CN102587983B - Comprehensive early-warning observation method for coal mine rock burst - Google Patents
Comprehensive early-warning observation method for coal mine rock burst Download PDFInfo
- Publication number
- CN102587983B CN102587983B CN 201210022940 CN201210022940A CN102587983B CN 102587983 B CN102587983 B CN 102587983B CN 201210022940 CN201210022940 CN 201210022940 CN 201210022940 A CN201210022940 A CN 201210022940A CN 102587983 B CN102587983 B CN 102587983B
- Authority
- CN
- China
- Prior art keywords
- rock burst
- roof
- stress field
- range
- mining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000011435 rock Substances 0.000 title claims abstract description 37
- 239000003245 coal Substances 0.000 title claims abstract description 27
- 238000000034 method Methods 0.000 title claims abstract description 16
- 238000012544 monitoring process Methods 0.000 claims abstract description 12
- 238000005065 mining Methods 0.000 claims description 22
- 230000008569 process Effects 0.000 claims description 7
- 230000008859 change Effects 0.000 claims description 5
- 238000013459 approach Methods 0.000 claims description 3
- 238000005422 blasting Methods 0.000 claims description 3
- 238000005474 detonation Methods 0.000 claims description 3
- 239000002360 explosive Substances 0.000 claims description 3
- 238000009826 distribution Methods 0.000 abstract description 5
- 238000009412 basement excavation Methods 0.000 abstract 1
- 238000011161 development Methods 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 230000002265 prevention Effects 0.000 description 3
- 238000011160 research Methods 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000005755 formation reaction Methods 0.000 description 2
- 238000009933 burial Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 230000001939 inductive effect Effects 0.000 description 1
- 229910052500 inorganic mineral Inorganic materials 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 239000011707 mineral Substances 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000009897 systematic effect Effects 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Images
Landscapes
- Testing Or Calibration Of Command Recording Devices (AREA)
Abstract
本发明公开了一种煤矿冲击地压综合预警观测方法,它首先获得冲击地压煤层的高应力场范围;然后人为干预观测扰动范围;最后全方位动态监测。本发明通过将采掘工作面覆岩运动破坏和应力场应力大小及分布密切联系在一起进行综合监测,从而预测出冲击地压发生的危险性并及时报警措施,避免冲击地压危险事故的发生。
The invention discloses a coal mine rock burst comprehensive early warning observation method, which first obtains the high stress field range of the rock burst coal seam; then artificially interferes and observes the disturbance range; and finally monitors all-round dynamics. In the present invention, the movement damage of the overlying rock in the excavation face is closely connected with the stress size and distribution of the stress field for comprehensive monitoring, so as to predict the risk of rock burst and take timely alarm measures to avoid the occurrence of dangerous rock burst accidents.
Description
技术领域 technical field
本发明属于煤矿开采技术领域。The invention belongs to the technical field of coal mining.
背景技术 Background technique
冲击地压是世界范围内煤矿中最严重的自然灾害之一。我国大多数矿山的煤层与岩层都具有不同程度的冲击倾向性,在一定的临界深度下煤岩冲击极为严重,特别是随着我国煤矿开采深度以每年约20m的深度不断增加,冲击地压越来越严重,已成为制约我国矿山生产和安全的主要重大灾害性事故之一。尽管国内外学者在冲击地压发生机理、监测手段及控制技术等研究方面取得了重要进展,但还远没有从根本上解决其有效预测和防治问题。我国煤矿矿井大多建于五六十年代,随着时间推移和矿产资源开发向深部转移,这些矿井将进入深部开采,冲击地压灾害问题将更趋严重、更为突出、更为普遍。Rock burst is one of the most serious natural disasters in coal mines worldwide. The coal seams and rock formations in most mines in my country have different degrees of impact tendency. At a certain critical depth, the impact of coal and rock is extremely serious, especially as the mining depth of my country's coal mines continues to increase at a depth of about 20m per year. It has become more and more serious and has become one of the major catastrophic accidents restricting mine production and safety in my country. Although scholars at home and abroad have made important progress in the research on the mechanism of rock burst, monitoring methods and control technology, it is far from fundamentally solving the problem of its effective prediction and prevention. Most of the coal mines in my country were built in the 1950s and 1960s. With the passage of time and the development of mineral resources moving to the deep, these mines will enter deep mining, and the problem of rock burst disasters will become more serious, more prominent, and more common.
在冲击地压预测与防治方面,由于对开采后上覆岩层运动变化规律及采场围岩应力场的时空分布规律不清,开拓与回采的决策理论不完善,目前在冲击地压煤层的采掘设计基本上依靠统计经验来决策,因而经常出现在高应力区内、孤岛与半孤岛煤柱中进行采掘工作,为冲击地压的发生提供了力源条件。由于没有把握复杂高应力和大埋深条件下的冲击煤岩层破坏过程的内在本质规律,因而对冲击地压发生的时间、地点及强度等没有达到定量预计的程度;冲击地压矿井普遍采用的信息采集技术,其测试参数不完善,监测的信息还不十分可靠,只能进行冲击地压的定性监测;对监测到的信息没有从理论上、实验上、方法上进行综合处理,其反馈信息对冲击地压预测的可靠性较差。所以目前冲击地压控制是全面防治,造成大量的人力、物力的浪费,极大地影响生产组织,降低了生产效率。在冲击地压预测预报方面,近几年来这方面的研究取得了重大的进展,但在在动态应力范围、高应力区能量释放特征的定量观测方面,还没有形成系统、可靠的观测方法,特别是深井条件下,岩层的软化作用明显,其动应力范围的判断准则很难建立,目前的观测手段与方法很难取得定量数值。。In terms of prediction and prevention of rock burst, due to the unclear movement of the overlying strata after mining and the spatio-temporal distribution of the stress field of the surrounding rock in the stope, the decision-making theory of development and recovery is not perfect. The design basically relies on statistical experience to make decisions, so mining work often occurs in high-stress areas, islands and semi-isolated coal pillars, providing a source of force for the occurrence of rock bursts. Due to the lack of grasp of the intrinsic law of the failure process of rock burst under the conditions of complex high stress and large burial depth, the time, place and intensity of rock burst occurrence have not reached the level of quantitative prediction; Information collection technology, its test parameters are not perfect, and the monitoring information is not very reliable, so it can only conduct qualitative monitoring of rock burst; the monitored information has not been comprehensively processed in theory, experiment, and method, and its feedback information The reliability of rock burst prediction is poor. Therefore, the current rockburst control is comprehensive prevention and control, which causes a lot of waste of manpower and material resources, greatly affects the production organization, and reduces production efficiency. In recent years, significant progress has been made in the research of rock burst prediction and prediction, but there is no systematic and reliable observation method in terms of the dynamic stress range and the quantitative observation of energy release characteristics in high stress areas, especially Especially under the condition of deep wells, the softening effect of the rock formation is obvious, and it is difficult to establish the judgment criterion of the dynamic stress range, and it is difficult to obtain quantitative values with the current observation means and methods. .
所以,我国煤矿冲击地压煤层的开采设计和实施仍然停留在对开采覆岩运动和应力场分布发展规律不清的发展阶段。这是当前煤矿冲击地压事故频繁,特别是重大灾害事故没有从根本上得到控制,开采经济效益低的重要原因之一。理论研究和生产实践证明,冲击地压事故几乎都与采掘工作面覆岩运动破坏和应力场应力大小及分布密切联系在一起。Therefore, the mining design and implementation of rockburst coal seams in my country's coal mines are still in the development stage where the development laws of mining overlying rock movement and stress field distribution are unclear. This is one of the important reasons for the frequent rockburst accidents in coal mines, especially the major disaster accidents that have not been fundamentally controlled, and the economic benefits of mining are low. Theoretical research and production practice have proved that almost all rock burst accidents are closely related to the movement damage of the overlying rock in the mining face and the magnitude and distribution of stress in the stress field.
发明内容 Contents of the invention
本发明的目的是为完善煤矿冲击地压危险性预测的可靠性问题,提出一种综合预警观测方法。The purpose of the present invention is to propose a comprehensive early warning observation method in order to improve the reliability of coal mine rock burst risk prediction.
本发明采取的技术方案是:The technical scheme that the present invention takes is:
第一步:获得冲击地压煤层的高应力场范围Step 1: Obtain the high stress field range of rockburst coal seams
在冲击地压煤层工作面开采过程中,首先在回采巷道中沿工作面前进方向,每间隔10-20米布置一台顶板动态仪,进行连续观测顶板下沉速度,从而获得顶板下沉速度突变的地点;然后在该地点逐步缩小顶板动态仪的间隔距离,继续连续观测顶板下沉速度,直至逼近准确的超前压力范围值,该范围确定为顶板高应力场范围。During the mining process of rock burst coal seam, firstly, along the advancing direction of the working face in the mining roadway, a roof dynamic instrument is arranged at intervals of 10-20 meters to continuously observe the roof sinking speed, so as to obtain the sudden change of roof sinking speed Then gradually reduce the interval distance of the roof dynamic instrument at this location, and continue to observe the roof sinking velocity continuously until it approaches the accurate leading pressure range value, which is determined as the roof high stress field range.
第二步:人为干预观测扰动范围Step 2: Human intervention to observe the disturbance range
在回采巷道中,从高应力场边缘处开始,沿工作面前进方向每间隔5-10m布置一台高敏感应力计,布置4台以上;并在动应力场范围内的应力峰值位置向煤层中钻3-5个孔,孔间距3-5m,孔深8-10米,孔中装入炸药,一次爆破;爆破后爆轰波在煤层中传播并逐渐衰减,同时高敏感应力计观测记录到应力波数据,根据每台应力波显示数据的大小从而确定出动压区能量释放的扰动范围。In the mining roadway, starting from the edge of the high stress field, a high-sensitivity strain gauge is arranged at intervals of 5-10m along the advancing direction of the working face, and more than 4 sets are arranged; Drill 3-5 holes with a hole spacing of 3-5m and a hole depth of 8-10m. Fill the holes with explosives and blast once; after the blasting, the detonation wave propagates in the coal seam and gradually attenuates. Stress wave data, according to the size of each stress wave display data to determine the disturbance range of energy release in the dynamic pressure zone.
第三步:全方位动态监测The third step: all-round dynamic monitoring
在上述确定的高应力场范围与扰动范围内的巷道中,布置埋设多组敏感压力传感器,组与组之间的间距根据应力分布规律定为20-40m,每组埋设2-3个间距0.5m的2-3个敏感压力传感器,且每组的的传感器在不同深度上;埋设时首先向围岩中钻孔,将敏感压力传感器浇筑在钻孔中,并将传感器信号传输到数据采集处理器上;在工作面开采中,数据采集处理器及时处理应力场的变化数据,当达到系统设置的预警参数时,进行报警,从而实现煤矿冲击地压危险性监测预警。In the roadway within the high stress field range and disturbance range determined above, arrange and bury multiple groups of sensitive pressure sensors. 2-3 sensitive pressure sensors per m, and the sensors of each group are at different depths; when burying, first drill holes into the surrounding rock, pour the sensitive pressure sensors in the drill holes, and transmit the sensor signals to the data acquisition and processing In the mining of the working face, the data acquisition processor processes the change data of the stress field in time, and when the early warning parameters set by the system are reached, an alarm is issued, so as to realize the monitoring and early warning of the coal mine rock burst risk.
本发明的积极效果是:通过将采掘工作面覆岩运动破坏和应力场应力大小及分布密切联系在一起进行综合监测,从而预测出冲击地压发生的危险性并及时报警措施,避免冲击地压危险事故的发生。The positive effect of the present invention is: by closely linking the movement damage of the overlying rock in the mining face with the stress size and distribution of the stress field for comprehensive monitoring, the danger of rock burst can be predicted and timely alarm measures can be taken to avoid rock burst occurrence of dangerous accidents.
附图说明 Description of drawings
图1是本发明顶板动态仪布置及动应力场示意图;Fig. 1 is a roof dynamic instrument arrangement and a schematic diagram of a dynamic stress field of the present invention;
图2是本发明人为干预诱发与观测仪器布置示意图;Fig. 2 is a schematic diagram of the arrangement of human intervention inducing and observing instruments of the present invention;
图3是本发明全方位动态监测示意图。Fig. 3 is a schematic diagram of omni-directional dynamic monitoring of the present invention.
具体实施方式 Detailed ways
下面结合附图说明本发明的实施。The implementation of the present invention will be described below in conjunction with the accompanying drawings.
第一步:获得动应力场范围Step 1: Obtain the range of dynamic stress field
如图1所示,在冲击地压煤层工作面开采过程中,首先在回采巷道中沿工作面前进方向,每间隔10-20米布置一台顶板动态仪,进行连续观测顶板下沉速度,从而获得顶板下沉速度突变的地点;然后在该地点逐步缩小顶板动态仪的间隔距离,继续连续观测顶板下沉速度,直至逼近准确的超前压力范围值,该范围确定为顶板动应力场范围。As shown in Figure 1, during the mining process of rock burst coal seam working face, a roof dynamic instrument is arranged at intervals of 10-20 meters along the advancing direction of the working face in the mining roadway to continuously observe the roof sinking speed, thereby Obtain the location where the roof sinking velocity changes suddenly; then gradually reduce the distance between the roof dynamic instruments at this location, and continue to observe the roof sinking velocity continuously until it approaches the accurate leading pressure range value, which is determined as the roof dynamic stress field range.
第二步:人为干预确定扰动范围Step 2: Human intervention to determine the disturbance range
如图2所示,在回采巷道中,从动应力场边缘处开始,沿工作面前进方向每间隔5-10m布置一台高敏感应力计,布置4台以上;并在动应力场范围内的应力峰值位置向煤层中钻3-5个孔,孔间距3-5m,孔深8-10米,孔中装入炸药,一次爆破;爆破后爆轰波在煤层中传播并逐渐衰减,同时高敏感应力计观测记录到应力波数据,根据每台应力波显示数据的大小从而确定出动压区能量释放的扰动范围。As shown in Figure 2, in the mining roadway, starting from the edge of the dynamic stress field, a high-sensitivity strain gauge is arranged at intervals of 5-10m along the advancing direction of the working face, and more than 4 sets are arranged; and within the range of the dynamic stress field Drill 3-5 holes into the coal seam at the stress peak position, the hole spacing is 3-5m, and the hole depth is 8-10m. The holes are filled with explosives and blasted at one time; after the blasting, the detonation wave propagates in the coal seam and gradually attenuates. Sensitive stress gauges observe and record stress wave data, and determine the disturbance range of energy release in the dynamic pressure zone according to the size of the data displayed by each stress wave.
第三步:全方位动态监测The third step: all-round dynamic monitoring
在上述确定的高应力场范围与扰动范围内的巷道中,布置埋设若干组敏感压力传感器,如图3所示,组与组之间的间距根据应力分布规律定为20-40m,每组埋设2-3个间距0.5m的2-3个敏感压力传感器,且每组的的传感器在不同深度上;埋设时首先向围岩中钻孔,将敏感压力传感器浇筑在钻孔中,并将传感器信号传输到数据采集处理器上;在工作面开采中,数据采集处理器及时处理应力场的变化数据,当达到系统设置的预警参数时,进行报警,从而实现煤矿冲击地压危险性监测预警。In the roadway within the high stress field range and disturbance range determined above, arrange and bury several groups of sensitive pressure sensors, as shown in Fig. 2-3 sensitive pressure sensors with a spacing of 0.5m, and the sensors of each group are at different depths; when embedding, first drill holes into the surrounding rock, pour the sensitive pressure sensors in the drill holes, and place the sensors The signal is transmitted to the data acquisition processor; in the mining of the working face, the data acquisition processor processes the change data of the stress field in time, and when the early warning parameters set by the system are reached, an alarm is issued, so as to realize the monitoring and early warning of the coal mine rock burst risk.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201210022940 CN102587983B (en) | 2012-01-12 | 2012-01-12 | Comprehensive early-warning observation method for coal mine rock burst |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201210022940 CN102587983B (en) | 2012-01-12 | 2012-01-12 | Comprehensive early-warning observation method for coal mine rock burst |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102587983A CN102587983A (en) | 2012-07-18 |
CN102587983B true CN102587983B (en) | 2013-12-25 |
Family
ID=46477150
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201210022940 Expired - Fee Related CN102587983B (en) | 2012-01-12 | 2012-01-12 | Comprehensive early-warning observation method for coal mine rock burst |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102587983B (en) |
Families Citing this family (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103256073B (en) * | 2013-04-28 | 2015-07-29 | 中国矿业大学 | Underground coal mine impact mine pressure partition grading prediction method |
CN103306722B (en) * | 2013-06-21 | 2015-08-05 | 中国矿业大学 | Micro-seismic multi-dimensional information comprehensive region detection and evaluation method for impact danger region |
CN104763470B (en) * | 2015-03-27 | 2017-03-08 | 辽宁工程技术大学 | A mining hole multi objective intelligent early-warning bump system and method |
CN105275495B (en) * | 2015-09-30 | 2017-08-29 | 山东科技大学 | A kind of method for judging shock wave harmfulness |
CN106443784A (en) * | 2016-10-20 | 2017-02-22 | 山东科技大学 | Fault zone rock burst dangerousness monitoring method |
CN106437702B (en) * | 2016-10-20 | 2018-06-19 | 山东科技大学 | Soft seam tunnel is met head on the monitoring method of bump danger |
CN108871641A (en) * | 2018-07-03 | 2018-11-23 | 中国矿业大学(北京) | The prediction technique of bump risk in a kind of exploitation of coal mine underground |
CN109798106B (en) * | 2018-11-13 | 2022-09-20 | 辽宁工程技术大学 | Method for predicting risk of rock burst and prevention and treatment measures |
CN110905528A (en) * | 2019-12-13 | 2020-03-24 | 山东科技大学 | Method of Renovating Dangerous Roadway of Rock Burst with Strong Disturbance and Segmentation |
CN112540400A (en) * | 2020-12-18 | 2021-03-23 | 山东科技大学 | Fracture zone dynamic pressure display strength and weakness degree judgment method |
CN112483178A (en) * | 2020-12-18 | 2021-03-12 | 山东科技大学 | Method for judging impact risk of deep syncline shaft part stope by large window destruction method |
CN115234303A (en) * | 2022-07-28 | 2022-10-25 | 华北科技学院 | Method and device for predicting rock burst danger by fixed-force drill cuttings |
CN116484186B (en) * | 2023-04-13 | 2023-09-08 | 煤炭科学研究总院有限公司 | Multi-field coupling-based rock burst intelligent early warning method and device |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1645558A2 (en) * | 1989-05-31 | 1991-04-30 | Институт Физики И Механики Горных Пород Ан Киргсср | Method of preventing tectonic and rock bumps |
US5233568A (en) * | 1991-06-28 | 1993-08-03 | Atlantic Richfield Company | Geopressure analysis system |
CN101936162B (en) * | 2010-04-16 | 2012-04-18 | 兖州煤业股份有限公司 | Method for preventing rock burst of bottom plate of layered tunnel in tectonic stress region of coal mine |
CN102296958A (en) * | 2011-07-22 | 2011-12-28 | 山东科技大学 | Method for preventing rock burst by artificial space defect body |
-
2012
- 2012-01-12 CN CN 201210022940 patent/CN102587983B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN102587983A (en) | 2012-07-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102587983B (en) | Comprehensive early-warning observation method for coal mine rock burst | |
CN104454010B (en) | A kind of deep-well tunnel tunneling construction dynamic comprehensive monitor and early warning system and method for early warning | |
CN102505965B (en) | A method for early warning and identification of rock mass failure and instability | |
CN105179018B (en) | A kind of coal mine rock burst detection method | |
CN105350965B (en) | Press prevention and controls exploiting colliery roadway bump | |
CN102392685B (en) | Dense roadway group rock burst hazard prediction method | |
CN106443784A (en) | Fault zone rock burst dangerousness monitoring method | |
CN104373154B (en) | A kind of back stability monitoring method | |
CN105626070A (en) | Rock burst prevention method through deep hole blasting and depressurizing | |
CN109611143A (en) | The multi-parameter integrated monitoring system of top plate hydrofracturing and fracturing effect method of discrimination | |
CN103939099B (en) | The prevention and controls of the dangerous coal seam group bump of a kind of thump | |
CN102955025B (en) | Method for determining height and range of stope overlying rock beam fracture zone of coal mine | |
CN106089296B (en) | A kind of prevention and treatment method of roof absciss layer water | |
CN104653226A (en) | Stress-gradient-based method for dividing coal impact ground pressure danger area | |
CN104481587A (en) | Large-mining depth and long-span fully-mechanized top-coal caving face roof sandstone fracture water detecting and preventing method | |
CN103670516A (en) | Identification method for rockburst disaster micro-seismic monitoring and early-warning key points | |
CN101581234A (en) | Comprehensive underground test method for deformation and damage of terranes of mining top plate and mining bottom plate of coal bed | |
CN102928144A (en) | System for monitoring gob stress in real time and overlying strata breakage judgment method | |
Lai et al. | Research on the mechanism of rockburst induced by mined coal-rock linkage of sharply inclined coal seams | |
CN104832163B (en) | The dangerous monitoring method of bump in a kind of coal mine underground exploitation | |
CN203271815U (en) | Optical fiber sensing technology-based safety monitoring system of coal mine roof | |
CN103760622A (en) | Method for monitoring activity state of underground fault | |
CN106494460B (en) | The high ferro subgrade stability method for early warning in Strong tremor region | |
CN105114069A (en) | Novel method for monitoring destruction situation of heavy oil reservoir cover layer by means of acoustic emission signals | |
CN112377256B (en) | An inspection method for large-diameter boreholes with impact risk based on microseismic monitoring |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20131225 Termination date: 20220112 |