CN102570333A - Arrangement method for underground substations - Google Patents

Arrangement method for underground substations Download PDF

Info

Publication number
CN102570333A
CN102570333A CN2010105962531A CN201010596253A CN102570333A CN 102570333 A CN102570333 A CN 102570333A CN 2010105962531 A CN2010105962531 A CN 2010105962531A CN 201010596253 A CN201010596253 A CN 201010596253A CN 102570333 A CN102570333 A CN 102570333A
Authority
CN
China
Prior art keywords
equipment
substation
arrangement
confirming
per
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105962531A
Other languages
Chinese (zh)
Inventor
王怡风
倪镭
许建华
乐党救
张景峰
王洁
刘爱勤
陈宝运
苏青松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI ELECTRIC POWER COMMUNICATION CO Ltd
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Original Assignee
Shanghai Jiulong Electric Power Technology Co Ltd
Shanghai Municipal Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiulong Electric Power Technology Co Ltd, Shanghai Municipal Electric Power Co filed Critical Shanghai Jiulong Electric Power Technology Co Ltd
Priority to CN2010105962531A priority Critical patent/CN102570333A/en
Publication of CN102570333A publication Critical patent/CN102570333A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to an arrangement method for underground substations, and the method includes the following steps: 1) confirming a main wire, a high voltage side wire as well as a medium voltage side wire and a low voltage side wire; 2) confirming main equipment, including selecting a transformer, a low voltage reactor and GIS equipment; 3) confirming the model of a cable matched with the equipment as per the model of the selected equipment; 4) selecting the structure form of a substation as per the model and specification of the equipment; 5) confirming the arrangement of a fire extinguishing system and an air prevention and exhaust system as per the structure form of the substation; 6) coordinating surrounding environments as per the design of the underground substation. Compared with the prior art, the arrangement method enables the arrangement of the substation to be reasonable, reduces the occupied land area on the premise of ensuring the performance, optimizes the working environment, ensures the safe operation of the equipment, coordinates with the surrounding environments, and plays a good demonstration function for design and arrangement of further underground substations.

Description

The layout method of underground substation
Technical field
The present invention relates to a kind of layout method of underground substation.
Background technology
At present,, implement relatively difficulty of transformer station site, can combine the stage variable pressure construction in suitable site sometimes, combine to build such as 500kV and 220kV, 220kV and 110kV transformer station because the down town land used is nervous.Such construction mode can improve the support situation that the superelevation power grid construction can't really obtain engineering location units concerned.The optimization of emphasis consideration electric network composition when building superhigh pressure transformer station in the past; But can not take into account the on-site terminal of solution workload demand because the outlet electric pressure is too high; After adopting multistage step-down mode, can increase the outlet of the low-voltage that can solve the needs of electricity consumption on the spot; When building the superhigh pressure engineering, need take local need for electricity into account like this, be a technical problem to be solved for the layout of the so large-scale underground substation of 500kV Expo transformer station.
Summary of the invention
The object of the invention is exactly the layout method that a kind of underground substation is provided for the defective that overcomes above-mentioned prior art existence.
The object of the invention can be realized through following technical scheme: the layout method of underground substation may further comprise the steps: 1) confirm main electrical scheme, graceful side joint line and in, the low-pressure side wiring; 2) confirm main equipment, comprise transformer, low tension reactor and the GIS equipment selected; 3) according to the definite cable model that is complementary with equipment of selected unit type; 4) select the substation structure form according to the unit type specification; 5) confirm the layout of fire-fighting system and anti-exhaust system according to the substation structure form; 6) coordinate surrounding enviroment according to the design of underground substation.
Compared with prior art, the present invention makes the rationally distributed of transformer station, under the prerequisite of assurance function; Reduce floor space, optimized operational environment, guaranteed the operation of device security; And with the environment coordination of periphery, the layout of underground substation is from now on had good exemplary role.
Embodiment
The layout method of underground substation may further comprise the steps: 1) confirm main electrical scheme, graceful side joint line and in, the low-pressure side wiring; 2) confirm main equipment, comprise transformer, low tension reactor and the GIS equipment selected; 3) according to the definite cable model that is complementary with equipment of selected unit type; 4) select the substation structure form according to the unit type specification; 5) confirm the layout of fire-fighting system and anti-exhaust system according to the substation structure form; 6) coordinate surrounding enviroment according to the design of underground substation.
The construction scale of transformer station should be taken all factors into consideration definite according to status, regional power supply condition, workload demand, operational mode and the total investment of engineering etc. of the system wiring mode in the residing electric network composition, transformer station's rack of living in.Under the characteristics condition; The planning of underground substation part maybe be different with the consideration of conventional ground transformer station; Should make full use of the site resource for the consideration of underground substation accomplishes planning and layouts; Electrical main connecting wire: the underground substation should be reduced electric pressure and simplify wiring under the condition that satisfies Electric Power Network Planning and reliability requirement.To reach minimum electric component, improve the reliability of equipment.Main equipment selects to combine the characteristics of underground substation; The reliability of equipment, freedom from repairs or few maintenance requirement are high; Consider by following principle: device miniaturization, device efficiency height; Caloric value is few, the temperature rise requirement for restriction high, the type of cooling of oil immersion equipment is chosen in the acceptable scope of cost performance after should carrying out fully relatively, adopts no liquefying apparatus as far as possible, to reduce disaster hidden-trouble and fire-fighting investment.The underground substation at first answers emphasis to confirm that transformer station intends the employing planform aspect layout, and then carries out planar design.Needs in the time of on the layout of integral body, should taking into full account characteristics and installation, equipment carrying, operation maintenance and the enlarging of transformer station.Should consider simultaneously the imagination of structural fire protection during layout synchronously, especially the setting of fire prevention zone, fire escape and vertical channel should be rationally convenient.Take into full account for the rational fire compartment Ying Yu of ultra-large type transformer station.Cable floor rationally is set is convenient to the butt joint of cable tunnel.Heating and ventilation and air handling system also are the requisite systems of a underground substation, and a perfect system can be built a good running environment for the underground substation.Division of equipment room ventilation systems and system form should take into full account the various kinds of equipment operation characteristic and design.Fire-fighting system is relied mainly on prevention in principle, and it is auxilliary disappearing.Should take into full account estimating and the setting of fire alarm system of fire risk in the design.Should consider design according to different fire risks and distinct device for fire protection equipment, and should fully link up the back with the Fire Department of locality and confirm the safe and rational fire-fighting system.Environment compatibility: the construction of underground change should take into full account the planning of above ground portion, should with urban afforestation, public garage etc. auxiliary construction be set as far as possible.

Claims (1)

1. the layout method of underground substation is characterized in that, may further comprise the steps:
1) confirm main electrical scheme, graceful side joint line and in, the low-pressure side wiring;
2) confirm main equipment, comprise transformer, low tension reactor and the GIS equipment selected;
3) according to the definite cable model that is complementary with equipment of selected unit type;
4) select the substation structure form according to the unit type specification;
5) confirm the layout of fire-fighting system and anti-exhaust system according to the substation structure form;
6) coordinate surrounding enviroment according to the design of underground substation.
CN2010105962531A 2010-12-20 2010-12-20 Arrangement method for underground substations Pending CN102570333A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105962531A CN102570333A (en) 2010-12-20 2010-12-20 Arrangement method for underground substations

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105962531A CN102570333A (en) 2010-12-20 2010-12-20 Arrangement method for underground substations

Publications (1)

Publication Number Publication Date
CN102570333A true CN102570333A (en) 2012-07-11

Family

ID=46415083

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105962531A Pending CN102570333A (en) 2010-12-20 2010-12-20 Arrangement method for underground substations

Country Status (1)

Country Link
CN (1) CN102570333A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104167679A (en) * 2014-07-30 2014-11-26 国家电网公司 Underground arrangement system and method of secondary device of vertical-shaft-type substation
CN105003100A (en) * 2015-07-20 2015-10-28 国网上海市电力公司 Underground transformer substation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4886027A (en) * 1972-02-16 1973-11-14
CN101051733A (en) * 2006-04-07 2007-10-10 夏曙光 Non-metal full ground buried landscape box type transformer substion box
CN101635440A (en) * 2008-07-22 2010-01-27 夏曙光 Buried transformer substation with escape passage

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4886027A (en) * 1972-02-16 1973-11-14
CN101051733A (en) * 2006-04-07 2007-10-10 夏曙光 Non-metal full ground buried landscape box type transformer substion box
CN101635440A (en) * 2008-07-22 2010-01-27 夏曙光 Buried transformer substation with escape passage

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
沈婷等: "500KV静安(世博)地下变电站设计方案", 《电力建设》, vol. 29, no. 7, 31 July 2008 (2008-07-31), pages 8 - 11 *
范绍有: "地下变电站的设计探讨", 《湖北电力》, vol. 34, no. 2, 28 February 2010 (2010-02-28), pages 44 - 45 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104167679A (en) * 2014-07-30 2014-11-26 国家电网公司 Underground arrangement system and method of secondary device of vertical-shaft-type substation
CN105003100A (en) * 2015-07-20 2015-10-28 国网上海市电力公司 Underground transformer substation

Similar Documents

Publication Publication Date Title
CN105207097A (en) Regional power grid emergency rescue equipment
CN201667498U (en) Box type transformer substation for open-pit mine
CN104631410A (en) Offshore platform used for alternating-current booster station of offshore wind plant
CN203722058U (en) Totally-enclosed-type vehicle-mounted mobile transformer station
CN203415882U (en) Box type transformer station
CN106057005A (en) Building power supply and distribution teaching technology simulation training system
CN204885964U (en) Photovoltaic case becomes with contravariant function of stepping up
CN103208753B (en) A kind of vehicle-mounted removable transformer station
CN201975713U (en) Novel box-type substation
CN102570333A (en) Arrangement method for underground substations
CN208874158U (en) A kind of wind farm substation
CN208656179U (en) Mobile emergency power supply cabinet for power grid low-voltage equipment bypass
CN107681622A (en) A kind of removal cable feeder pillar
CN201994584U (en) Underground transformer substation equipment layout structure
CN204271510U (en) Photovoltaic inversion boosting intelligent box becomes
CN204031042U (en) Integrated photovoltaic power supply unit system
CN203536830U (en) Vehicle-mounted mobile power transformation trolley
CN204205380U (en) Portable GIS transformer station
CN109004566A (en) A kind of wind farm substation
CN205724593U (en) Transformer station and a kind of layer fraction transformer station
CN204156379U (en) A kind of Combined intelligent box-type transformer substation
CN210723704U (en) Double-layer linear outgoing line arrangement structure of 220kV indoor GIS equipment
CN204258114U (en) A kind of 500kV substation equipment arrangement
CN205319545U (en) Novel substation box
CN203813513U (en) Complete set of kilowatt power equipment for oil and gas station

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA SHANGHAI ELECTRIC

Free format text: FORMER OWNER: SHANGHAI JIULONG ELECTRIC POWER SCIENCE + TECHNOLOGY CO., LTD.

Effective date: 20121221

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121221

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant after: Shanghai Electric Power Corporation

Applicant after: State Grid Corporation of China

Applicant after: Shanghai Electric Power Communication Co., Ltd.

Address before: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant before: Shanghai Electric Power Corporation

Applicant before: Shanghai Jiulong Electric Power Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20120711

RJ01 Rejection of invention patent application after publication