CN102587674A - Method for grouting pre-stress duct - Google Patents

Method for grouting pre-stress duct Download PDF

Info

Publication number
CN102587674A
CN102587674A CN2012100665472A CN201210066547A CN102587674A CN 102587674 A CN102587674 A CN 102587674A CN 2012100665472 A CN2012100665472 A CN 2012100665472A CN 201210066547 A CN201210066547 A CN 201210066547A CN 102587674 A CN102587674 A CN 102587674A
Authority
CN
China
Prior art keywords
duct
grouting
pressure
slurry
pore passage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100665472A
Other languages
Chinese (zh)
Inventor
张卫兵
秦亚林
王德桂
魏建国
黄明洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Industry Huaxing Construction Co Ltd
Original Assignee
China Nuclear Industry Huaxing Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nuclear Industry Huaxing Construction Co Ltd filed Critical China Nuclear Industry Huaxing Construction Co Ltd
Priority to CN2012100665472A priority Critical patent/CN102587674A/en
Publication of CN102587674A publication Critical patent/CN102587674A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention relates to a method for grouting a pre-stress duct, belonging to the technical field of building construction. The method comprises the following steps of: firstly, introducing compressed air with predetermined pressure to an duct to be grouted and keeping the pressure, if the pressure loss within the predetermined time duration is less than a specified numeric value, judging a sealing test is qualified, carrying out routine high-pressure grouting work until the duct is fully grouted, or else, performing the second step; secondly, grouting by using low pressure of 1/5-1/3 of the conventional high pressure so that the duct is filled with slurry, standing for 3-8min and then discharging the slurry in the duct, washing the duct by using clear water, and drying water vapor by using the compressed air; and thirdly, after the slurry waiting to enter a leakage point is hardened, carrying out routine high-pressure grouting work until the duct is fully filled. In the method for grouting the pre-stress duct, the possible internal defect in the structural concrete around the duct can be found in time and treated appropriately, therefore, the damage of grouting construction to the concrete and an adhesion structure can be effectively avoided, and the smooth implementation of the high-quality grouting construction can be guaranteed.

Description

The prestressed pore passage grouting method
Technical field
The present invention relates to a kind of grouting method of nuclear power plant containment shell prestressed pore passage, especially a kind of prestressed pore passage grouting method belongs to technical field of building construction.
Background technology
Understand according to the applicant, in the post-tensioned prestressing architecture of design such as nuclear power plant containment shell, steel beam hole road is embedded in the structural concrete with rigid steel pipes or bellows and forms.After prestress system stretch-draw, need grouting treatment to be carried out in the duct, corrode prestress wire to stop extraneous hazardous medium with cement slurry.Conventional grouting method is disposable the duct to be filled; Because grouting pressure is bigger, and used steel pipe or the bellows bearing capacity of pore-forming is limited, when around concrete when comparatively closely knit; Under the externally concrete acting in conjunction, the disposable grouting basic feasible solution of high pressure.But when there is uncompacted defective in the duct surrounding concrete, adopt the big pressure effect of conventional method, be easy to make duct, structural concrete and adhering member (in steel lining) to damage.
Summary of the invention
The objective of the invention is to: to the problem of above prior art existence; Pass through process modification; A kind of can effectively being filled in the duct proposed; Guarantee fully closely knit, avoid the cavity the prestressed pore passage grouting method, even and this method duct surrounding concrete have the leakiness defective, can not cause any damage yet.
In order to reach above purpose, prestressed pore passage grouting method of the present invention comprises following basic step:
The first step, test sealing---in the duct of waiting to be in the milk, feed the compressed air of predetermined pressure and keep-up pressure,, carry out conventional high pressure grouting operation, fill until the duct if scheduled time internal pressure loss judges then that less than regulation numerical value performing leak test is qualified; Otherwise carried out for second step;
Second step, grouting treatment---adopt low-pressure grouting, make slurry be full of the duct, leave standstill the slurry in the emptying duct after the scheduled time, dry up steam with the flushing with clean water duct and with compressed air; Therefore can play effect to breakthrough sealing because the slurry that has got in the breakthrough can not be flushed away this moment;
The 3rd step, implement grouting---wait to get into the slurry sclerosis in the breakthrough after, carry out conventional high pressure grouting operation, fill until the duct.
The present invention is through the simple processing arrangement that is suitable for; Need not to increase construction equipment; Not only can in time find the internal flaw that duct surrounding structure concrete possibly exist; And deal carefully with, thereby can effectively avoid the destruction of grouting construction to concrete and attaching structure generation, guarantee the high-quality smooth implementation of grouting construction.
Description of drawings
Below in conjunction with accompanying drawing the present invention is further described.
Fig. 1 is the grouting duct sketch map of the embodiment of the invention one.
Fig. 2 is the grouting duct sketch map of the embodiment of the invention two.
The specific embodiment
Embodiment one
The prestressed pore passage of present embodiment is horizontal hole T (referring to Fig. 1), and its grouting concrete steps are:
The first step, test sealing---in the duct of waiting to be in the milk, feed 0.5-0.6MPa compressed air; Keep-uped pressure 1 ± 0.5 minute, if this time internal pressure loss less than 0.1MPa, judges that then performing leak test is qualified; Carry out conventional high pressure grouting operation, disposable the duct is filled; Otherwise carried out for second step.
Second step, grouting treatment---adopt the low-pressure grouting of conventional high pressure 1/5-1/3, make slurry be full of the duct, leave standstill the slurry in the emptying duct after 3-8 minute, dry up steam with the flushing with clean water duct and with compressed air; Therefore can play effect to breakthrough sealing because the slurry that has got in the breakthrough can not be flushed away this moment.
The 3rd step, implement grouting---wait to get into the slurry sclerosis in the breakthrough after, carry out conventional high pressure grouting operation, fill until the duct.
Embodiment two
The prestressed pore passage of present embodiment is vertical channel T (referring to Fig. 2,1 is in the steel lining among the figure, the 2nd, containment concrete, Tn are n section ducts to be in the milk), and its grouting concrete steps are:
The first step, test sealing---in the duct of waiting to be in the milk, feed 0.5-0.6MPa compressed air; Keep-uped pressure 1 ± 0.5 minute, if this time internal pressure loss less than 0.1MPa, judges that then performing leak test is qualified; Carry out conventional high pressure grouting operation, disposable the duct is filled; Otherwise, carried out for second step with vertical channel segmentation (about common every section height 10m).
Second step, grouting treatment---adopt the low-pressure grouting of conventional high pressure 1/5-1/3, make slurry be full of duct section to be in the milk, leave standstill the slurry in the emptying duct after 3-8 minute, dry up steam with the flushing with clean water duct and with compressed air; Therefore can play effect to breakthrough sealing because the slurry that has got in the breakthrough can not be flushed away this moment.
The 3rd step, implement grouting---wait to get into the slurry sclerosis in the breakthrough after, carry out conventional high pressure grouting operation, fill until duct section to be in the milk.
The 4th step, the repetition first step are filled until whole duct.
Repeatedly practise proof; The grouting process method of the foregoing description can in time be found the internal flaw that duct surrounding structure concrete possibly exist; And deal carefully with; Thereby can effectively avoid the destruction of grouting construction, guarantee the high-quality smooth implementation of grouting construction concrete and attaching structure generation; This process has eliminated effectively that in the duct cavity of slurry in addition; Significantly improved the compactness of duct grouting; The full pattern cutting plane in duct is closely knit fully after grouting, does not have any cavity, thereby is that the construction quality that guarantees nuclear power plant containment shell has been established solid foundation.

Claims (5)

1. prestressed pore passage grouting method is characterized in that may further comprise the steps:
The first step, test sealing---in the duct of waiting to be in the milk, feed the compressed air of predetermined pressure and keep-up pressure,, carry out conventional high pressure grouting operation, fill until the duct if scheduled time internal pressure loss judges then that less than regulation numerical value performing leak test is qualified; Otherwise carried out for second step;
Second step, grouting treatment---adopt low-pressure grouting, make slurry be full of the duct, leave standstill the slurry in the emptying duct after the scheduled time, dry up steam with the flushing with clean water duct and with compressed air;
The 3rd step, implement grouting---wait to get into the slurry sclerosis in the breakthrough after, carry out conventional high pressure grouting operation, fill until the duct.
2. prestressed pore passage grouting method according to claim 1; It is characterized in that: said duct is a vertical channel; When the first step judges that performing leak test is defective,, and carry out packer grouting processing and segmentation enforcement respectively in second step and the 3rd step and be in the milk the vertical channel segmentation; And the above step that circulates, fill until whole duct.
3. prestressed pore passage grouting method according to claim 1 and 2 is characterized in that: in the said first step, predetermined pressure is 0.5-0.6MPa, and the scheduled time is 1 ± 0.5 minute, and regulation numerical value is 0.1MPa.
4. prestressed pore passage grouting method according to claim 3 is characterized in that: adopting low pressure in said second step is conventional high pressure 1/5-1/3.
5. prestressed pore passage grouting method according to claim 4 is characterized in that: said time of repose was controlled at 3-8 minute.
CN2012100665472A 2012-03-14 2012-03-14 Method for grouting pre-stress duct Pending CN102587674A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100665472A CN102587674A (en) 2012-03-14 2012-03-14 Method for grouting pre-stress duct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100665472A CN102587674A (en) 2012-03-14 2012-03-14 Method for grouting pre-stress duct

Publications (1)

Publication Number Publication Date
CN102587674A true CN102587674A (en) 2012-07-18

Family

ID=46476857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100665472A Pending CN102587674A (en) 2012-03-14 2012-03-14 Method for grouting pre-stress duct

Country Status (1)

Country Link
CN (1) CN102587674A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877415A (en) * 2012-10-26 2013-01-16 上海市城市建设设计研究总院 Ultra-high-difference, ultra-long and ultra-large-tonnage prestress pipeline grouting method and herring-bone pipe bundle
CN109653379A (en) * 2018-12-20 2019-04-19 武汉源锦建材科技有限公司 A kind of assembly concrete building grouting pretreatment construction method
CN113323162A (en) * 2021-05-17 2021-08-31 中建旷博(福建)有限公司 Construction method for installing pre-buried box through silicon rubber plugging

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005116367A1 (en) * 2004-05-31 2005-12-08 Anderson Technology Corporation Grout injection method including process for drawing vacuum from cable sheath of post-tension-type pc structure
CN101165291A (en) * 2007-07-12 2008-04-23 中国建筑第七工程局 Vertical prestressing force opening mud jacking construction method and construction device
CN101435266A (en) * 2008-11-20 2009-05-20 中国核工业华兴建设有限公司 Prestress pore passage dense grouting method
CN101672181A (en) * 2009-08-13 2010-03-17 重庆市十八土鑫诚灌浆防水工程有限公司 Controllable cement backfilling grouting method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005116367A1 (en) * 2004-05-31 2005-12-08 Anderson Technology Corporation Grout injection method including process for drawing vacuum from cable sheath of post-tension-type pc structure
CN101165291A (en) * 2007-07-12 2008-04-23 中国建筑第七工程局 Vertical prestressing force opening mud jacking construction method and construction device
CN101435266A (en) * 2008-11-20 2009-05-20 中国核工业华兴建设有限公司 Prestress pore passage dense grouting method
CN101672181A (en) * 2009-08-13 2010-03-17 重庆市十八土鑫诚灌浆防水工程有限公司 Controllable cement backfilling grouting method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
严跃兰: "岭澳核电站安全壳预应力灌浆用浆体配合比试验及应用", 《建筑科学》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877415A (en) * 2012-10-26 2013-01-16 上海市城市建设设计研究总院 Ultra-high-difference, ultra-long and ultra-large-tonnage prestress pipeline grouting method and herring-bone pipe bundle
CN102877415B (en) * 2012-10-26 2014-07-09 上海市城市建设设计研究总院 Ultra-high-difference, ultra-long and ultra-large-tonnage prestress pipeline grouting method and herring-bone pipe bundle
CN109653379A (en) * 2018-12-20 2019-04-19 武汉源锦建材科技有限公司 A kind of assembly concrete building grouting pretreatment construction method
CN109653379B (en) * 2018-12-20 2020-10-27 武汉源锦建材科技有限公司 Grouting pretreatment construction method for fabricated concrete building
CN113323162A (en) * 2021-05-17 2021-08-31 中建旷博(福建)有限公司 Construction method for installing pre-buried box through silicon rubber plugging

Similar Documents

Publication Publication Date Title
AU2016306883B2 (en) Heat transfer pipe embedded in a prefabricated pipe pile and embedding method
CN108487249B (en) Method for reinforcing wind turbine foundation
CN104088254B (en) Pressure-bearing reinforced concrete structure leakage repair device and construction method thereof
CN103470046B (en) The casting method of ultra-high steel tube concrete column tremie method concrete casting device
CN109944228B (en) Equipment and method for treating sludge with ultrahigh water content by vacuum preloading-curing
CN110658332B (en) Concrete lining pre-pressure measurement test device and test method thereof
CN102587674A (en) Method for grouting pre-stress duct
CN105220687A (en) Prestressed concrete pipe pile grouting behind shaft or drift lining method fills with core reinforcing construction method
CN105386454A (en) United assembled foundation for power transmission tower
CN101672187A (en) Anti-seepage water treatment method
CN104099932A (en) Breaking device and breaking method of pile head of underwater concrete pile
CN105369797A (en) Vacuum radiation solidification method for collapsible loess
CN107724349A (en) A kind of seat ring and the method for improving seat ring bottom concrete density
CN203890978U (en) Contact grouting structure for buried pressure pipe
CN109719837A (en) A kind of method for exhausting of padded coaming block preparation
CN104018476A (en) Embedded type penstock contact grouting structure and grouting technology
CN204212161U (en) System shored by the oblique steel of pattern foundation pit supporting structure
CN104526879A (en) Rapid ceramsite prewetting stock bin and rapid ceramsite prewetting treatment process
CN114718313A (en) High-throwing self-compacting vibration-free construction method for inclined steel pipe concrete column with spherical steel structure
CN204608695U (en) A kind of New-old concrete horizontal bedding syndeton
CN110453659B (en) Construction method for rock plug reservation construction key technology of diversion tunnel of weak surrounding rock
CN204247953U (en) A kind of tundish centralizer
CN106948459A (en) A kind of rain dirt is dammed gate
CN207673965U (en) Circulating water pipeline plugging device through walls
CN207453121U (en) A kind of hydraulic structure flow-passing surface pre-embedded anchoring bolts

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120718