CN102587354A - Method for enhancing soil retaining of soil nails between fender posts in soft soil - Google Patents

Method for enhancing soil retaining of soil nails between fender posts in soft soil Download PDF

Info

Publication number
CN102587354A
CN102587354A CN2012100310403A CN201210031040A CN102587354A CN 102587354 A CN102587354 A CN 102587354A CN 2012100310403 A CN2012100310403 A CN 2012100310403A CN 201210031040 A CN201210031040 A CN 201210031040A CN 102587354 A CN102587354 A CN 102587354A
Authority
CN
China
Prior art keywords
soil
concrete
adjacent
retaining
main muscle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100310403A
Other languages
Chinese (zh)
Inventor
张仲文
华学严
李小玥
杨伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN2012100310403A priority Critical patent/CN102587354A/en
Publication of CN102587354A publication Critical patent/CN102587354A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a method for enhancing soil retaining of soil nails between fender posts in soft soil, which includes the following steps: step 1 enabling soil mass between two adjacent drilled poured fender posts to be constructed to the shape of a circular arc recessed inwards and tangential to outer edges of the two adjacent drilled poured fender posts; step 2 spraying a first layer of concrete; step 3 hitting soil nails into the soil mass from the surface of the first layer of concrete; step 4 arranging a steel bar attached to the outer wall of the first layer of concrete between the two adjacent drilled poured fender posts along the vertical direction to form a main reinforcing bar; step 5 sequentially arranging horizontal steel bars the two ends of which are respectively abutted against the two adjacent drilled poured fender posts along the main reinforcing bar from top to bottom, enabling the main reinforcing bar and the horizontal steel bars to form steel bar meshes and enabling the soil tails to be welded with adjacent horizontal steel bars; and step 6 spraying or pouring a second layer of concrete in a formwork mode on the surface of the steel bar meshes. The method is capable of effectively preventing the soil mass between the drilled poured fender posts from falling and ensuring safety of subsequent construction.

Description

Soil nailing enhancing retaining indigenous method between fender post in a kind of weak soil
Technical field
The present invention relates to the realm of building construction, be specifically related in a kind of weak soil that soil nailing strengthens the retaining indigenous method between fender post.
Background technology
During the soft soil foundation pit soil excavation, bored pile is set as going along with sb. to guard him soil-baffling structure, goes along with sb. to guard him and have certain headroom crack between the bored pile; The landing phenomenon takes place or flows phenomenons such as soil, flowing water in the soil body easily therebetween; Particularly in weak soil, because the landing phenomenon takes place the stream plasticity of mud and mucky soil more easily, the landing soil body can injure the constructor; And the soil body of cleaning landing can influence follow-up construction, and influences safety of construction.Therefore need to adopt effectively retaining indigenous method, prevent the landing of the soil body between bored pile, guarantee follow-up safety of construction.
Summary of the invention
Technical problem to be solved by this invention is to provide in a kind of weak soil that soil nailing strengthens the retaining indigenous method between fender post, can prevent the landing of the soil body between bored pile effectively, guarantees follow-up safety of construction.
For solving above-mentioned existing technical problem, the present invention adopts following scheme: soil nailing enhancing retaining indigenous method between fender post in a kind of weak soil may further comprise the steps:
Step 1: two adjacent rhizospheres are protected the soil body between the bored pile accomplish the tangent circular arc of outer rim inwardly recessed and that protect bored pile with two adjacent rhizospheres;
Step 2: spray the first floor concrete in the soil body surface that trims;
Step 3: after treating the final set of first floor concrete, throw soil nailing into to the soil body, make the first floor concrete fix from the first floor concrete surface;
Step 4: protect between the bored pile reinforcing bar of fitting at two adjacent rhizospheres and form main muscle along vertical direction setting and first floor outer walls of concrete;
Step 5: set gradually two ends from top to bottom and two adjacent rhizospheres protect the transverse reinforcement that bored pile holds out against respectively along main muscle; And with a transverse reinforcement and the colligation of main muscle employing bundle silk; Said transverse reinforcement curves the circular arc that fits with the first floor concrete, and to protect the outer rim of bored pile tangent with two adjacent rhizospheres, and main muscle and transverse reinforcement form reinforced mesh; Soil nailing and the welding of adjacent transverse reinforcing bar make reinforced mesh fix;
Step 6: perhaps adopt formwork way to build second layer concrete at the reinforced mesh jet surface.
As preferably, the main muscle in the said step 4 adopts Φ 12150 reinforcing bars.
As preferably, the transverse reinforcement in the said step 5 adopts Φ 6300 reinforcing bars.
As preferably, first floor concrete in the said step 2 and the second layer concrete in the step 6 are the thick C15 concrete of 30mm.
As preferably, said step 1, step 2, step 3, step 4, step 5, step 6 are carried out with the excavation progress of the soil body.
As preferably, the main muscle in the vertical direction of said step 4 adopts the segmentation setting.
Beneficial effect:
The present invention adopts technique scheme to provide in a kind of weak soil that soil nailing strengthens the retaining indigenous method between fender post, has prevented the landing of the soil body between bored pile effectively, has guaranteed follow-up safety of construction.
Description of drawings
Fig. 1 is the structural representation of the fender post behind employing the present invention;
Fig. 2 is the sectional view of A-A face among Fig. 1.
The specific embodiment
As shown in Figure 1, before foundation ditch 2 soil excavations, build earlier and go along with sb. to guard him bored pile 1, and capping beam 3 is set going along with sb. to guard him bored pile 1 top.As depicted in figs. 1 and 2, then in a kind of weak soil of providing of embodiment of the present invention between fender post soil nailing strengthen the retaining indigenous method, may further comprise the steps:
Step 1: two adjacent rhizospheres are protected the soil body 4 between the bored pile 1 accomplish the tangent circular arc of outer rim inwardly recessed and that protect bored pile 1 with two adjacent rhizospheres;
Step 2: at the soil body that trims 4 jet surface first floor concrete, said first floor concrete is the thick C15 concrete of 30mm;
Step 3: after treating the final set of first floor concrete, throw soil nailing 7 into to the soil body, make the first floor concrete fix from the first floor concrete surface;
Step 4: protect between the bored pile 1 Φ 12150 reinforcing bars of fitting at two adjacent rhizospheres and form main muscle 5 along vertical direction setting and first floor outer walls of concrete;
Step 5: set gradually two ends from top to bottom and two adjacent rhizospheres protect Φ 6300 transverse reinforcements 6 that bored pile 1 holds out against respectively along main muscle 5; And with a transverse reinforcement 6 and main muscle 5 employing bundle silk colligations; Said transverse reinforcement 6 curves the circular arc that fits with the first floor concrete, and to protect the outer rim of bored pile 1 tangent with two adjacent rhizospheres, and main muscle 5 forms reinforced mesh with transverse reinforcement 6; Soil nailing 7 and 6 welding of adjacent transverse reinforcing bar make reinforced mesh fix;
Step 6: perhaps adopt formwork way to build second layer concrete at the reinforced mesh jet surface, said second layer concrete is the thick C15 concrete of 30mm.
Said step 1, step 2, step 3, step 4, step 5, step 6 are carried out with the excavation progress of the soil body.When foundation ditch 2 degree of depth were dark, the main muscle in the vertical direction of step 4 adopted the segmentation setting.Concrete strength grade of the first floor concrete and the second layer and thickness are looked the actual conditions adjustment.The diameter and the spacing of main muscle 5, transverse reinforcement 6 are decided by on-site actual situations, and soil nailing 7 length and spacing are looked soil pressure and decided.Prevent the landing of the soil body between bored pile effectively, guaranteed follow-up safety of construction.

Claims (6)

  1. In the weak soil between fender post soil nailing strengthen the retaining indigenous method, it is characterized in that: may further comprise the steps:
    Step 1: two adjacent rhizospheres are protected the soil body between the bored pile accomplish the tangent circular arc of outer rim inwardly recessed and that protect bored pile with two adjacent rhizospheres;
    Step 2: spray the first floor concrete in the soil body surface that trims;
    Step 3: after treating the final set of first floor concrete, throw soil nailing into to the soil body, make the first floor concrete fix from the first floor concrete surface;
    Step 4: protect between the bored pile reinforcing bar of fitting at two adjacent rhizospheres and form main muscle along vertical direction setting and first floor outer walls of concrete;
    Step 5: set gradually two ends from top to bottom and two adjacent rhizospheres protect the transverse reinforcement that bored pile holds out against respectively along main muscle; And with a transverse reinforcement and the colligation of main muscle employing bundle silk; Said transverse reinforcement curves the circular arc that fits with the first floor concrete, and to protect the outer rim of bored pile tangent with two adjacent rhizospheres, and main muscle and transverse reinforcement form reinforced mesh; Soil nailing and the welding of adjacent transverse reinforcing bar make reinforced mesh fix;
    Step 6: perhaps adopt formwork way to build second layer concrete at the reinforced mesh jet surface.
  2. 2. soil nailing enhancing retaining indigenous method between fender post in a kind of weak soil according to claim 1, it is characterized in that: the main muscle in the said step 4 adopts Φ 12150 reinforcing bars.
  3. 3. soil nailing enhancing retaining indigenous method between fender post in a kind of weak soil according to claim 1, it is characterized in that: the transverse reinforcement in the said step 5 adopts Φ 6300 reinforcing bars.
  4. 4. soil nailing enhancing retaining indigenous method between fender post in a kind of weak soil according to claim 1, it is characterized in that: first floor concrete in the said step 2 and the second layer concrete in the step 6 are the thick C15 concrete of 30mm.
  5. 5. soil nailing enhancing retaining indigenous method between fender post in a kind of weak soil according to claim 1, it is characterized in that: said step 1, step 2, step 3, step 4, step 5, step 6 are carried out with the excavation progress of the soil body.
  6. 6. soil nailing enhancing retaining indigenous method between fender post in a kind of weak soil according to claim 1, it is characterized in that: the main muscle in the vertical direction of said step 4 adopts the segmentation setting.
CN2012100310403A 2012-02-13 2012-02-13 Method for enhancing soil retaining of soil nails between fender posts in soft soil Pending CN102587354A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100310403A CN102587354A (en) 2012-02-13 2012-02-13 Method for enhancing soil retaining of soil nails between fender posts in soft soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100310403A CN102587354A (en) 2012-02-13 2012-02-13 Method for enhancing soil retaining of soil nails between fender posts in soft soil

Publications (1)

Publication Number Publication Date
CN102587354A true CN102587354A (en) 2012-07-18

Family

ID=46476547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100310403A Pending CN102587354A (en) 2012-02-13 2012-02-13 Method for enhancing soil retaining of soil nails between fender posts in soft soil

Country Status (1)

Country Link
CN (1) CN102587354A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321210A (en) * 2013-06-08 2013-09-25 郭红标 Prestressed anchor cable sheet-pile wall
CN103334421A (en) * 2013-07-05 2013-10-02 郭红标 Pre-stressed anchor cable slab-pile wall
CN103615009A (en) * 2013-11-26 2014-03-05 中冶天工集团有限公司 Method for excavating soil between piles of CFG pile composite foundation

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202047415U (en) * 2011-05-09 2011-11-23 中铁二院工程集团有限责任公司 Composite support structure among piles

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202047415U (en) * 2011-05-09 2011-11-23 中铁二院工程集团有限责任公司 Composite support structure among piles

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
佘远逢: "超大深基坑工程关键施工技术的研究", 《工程质量》 *
刘兴旺等: "土钉式桩间护水平加固技术在复杂深基坑设计中的应用", 《建筑技术》 *
高炳东等: "土钉墙支护在高边坡施工中的应用", 《西部探矿工程》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321210A (en) * 2013-06-08 2013-09-25 郭红标 Prestressed anchor cable sheet-pile wall
CN103334421A (en) * 2013-07-05 2013-10-02 郭红标 Pre-stressed anchor cable slab-pile wall
CN103615009A (en) * 2013-11-26 2014-03-05 中冶天工集团有限公司 Method for excavating soil between piles of CFG pile composite foundation

Similar Documents

Publication Publication Date Title
CN101858124A (en) Novel seismic hardening constructional column of masonry structure
CN204000652U (en) Semi-rigid protective screening for Falling Rocks protection
CN103174438A (en) Tunnel vault cavity pumping backfill construction method
CN102587411A (en) Method for blocking soil by casting concrete through hanging nets among fender piles in soft soil
CN108425387B (en) Foundation reinforcing construction technology for building foundation
CN103306282A (en) Prestressed concrete pile configured with reinforced bars in sections and construction method
CN102587354A (en) Method for enhancing soil retaining of soil nails between fender posts in soft soil
CN103498574B (en) After in masonry panel, increase stem stem Shockproof reinforcing method
CN102304927A (en) Prestress anchor cable buttress-type parapet suitable for rock substrate
CN103737718B (en) Prefabricated reinforced concrete hollow column template and preparation method thereof
CN108104367A (en) A kind of doubly-linked beam and its construction method
CN103015414A (en) Precast concrete post grouting pile and grouting process
CN104131566A (en) Method for constructing basement foundation pit without horizontal braces
CN203768928U (en) Device for blocking inside of foundation pit during sand shifting
CN103603357A (en) Multi-platform inner-support-free self-waterproof foundation pit retaining structure and construction method thereof
CN102936953B (en) Construction method of a bridging-arm stiffened steel structure template
CN108166395A (en) A kind of construction method that beam bridge is built across Business Line
CN102296543A (en) Method for constructing columns and capping beams of bridges
CN102359395B (en) Method for plugging large-scale water-inrush burst-mud burst hole of tunnel fault
CN104196036A (en) Foundation pit supporting structure and method based on old basement exterior wall structure
CN101608450A (en) A kind of callable combined soil nailing wall base pit enclosure method
CN204199296U (en) Based on the foundation pit supporting construction of old outer wall of basement structure
CN102644266B (en) Method utilizing fracture anchor rod piles for reinforcing soft soil stratum pavements in abutment areas
CN204266111U (en) Deep foundation ditch steel trestle
CN210460696U (en) Tunnel inner wall slip casting reinforced structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120718