CN102663168A - Method for three-dimensional conversion and pipeline conflict processing of two-dimensional drawing of cable layer - Google Patents

Method for three-dimensional conversion and pipeline conflict processing of two-dimensional drawing of cable layer Download PDF

Info

Publication number
CN102663168A
CN102663168A CN2012100752682A CN201210075268A CN102663168A CN 102663168 A CN102663168 A CN 102663168A CN 2012100752682 A CN2012100752682 A CN 2012100752682A CN 201210075268 A CN201210075268 A CN 201210075268A CN 102663168 A CN102663168 A CN 102663168A
Authority
CN
China
Prior art keywords
information
dimensional
pipeline
model
dimension drawing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100752682A
Other languages
Chinese (zh)
Other versions
CN102663168B (en
Inventor
朱玉林
郑思国
钱虹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI ELECTRIC POWER COMMUNICATION CO Ltd
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Original Assignee
Shanghai Jiulong Electric Power Technology Co Ltd
Shanghai Municipal Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiulong Electric Power Technology Co Ltd, Shanghai Municipal Electric Power Co filed Critical Shanghai Jiulong Electric Power Technology Co Ltd
Priority to CN201210075268.2A priority Critical patent/CN102663168B/en
Publication of CN102663168A publication Critical patent/CN102663168A/en
Application granted granted Critical
Publication of CN102663168B publication Critical patent/CN102663168B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Processing Or Creating Images (AREA)

Abstract

The invention relates to a method for three-dimensional conversion and pipeline conflict processing of a two-dimensional drawing of a cable layer. The method includes: (1) building a three-dimensional information model; and (2) performing three-dimensional information fusion on the model built in the step (1) on the basis of guiding. Compared with the prior art, the method for three-dimensional conversion and the pipeline conflict processing of the two-dimensional drawing of the cable layer has the advantages that processing capability of the whole construction process unit to cope with a complex and changeable project is improved, and the like.

Description

The three-dimensional conversion and the pipeline conflict processing method of cable floor two dimension drawing
Technical field
The present invention relates to a kind of robotization treatment technology of cable floor drawing, especially relate to a kind of three-dimensional conversion and pipeline conflict processing method of cable floor two dimension drawing.
Background technology
Traditional architectural design all is the design of two dimension.Current, the 2D drawing is the final design achievement of paying of China's architectural design industry, and this is present industrial practice.Therefore, the Organization And Management of production procedure carries out round the making of 2D drawing.The CAD platform is all used in the making of 2D drawing now, in order to replace manual drawing.2D design is low to hardware requirement, it is very high to be easy to training, flexible design, efficient.Human in the architectural creation process, be primary in fact forever for the pursuit of aesthetic feeling.Human just beginning for the beautiful exploration of curved surface a long time ago, and be used among some famous buildings, and the designers that had a The present computer technology naturally more serious hope control complicated and changeable and more esthetical free form surface.Yet what make 2D designing technique blushing with shame is that it even the most basic geometric shape of this type building also are beyond expression.In this case, the 3D design has just been arisen at the historic moment.Draw with respect to 2D, the geometric properties that building can be accurately expressed in the 3D design, there is not the geometric expression obstacle in the 3D design, and no matter how complicated architectural image all can accurately show with the 3D design.
Use in the process increasingly extensive, deeply development in the building digital technology, manyly in architectural design influence the problem that digital technology develops in depth and gradually reveal clue.The degree of information sharing that wherein the most outstanding is is low.This shows that " information island " in the design department exists in a large number, the program independent operating that design software is incompatible, each is professional of different brands and can not swap data, and information resources can't be shared and integrate.The result who causes be the information transmission slowly, design information repeats, inconsistent or phenomenon such as lose and exist in a large number.A lot of design team still use the architectural drawing software of standalone version to draw architectural drawing, and managerial personnel continue to use outmoded mode and manage design.Owing to coordinate badly between the designer, working drawing repeats to draw, working drawing disappearance or working drawing are inconsistent each other etc., and phenomenon happens occasionally, and engineering construction and design management are caused very big influence.Simultaneously; Because resource and poor information analysis comprehensive, system and utilization between each business department of design companies; The level of adding enterprise institution is many; Cause horizontal communication difficulty, information to transmit distortion, therefore can't improve the management level and the effectiveness of operation of whole enterprise at all.These problems have become the obstacle of digital building designs, must strive to find the breach that can deal with problems.This breach is exactly information integration.Along with construction scale enlarges day by day, to architectural design require increasingly highly, architectural design must develop to the direction of collaborative design.
Summary of the invention
The object of the invention is exactly three-dimensional conversion and the pipeline conflict processing method that a kind of cable floor two dimension drawing is provided for the defective that overcomes above-mentioned prior art existence.
The object of the invention can be realized through following technical scheme:
A kind of three-dimensional conversion and pipeline conflict processing method of cable floor two dimension drawing is characterized in that, comprising:
1) makes up the three-dimensional information model;
2) model that step 1) is made up carries out merging based on the three-dimensional information of guiding.
Described step 1) makes up the three-dimensional information model and is specially:
1) receives two-dimentional drawing through common CAD file input interface based on RUBY;
2) the two-dimentional drawing that receives being carried out three-dimensional constitutes;
3) generate the three-dimensional information model.
Described X-Y scheme paper bag is drawn together civil engineering two dimension drawing, fire line two dimension drawing, illuminator two dimension drawing, cable testing bridge two dimension drawing and drainage pipeline two dimension drawing.
Described three-dimensional information model comprises the information-based model of civil engineering, the information-based model of fire line, the information-based model of illuminator, the information-based model of cable testing bridge and the information-based model of drainage pipeline.
The information-based model of described civil engineering comprises support post, trench drain hole, crossbeam, metope hole and the ceiling hole information of cable floor.
The information-based model of described fire line comprise the fire-fighting spraying pipe lay with volume coordinate and air sampling tube lay direction of routing and volume coordinate information.
The information-based model of described illuminator comprises locus, the power lead trend in space and the illuminating effect information of lighting that lighting is laid.
The information-based model of described cable testing bridge comprises the arrangement and method for construction information of size, spatial placement and the cable floor crane span structure of cable floor crane span structure.
Described three-dimensional information fusion based on guiding is specially:
1) collision detection in the actual physics space;
2) fire protection pipeline detects and the detection of blocking property of illumination;
3) collision detection in the work progress.
Compared with prior art, the present invention has the following advantages:
Through at working interface of corresponding increase of construction stage; And combine the collaborative design thought of advanced architecture information model to do corresponding improvement; Make construction building course itself have the mechanism of taking precautions against in advance, improve the processing power that engineering complicated and changeable is tackled in the whole construction course unit.
Description of drawings
Fig. 1 is a process flow diagram of the present invention.
Embodiment
Below in conjunction with accompanying drawing and specific embodiment the present invention is elaborated.
Embodiment
As shown in Figure 1, a kind of three-dimensional conversion and pipeline conflict processing method of cable floor two dimension drawing comprise:
1) makes up the three-dimensional information model;
2) model that step 1) is made up carries out merging based on the three-dimensional information of guiding.
Described step 1) makes up the three-dimensional information model and is specially:
1) receives two-dimentional drawing through common CAD file input interface based on RUBY;
2) the two-dimentional drawing that receives being carried out three-dimensional constitutes;
3) generate the three-dimensional information model.
Described X-Y scheme paper bag is drawn together civil engineering two dimension drawing, fire line two dimension drawing, illuminator two dimension drawing, cable testing bridge two dimension drawing and drainage pipeline two dimension drawing.Described three-dimensional information model comprises the information-based model of civil engineering, the information-based model of fire line, the information-based model of illuminator, the information-based model of cable testing bridge and the information-based model of drainage pipeline.
The information-based model of described civil engineering comprises support post, trench drain hole, crossbeam, metope hole and the ceiling hole information of cable floor.
The information-based model of described fire line comprise the fire-fighting spraying pipe lay with volume coordinate and air sampling tube lay direction of routing and volume coordinate information; Its arrangement principle is divided into according to the civil engineering span and on average lays and require to lay two kinds according to reality; What in practice of construction, often adopt is that the civil engineering span on average lays principle, promptly according to the cable floor developed width fire line and air sampling pipeline is carried out the vertical layout of single-candidate distance.
The information-based model of described illuminator comprises locus, the power lead trend in space and the illuminating effect information of lighting that lighting is laid; On the attribute of each light fixture, encapsulated lighting parameter and space daylighting parameter, these will help in the illumination stage of blocking blocking of actual object being made judgement.
The information-based model of described cable testing bridge comprises the arrangement and method for construction information of size, spatial placement and the cable floor crane span structure of cable floor crane span structure.The crane span structure spatial placement partial information of the information-based model of cable testing bridge is that the engineering drawing through two dimension obtains, and a part of in addition arrangement and method for construction needs artificially to collect on-the-spot construction experience and add, as much as possible the situation of construction stage is considered fully.
Described three-dimensional information fusion based on guiding is specially:
Five class models carry out the information fusion based on guiding, and the guiding classification is divided into collision, the collision in the work progress, fire line in the actual physics space and lays unreasonable and illumination is blocked etc.Can the guiding fusion be divided into three levels and carry out, first degree fusion belongs to the collision detection of physical space; The object of the spatial placement that the collision traversal is all detects the overlapping on how much.
The rationalization detection of fire protection pipeline and the detection of blocking property of illumination belong to the second layer and merge.The principle that fire protection pipeline lays should lay the position according to cable testing bridge and carry out; It is more rational arranging like this; And what in practice of construction, often adopt is that the civil engineering span on average lays principle; In actual engineering, can produce a lot of conflicts, the detection of the irrationality that fire protection pipeline lays need be merged information-based model of fire line and the information-based model of cable testing bridge.
Illumination is blocked and will be considered the information-based model of illuminator, the information-based model of civil engineering, the information-based model of cable testing bridge, produces the possibility of blocking because the crane span structure illumination of civil engineering column and measurement and cable has;
Collision detection in the work progress belongs to the 3rd layer of fusion, and belongs to the collision detection on the four-dimentional space, except space coordinates, increases free dimension again in addition.Common way is the information on the time dimension to be superimposed form the three dimensions after superposeing; Then under this three dimensions, carry out collision detection process; This way has been simplified the complexity of algorithm design aspect; Carrying out high efficient and reliable, is effective for the cable testing bridge of construction final stage and the installation of high-tension cable.

Claims (9)

1. the three-dimensional conversion and the pipeline conflict processing method of a cable floor two dimension drawing is characterized in that, comprising:
1) makes up the three-dimensional information model;
2) model that step 1) is made up carries out merging based on the three-dimensional information of guiding.
2. the three-dimensional conversion and the pipeline conflict processing method of a kind of cable floor two dimension drawing according to claim 1 is characterized in that described step 1) makes up the three-dimensional information model and is specially:
1) receives two-dimentional drawing through common CAD file input interface based on RUBY;
2) the two-dimentional drawing that receives being carried out three-dimensional constitutes;
3) generate the three-dimensional information model.
3. the three-dimensional conversion and the pipeline conflict processing method of a kind of cable floor two dimension drawing according to claim 2; It is characterized in that described X-Y scheme paper bag is drawn together civil engineering two dimension drawing, fire line two dimension drawing, illuminator two dimension drawing, cable testing bridge two dimension drawing and drainage pipeline two dimension drawing.
4. the three-dimensional conversion and the pipeline conflict processing method of a kind of cable floor two dimension drawing according to claim 3; It is characterized in that described three-dimensional information model comprises the information-based model of civil engineering, the information-based model of fire line, the information-based model of illuminator, the information-based model of cable testing bridge and the information-based model of drainage pipeline.
5. the three-dimensional conversion and the pipeline conflict processing method of a kind of cable floor two dimension drawing according to claim 4; It is characterized in that the information-based model of described civil engineering comprises support post, trench drain hole, crossbeam, metope hole and the ceiling hole information of cable floor.
6. the three-dimensional conversion and the pipeline conflict processing method of a kind of cable floor two dimension drawing according to claim 4; It is characterized in that, the information-based model of described fire line comprise the fire-fighting spraying pipe lay with volume coordinate and air sampling tube lay direction of routing and volume coordinate information.
7. the three-dimensional conversion and the pipeline conflict processing method of a kind of cable floor two dimension drawing according to claim 4; It is characterized in that the information-based model of described illuminator comprises locus, the power lead trend in space and the illuminating effect information of lighting that lighting is laid.
8. the three-dimensional conversion and the pipeline conflict processing method of a kind of cable floor two dimension drawing according to claim 4; It is characterized in that the information-based model of described cable testing bridge comprises the arrangement and method for construction information of size, spatial placement and the cable floor crane span structure of cable floor crane span structure.
9. the three-dimensional conversion and the pipeline conflict processing method of a kind of cable floor two dimension drawing according to claim 4 is characterized in that, described three-dimensional information fusion based on guiding is specially:
1) collision detection in the actual physics space;
2) fire protection pipeline detects and the detection of blocking property of illumination;
3) collision detection in the work progress.
CN201210075268.2A 2012-03-20 2012-03-20 The three-dimensional conversion of cable floor two dimension drawing and pipeline conflict processing method Active CN102663168B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210075268.2A CN102663168B (en) 2012-03-20 2012-03-20 The three-dimensional conversion of cable floor two dimension drawing and pipeline conflict processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210075268.2A CN102663168B (en) 2012-03-20 2012-03-20 The three-dimensional conversion of cable floor two dimension drawing and pipeline conflict processing method

Publications (2)

Publication Number Publication Date
CN102663168A true CN102663168A (en) 2012-09-12
CN102663168B CN102663168B (en) 2015-11-25

Family

ID=46772659

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210075268.2A Active CN102663168B (en) 2012-03-20 2012-03-20 The three-dimensional conversion of cable floor two dimension drawing and pipeline conflict processing method

Country Status (1)

Country Link
CN (1) CN102663168B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103093061A (en) * 2013-02-07 2013-05-08 中铁二十二局集团电气化工程有限公司 Complex pipeline collision optimization method of subway electromechanical engineering
CN103256574A (en) * 2013-04-18 2013-08-21 李宪坤 Intelligent wiring method and system for LED lamps
CN106897448A (en) * 2017-03-03 2017-06-27 广州地铁集团有限公司 The crossed construction intelligent graphic displaying of subway engineering Gui Hang areas and collision detecting system
CN109033631A (en) * 2018-07-25 2018-12-18 中国长江电力股份有限公司 A kind of power station optical cable or cable routing three-dimensional display method based on design information
CN109162407A (en) * 2018-09-25 2019-01-08 重庆大学产业技术研究院 A kind of reinforced concrete member intersection region reinforcing bar automatic obstacle-avoiding method based on Artificial Potential Field Method
CN112669465A (en) * 2020-12-02 2021-04-16 海能达通信股份有限公司 Scene conversion method, electronic device and storage medium

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101308583A (en) * 2008-07-16 2008-11-19 永凯软件技术(上海)有限公司 Curved surface body line boundary model rebuilding method based on three-views and apparatus thereof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101308583A (en) * 2008-07-16 2008-11-19 永凯软件技术(上海)有限公司 Curved surface body line boundary model rebuilding method based on three-views and apparatus thereof

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
潘霞 等: "三维技术在大型建筑综合管线施工中的应用", 《施工技术》 *
王惠桐 等: "应用三维制图技术综合布置机电管线", 《建筑工程》 *
高远 等: "基于BIM的建筑MEP设计技术研究", 《土木建筑工程信息技术》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103093061A (en) * 2013-02-07 2013-05-08 中铁二十二局集团电气化工程有限公司 Complex pipeline collision optimization method of subway electromechanical engineering
CN103093061B (en) * 2013-02-07 2015-09-09 中铁二十二局集团电气化工程有限公司 A kind of subway electromechanical engineering comprehensive pipeline collision optimization method
CN103256574A (en) * 2013-04-18 2013-08-21 李宪坤 Intelligent wiring method and system for LED lamps
CN106897448A (en) * 2017-03-03 2017-06-27 广州地铁集团有限公司 The crossed construction intelligent graphic displaying of subway engineering Gui Hang areas and collision detecting system
CN106897448B (en) * 2017-03-03 2020-09-25 广州地铁集团有限公司 Subway engineering rail-running area cross construction intelligent graphical display and collision detection system
CN109033631A (en) * 2018-07-25 2018-12-18 中国长江电力股份有限公司 A kind of power station optical cable or cable routing three-dimensional display method based on design information
CN109162407A (en) * 2018-09-25 2019-01-08 重庆大学产业技术研究院 A kind of reinforced concrete member intersection region reinforcing bar automatic obstacle-avoiding method based on Artificial Potential Field Method
CN109162407B (en) * 2018-09-25 2020-08-04 重庆大学产业技术研究院 Automatic obstacle avoidance method for reinforcing steel bars in crossed area of reinforced concrete member based on artificial potential field method
CN112669465A (en) * 2020-12-02 2021-04-16 海能达通信股份有限公司 Scene conversion method, electronic device and storage medium
CN112669465B (en) * 2020-12-02 2024-03-15 海能达通信股份有限公司 Scene change method, electronic device and storage medium

Also Published As

Publication number Publication date
CN102663168B (en) 2015-11-25

Similar Documents

Publication Publication Date Title
CN102663168A (en) Method for three-dimensional conversion and pipeline conflict processing of two-dimensional drawing of cable layer
CN204303029U (en) For the BIM Database Systems of subway pipeline collision detection and later stage operation maintenance
CN106202825A (en) Underground pipe gallery method for designing based on BIM
CN104392482B (en) Substation project project three-dimensional calculation amount model generation system and method
CN108228986B (en) Automatic generation method of three-dimensional building model of subway station
CN102750618A (en) {0>Auxiliary management system for subway integrated pipeline construction and implementation method thereof
CN104965947A (en) BIM (Building Information Modeling) technology based bridge three-dimensional design method
CN104112028A (en) Method and device for displaying cable underground pipe network
CN102750419A (en) Subway comprehensive pipeline aided design system and method
CN113536421A (en) BIM-based port planning collaborative analysis method and system
Javohir et al. APPLICATION AND CAPABILITIES OF THE AUTOCAD PROGRAM IN ARCHITECTURE
CN114004000A (en) System for intelligent pipeline arrangement based on BIM technology
Goes et al. Design coordination with Building Information Modeling: a case study
CN108984876A (en) A kind of service sleeve automation modeling method and system based on BIM
CN202486782U (en) Three-dimensional (3D) transformation and pipeline conflict processing system of two-dimensional (2D) drawings of cable layers
CN107657087A (en) Pipeline layout method for arranging based on BIM technology
CN115587456A (en) BIM (building information modeling) forward design method and system for outdoor water supply and drainage pipe network
Shengyi et al. Research on integrated application of virtual reality technology based on BIM
Saini et al. BIM an emerging technology in AEC industry for time optimization
Zhadanovsky et al. Visualization of design, organization of construction and technological solutions
Ghaffarianhoseini et al. Integrating augmented reality and building information modelling to facilitate construction site coordination
Borkowski File Hygiene and BIM Models Restrictions
CN110929311A (en) Three-dimensional component modeling and construction drawing linkage editing method thereof
KR20110099151A (en) Methods of standard about ifc based architectural elements
Zheng Design method of assembly architecture based on BIM Technology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA SHANGHAI ELECTRIC

Free format text: FORMER OWNER: SHANGHAI JIULONG ELECTRIC POWER SCIENCE + TECHNOLOGY CO., LTD.

Effective date: 20121219

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121219

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant after: Shanghai Electric Power Corporation

Applicant after: State Grid Corporation of China

Applicant after: Shanghai Electric Power Communication Co., Ltd.

Address before: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant before: Shanghai Electric Power Corporation

Applicant before: Shanghai Jiulong Electric Power Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant