CN102680798B - 杆塔接地电阻在线测量方法与装置 - Google Patents

杆塔接地电阻在线测量方法与装置 Download PDF

Info

Publication number
CN102680798B
CN102680798B CN201210046011.4A CN201210046011A CN102680798B CN 102680798 B CN102680798 B CN 102680798B CN 201210046011 A CN201210046011 A CN 201210046011A CN 102680798 B CN102680798 B CN 102680798B
Authority
CN
China
Prior art keywords
centerdot
prime
module
voltage
current
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210046011.4A
Other languages
English (en)
Other versions
CN102680798A (zh
Inventor
王涛
鲁守银
隋首钢
高焕兵
刘存根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jianzhu University
Original Assignee
Shandong Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jianzhu University filed Critical Shandong Jianzhu University
Priority to CN201210046011.4A priority Critical patent/CN102680798B/zh
Publication of CN102680798A publication Critical patent/CN102680798A/zh
Application granted granted Critical
Publication of CN102680798B publication Critical patent/CN102680798B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Measurement Of Resistance Or Impedance (AREA)

Abstract

本发明提出一种在线测量接地电阻的方法及装置。采用钳表法,利用四对电压互感器PT和电流互感器CT分别接在杆塔左右两端的两条防雷线上,通过电压互感器将电压信号感应至防雷线,采集测量电流信号并通过滤波放大等信号处理环节,得到反馈电流与感应电压的关系,最终通过特定的计算方法,得到被测杆塔的接地电阻阻值。本发明实现了在杆塔顶端进行数据测量,可适用于含有多条引下线的杆塔,既可以解决防盗问题,又可以实现接地电阻的快速准确测量。

Description

杆塔接地电阻在线测量方法与装置
所属技术领域
本发明属于电力科学的高电压技术领域,涉及一种在线测量接地电阻的方法及装置,可适用于含有多条引下线的杆塔,并可将数据的远程传输,实现接地电阻的远程快速精确测量。
背景技术
接地电阻值是输电线路接地系统的重要技术指标。若设备的接地电阻超出正常范围,当发生电击情况时,会对电力系统设备造成严重破坏。为了保证各种电气设备利用电设备接地装置安全可靠运行,必须按规定定期对接地系统的接地电阻值进行测量检查。而由于输电系统杆塔数量众多,对接地系统的接地电阻进行现场实际测量便成为非常繁重的工作,一种杆塔接地电阻在线测量方法与装置能够实现接地电阻自动测量并将数据无线传输至监控中心计算机,极大降低劳动强度,减少因设备接地不良而导致的电力事故发生。
发明内容
为了克服现有的接地电阻测试方法中,测试人员必须到达测试现场,并且必须将杆塔多余引下线解开的问题,本发明提出一种在线测量接地电阻的方法及装置,该方法及装置一方面可以实现含有多条引下线杆塔的接地电阻自动测量,同时可以实现测量结果的自动远程传输至中心服务器并存储。
本发明解决其技术问题所采用的技术方案是:采用钳表法,利用四对电压互感器PT和电流互感器CT分别接在杆塔左右两端的两条防雷线上,由电压互感器感应至被测杆塔一个特定的电压信号,同时由电流互感器测量此时避雷线中的电流,并通过电流电压转换模块转换为电压值,再通过滤波模块滤波,根据被测量大小通过量程切换模块选择量程,再通过交直流转换模块转换为直流量并测量其大小,经过AD转换模块转换为数字量送入MCU单元,得到电压与电流的关系,最终通过特定的计算方法,得到被测杆塔的接地电阻阻值,该方法无需考虑杆塔接地引线数量,可适用于含有任意多条引下线的杆塔。
本发明所采用的测量接地电阻的方法,采用特定的计算方法,设Z为被测杆塔接地电阻阻抗值,ZL为左侧所有杆塔并联等效电阻阻抗值,Z1和Z2分别为被测杆塔与左侧第一级杆塔之间两防雷线等效电阻阻抗值,ZR为右侧所有杆塔并联等效电阻阻抗值,Z3和Z4分别为被测杆塔与右侧第一级杆塔之间两防雷线等效电阻阻抗值,如图1所示。
首先进行第一次测量,分别示意图中位置通过电压互感器施加电压同时利用电流互感器测量对应支路中所产生电流为可得如下矩阵方程:
I · 1 0 0 0 I · 1 + I · 3 0 I · 1 + I · 2 + I · 3 + I · 4 0 I · 2 0 0 I · 1 + I · 2 0 I · 1 + I · 2 + I · 3 + I · 4 0 0 I · 3 0 0 I · 3 + I · 4 I · 1 + I · 2 + I · 3 + I · 4 0 0 0 I · 4 0 I · 3 + I · 4 I · 1 + I · 2 + I · 3 + I · 4 Z 1 Z 2 Z 3 Z 4 Z L Z R Z = U · 1 U · 2 U · 3 U · 4
该方程的解不唯一,无法确定电路参数,因此,需进行第二次测量。按照同样的方法在相同位置施加第二次测量电压并再次测量各对应支路中所产生电流为补充至上式中,得:
I · 1 0 0 0 I · 1 + I · 2 0 I · 1 + I · 2 + I · 3 + I · 4 0 I · 2 0 0 I · 1 + I · 2 0 I · 1 + I · 2 + I · 3 + I · 4 0 0 I · 3 0 0 I · 3 + I · 4 I · 1 + I · 2 + I · 3 + I · 4 0 0 0 I · 4 0 I · 3 + I · 4 I · 1 + I · 2 + I · 3 + I · 4 I · 1 ′ 0 0 0 I · 1 ′ + I · 2 ′ 0 I · 1 ′ + I · 2 ′ + I · 3 ′ + I · 4 ′ 0 I · 2 ′ 0 0 I · 1 ′ + I · 2 ′ 0 I · 1 ′ + I · 2 ′ + I · 3 ′ + I · 4 ′ 0 0 I · 3 ′ 0 0 I · 3 ′ + I · 4 ′ I · 1 ′ + I · 2 ′ + I · 3 ′ + I · 4 ′ 0 0 0 I · 4 ′ 0 I · 3 ′ + I · 4 ′ I · 1 ′ + I · 2 ′ + I · 3 ′ + I · 4 ′ Z 1 Z 2 Z 3 Z 4 Z L Z R Z = U · 1 U · 2 U · 3 U · 4 U · 1 ′ U · 2 ′ U · 3 ′ U · 4 ′
分析电路,结合相关知识,可得结论:当满足
U · 1 ′ Z 2 + U 2 ′ Z 1 U · 1 Z 2 + U · 2 Z 1 ≠ U · 3 ′ Z 4 + U 4 ′ Z 3 U 3 Z 4 + U 4 + Z 3
时,方程的解存在并唯一,求解方程,即可确定电路参数。设杆塔的接地电阻为Rg,则Rg=Re(Z)。
本发明在线测量接地电阻的装置,其硬件构成为四个环形电压互感器(PT),四个环形电流互感器(CT)以及接地电阻测试仪组成。其中,接地电阻测试仪由MCU单元(1)、信号发生模块(2)、电流电压转换模块(3)、信号放大模块(4)、信号选择模块(5)、功率放大模块(6)、电压互感器(7)、电流互感器(8)、电流电压转换模块(9)、滤波模块(10)、量程切换模块(11)、交直流转换模块(12)、AD转换模块(13)、显示模块(14)、串口模块(15)、时钟模块(16)、存储模块(17)、GPRS模块(18)、电源模块(19)组成,其中电源模块(19)采用太阳能电池板供电,负责为整个系统各个芯片提供所需电压,MCU单元(1)为系统的总控制器,信号发生模块(2)发出正弦交流信号并通过电流电压转换模块(3)、信号放大模块(4)输出确定电压值的正弦交流信号,再通过信号选择模块(5)将不同的电压值分配至四路电压互感器输出支路中,同时由功率放大模块(6)提高电路的负载驱动能力从而驱动电压互感器(7),当由电压互感器感应至被测回路电压信号时,回路中应产生电流,由四个电流互感器(8)分别将四路电流信号检测出,并通过电流电压转换模块(9)转换为电压值,再通过滤波模块(10)滤波,根据被测量大小通过量程切换模块(11)选择量程,再通过交直流转换模块(12)转换为直流量并测量其大小,经过AD转换模块(13)转换为数字量送入MCU单元,其接地电阻测试数值可通过显示模块(14)显示或通过GPRS模块(18)远程发送至监控中心计算机,在设备的使用中,如需调整参数及程序可通过串口模块(15)实现,时钟模块(16)用于确定系统时间,存储模块(17)用于存储测量结果。
本发明的有益效果是,可以实现杆塔接地电阻的远程快速测量,避免了测试人员必须到达现场的繁重工作,同时该设备可适用于于含有任意多条引下线的杆塔,无需解开多余的引下线,减轻了工作人员的劳动强度。
附图说明
图1,系统整体示意图
图中1为监测中心计算机、2为杆塔接地电阻测试仪、3为被测杆塔
图2,设备安装示意图
图3,采用该方法测试等效电路图
图4,杆塔接地电阻测试仪原理示意图
图中1MCU单元、2信号发生模块、3电流电压转换模块、4信号放大模块、5信号选择模块、6功率放大模块、7电压互感器、8电流互感器9电流电压转换模块、10滤波模块、11量程切换模块、12交直流转换模块、13AD转换模块、14显示模块、15串口模块、16时钟模块、17存储模块、18GPRS模块、19电源模块
具体实施方案
安装设备时应如图2所示,四对电压互感器电流互感器应分别安装于两条避雷线上,并分别安装于杆塔两侧,安装时应尽可能靠近杆塔与避雷线的连按处,并且应使得磁路严密闭合,以减小误差;杆塔接地电阻测试仪距离电压互感器电流互感器不应太远,并且牢固安装于杆塔之上;太阳能电池板应按生产厂商要求放置于杆塔上。
图3为输电线路杆塔的等效电路图,其中,Z为本级杆塔的接地电阻阻抗值。该算法的程序已经内置于接地电阻测试仪的MCU单元中,只需按要求测量出杆塔中感应电流,并将数据送入MCU单元,即可得接地电阻阻值。
图4为杆塔接地电阻在线测试仪原理示意图,其中电源模块(19)采用太阳能电池板供电,负责为整个系统各个芯片提供所需电压,MCU单元(1)为系统的总控制器,信号发生模块(2)发出正弦交流信号并通过电流电压转换模块(3)、信号放大模块(4)输出特定电压值的正弦交流信号,再通过信号选择模块(5)将不同的电压值分配至四路电压互感器输出支路中,同时由功率放大模块(6)提高电路的负载驱动能力从而驱动电压互感器(7),当由电压互感器感应至被测回路电压信号时,回路中应产生电流,由四个电流互感器(8)分别将四路电流信号检测出,并通过电流电压转换模块(9)转换为电压值,再通过滤波模块(10)滤波,根据被测量大小通过量程切换模块(11)选择量程,再通过交直流转换模块(12)转换为直流量并测量其大小,经过AD转换模块(13)转换为数字量送入MCU单元,,并计算得出接地电阻阻值,其接地电阻测试数值可通过显示模块(14)显示或通过GPRS模块(18)远程发送至监控中心计算机,在设备的使用中,如需调整参数及程序可通过串口模块(15)实现,时钟模块(16)用于确定系统时间,存储模块(17)用于存储测量结果。
具体工作步骤如下:
1、由中心监控计算机发出命令,并通过GPRS模块将命令发送给杆塔接地电阻测试仪,启动设备。
2、由杆塔接地电阻测试仪向电压互感器发出正弦电压信号,并将此交流电压感应至避雷线。
3、与此同时,由电流互感器感应得到避雷线中的电流,并送入杆塔接地电阻测试仪。
4、在杆塔接地电阻测试仪内部,将该电流进行一系列处理分析,得到电流值,将电流值送入MCU单元。
5、由MCU单元按照特定程序求解方程,得出接地电阻阻值。
6、将接地电阻阻值通过GPRS模块发送至中心监控计算机,并将数据存储。

Claims (3)

1.一种在线测量接地电阻的方法,采用钳表法,利用四对电压互感器PT和电流互感器CT分别接在杆塔左右两端的两条防雷线上,测量并得到电流与电压的关系,最终通过特定的计算方法,得到被测杆塔的接地电阻阻值,其中由一个电压互感器PT和一个电流互感器CT形成一对,共有四对,所述四对电压互感器PT和电流互感器CT平均设置在杆塔左右两端,即左端设置两对,右端设置两对,其特征在于,PT用于产生感应电压信号,CT用于测量由感应电压所生成的电流信号,该方法无需考虑杆塔接地引线数量,可适用于含有任意多条引下线的杆塔;
采用特定的计算方法,设Z为被测杆塔接地电阻阻抗值,ZL为左侧所有杆塔并联等效电阻阻抗值,Z1和Z2分别为被测杆塔与左侧第一级杆塔之间两防雷线等效电阻阻抗值,ZR为右侧所有杆塔并联等效电阻阻抗值,Z3和Z4分别为被测杆塔与右侧第一级杆塔之间两防雷线等效电阻阻抗值,为由PT感应至杆塔的电压值,同时对应支路中所产生电流为可得如下矩阵方程:
I · 1 0 0 0 I · 1 + I · 2 0 I · 1 + I · 2 + I · 3 + I · 4 0 I · 2 0 0 I · 1 + I · 2 0 I · 1 + I · 2 + I · 3 + I · 4 0 0 I · 3 0 0 I · 3 + I · 4 I · 1 + I · 2 + I · 3 + I · 4 0 0 0 I · 4 0 I · 3 + I · 4 I · 1 + I · 2 + I · 3 + I · 4 Z 1 Z 2 Z 3 Z 4 Z L Z R Z = U · 1 U · 2 U · 3 U · 4
该方程的解不唯一,无法确定电路参数,因此,需进行第二次测量;设第二次测量外加电源分别为 各对应支路中所产生电流为补充至上式中,得:
I · 1 0 0 0 I · 1 + I · 2 0 I · 1 + I · 2 + I · 3 + I · 4 0 I · 2 0 0 I · 1 + I · 2 0 I · 1 + I · 2 + I · 3 + I · 4 0 0 I · 3 0 0 I · 3 + I · 4 I · 1 + I · 2 + I · 3 + I · 4 0 0 0 I · 4 0 I · 3 + I · 4 I · 1 + I · 2 + I · 3 + I · 4 I · 1 ′ 0 0 0 I · 1 ′ + I · 2 ′ 0 I · 1 ′ + I · 2 ′ + I · 3 ′ + I · 4 ′ 0 I · 2 ′ 0 0 I · 1 ′ + I · 2 ′ 0 I · 1 ′ + I · 2 ′ + I · 3 ′ + I · 4 ′ 0 0 I · 3 ′ 0 0 I · 3 ′ + I · 4 ′ I · 1 ′ + I · 2 ′ + I · 3 ′ + I · 4 ′ 0 0 0 I · 4 ′ 0 I · 3 ′ + I · 4 ′ I · 1 ′ + I · 2 ′ + I · 3 ′ + I · 4 ′ Z 1 Z 2 Z 3 Z 4 Z L Z R Z U · 1 U · 2 U · 3 U · 4 U · 1 ′ U · 2 ′ U · 3 ′ U · 4 ′
求解方程,即可确定电路参数。
2.采用权利要求1所述方法的在线测量接地电阻的装置,其特征在于:由四个电压互感器PT,四个电流互感器CT以及接地电阻测试仪组成,接地电阻测试仪由MCU单元(1)、信号发生模块(2)、第一电流电压转换模块(3)、信号放大模块(4)、信号选择模块(5)、功率放大模块(6)、第二电流电压转换模块(9)、滤波模块(10)、量程切换模块(11)、交直流转换模块(12)、AD转换模块(13)、显示模块(14)、串口模块(15)、时钟模块(16)、存储模块(17)、GPRS模块(18)、电源模块(19)组成,其中电源模块(19)负责为接地电阻测试仪各个芯片提供所需电压,MCU单元(1)为接地电阻测试仪的总控制器,信号发生模块(2)发出正弦交流信号并通过第一电流电压转换模块(3)、信号放大模块(4)输出特定电压值的正弦交流信号,再通过信号选择模块(5)将不同的电压值分配至不同的电压互感器PT输出支路中,同时由功率放大模块(6)提高电路的负载驱动能力从而驱动电压互感器PT,当由电压互感器PT感应至被测回路电压信号时,回路中应产生电流,由电流互感器CT将该电流信号检测出,并通过第二电流电压转换模块(9)转换为电压值,再通过滤波模块(10)滤波,根据被测量大小通过量程切换模块(11)选择量程,再通过交直流转换模块(12)转换为直流量并测量其大小,经过AD转换模块(13)转换为数字量送入MCU单元,并计算得出接地电阻阻值,其接地电阻测试数值可通过显示模块(14)显示或GSM/GPRS模块(18)远程传送至监控中心计算机,串口模块(15)用于调试设备,时钟模块(16)用于确定系统时间,存储模块(17)用于存储测量结果。
3.如权利要求2所述的在线测量接地电阻的装置,其特征在于:通过GSM/GPRS模块(18)远程传送至监控中心计算机。
CN201210046011.4A 2012-02-28 2012-02-28 杆塔接地电阻在线测量方法与装置 Expired - Fee Related CN102680798B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210046011.4A CN102680798B (zh) 2012-02-28 2012-02-28 杆塔接地电阻在线测量方法与装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210046011.4A CN102680798B (zh) 2012-02-28 2012-02-28 杆塔接地电阻在线测量方法与装置

Publications (2)

Publication Number Publication Date
CN102680798A CN102680798A (zh) 2012-09-19
CN102680798B true CN102680798B (zh) 2015-07-22

Family

ID=46813030

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210046011.4A Expired - Fee Related CN102680798B (zh) 2012-02-28 2012-02-28 杆塔接地电阻在线测量方法与装置

Country Status (1)

Country Link
CN (1) CN102680798B (zh)

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103018571A (zh) * 2012-12-05 2013-04-03 北京工业大学 双耦合式输电线路接地阻抗在线监测装置
JP2014169999A (ja) * 2013-03-02 2014-09-18 Fluke Corp 接地抵抗測定装置及び方法
CN103293451B (zh) * 2013-05-24 2015-10-28 华南理工大学 一种高压输电线路杆塔接地装置防雷特性的评估方法
CN104749444A (zh) * 2013-12-31 2015-07-01 孙巍巍 一种接地电阻测量装置
CN103954843B (zh) * 2014-05-21 2016-06-15 重庆大学 一种不断开接地引线杆塔接地电阻测量注入电流频率范围的确定方法
CN104502726B (zh) * 2014-12-01 2017-12-15 国网辽宁省电力有限公司锦州供电公司 铁塔和水泥杆工频接地电阻的测量方法
CN104360168A (zh) * 2014-12-09 2015-02-18 广东电网公司惠州供电局 接地电阻测量中引线互感消除的方法及系统
CN105116240A (zh) * 2015-06-05 2015-12-02 国网辽宁省电力有限公司葫芦岛供电公司 输电线路杆塔及人工接地体防雷泄流通道检测方法
CN104931792A (zh) * 2015-06-23 2015-09-23 中山市木易万用仪器仪表有限公司 钳形绝缘电阻测试装置
CN105021897A (zh) * 2015-08-17 2015-11-04 国网辽宁省电力有限公司抚顺供电公司 一种免拆接地引下线的杆塔接地电阻测量装置及测量方法
CN105467220A (zh) * 2015-11-20 2016-04-06 国网山东省电力公司电力科学研究院 一种便携式接地电阻测试仪
CN107782975B (zh) * 2017-09-19 2019-11-12 山东建筑大学 基于无线信号源的分布式接地电阻检测系统及检测方法
CN107656144A (zh) * 2017-11-14 2018-02-02 国网山东省电力公司电力科学研究院 一种输电线路接地系统的综合检测系统及方法
CN109030951A (zh) * 2018-08-27 2018-12-18 云南电网有限责任公司电力科学研究院 一种共享电力铁塔接地电阻的在线测量系统及方法
CN110514903A (zh) * 2019-09-29 2019-11-29 国网河南省电力公司濮阳供电公司 接地电阻状态评价与在线预警云监控系统
CN110514904A (zh) * 2019-09-29 2019-11-29 国网河南省电力公司濮阳供电公司 接地电阻检测预警系统
CN111090000B (zh) * 2019-12-23 2022-01-14 浙江天正智能电器有限公司 一种可实现剩余电流高精度测量的方法
CN112485532B (zh) * 2020-12-01 2022-02-25 山东建筑大学 基于结点电压法的多引下线接地电阻测量方法
CN112485533B (zh) * 2020-12-01 2022-02-25 山东建筑大学 基于引下线伏安特性的接地电阻测量方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1828313A (zh) * 2006-02-21 2006-09-06 武汉高压研究所 免解线杆塔接地电阻快速测量方法及装置
CN101216515A (zh) * 2007-12-27 2008-07-09 武汉华瑞防雷科技股份有限公司 一种输电线路杆塔接地电阻测量方法及其测试仪
CN202041584U (zh) * 2011-01-10 2011-11-16 西安交通大学 可移动式冲击接地电阻的测量装置

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1828313A (zh) * 2006-02-21 2006-09-06 武汉高压研究所 免解线杆塔接地电阻快速测量方法及装置
CN101216515A (zh) * 2007-12-27 2008-07-09 武汉华瑞防雷科技股份有限公司 一种输电线路杆塔接地电阻测量方法及其测试仪
CN202041584U (zh) * 2011-01-10 2011-11-16 西安交通大学 可移动式冲击接地电阻的测量装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
一般化三电极接地电阻测量方法;王涛 等;《中国电力》;20110331;第44卷(第3期);第31-33页 *

Also Published As

Publication number Publication date
CN102680798A (zh) 2012-09-19

Similar Documents

Publication Publication Date Title
CN102680798B (zh) 杆塔接地电阻在线测量方法与装置
CN103293443A (zh) 一种配网架空线路接地故障定位方法
CN202994931U (zh) 一种基于无线传感技术的避雷器状态监测装置
US20220187347A1 (en) Current and voltage measuring unit
CN104656017B (zh) 高压电机能效计量检测方法
CN101876673A (zh) 特高压直流非接触测距式验电方法
CN107656144A (zh) 一种输电线路接地系统的综合检测系统及方法
CN202024755U (zh) 基于磁场传感器的高压线施工安全监测系统
CN104777388A (zh) 零序电流采样法在供电分支线路用户识别中的方法
CN114264890A (zh) 一种运行电力设备非接触式电参数量测核验装置及方法
CN103487725B (zh) 一种基于零序分量法的架空配电线路接地故障指示装置
CN103424627B (zh) 双端测量平行电网线路零序阻抗的方法
CN103645415A (zh) 一种带电检查电能计量装置接线的实用方法
CN108318732B (zh) 一种变压器铁芯接地电流在线监测装置及方法
CN103995171A (zh) 非接触式直流输电线路电流测量方法
CN102879657B (zh) 一种线路相序核对方法
CN203587736U (zh) 一种基于零序分量法的架空配电线路接地故障指示装置
CN103777064A (zh) 免外接交流电源的氧化锌避雷器带电检测装置
CN103869113B (zh) 高压串联谐振装置和利用该装置的耐压试验方法
CN103176048B (zh) 一种快速测量变压器三角形接线方式绕组直流电阻的方法
CN202502136U (zh) 交流线路感应电压和感应电流测量装置
CN105203886A (zh) 一种电容型电流互感器在线检测装置及方法
CN205720386U (zh) 一种双通道非接触式1000v以下电压测量装置
CN213302497U (zh) 一种电流互感器二次侧回路检测装置及电路
CN206038784U (zh) 带电测量氧化锌避雷器的无线测试仪

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150722