspension bridge, wherein the anchor heads are fixedly connected with an anchor by a connecting device; and a preserved hole for penetrating through the two ends of the anchor is formed in the anchor. The anchorage method is characterized in that the connecting device is a tension rod arranged in the preserved holes of the anchor; the two ends, i.e., the front end and the rear end, of the tension rod extend out of the surface of the anchor, wherein the front end of the tension rod is connected with the anchor heads, and the rear end of the tension rod is connected with an anchor bearing plate. The anchorage method for the main cable of the suspension bridge is reliable in anchorage, high in connecting strength, simple in a connecting structure, convenient to construct, specific in stress, low in strength requirements for each connecting member, time-saving and force-saving, capable of greatly reducing the cost and suitable for large-scale application and popularization.

Description

A kind of main rope of suspension bridge anchoring process
Technical field
The present invention relates to a kind of anchoring process, specifically is a kind of main rope of suspension bridge anchoring process.
Background technology
The main supporting member of suspension bridge is a main push-towing rope, and main push-towing rope normally forms an integral body by the very high steel wire of some tensile strength by the mode that is arranged in parallel, and the two ends of main push-towing rope are through anchorage 5 and basic anchor connection.Because whether the anchoring property of main push-towing rope reliably is directly connected to the safety of suspension bridge, therefore, during the main push-towing rope anchoring, with anchorage 5 sizes do enough big, to guarantee itself and basic bonding strength.Simultaneously main push-towing rope is dispersed through loose cable saddle or diffusing noose and be multiply strand 1; Pass the preformed hole 4 in the anchorage 5; Carry out anchoring in anchorage 5 back,, reduce the pressure of main push-towing rope anchorage 5 to enlarge the contact area of main push-towing rope and anchorage 5; For reducing the influence of 4 pairs of anchorage 5 intensity of preformed hole, the size of preformed hole 4 is as far as possible little.
As shown in Figure 1; The anchoring process of traditional main push-towing rope and anchorage 5 is prestress wire 6 anchoring process; To be connected with anchorage 5 respectively through the strand 1 usefulness multi beam prestress wire of dispersing 6; Its method of attachment is that front end is connected with strand 1 through connector 3, and the rear end is fixing on the back anchor face of anchorage 5 through anchor plate 7 and ground tackle 8.
Because front end connects through connector 3, connector 3 is connected with strand 1 again, this multiple connection, and power transmission is complicated.Each connector requirement of strength is increased, and syndeton is more complicated, construction is more difficult.
Because steel strand 6 are standardization approved products, its maximum functional intensity is a rated value.Therefore in order to ensure bonding strength, the bundle number of steel strand 6 is more.Because anchorage 5 sizes are big, steel strand 6 length are big, cause steel strand 6 degree of disturbing big.
Steel strand 6 quantity are many, length is long, degree of disturbing is big, little these four factors of preformed hole 4 sizes, determined very difficulty of the installation of steel strand 6 anchorage 5 in, simultaneously for guaranteeing the safety of steel strand 6, must guarantee its every stressed even, difficulty of construction is very big.
Summary of the invention
The objective of the invention is to: the deficiency to above-mentioned prior art provides a kind of easy row convenient and simple for operation, efficient quick, practical and reliable main rope of suspension bridge anchoring process.
The technical scheme that the present invention adopts is:
A kind of main rope of suspension bridge anchoring process, said main rope of suspension bridge two ends are provided with anchor head, and anchor head is fixedly connected with the anchor ingot through linkage, and the anchor ingot is provided with the preformed hole that runs through its two ends; It is characterized in that: said linkage is arranged on the interior pull bar of preformed hole of anchor ingot, and the two ends of pull bar are all stretched out the anchor ingot surface, are called the front-end and back-end of pull bar, and wherein: the front end of pull bar connects anchor head, the rear end connects anchor plate.
Said pull bar front end is provided with external screw thread, the anchor head rear end is provided with internal thread intermeshing with it.
Said anchor plate is provided with the installing hole of pull bar, and back end of tie rod passes this installing hole, makes anchor plate be adjacent to anchor ingot end face, and the back end of tie rod behind the anchor plate is provided with external screw thread and supporting locking nut thereof.
Be provided with spherical washer between said anchor plate and the locking nut.
The technique effect that the present invention produces is:
Main rope of suspension bridge anchoring process of the present invention, anchoring is reliable, bonding strength is high, simple, the easy construction, stressed clear of syndeton, little for the requirement of strength of each connector, time saving and energy saving, cost significantly reduces, and is applicable to use on a large scale and promote.
Description of drawings
Fig. 1 is the structural representation of the prestress wire anchoring process of prior art;
Fig. 2 is the structural representation of anchoring process of the present invention;
Label is represented among the figure: 1-strand, 2-anchor head, 3-connector, 4-preformed hole, 5-anchorage, 6-prestress wire, 7-anchor plate, 8-ground tackle, 9-pull bar, 10-Internal Spherical Surface packing ring, 11-spherical outside surface packing ring, 12-nut.
The specific embodiment
As shown in Figure 2; The present invention is a kind of main rope of suspension bridge anchoring process; Main rope of suspension bridge is dispersed through loose cable saddle or diffusing noose and is multiply strand 1, and the two ends of strand 1 are provided with anchor head 2, and anchor head 2 is fixedly connected with anchor ingot 5 through linkage; The back anchor face of anchorage 5 is fixedly connected with anchor plate 7, anchor plate 7 is fixed on the concrete foundation again.
Anchor ingot 5 is provided with the preformed hole 4 that runs through its two ends, and linkage of the present invention is arranged on the push-and-pull rod 9 in the preformed hole 4 of anchor ingot 5.The two ends of pull bar 9 are all stretched out anchor ingot 5 surfaces, are called the front-end and back-end of pull bar 9, and wherein: the front end of pull bar 9 connects anchor head 2, the rear end connects anchor plate 7.The structure that is strand 1 of the present invention and anchorage 5 is the same with traditional anchorage style, but because its strand 1 directly is connected with anchorage 5 interior push-and-pull rods 9, makes stressed clear, simple in structure, the easy construction of main push-towing rope.
The rear end that the front end of pull bar 9 is provided with external screw thread, anchor head 2 is provided with internal thread intermeshing with it, thus with the front end of pull bar 9 through being threaded on the anchor head 2, make pull bar 9 and strand 1 be connected to one.
Anchor plate 7 is provided with the installing hole of pull bar 9; The rear end of pull bar 9 is passed this installing hole, is made anchor plate 7 be adjacent to the installation of anchor ingot 5 rear end faces; Pull bar 9 rear ends behind the anchor plate 7 are provided with external screw thread and supporting locking nut 12 thereof; Utilize anchor plate 7 to support, behind the tensile force of assurance pull bar 9, regulate back end nut 12, be that above-mentioned connection is locked.Simultaneously, be provided with spherical washer between anchor plate 7 and the locking nut 12, what make locking nut 12 and pull bar 9 rear end screw threads cooperates, realizes length adjustment and fastening, promptly makes adjustable positions between locking nut 12 and the anchor plate 7 (anchor ingot 5).This spherical washer is 2 supporting Internal Spherical Surface packing rings 10 and spherical outside surface packing ring 11, can realize the rotation of pull bar 9, prevents to install the bending that just do not causing pull bar 9, influences safety.

Claims (4)

1. main rope of suspension bridge anchoring process, said main rope of suspension bridge two ends are provided with anchor head, and anchor head is fixedly connected with the anchor ingot through linkage, and the anchor ingot is provided with the preformed hole that runs through its two ends; It is characterized in that: said linkage is arranged on the interior pull bar of preformed hole of anchor ingot, and the two ends of pull bar are all stretched out the anchor ingot surface, are called the front-end and back-end of pull bar, and wherein: the front end of pull bar connects anchor head, the rear end connects anchor plate.
2. main rope of suspension bridge anchoring process according to claim 1 is characterized in that: said pull bar front end is provided with external screw thread, the anchor head rear end is provided with internal thread intermeshing with it.
3. main rope of suspension bridge anchoring process according to claim 1; It is characterized in that: said anchor plate is provided with the installing hole of pull bar; Back end of tie rod passes this installing hole, makes anchor plate be adjacent to anchor ingot end face, and the back end of tie rod behind the anchor plate is provided with external screw thread and supporting locking nut thereof.
4. main rope of suspension bridge anchoring process according to claim 3 is characterized in that: be provided with spherical washer between said anchor plate and the locking nut.
CN201210213669XA 2012-06-27 2012-06-27 Anchorage method for main cable of suspension bridge Pending CN102704396A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210213669XA CN102704396A (en) 2012-06-27 2012-06-27 Anchorage method for main cable of suspension bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210213669XA CN102704396A (en) 2012-06-27 2012-06-27 Anchorage method for main cable of suspension bridge

Publications (1)

Publication Number Publication Date
CN102704396A true CN102704396A (en) 2012-10-03

Family

ID=46897428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210213669XA Pending CN102704396A (en) 2012-06-27 2012-06-27 Anchorage method for main cable of suspension bridge

Country Status (1)

Country Link
CN (1) CN102704396A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11117229A (en) * 1997-08-05 1999-04-27 Dyckerhoff & Widmann Ag Method for providing built-in tendon being freely pulled and pulling tendon and device for executing the method
CN2412028Y (en) * 1998-10-15 2000-12-27 侯引程 Bridge dragline structure
EP1065317A1 (en) * 1999-07-01 2001-01-03 GTM Construction S.A. Cable suspension for a suspension bridge
CN2448871Y (en) * 2000-11-14 2001-09-19 柳州市建筑机械总厂 Prestressed anchoring for suspension bridge
CN2510533Y (en) * 2001-09-12 2002-09-11 柳州市建筑机械总厂 Double-rope prestressed-anchor anchoring system
CN2527588Y (en) * 2002-01-30 2002-12-25 柳州市建筑机械总厂 Suspension bridge anchored grouser
CN2739227Y (en) * 2004-11-06 2005-11-09 柳州欧维姆机械股份有限公司 Changeable suspension bridge anchored prestressed anchoring system
CN202031026U (en) * 2011-04-02 2011-11-09 柳州欧维姆机械股份有限公司 Finished cable type anchorage anchoring system
CN202031027U (en) * 2011-04-02 2011-11-09 柳州欧维姆机械股份有限公司 Whole replaceable anchorage system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11117229A (en) * 1997-08-05 1999-04-27 Dyckerhoff & Widmann Ag Method for providing built-in tendon being freely pulled and pulling tendon and device for executing the method
CN2412028Y (en) * 1998-10-15 2000-12-27 侯引程 Bridge dragline structure
EP1065317A1 (en) * 1999-07-01 2001-01-03 GTM Construction S.A. Cable suspension for a suspension bridge
CN2448871Y (en) * 2000-11-14 2001-09-19 柳州市建筑机械总厂 Prestressed anchoring for suspension bridge
CN2510533Y (en) * 2001-09-12 2002-09-11 柳州市建筑机械总厂 Double-rope prestressed-anchor anchoring system
CN2527588Y (en) * 2002-01-30 2002-12-25 柳州市建筑机械总厂 Suspension bridge anchored grouser
CN2739227Y (en) * 2004-11-06 2005-11-09 柳州欧维姆机械股份有限公司 Changeable suspension bridge anchored prestressed anchoring system
CN202031026U (en) * 2011-04-02 2011-11-09 柳州欧维姆机械股份有限公司 Finished cable type anchorage anchoring system
CN202031027U (en) * 2011-04-02 2011-11-09 柳州欧维姆机械股份有限公司 Whole replaceable anchorage system

Similar Documents

Publication Publication Date Title
CN101831871B (en) Adjustable wind cable and installing method thereof
CN201635015U (en) Adjustable guy rope
CN203383401U (en) Clamping anchor for carbon-fiber composite material bar
CN104847122B (en) Device assembly for tensioning fork ear type stay rope or steel pull rod and tensioning construction method of device assembly
CN101603353A (en) A kind of composite anchorage that is used for anchoring multiple fibre reinforced plastic twisted wire muscle or drag-line
CN203412200U (en) Slotting clamping piece prestress fiber reinforcing compound material rope anchoring device
CN102747683B (en) Wire dividing plate of cold cast anchorage and wire dividing method thereof
CN202611109U (en) Steel strand connector
CN100567680C (en) Backstay cable lever stretching device
CN204475874U (en) A kind of novel pre-stressed steel strand draw-gear
CN201567677U (en) Stretching device for prestress applying bolt for cable membrane structure
CN102587572A (en) Steel strand stay rope and manufacturing method thereof
CN112376916A (en) Prestressed steel cable tensioning and tightening device and construction method
CN105064214A (en) Stay cable tension device for eliminating back-twist
CN102704396A (en) Anchorage method for main cable of suspension bridge
CN204174840U (en) The locking ground tackle of prestress anchoraging
CN102561599A (en) Connector of steel stranded wires and finished twisted steel
CN109441122B (en) I-beam prestress application device
CN202391018U (en) Connector between steel strand and finished deformed bar
CN202519876U (en) Steel strand inhaul cable
CN214462686U (en) Prestress steel cable tensioning and tightening device
CN208815415U (en) A kind of steel strand penetrating device
CN103352538A (en) Prestress fiber reinforced polymer cable anchoring device with auxiliary clamp rings
CN203412199U (en) Prestressed fiber reinforced composite cable anchoring device with auxiliary clamp rings
CN203743308U (en) Rope fastening device of hoisting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121003