On livewire work circuit for connecting the T connection device of upper fourth cross-arm
Technical field
The present invention relates on a kind of livewire work circuit for connecting the T connection device of upper fourth cross-arm, belong to the mounting technique field of upper fourth cross-arm on alive circuit.
Background technology
The transformer of installing on transmission line of electricity, need to do and become platform down lead by means of upper fourth cross-arm, connects and draws rear use.At present, the mode of installing fourth cross-arm is roughly divided into following two kinds: first kind of way is that on replacing transmission line of electricity, original straight line pole cross-arm is the special cross-arm that can install fourth cross-arm, then carry out the installation of upper fourth cross-arm, this mounting method is due to livewire work on the line, make construction method complexity, have certain hazards; The second way is for to install after support cross arm below transmission line of electricity, then installs in the above fourth cross-arm, although this operational method has solved safety problem, owing to installing support cross arm additional, makes to cause the waste of material.
Summary of the invention
The present invention is the installation in order to solve upper fourth cross-arm on existing transmission line of electricity, and construction complexity and unsafe problem, provide on a kind of livewire work circuit for connecting the T connection device of upper fourth cross-arm.
On livewire work circuit of the present invention, for connecting the T connection device of upper fourth cross-arm, it comprises straight line pole cross-arm, and it also comprises that T connects transverse link, T connects longitudinal rod and two quarter bend studs,
T connects transverse link, T connects longitudinal rod and straight line pole cross-arm is made by angle steel, and straight line pole cross-arm and T connect longitudinal rod and be socketed with opening direction, and straight line pole cross-arm is positioned at T and connects longitudinal rod,
The middle part that T connects transverse link has outward extending brace, this brace clamping connection is fixed on straight line pole cross-arm and T connects between longitudinal rod, make T connect transverse link and connect with T that longitudinal rod is T-shaped to be connected, straight line pole cross-arm, T connect longitudinal rod and brace is bolted
On each quarter bend stud, there are two and coordinate right angle pad and two nuts, a right-angle plane of each cooperation right angle pad is enclosed within on quarter bend stud, the two ends of each quarter bend stud are combined with respectively a nut, and two quarter bend studs connect longitudinal rod by T and are fixedly connected with straight line pole cross-arm.
Described T connects on longitudinal rod along two locating slots of horizontally set, and these two locating slots are for realizing spacing to two quarter bend studs.
Described two locating slots connect on longitudinal rod and are symmetric along horizontal center line at T.
It also comprises boss, and this boss is arranged on T and connects the lateral middle of longitudinal rod.
Advantage of the present invention is: the present invention by installing one group of linkage additional on original straight line pole cross-arm, original straight line pole cross-arm can be effectively connected easily with upper fourth cross-arm, make the livewire work process on transmission line of electricity safer, and construction method is simple, convenient.
Safety of the present invention and economy are taken into account, and have both ensured work progress personnel's safety, make again the process of charged installation become simply, and operating efficiency is high.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is the A-A view of Fig. 1;
Fig. 4 is the structural representation that T connects transverse link and brace;
Fig. 5 is the structural representation of embodiment four;
Fig. 6 is the use view after the present invention is connected with upper fourth cross-arm.
The specific embodiment
The specific embodiment one: present embodiment is described below in conjunction with Fig. 1 to Fig. 6, described in present embodiment on livewire work circuit for connecting the T connection device of upper fourth cross-arm, it comprises straight line pole cross-arm 1, and it also comprises that T connects transverse link 2, T connects longitudinal rod 3 and two quarter bend studs 4
T connects transverse link 2, T connects longitudinal rod 3 and straight line pole cross-arm 1 is made by angle steel, and straight line pole cross-arm 1 and T connect longitudinal rod 3 with opening direction socket, and straight line pole cross-arm 1 is positioned at T and connects longitudinal rod 3,
The middle part that T connects transverse link 2 has outward extending brace 2-1, this brace 2-1 clamping connection is fixed on straight line pole cross-arm 1 and T connects between longitudinal rod 3, make T connect transverse link 2 and connect with T that longitudinal rod 3 is T-shaped to be connected, straight line pole cross-arm 1, T connect longitudinal rod 3 and brace 2-1 is bolted
On each quarter bend stud 4, there are two and coordinate right angle pad 4-1 and two nuts, a right-angle plane of each cooperation right angle pad 4-1 is enclosed within on quarter bend stud 4, the two ends of each quarter bend stud 4 are combined with respectively a nut, and two quarter bend studs 4 connect longitudinal rod 3 by T and are fixedly connected with straight line pole cross-arm 1.
Present embodiment cathetus bar cross-arm 1 is original accessory in distribution line, in order to install on the line fourth cross-arm, by introducing T connection device, realize the direct installation in charged situation on straight line pole cross-arm 1 of upper fourth cross-arm, got rid of the hazards in charging construction process, it is simple and easy that work progress becomes.
The specific embodiment two: present embodiment is described below in conjunction with Fig. 2, present embodiment is further illustrating embodiment one, described in present embodiment, T connects on longitudinal rod 3 along two locating slots of horizontally set, and these two locating slots are for realizing spacing to two quarter bend studs 4.
What in present embodiment, locating slot connect longitudinal rod 3 at T has laterally carried out spacingly to quarter bend stud 4, can realize that T is connect to longitudinal rod 3 and straight line pole cross-arm 1 is better fixing each other.
The specific embodiment three: below in conjunction with Fig. 2, present embodiment is described, present embodiment is to the further illustrating of embodiment two, two locating slots connect on longitudinal rod 3 and are symmetric along horizontal center line at T described in present embodiment.
It is better that the set-up mode of the locating slot in present embodiment makes T connect the stability that longitudinal rod 3 and straight line pole cross-arm 1 interfix.
The specific embodiment four: present embodiment is described below in conjunction with Fig. 5, present embodiment is further illustrating embodiment one, present embodiment also comprises two couples of gag lever post 3-1, two couples of gag lever post 3-1 connect on longitudinal rod 3 along horizontally set at T, for realizing spacing to two quarter bend studs 4, these two couples of gag lever post 3-1 connect on longitudinal rod 3 and are symmetric along horizontal center line at T.
In present embodiment, by two couples of gag lever post 3-1, carry out the spacing of quarter bend stud 4.
The specific embodiment five: present embodiment is described below in conjunction with Fig. 1, Fig. 2, Fig. 5 and Fig. 6, present embodiment is further illustrating embodiment one, two, three or four, present embodiment also comprises boss 3-2, and this boss 3-2 is arranged on T and connects the lateral middle of longitudinal rod 3.
In Fig. 6, upper fourth cross-arm 5 is inserted into T and is connect the Kong Zhonghou of a sidewall of transverse link 2 by two connectors, and connecing transverse link 2 with T can achieve a fixed connection by bolt.