CN102605761A - 地基土体砂井分层增湿施工方法 - Google Patents

地基土体砂井分层增湿施工方法 Download PDF

Info

Publication number
CN102605761A
CN102605761A CN2012101141597A CN201210114159A CN102605761A CN 102605761 A CN102605761 A CN 102605761A CN 2012101141597 A CN2012101141597 A CN 2012101141597A CN 201210114159 A CN201210114159 A CN 201210114159A CN 102605761 A CN102605761 A CN 102605761A
Authority
CN
China
Prior art keywords
humidification
hole
layering
water
foundation soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101141597A
Other languages
English (en)
Inventor
黄勇
樊晓牧
胡林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang electric power design institute
Original Assignee
Xinjiang electric power design institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang electric power design institute filed Critical Xinjiang electric power design institute
Priority to CN2012101141597A priority Critical patent/CN102605761A/zh
Publication of CN102605761A publication Critical patent/CN102605761A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

地基土体砂井分层增湿施工方法,对地基土分层增湿的施工方法包括增湿孔(7)布置、填料(5)及埋透水管(4)和分层增湿,明显增加有效增湿深度,适用于深层增湿,对10米以下土层的增湿效果明显;各土层含水率均匀,施工质量容易保证,上层和下层加水量可以分开控制,避免出现不同深度含水率差别过大的情况。

Description

地基土体砂井分层增湿施工方法
技术领域
本发明涉及国际专利分类E02D基础结构物技术领域,尤其是地基土体砂井分层增湿施工方法。
背景技术
目前,湿陷性黄土在我国分布较广,在湿陷性黄土地区建筑物的设计及施工中,必须采用合理的地基处理方式消除或部分消除地基土的湿陷性,才能满足建筑物的使用要求。常用方法有:强夯、换土、挤密法等。这些方法的根本目的都是减小土体的孔隙比,使土体密实。为达到较好的效果,就要求土体含水率应在最优含水率附近,太大、太小都会影响处理效果。
许多地区由于气候干旱,降水量远小于蒸发量的气候特点,使地基土的含水率远小于最优含水率。实践经验表明,在这种情况下各种处理方法对地基土挤密效果差,湿陷性难以完全消除。为达到较好的处理效果必须采取适当的增湿措施,提高地基土的含水量。
已公开的专利申请中也未找到较多相关改进技术,如,专利申请号200910075102一种湿陷性黄土地基的处理方法,特别适合含水量小于14%的湿陷性黄土地基的处理,包括下列步骤:场地平整,对待处理的湿陷性黄土地基表面进行场地平整;冲孔挤密,利用柱锤成孔机对待处理的地基进行冲孔;分层夯实成桩,向孔中分层添埋水泥土,分层夯实,直至距基础表面300-500mm;灰土垫层,在桩顶面上用灰土垫层,夯实;基础施工。
目前通常使用的方法是普通砂井增湿法。该施工方法虽然施工方便,施工速度快,费用较低;但是,有效增湿深度有限,仅适用于浅层增湿,当增湿孔深大于10米时质量难以控制;而且,均匀性不易控制,孔内填料粒径较大时,渗透系数较大,造成底部含水率过高,而上部含水率不足;孔内填料粒径较小时,渗透系数较小,造成底部达不到增湿效果,而上部含水率却已经接近饱和。
发明内容
本发明的目的是提供一种针对湿陷性黄土地基人工增湿的有效施工方法,即地基土体砂井分层增湿施工方法。
本发明的发明目的是通过如下技术措施实现的:对地基土分层增湿的施工方法包括增湿孔布置、填料及埋透水管和分层增湿,具体的包括:
A.增湿孔布置,在需要增湿的地基土中修造增湿孔;:
(1)增湿孔按间距1.5m,正三角形布置;
(2)增湿孔成孔孔径为φ130~φ150mm,成孔深度比相应范围的桩长少度2米;
B.填料及埋透水管:
(1)增湿孔内填料5采用中、粗砂,含泥量不大于3%,渗透系数不低于2×10-2cm/s,无杂物和有机质混入;
(2)填料最大粒径不应大于50mm,D85应在0.84~3.0之间,D15应在0.1~0.84之间,均质系数Cu应大于3;
(3)装入填料的增湿孔形成砂井,其中埋设直径
Figure BSA00000703168300021
透水管,其厚度足以能承受足够的径向压力,无径向变形;
(4)透水管埋设深度为增湿孔深度的1/2,并不小于5米;
C.分层注水增湿:从装入填料的增湿孔后的沙井口对中、浅层地基土注水增湿;同时,从透水管上端露出沙井口上的管口对10米以下地基土层注水增湿。
本发明的有益效果是:明显增加有效增湿深度,适用于深层增湿,对10米以下土层的增湿效果明显;各土层含水率均匀,施工质量容易保证,上层和下层加水量可以分开控制,避免出现不同深度含水率差别过大的情况。
附图说明:
图1是本发明中的施工方法程序示意图
图2是本发明中的施工结构示意图
附图标记包括:沙井口1,管口2,地面3,透水管4,填料5,透水孔6,增湿孔7。
具体实施方式
下面结合具体实施方式,进一步阐述本发明。
本发明中,对地基土分层增湿的施工方法包括增湿孔7布置、填料5及埋透水管4和分层增湿,具体的包括:
A.增湿孔7布置:在需要增湿的地基土中修造增湿孔7;
(1)增湿孔7按间距1.5m,正三角形布置;
(2)增湿孔7成孔孔径为φ130~φ150mm,成孔深度比相应范围的桩长少2米;
B.填料5及埋透水管4:
(1)增湿孔7内填料5采用中、粗砂,含泥量不大于3%,渗透系数不低于2×10-2cm/s,无杂物和有机质混入;
(2)填料5最大粒径不应大于50mm,D85应在0.84~3.0之间,D15应在0.1~0.84之间,均质系数Cu应大于3;
(3)装入填料5的增湿孔7形成砂井,其中埋设透水管4,其厚度足以能承受足够的径向压力,无径向变形;
(4)透水管4埋设深度为增湿孔4深度的1/2,并不小于5米;
C.分层注水增湿:从装入填料5的增湿孔7后的沙井口1对中、浅层地基土注水增湿;同时,从透水管4上端露出沙井口1上的管口2对10米以下地基土层注水增湿。
前述中,增湿孔7上端开于地面3,形成沙井口1。
前述中,透水管4直径
Figure BSA00000703168300031
在透水管4底1米范围内应布置有透水孔6。透水管4由PVC制成。
前述中透水孔6φ3~φ5mm。
前述中透水孔6梅花形排列,其相邻透水孔6间距5cm。
本发明的使用,明显增加有效增湿深度,适用于深层增湿,对10米以下土层的增湿效果明显;各土层含水率均匀,施工质量容易保证,上层和下层加水量可以分开控制,避免出现不同深度含水率差别过大的情况。
这些实施例仅用于说明本发明,而不用于限制本发明的范围。此外,本领域技术人员在阅读了本发明的内容之后,以等同替代或变劣进行对本发明作各种改动或修改,同样落于本申请所附权利要求书所限定的范围。

Claims (4)

1.地基土体砂井分层增湿施工方法,其特征是:对地基土分层增湿的施工方法包括增湿孔(7)布置、填料(5)及埋透水管(4)和分层增湿,具体的包括:
A.增湿孔(7)布置:在需要增湿的地基土中修造增湿孔(7);
(1)增湿孔(7)按间距1.5m,正三角形布置;
(2)增湿孔(7)成孔孔径为φ130~φ150mm,成孔深度比相应范围的桩长度少2米;
B.填料(5)及埋透水管(4):
(1)增湿孔(7)内填料(5)采用中、粗砂,含泥量不大于3%,渗透系数不低于2×10-2cm/s,无杂物和有机质混入;
(2)填料(5)最大粒径不应大于50mm,D85应在0.84~3.0之间,D15应在0.1~0.84之间,均质系数Cu应大于3;
(3)装入填料(5)的增湿孔(7)形成砂井,其中埋设透水管(4),其厚度足以能承受足够的径向压力,无径向变形;
(4)透水管(4)埋设深度为增湿孔(4)深度的1/2,并不小于5米;
C.分层注水增湿:从装入填料(5)的增湿孔(7)后的沙井口(1)对中、浅层地基土注水增湿;同时,从透水管(4)上端露出沙井口(1)上的管口(2)对10米以下地基土层注水增湿。
2.如权利要求1所述的地基土体砂井分层增湿施工方法,其特征在于,透水管(4)直径
Figure FSA00000703168200011
在透水管(4)底1米范围内应布置有透水孔(6)。
3.如权利要求1所述的地基土体砂井分层增湿施工方法,其特征在于,透水孔(6)φ3~φ5mm。
4.如权利要求1所述的地基土体砂井分层增湿施工方法,其特征在于,透水孔(6)梅花形排列,其相邻透水孔(6)间距5cm。
CN2012101141597A 2012-04-18 2012-04-18 地基土体砂井分层增湿施工方法 Pending CN102605761A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101141597A CN102605761A (zh) 2012-04-18 2012-04-18 地基土体砂井分层增湿施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101141597A CN102605761A (zh) 2012-04-18 2012-04-18 地基土体砂井分层增湿施工方法

Publications (1)

Publication Number Publication Date
CN102605761A true CN102605761A (zh) 2012-07-25

Family

ID=46523495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101141597A Pending CN102605761A (zh) 2012-04-18 2012-04-18 地基土体砂井分层增湿施工方法

Country Status (1)

Country Link
CN (1) CN102605761A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864767A (zh) * 2012-09-18 2013-01-09 贵州正业工程技术投资有限公司 填方地基蠕变原位试验承台注水装置
CN111074876A (zh) * 2019-12-03 2020-04-28 海南民投建筑工程有限公司 一种地基基础新型环保低真空击密法施工方法
CN111519601A (zh) * 2020-05-18 2020-08-11 兰州交通大学 一种利用水蒸汽增湿土体的方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1228494A (zh) * 1998-03-06 1999-09-15 张凌 真空深井加固大厚度软土地基的方法
CN101392525A (zh) * 2008-10-13 2009-03-25 西北大学 消除铁路、公路路基黄土液化的地基处理技术
KR20100016667A (ko) * 2008-08-05 2010-02-16 주식회사 엠. 에이. 피. 코리아 수상 복토 포설을 이용한 연약 지반 개량 방법
CN102322057A (zh) * 2011-06-30 2012-01-18 广东省长大公路工程有限公司 一种可连续施工作业注浆式cfg桩施工方法
CN202164594U (zh) * 2011-08-02 2012-03-14 辽宁省水利水电科学研究院 自动注水装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1228494A (zh) * 1998-03-06 1999-09-15 张凌 真空深井加固大厚度软土地基的方法
KR20100016667A (ko) * 2008-08-05 2010-02-16 주식회사 엠. 에이. 피. 코리아 수상 복토 포설을 이용한 연약 지반 개량 방법
CN101392525A (zh) * 2008-10-13 2009-03-25 西北大学 消除铁路、公路路基黄土液化的地基处理技术
CN102322057A (zh) * 2011-06-30 2012-01-18 广东省长大公路工程有限公司 一种可连续施工作业注浆式cfg桩施工方法
CN202164594U (zh) * 2011-08-02 2012-03-14 辽宁省水利水电科学研究院 自动注水装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨世江等: "DDC(复合地基)法结合增湿法处理湿陷黄土地基", 《新疆电力技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864767A (zh) * 2012-09-18 2013-01-09 贵州正业工程技术投资有限公司 填方地基蠕变原位试验承台注水装置
CN111074876A (zh) * 2019-12-03 2020-04-28 海南民投建筑工程有限公司 一种地基基础新型环保低真空击密法施工方法
CN111519601A (zh) * 2020-05-18 2020-08-11 兰州交通大学 一种利用水蒸汽增湿土体的方法
CN111519601B (zh) * 2020-05-18 2021-06-08 兰州交通大学 一种利用水蒸汽增湿土体的方法

Similar Documents

Publication Publication Date Title
CN101302757B (zh) 一种快速处理厚层软土地基的方法
CN201952698U (zh) 利用土工织物散体桩加固的路基结构
CN104131546B (zh) 一种湿陷性黄土地基的处理方法
CN101845811A (zh) 一种改进的高真空击密软地基处理方法
CN113445396B (zh) 一种高液限土路段的高填土路基填筑施工方法
WO2021072941A1 (zh) 一种滨海淤泥软土地基二次强夯碎石置换加固方法
CN103074882A (zh) 用于采用碎石桩加固处理岛状多年冻土地基的施工方法
CN104264655A (zh) 预成孔深层水下夯实法
CN1807773A (zh) 一种深厚湿陷性黄土地基的处理方法
CN101021068A (zh) 低位预压排水强夯法软土地基处理工法
CN101967819B (zh) 一种用于变电站软土地基施工的强夯置换综合法
CN102605761A (zh) 地基土体砂井分层增湿施工方法
CN103215945B (zh) 非均质场地软土地基立体式组合动力排水固结系统和方法
CN206385525U (zh) 一种防止高回填土方下沉的木桩结构
CN103774639A (zh) 一种堆载预压系统及施工方法
CN204000848U (zh) 一种用于水下施工的嵌岩桩
CN208293556U (zh) 一种吹填软土地基真空动力固结复合排水系统
CN108385651B (zh) 一种利用复合土工织物进行软基加固的设计和施工方法
CN103122631A (zh) 软土地基堆载冲压加固法
CN214832575U (zh) 一种高填方软基施工综合立体排水固结系统
CN102828499A (zh) 改进型快速高真空击密软地基处理方法
CN115288162A (zh) 一种软土地基填方边坡的加固方法
CN216075211U (zh) 一种针对深厚湿陷性黄土地基处理的组合桩体系
CN106337409A (zh) 一种利用堆载预压结合盐桩处理泥炭土地基的方法
CN106759541B (zh) 柔性基础下复合地基桩土应力比极限值的确定方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 830001, three bend road, the Xinjiang Uygur Autonomous Region, Urumqi, No. 100

Applicant after: Co., Ltd of Chinese energy construction group Xinjiang Electric Power Design Inst. Wang Dazhi

Address before: 830001, three bend road, the Xinjiang Uygur Autonomous Region, Urumqi, No. 100

Applicant before: Xinjiang Electric Power Design Institute

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: XINJIANG ELECTRIC POWER DESIGN INST. WANG DAZHI TO: CHINA ENERGY ENGINEERING GROUP XINJIANG ELECTRIC POWER DESIGN INSTITUTE CO., LTD.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120725