CN102587412B - Stage construction basement support change method using underground continuous wall as separation containment - Google Patents

Stage construction basement support change method using underground continuous wall as separation containment Download PDF

Info

Publication number
CN102587412B
CN102587412B CN201210030873.8A CN201210030873A CN102587412B CN 102587412 B CN102587412 B CN 102587412B CN 201210030873 A CN201210030873 A CN 201210030873A CN 102587412 B CN102587412 B CN 102587412B
Authority
CN
China
Prior art keywords
basement
stage
diaphragm wall
shaped steel
support change
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210030873.8A
Other languages
Chinese (zh)
Other versions
CN102587412A (en
Inventor
刘玉涛
曹跃军
李小玥
陈正立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN201210030873.8A priority Critical patent/CN102587412B/en
Publication of CN102587412A publication Critical patent/CN102587412A/en
Application granted granted Critical
Publication of CN102587412B publication Critical patent/CN102587412B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a stage construction basement support change method using an underground continuous wall as separation containment. The method comprises the following steps that: 1, a separation containment structure using the underground continuous wall as a body is built, and in addition, pre-buried sectional steel is buried on the underground wall; 2, first-stage basement support change is carried out, support change sectional steel is welded at one end of the pre-buried sectional steel, and the other end of the support change sectional steel is cast with an underground slab of the first-stage basement; 3, secondary second-stage basement support change is carried out, support change sectional steel is welded at the other end of the pre-buried sectional steel in the same way, and a basement slab of the second-stage basement is cast at the other end of the support change sectional steel; 4, the underground continuous wall is dismounted, the pre-buried sectional steel is preserved, the connecting steel bars are tied and bundled, and concrete is cast, so the first-stage basement and the second-stage basement are connected. The support change problem of the front-stage construction basement and the back-stage construction basement can be perfectly solved, the support change effect is good, in addition, the basement structure can be smoothly built, and the construction is convenient.

Description

A kind of stage construction basement support change method of going along with sb. to guard him with the separation of diaphragm wall do
Technical field
The present invention relates to the realm of building construction, be specifically related to a kind of stage construction basement support change method of going along with sb. to guard him with the separation of diaphragm wall do.
Background technology
In the basement construction of construction projects, due to reasons such as place, safety or funds, usually need to carry out stage construction, stage construction is often taking diaphragm wall as separating space enclosing structure, after having constructed, diaphragm wall is removed, front and back two phases basement is connected.In aggregates for ensureing that basement can connect mutually, just must handle the support replacement problem of front construction in later period part well.Conventionally adopt at present the contrary mode of doing, along with the carrying out of construction successively removed diaphragm wall from top to bottom, so that front and back phase basement is communicated with, construction is trouble comparatively.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of and makes to separate the stage construction basement support change method of going along with sb. to guard him with diaphragm wall, the support replacement problem of phase construction basement before and after can solving well, support replacement is effective, and can be along making basement structure, easy construction.
For solving above-mentioned existing technical problem, the present invention adopts following scheme: a kind of stage construction basement support change method of going along with sb. to guard him with the separation of diaphragm wall do, comprises the following steps:
Step 1: build separation space enclosing structure taking diaphragm wall as main body between first phase basement and the second stage of basement, and the girder and the secondary beam position that are positioned at floor structure on diaphragm wall are embedded into pre-buried shaped steel;
Step 2: when the construction of first phase basement support change, at the support replacement shaped steel of one end of pre-buried shaped steel welding same model, the other end of support replacement shaped steel pours into the basement floor of first phase basement, and the side near diaphragm wall on the basement floor of first phase basement is reserved connecting reinforcement;
Step 3: when the second stage of basement support change construction, weld equally the support replacement shaped steel of same model at the other end of pre-buried shaped steel, the other end of support replacement shaped steel pours into the basement floor of the second stage of basement, and the side near diaphragm wall on the basement floor of the second stage of basement is reserved connecting reinforcement;
Step 4: carry out the dismounting of diaphragm wall from top to bottom, retain pre-buried shaped steel, connecting reinforcement between the basement floor of colligation first phase basement and the basement floor of the second stage of basement, concreting, couples together first phase basement and the second stage of basement.
As preferably, the thickness of described pre-buried shaped steel equals the wall thickness of diaphragm wall.
As preferably, described pre-buried shaped steel is hollow or H type.As preferably, when described basement floor is top board or base plate, building before basement floor, on basement floor near a side pre-embedded steel slab waterstop of diaphragm wall.Beneficial effect: the present invention adopts technique scheme to provide a kind of and makes to separate the stage construction basement support change method of going along with sb. to guard him with diaphragm wall, the support replacement problem of phase construction basement before and after having solved well, support replacement is effective, and can be along making basement structure, easy construction.
Brief description of the drawings
Fig. 1 is the schematic diagram that diaphragm wall of the present invention is imbedded pre-buried shaped steel;
Fig. 2 is first phase basement support change construction floor map of the present invention;
Fig. 3 is the second stage of basement support change construction floor map of the present invention;
Fig. 4 be in the present invention diaphragm wall remove after one, the connection diagram of the second stage of basement;
Fig. 5 is the sectional view of A-A face in Fig. 1;
Fig. 6 is the sectional view of B-B face in Fig. 2;
Fig. 7 is the sectional view of C-C face in Fig. 3;
Fig. 8 is the sectional view of D-D face in Fig. 4.
Detailed description of the invention
As shown in Figures 1 to 8, a kind of stage construction basement support change method of going along with sb. to guard him with the separation of diaphragm wall do, comprises the following steps:
Step 1: build the separation space enclosing structure taking diaphragm wall 1 as main body between first phase basement and the second stage of basement, and the girder 5 and secondary beam 6 positions that are positioned at floor structure on diaphragm wall 1 are embedded into pre-buried shaped steel 2, the thickness of described pre-buried shaped steel 2 equals the wall thickness of diaphragm wall 1;
Step 2: when the construction of first phase basement support change, at the support replacement shaped steel 3 of one end of pre-buried shaped steel 2 welding same model, the other end of support replacement shaped steel 3 pours into the basement floor 4 of first phase basement, and the side near diaphragm wall 1 on the basement floor 4 of first phase basement is reserved connecting reinforcement 7;
Step 3: when the second stage of basement support change construction, weld equally the support replacement shaped steel 3 of same model at the other end of pre-buried shaped steel 2, the other end of support replacement shaped steel 3 pours into the basement floor 4 of the second stage of basement, and the side near diaphragm wall 1 on the basement floor 4 of the second stage of basement is reserved connecting reinforcement 7;
Step 4: carry out the dismounting of diaphragm wall 1 from top to bottom, retain pre-buried shaped steel 2, connecting reinforcement 7 between the basement floor 4 of colligation first phase basement and the basement floor 4 of the second stage of basement, concreting, couples together first phase basement and the second stage of basement.
The support replacement problem of phase construction basement before and after having solved well, support replacement is effective, and can be with top-down along the basement of constructing as mode, easy construction.Pre-buried shaped steel 2 in step 1 is hollow or H type.3 length of support replacement shaped steel described in step 2 and step 3 are determined according to the force analysis of support replacement shaped steel 3.When described basement floor 4 is top board or base plate, building before basement floor 4, on basement floor 4 near a side pre-embedded steel slab waterstop of diaphragm wall 1.

Claims (4)

1. do to separate a stage construction basement support change method of going along with sb. to guard him with diaphragm wall, it is characterized in that: comprise the following steps:
Step 1: build separation space enclosing structure taking diaphragm wall (1) as main body between first phase basement and the second stage of basement, and the girder (5) and secondary beam (6) position that are positioned at floor structure on diaphragm wall (1) are embedded into pre-buried shaped steel (2);
Step 2: when the construction of first phase basement support change, at the support replacement shaped steel (3) of one end of pre-buried shaped steel (2) welding same model, the other end of support replacement shaped steel (3) pours into the basement floor (4) of first phase basement, the reserved connecting reinforcement (7) of the upper side near diaphragm wall (1) of basement floor (4) of first phase basement;
Step 3: when the second stage of basement support change construction, weld equally the support replacement shaped steel (3) of same model at the other end of pre-buried shaped steel (2), the other end of support replacement shaped steel (3) pours into the basement floor (4) of the second stage of basement, the reserved connecting reinforcement (7) of the upper side near diaphragm wall (1) of basement floor (4) of the second stage of basement;
Step 4: carry out the dismounting of diaphragm wall (1) from top to bottom, retain pre-buried shaped steel (2), connecting reinforcement (7) between the basement floor (4) of colligation first phase basement and the basement floor (4) of the second stage of basement, concreting, couples together first phase basement and the second stage of basement.
2. a kind of stage construction basement support change method of going along with sb. to guard him with the separation of diaphragm wall do according to claim 1, is characterized in that: the thickness of described pre-buried shaped steel (2) equals the wall thickness of diaphragm wall (1).
3. a kind of stage construction basement support change method of going along with sb. to guard him with the separation of diaphragm wall do described in, is characterized in that: described pre-buried shaped steel (2) is hollow or H type.
4. a kind of stage construction basement support change method of going along with sb. to guard him with the separation of diaphragm wall do described in, it is characterized in that: when described basement floor (4) is top board or base plate, building, basement floor (4) is front, in the upper side pre-embedded steel slab waterstop near diaphragm wall (1) of basement floor (4).
CN201210030873.8A 2012-02-13 2012-02-13 Stage construction basement support change method using underground continuous wall as separation containment Active CN102587412B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210030873.8A CN102587412B (en) 2012-02-13 2012-02-13 Stage construction basement support change method using underground continuous wall as separation containment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210030873.8A CN102587412B (en) 2012-02-13 2012-02-13 Stage construction basement support change method using underground continuous wall as separation containment

Publications (2)

Publication Number Publication Date
CN102587412A CN102587412A (en) 2012-07-18
CN102587412B true CN102587412B (en) 2014-06-11

Family

ID=46476603

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210030873.8A Active CN102587412B (en) 2012-02-13 2012-02-13 Stage construction basement support change method using underground continuous wall as separation containment

Country Status (1)

Country Link
CN (1) CN102587412B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864946B (en) * 2012-10-23 2014-07-16 山东建筑大学 Process for supporting existing buildings through structural steel and horizontal rachel rod member and additionally adding multilayer basement
CN104631824B (en) * 2014-12-28 2017-07-14 上海建工一建集团有限公司 Structure floor support replacement construction method at interim dividing wall
CN104652474B (en) * 2015-01-21 2016-08-24 中国建筑第八工程局有限公司 Diaphram wall support changing structure for use and construction method
CN110080526B (en) * 2019-04-22 2021-05-07 上海建工一建集团有限公司 Stage reverse construction method for basement
CN110080527B (en) * 2019-04-22 2020-12-04 上海建工一建集团有限公司 Support changing construction method for staged diaphragm wall of reverse construction method steel structure basement
CN110055975A (en) * 2019-04-25 2019-07-26 中建四局第四建筑工程有限公司 A kind of large-span deep foundation pit basement stage construction method and temporary structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000054409A (en) * 1998-08-05 2000-02-22 Ohbayashi Corp Work execution method of top-down construction stanchion in underground excavated space peripheral part
CN101012655A (en) * 2006-12-30 2007-08-08 上海市城市建设设计研究院 Construction method of carrying out underground space rigid connection by stages
CN201261916Y (en) * 2008-09-09 2009-06-24 贵阳铝镁设计研究院 Late poured band structure adopting profiled bar short beam to improve shear force
CN201546227U (en) * 2009-10-31 2010-08-11 华丰建设股份有限公司 Steel support beam for supporting foundation pit bracing piling wall and basement structure outer wall
CN102116036A (en) * 2009-12-30 2011-07-06 中国京冶工程技术有限公司厦门分公司 Method for constructing underground large building by combining top-down construction method technology with sequence construction method technology
CN103061357A (en) * 2012-12-26 2013-04-24 广东省建科建筑设计院 Connection joint between basement base plate and underground diaphragm wall

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000054409A (en) * 1998-08-05 2000-02-22 Ohbayashi Corp Work execution method of top-down construction stanchion in underground excavated space peripheral part
CN101012655A (en) * 2006-12-30 2007-08-08 上海市城市建设设计研究院 Construction method of carrying out underground space rigid connection by stages
CN201261916Y (en) * 2008-09-09 2009-06-24 贵阳铝镁设计研究院 Late poured band structure adopting profiled bar short beam to improve shear force
CN201546227U (en) * 2009-10-31 2010-08-11 华丰建设股份有限公司 Steel support beam for supporting foundation pit bracing piling wall and basement structure outer wall
CN102116036A (en) * 2009-12-30 2011-07-06 中国京冶工程技术有限公司厦门分公司 Method for constructing underground large building by combining top-down construction method technology with sequence construction method technology
CN103061357A (en) * 2012-12-26 2013-04-24 广东省建科建筑设计院 Connection joint between basement base plate and underground diaphragm wall

Also Published As

Publication number Publication date
CN102587412A (en) 2012-07-18

Similar Documents

Publication Publication Date Title
CN102587412B (en) Stage construction basement support change method using underground continuous wall as separation containment
KR101391637B1 (en) Constrution methoed for Prestressed Composite Truss girder using steel truss member
CN110056092B (en) Connecting structure of bolting-inserting type upper and lower prefabricated shear walls and superimposed sheet and construction method
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
KR101600845B1 (en) The horizontal structural frame and the underground construction methods using it
CN205711776U (en) A kind of supporting bracket of bridge construction
CN204112525U (en) Band perps precast shear wall structure in strong concrete precast frame
CN102587420B (en) Supporter exchanging method for stage construction basement using cast-in-situ bored piles as separation palisade
KR20150005301A (en) Permanent form and construction method for coping
CN110185265A (en) A kind of isolation baffle plate for bean column node different labels concreting
CN203684060U (en) Temporary steel-frame bridge
CN203889454U (en) Integrated moving device of construction formwork of culvert wall
CN202280152U (en) Structure for arranging embedded part at bottom of reinforced concrete plate
JP6543077B2 (en) Construction method of structure
CN202989763U (en) Sectional type concrete filled steel tube pier adopting non-pulling resistant and non-shearing resistant limitation
CN207144456U (en) Builder's jack I-steel built-in fitting
CN110273432A (en) A kind of existing main structure of subway station enlarging construction method
CN106638679B (en) A kind of precast concrete pipe gallery connection method
CN103981810A (en) Steel tube arch main arch splicing and supporting system
CN205224014U (en) Precast underground continuous wall of pre -buried steel sheet
CN103741857A (en) Floor system with U-shaped steel beams, steel bar trusses and floor bearing plates
CN202509403U (en) Steel pipe support concrete foundation structure
KR101485563B1 (en) The horizontal structural frame
CN203741845U (en) Structure for assisting in communicating fountain pits in semi-reversed construction method
CN204589824U (en) A kind of " embracing ear Implant Method " template system for pier stud construction in water

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant