CN102693675A - Movable Gantt chart drawing tool - Google Patents

Movable Gantt chart drawing tool Download PDF

Info

Publication number
CN102693675A
CN102693675A CN2012101082758A CN201210108275A CN102693675A CN 102693675 A CN102693675 A CN 102693675A CN 2012101082758 A CN2012101082758 A CN 2012101082758A CN 201210108275 A CN201210108275 A CN 201210108275A CN 102693675 A CN102693675 A CN 102693675A
Authority
CN
China
Prior art keywords
teams
piece
gantt chart
gunter
chart
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101082758A
Other languages
Chinese (zh)
Inventor
许强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2012101082758A priority Critical patent/CN102693675A/en
Publication of CN102693675A publication Critical patent/CN102693675A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Drawing Aids And Blackboards (AREA)

Abstract

The invention discloses a movable Gantt chart drawing tool, and belongs to tools for drawing Gantt charts for national project management sand table competition. The movable Gantt chart drawing tool is mainly used for clearly, simply and quickly drawing Gantt charts, and comprises a Gantt chart board, I-shaped blocks and rectangular blocks, component numbers are printed on the rectangular blocks, and the I-shaped blocks replace weekly work output of various labor teams. The purpose of quickly drawing a Gantt chart is achieved by means of moving the I-shaped blocks on the Gantt chart board, erasing and testing links in a drawing and testing process are omitted, drawing efficiency is improved, a thinking process when the Gantt chart is drawn is clearly displayed on the 'board' via movement of the I-shaped blocks, cooperation of members in the teams is promoted, and cooperation spirit of the teams is strengthened.

Description

Packaged type establishment Gantt chart instrument
Technical field
The present invention relates to a kind of packaged type establishment Gantt chart instrument, belong to the instrument of establishment Gantt chart in the contest of national project management sand table, be mainly used in clear, work out Gantt chart succinctly, fast.
Technical background
In order to improve the adaptive faculty of university student under the fierce market competition environment; Wide Lian Da company has held the contest of project management sand table in the whole nation; Being intended to cultivate student's integrated use has gained knowledge and has taken action on one's own to solve the ability of enterprise practical problem; Strengthen undergraduate project management knowledge, improve manipulative ability, promote undergraduate overall qualities comprehensively, strengthen undergraduate employment competition advantage.This match is considered the Whole Course Management that engineering project finishes until completion of works from engineering acceptance of the bid beginning based on engineering construction unit visual angle; Through the simulating reality work progress, make student enrollment's registration leading zero apart from experiencing construction enterprises' practical project project management operation.
In this match, the establishment of programming phase Gantt chart is the key of the last victory or defeat of decision race-entry group, and its directly good and bad and final profit of project is got in touch, yet in the process of establishment Gantt chart, but has many problems:
1. in order to work out optimum scheme, in the process of establishment, need constantly relatively and trial, yet think during the course that interim change pillar and the sequence of construction between the pillar can be very loaded down with trivial details; If it is good to make the scheme of revising before the back is found to be not so good as to revise during the course, the scheme of wanting to change back before revising is difficult especially.Because the scheme vestige in the process of wiping and revising before revising has disappeared completely, add the influence of being revised the back thinking, the thinking of scheme is also interrupted completely before revising; At this moment the organizer understand thinking completely without; The brains complete confusion, the accent of having to begins, and loses time very much.
2. after Gantt chart is finished substantially, need carry out the part and transfer with the reduction of erection time, when seeking preferred plan, its process is complicated especially and difficult.There has been new thinking to want to attempt, but worried that the scheme before the debugging back is not as debugging is good, and can't reduce scheme before the debugging this moment, irresolute; Do not debug, do not know again which scheme is good on earth, unwilling in the heart.
3. generally work out Gantt chart in the group separately separately, the common completion of can't cooperating with each other will certainly be walked some detours in the process; After working out, spend the plenty of time to compare the quality of different schemes in the group again, this has had a strong impact on the efficient and the quality of Gantt chart establishment.
Summary of the invention
To the many shortcomings that exist in the present national project management sand table contest establishment Gantt chart process, the present invention provides a kind of packaged type establishment Gantt chart instrument.
The present invention realizes through following technical scheme: a kind of packaged type is worked out the Gantt chart instrument, comprises I shape piece and a plurality of rectangular parallelepiped piece of a plurality of three kinds of different colors of gunter chart board and the split of gunter chart board; Described gunter chart board is to have the chart board that magnetic attaches function, obdurability, on the front of gunter chart board, is printed with the form that is used to work out Gantt chart; Described I shape piece and rectangular parallelepiped piece can be adsorbed on the gunter chart board and can move; The I shape piece of three kinds of different colors is respectively applied for expression: reinforcing bar teams and groups work output/week; One template teams and groups work output/week; One concrete teams and groups work output/week; Be printed on the member numbering on rectangular parallelepiped piece surface.
Concrete method of application is: in establishment Gantt chart process, replace each labor service teams and groups unit week work output with the I shape piece, through on the gunter chart board, moving; Reach the purpose of quick establishment Gantt chart, saved wiping, test ring joint in establishment, the debug process, improved drawing efficiency; And the thinking processes in the time of will working out; Appear vividly clearly " on the plate " through moving of I shape piece, promote group member's cooperation, strengthened the team spirit of team.
The invention has the beneficial effects as follows:
1. will work out the thinking of Gantt chart, appear vividly clearly " on the plate " strengthened visuality.
2. when the Gantt chart scheme being debugged, convenient and swift, wiping in the middle of saving, test ring joint, thinking is not easy to upset; New thinking can access fast and attempt, and broadens one's scope of mind so more easily, produces inspiration.
3. open to discussion in the group, accomplish the establishment of Gantt chart jointly, improve the speed and the quality of establishment Gantt chart greatly.
4. according to actual needs, make the suitable magnet board of a block size, this achievement is introduced the classroom of university's " construction organization design " subject; Through practical operation establishment Gantt chart; Its knowwhy is shown clearly, improve undergraduate interest, strengthen classroom learning efficient.
Description of drawings
Fig. 1 is an one-piece construction synoptic diagram of the present invention;
Fig. 2 is an embodiment PORT OF TIANJIN construction drawing synoptic diagram;
Fig. 3 prepares synoptic diagram when member D-1 begins in the embodiment PORT OF TIANJIN;
Fig. 4 is the first procedure synoptic diagram of reinforcing bar teams and groups of member D-1 in the embodiment PORT OF TIANJIN;
Fig. 5 is the first procedure synoptic diagram of two reinforcing bar teams and groups of member D-1 in the embodiment PORT OF TIANJIN;
Fig. 6 is the second operation work synoptic diagram of template teams and groups of member D-1 in the embodiment PORT OF TIANJIN;
Fig. 7 is the second operation work synoptic diagram of two template teams and groups of member D-1 in the embodiment PORT OF TIANJIN;
Fig. 8 is the three process synoptic diagram of concrete teams and groups of member D-1 in the embodiment PORT OF TIANJIN;
Fig. 9 is the overall schedule in embodiment PORT OF TIANJIN---a Gantt chart synoptic diagram.
Among the figure: 1, gunter chart board, 2, I-shaped, 1. blue I-shaped, 2. orange I-shaped, 3. the purple color mixture of powder is I-shaped, and 3, rectangular blocks.
Embodiment
Below in conjunction with accompanying drawing and embodiment the present invention nearly is gone on foot explanation.
As shown in Figure 1, a kind of packaged type is worked out the gunter chart board, comprises I shape piece 2 and a plurality of rectangular parallelepiped piece 3 of gunter chart board 1, a plurality of three kinds of different colors; Described gunter chart board 1 is for to have the chart board that magnetic attaches function, obdurability, and magnetic attaches function, the obdurability material is processed by having.On the front of gunter chart board 1, be printed with the form that is used to work out Gantt chart; In the embedding of the bottom surface of each I shape piece 2 and rectangular parallelepiped piece 3 permanent magnet is arranged, I shape piece 2 and rectangular parallelepiped piece 3 can be adsorbed on the gunter chart board 1 also can move; The I shape piece 2 of three kinds of different colors is respectively applied for representative: reinforcing bar teams and groups work output/week; One template teams and groups work output/week; One concrete teams and groups work output/week; Be printed on the member numbering on rectangular parallelepiped piece 3 surfaces.
2 fens oranges of above-mentioned I shape piece, indigo plant, three kinds of colors of the purple color mixture of powder, 1. a blue I shape piece representes reinforcing bar teams and groups work 5 tons/week of output; 2. an orange I shape piece representes template teams and groups work output 5 square meters/week; 3. the purple color mixture I shape of a powder piece representes concrete teams and groups work 10 cubes/week of output.
In the present embodiment: totally 15 of rectangular parallelepiped pieces 3; Upper surface is printed on JC, D-1~D-4, B-12, B-23, B-34, B-13, B-14, B-24 member numbering respectively, remain four subsequent use.The I shape piece of every kind of color is 15~30 in the I shape piece 2 of three kinds of different colors.
Concrete method for making is: the form that will be used to work out Gantt chart is printed on to have magnetic and attaches on the thin plate that function, obdurability material make and process gunter chart board 1.Respectively 15~30 of the I shape pieces 2 of indigo plant made of plastic then, orange, three kinds of colors of the purple mixing of powder, the bottom surface embeds permanent magnet, can be adsorbed on the gunter chart board 1.Wherein, 1. a blue I shape piece representes reinforcing bar teams and groups work 5 tons/week of output; 2. one orange I shape piece representes template teams and groups work output 5 square meters/week; 3. the purple color mixture I shape of one powder piece representes concrete teams and groups work 10 cubes/week of output.Totally 15 of rectangular parallelepiped pieces 3 made of plastic, upper surface are printed on members such as JC, D-1~D-4, B-12, B-23, B-34, B-13, B-14, B-24 numbering respectively, remain four subsequent use.
Embodiment
Utilize first the project management sand table contest examination question in the achievement establishment whole nation of the present invention: the schedule of PORT OF TIANJIN---Gantt chart.
The PORT OF TIANJIN construction drawing is as shown in Figure 2.
The drawing explanation: each member comprises three operations; Post (reinforcing bar binding-formwork erection-concrete is built) plate (formwork erection-reinforcing bar binding-concrete is built); After two pillar concretes had been built, the plate of its top can be constructed, after concreting is accomplished; The template circulation material can be removed, and the construction of template teams and groups need not be considered form removal and maintenance.
Bill of quantities: the quantities of describing this each member working procedure of project engineering
Figure 2012101082758100002DEST_PATH_IMAGE002
Concrete operation method is:
With member D-1 is example
As shown in Figure 3, at first get the purple color mixture I shape of rectangular parallelepiped piece D-1,1. two of blue I shape pieces, 2. two of orange I shape pieces, powder piece 3. one be placed on respectively on the corresponding position.
First procedure: tie up reinforcing bar
As shown in Figure 4, if teams and groups, 1. two blue I shape pieces be arranged in order move to second all corresponding positions.
As shown in Figure 5, if 1. two teams and groups move to second all corresponding positions side by side with two blue I shape pieces.
Second operation work a: template
As shown in Figure 6, if teams and groups, 2. two orange I shape pieces be arranged in order move to the 3rd all corresponding positions.
As shown in Figure 7, if 2. two teams and groups move to the 3rd all corresponding positions side by side with two orange I shape pieces.
Three process: pouring concrete
As shown in Figure 8,3. the purple color mixture I shape of powder piece moved to the around the corresponding position.
Other members are the same.
The overall schedule in PORT OF TIANJIN---Gantt chart is as shown in Figure 9.

Claims (5)

1. a packaged type establishment Gantt chart instrument is characterized in that: the I shape piece (2) and a plurality of rectangular parallelepiped piece (3) that comprise a plurality of three kinds of different colors of gunter chart board (1) and the split of gunter chart board; Described gunter chart board (1) is printed with the form that is used to work out Gantt chart for to have the chart board that magnetic attaches function, obdurability on the front of gunter chart board (1); Described I shape piece (2) and rectangular parallelepiped piece (3) can be adsorbed on the gunter chart board and can move; The I shape piece (2) of three kinds of different colors is respectively applied for representative: reinforcing bar teams and groups work output/week; One template teams and groups work output/week; One concrete teams and groups work output/week; Be printed on the member numbering on rectangular parallelepiped piece (3) surface; The length of each I shape piece (2) is identical with the length that gunter chart board (1) is gone up a cycle of expression, and width is 1/2 of the last working procedure length of gunter chart board (1).
2. packaged type establishment Gantt chart instrument according to claim 1, it is characterized in that: said I shape piece (2) divides blue, orange, three kinds of colors of the purple color mixture of powder, and 1. a blue I shape piece representes reinforcing bar teams and groups work 5 tons/week of output; 2. an orange I shape piece representes template teams and groups work output 5 square meters/week; 3. the purple color mixture I shape of a powder piece representes concrete teams and groups work 10 cubes/week of output.
3. packaged type establishment Gantt chart instrument according to claim 1, it is characterized in that: embedding in the bottom surface of each I shape piece (2) and rectangular parallelepiped piece (3) has permanent magnet.
4. packaged type establishment Gantt chart instrument according to claim 1 is characterized in that: 15 of said rectangular parallelepiped pieces (3) totally; Upper surface is printed on JC, D-1~D-4, B-12, B-23, B-34, B-13, B-14, B-24 member numbering respectively, remain four subsequent use.
5. packaged type establishment Gantt chart instrument according to claim 1, it is characterized in that: the I shape piece of every kind of color is 15~30 in the I shape piece (2) of said three kinds of different colors.
CN2012101082758A 2012-04-13 2012-04-13 Movable Gantt chart drawing tool Pending CN102693675A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101082758A CN102693675A (en) 2012-04-13 2012-04-13 Movable Gantt chart drawing tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101082758A CN102693675A (en) 2012-04-13 2012-04-13 Movable Gantt chart drawing tool

Publications (1)

Publication Number Publication Date
CN102693675A true CN102693675A (en) 2012-09-26

Family

ID=46859065

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101082758A Pending CN102693675A (en) 2012-04-13 2012-04-13 Movable Gantt chart drawing tool

Country Status (1)

Country Link
CN (1) CN102693675A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104183173A (en) * 2014-09-19 2014-12-03 鲁东大学 Teaching aid used for workshop scheduling teaching
CN105512099A (en) * 2015-12-09 2016-04-20 金蝶软件(中国)有限公司 Gantt chart generation method and device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000013160A2 (en) * 1998-08-31 2000-03-09 Celemiab Systems Ab Simulation system i
CN201181528Y (en) * 2007-12-12 2009-01-14 谭俊峰 Simulation sandbox experiment real training teaching aid for enterprise management
CN101707022A (en) * 2009-11-10 2010-05-12 吕明哲 Teaching aids simulating production process and usage thereof
CN202601080U (en) * 2012-04-13 2012-12-12 许强 Movable Grant chart compiling tool

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000013160A2 (en) * 1998-08-31 2000-03-09 Celemiab Systems Ab Simulation system i
CN201181528Y (en) * 2007-12-12 2009-01-14 谭俊峰 Simulation sandbox experiment real training teaching aid for enterprise management
CN101707022A (en) * 2009-11-10 2010-05-12 吕明哲 Teaching aids simulating production process and usage thereof
CN202601080U (en) * 2012-04-13 2012-12-12 许强 Movable Grant chart compiling tool

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104183173A (en) * 2014-09-19 2014-12-03 鲁东大学 Teaching aid used for workshop scheduling teaching
CN105512099A (en) * 2015-12-09 2016-04-20 金蝶软件(中国)有限公司 Gantt chart generation method and device
CN105512099B (en) * 2015-12-09 2020-04-28 金蝶软件(中国)有限公司 Gantt chart generation method and apparatus

Similar Documents

Publication Publication Date Title
Brenner et al. Scaled Agile Framework: Presentation and real world example
CN202601080U (en) Movable Grant chart compiling tool
CN101299153A (en) Computer auxiliary assembly process control method facing to manual assembly
CN102693675A (en) Movable Gantt chart drawing tool
WO2018026424A3 (en) Nanoscale nuclear quadrupole resonance spectroscopy
CN109583145A (en) A kind of assembled architecture design method
Huntzinger Why standard work is not standard: training within industry provides an answer
Bademosi et al. Skills Assessment for Robotics in Construction Education.
Bednarek et al. The Methodology of implementation of kaizen in selected polish industrial plants
Biedry Linking Six Sigma analysis with human creativity
Lima et al. An experience of teaching industrial automation for industrial engineering undergraduate students
Wang et al. Research Article Research on Engineering Education Mode Based on CDIO Concept: Take Food Machinery Major as an Example
Weissbach et al. Industrial Sponsor Perspective on Leveraging Capstone Design Projects to Enhance Their Business.
Baleshta Increasing student practical experience with the hurdle of large class sizes
Nichols A comparative study of four bond wrenches with recommendations on changes to ASTM C1072
Shao et al. Application of case teaching method in electrical control technology
Zhu et al. Design and Implementation of Project Based Curriculum under" 1+ X" Certificate System-“Machining Technology” Course as an Example
Kathawala et al. Quality in a global context: a framework for analysis
Jiang et al. The new teaching model research on supply chain management course
Feng Exploration and Practice on Industrial Robot Experimental Teaching Based on Virtuality and Reality Combination
CN209620759U (en) A kind of modularization enclosure wall
Lopez et al. Using problem-based learning to engage engineering students in circular economy
CN108333037B (en) Actuator connecting device for three-dimensional pseudo-static test
Edl Educational framework of Product Lifecycle Management issues for Master and PhD study programmes
Gao et al. Research on Talents Training of Software Service Outsourcing for Japan Based on School-Enterprise Cooperation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120926