CN102527467A - Method for assembling barrel body and grinding roller of horizontal roller mill - Google Patents

Method for assembling barrel body and grinding roller of horizontal roller mill Download PDF

Info

Publication number
CN102527467A
CN102527467A CN2012100286866A CN201210028686A CN102527467A CN 102527467 A CN102527467 A CN 102527467A CN 2012100286866 A CN2012100286866 A CN 2012100286866A CN 201210028686 A CN201210028686 A CN 201210028686A CN 102527467 A CN102527467 A CN 102527467A
Authority
CN
China
Prior art keywords
girder steel
cylindrical shell
grinding roller
sliding machine
bottom case
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100286866A
Other languages
Chinese (zh)
Other versions
CN102527467B (en
Inventor
王冰
姜涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin MCC20 Construction Co Ltd
Original Assignee
Tianjin MCC20 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin MCC20 Construction Co Ltd filed Critical Tianjin MCC20 Construction Co Ltd
Priority to CN 201210028686 priority Critical patent/CN102527467B/en
Publication of CN102527467A publication Critical patent/CN102527467A/en
Application granted granted Critical
Publication of CN102527467B publication Critical patent/CN102527467B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a method for assembling a barrel body and a grinding roller of a horizontal roller mill. The method comprises the following steps of: (a) assembling an auxiliary platform; (b) hoisting a sliding trolley which is assembled onto a main rail; (c) hoisting the barrel body onto the sliding trolley; (d) hauling the sliding trolley by using traction equipment to move from one side of the main rail to a pedestal of equipment until the sliding trolley arrives above the pedestal of the equipment; (e) fixing the sliding trolley and supporting transverse beams of the sliding trolley respectively by using fixed supports; (f) disassembling steel beams on left side and right side, descending the fixed supports and descending the sliding trolley and the barrel body to the pedestal of the equipment; (g) disassembling the sliding trolley; (h) assembling a maintenance trolley on an auxiliary rail; and (i) hoisting the grinding roller onto the maintenance trolley, hauling the maintenance trolley to move from one side of the auxiliary rail to the pedestal of the equipment until the maintenance trolley and the grinding roller enter the barrel body, and connecting the grinding roller. By adoption of the method, assembly errors can be reduced and stability of the platform is guaranteed.

Description

Horizontal roll grinder cylindrical shell, grinding roller installation method
Technical field
The present invention relates to a kind of cylindrical shell, grinding roller installation method, the invention particularly relates to horizontal roll grinder cylindrical shell, grinding roller installation method.
Background technology
First horizontal roll grinder that gets into commercial Application is to be developed by French plant equipment group (FCB) in the world; Be called HOROMILL; In 1993 since coming into operation in Italian cement plant, just receive much concern because of advantage such as its economize on electricity, low noise, low abrasion, less trouble.Nearly 20 tame cement production enterprises of existing more than ten countries are using horizontal roll grinder all over the world at present, and the existing two tame cement production enterprises of China have used this equipment, and first horizontal roll grinder was constructed and put into operation in Mudanjiang in 2003.In recent years, from the demand of domestic market, China has developed the roller mill for sleeping in of the series with independent intellectual property right.
Be accompanied by the successful Application of China's horizontal roll grinder in cement industry; Technical-economic index and environmental protection effect are remarkable; New Building Materials Co., Ltd in capital entrusted Beijing China Metallurgical Engineering Ltd and FCB group to develop jointly and built and is used to make steel scrap steel ground-slag mill recycling project sunshine; The debugging of test run is at present produced, and the reaction of each item index has all reached requirement, becomes the focus that domestic each commercial production producer falls over each other to understand.
No matter be first cement horizontal roll grinder of China in Mudanjiang; Still at the first in the world platform slag horizontal roll grinder at sunshine, in installation process, cylindrical shell and grinding roller are because weight and volume is huge; And there is not upper space to lift; With sunshine the slag horizontal roll grinder be example: cylindrical shell weight 68t, internal diameter 3800mm, external diameter 4680mm; Grinding roller weight 54t, length 6407mm all becomes the emphasis in the installation process.
Because installing, domestic horizontal roll grinder cylindrical shell and grinding roller still be in the stage of fumbling at present; There is not ripe mount scheme; Be with reference to the installation of making amendment of the interim assistance platform of external similar item; Size did not meet during this just caused amended interim assistance platform and equipment is connected easily, and stability also can't be guaranteed.
Summary of the invention
The object of the present invention is to provide a kind of horizontal roll grinder cylindrical shell, grinding roller installation method; Use this method can not only guarantee to install smoothly cylindrical shell and grinding roller; And improved the sizing control in the installation process greatly, and reduced in the installation process causing a deviation, finally help producing the back and safeguard.
A kind of horizontal roll grinder cylindrical shell of the present invention, grinding roller installation method, it may further comprise the steps:
(a) assistance platform is installed, the installation process of described assistance platform is following: (1) makes up ground, the stepped footing of described ground for being made up of upper strata step and lower floor's step; (2) erection unit base on the step of described upper strata; Left and right side at the end face of described plant bottom case is installed at least two left and right carriage pillars respectively; Left and right side at the end face of described upper strata step and lower floor's step is installed a plurality of left and right pillars respectively successively at interval; The left side side girder steel of elongated setting is installed at least on described two left tray pillars and a plurality of left pillar; The right side girder steel of elongated setting is installed at least on described two right carriage pillars and a plurality of right pillar; The centre of the upper strata step between described left and right avris girder steel and the end face of lower floor's step is installed a plurality of left and right intermediate studdles respectively successively at interval; The middle girder steel in a left side of elongated setting is installed on described a plurality of left intermediate studdles, the right middle girder steel of elongated setting is installed on described a plurality of right intermediate studdles, described left and right avris girder steel and left and right middle girder steel along continuous straight runs each other laterally arrange;
(b) will assemble the sliding machine of accomplishing lifts to the main orbit of the assistance platform of being made up of left and right avris girder steel;
(c) cylindrical shell is lifted to sliding machine;
(d) adopt pulling equipment traction sliding machine to stop until arriving the plant bottom case top by a side direction plant bottom case side shifting of main orbit;
(e) fixing sliding machine adopts adjustable hold-down support to support the outwardly directed crossbeam in the sliding machine left and right sides respectively;
(f) remove the left and right avris girder steel of plant bottom case position, adjustable hold-down support and utilize jack that sliding machine and cylindrical shell integral body are dropped on the plant bottom case then gradually descends;
(g) remove sliding machine;
(h) with inspection trolley be installed in left and right in the middle of on the Auxiliary Track of the assistance platform formed of girder steel;
(i) grinding roller is lifted to inspection trolley and penetrate cylindrical shell by a side direction plant bottom case side shifting of Auxiliary Track until inspection trolley and grinding roller integral body, connect grinding roller, extract inspection trolley out cylindrical shell at last by pulling equipment traction inspection trolley.
The invention has the beneficial effects as follows: adopt this method can reduce the probability that installation process produces error, the stability of platform also is guaranteed.Assistance platform translation construction utilize to be installed not only to have solved the problem that can't lift, perfect this type of construction method, and also final assistance platform can be done the production maintenance platform and uses.The making of platform can be adopted the steel construction section bar, convenient and quick construction, and this platform can all adopt the high-strength bolt assembling, and the mounting or dismounting tube is prone to help using repeatedly; Translation gliding process tube list, operation easily; Employing in place jack commonly used and hold-down support support by turns, and the control that need is reduced height is stable, can well guarantee equipment axis line position and levelness.
Description of drawings
Fig. 1 is the assistance platform plane that a kind of horizontal roll grinder cylindrical shell of the present invention, grinding roller installation method adopt;
Fig. 2 is the assistance platform elevation that a kind of horizontal roll grinder cylindrical shell of the present invention, grinding roller installation method adopt;
Fig. 3 is the 1-1 profile of assistance platform shown in Figure 2;
Fig. 4 is the 2-2 profile of assistance platform shown in Figure 2;
Fig. 5 is the sliding machine profile that a kind of horizontal roll grinder cylindrical shell of the present invention, grinding roller installation method adopt.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the present invention is described in detail.
A kind of horizontal roll grinder cylindrical shell of the present invention, grinding roller installation method shown in accompanying drawing; It may further comprise the steps: assistance platform (a) is installed; The installation process of described assistance platform is following: (1) makes up ground, the stepped footing of described ground for being made up of upper strata step 1 and lower floor's step 2; (2) erection unit base 3 on described upper strata step 1; Left and right side at the end face of described plant bottom case is installed at least two left and right carriage pillar 4-1,4-2 respectively; Left and right side at the end face of described upper strata step and lower floor's step is installed a plurality of left and right pillar 5-1,5-2 respectively successively at interval; The left side side girder steel 8-1 of elongated setting is installed at least on described two left tray pillars and a plurality of left pillar; The right side girder steel 8-2 of elongated setting is installed at least on described two right carriage pillars and a plurality of right pillar; The centre of the upper strata step between described left and right avris girder steel and the end face of lower floor's step is installed a plurality of left and right intermediate studdle 7-1,7-2 respectively successively at interval; The middle girder steel 6-1 in a left side of elongated setting is installed on described a plurality of left intermediate studdles; The right middle girder steel 6-2 of elongated setting is installed on described a plurality of right intermediate studdles, and described left and right avris girder steel and left and right middle girder steel along continuous straight runs each other laterally arrange; Assistance platform as shown in Figure 2 divides stepped that 1a, 1b, 1c form.(b) will assemble the sliding machine lifting of accomplishing (like the A side among the figure) to the main orbit of the assistance platform of forming by left and right avris girder steel; (c) cylindrical shell is lifted to sliding machine; As shown in Figure 5; As one embodiment of the present invention; Described sliding machine comprises and the suitable car body of cylindrical shell shape; Bottom at the left and right side of described car body is separately installed with the roller 9 that can on left and right avris girder steel, roll, the sliding machine version that can certainly adopt other on left and right avris girder steel, to roll.(d) adopt a side direction plant bottom case side shifting the B side until arrival plant bottom case top stop promptly to scheme in of pulling equipment traction sliding machine by main orbit; Described pulling equipment can be bottle gouard moved by hands.(e) fixing sliding machine adopts adjustable hold-down support to support the outwardly directed crossbeam 12 in the sliding machine left and right sides respectively; (f) remove the left and right avris girder steel of plant bottom case position, adjustable hold-down support 11 and utilize jack that sliding machine and cylindrical shell integral body are dropped on the device carrier then gradually descends; As shown in Figure 5, as one embodiment of the present invention, adjustable hold-down support can comprise the supporting seat that links to each other with ground, and described supporting seat is provided with sandwich plate, can certainly adopt structures such as cylinder-push rod.(g) remove sliding machine; (h) with inspection trolley be installed in left and right in the middle of on the Auxiliary Track of the assistance platform formed of girder steel; (i) grinding roller is lifted to inspection trolley and penetrate cylindrical shell by a side direction plant bottom case side shifting of Auxiliary Track until inspection trolley and grinding roller integral body, connect grinding roller, extract inspection trolley out cylindrical shell at last by pulling equipment traction inspection trolley.Described inspection trolley is that roller mill is from carrying device.
The grinding machine center discrepancy in elevation was preferably 700~800mm after said cylindrical shell was installed in center and the installation in position on the sliding machine; Crossing low sliding machine then can't translation access arrangement base top (sliding machine will clash with plant bottom case in the translation process), too high then in process in place the required decline discrepancy in elevation excessive.
Embodiment 1
In the cylindrical shell of slag micro powder production line 3800mm horizontal roll grinder, grinding roller installation:
(a) assistance platform is installed, the installation process of described assistance platform is following: (1) makes up ground, the stepped footing of described ground for being made up of upper strata step 1 and lower floor's step 2; (2) erection unit base 3 on described upper strata step 1; Left and right side at the end face of described plant bottom case is installed at least two left and right carriage pillar 4-1,4-2 respectively; Left and right side at the end face of described upper strata step and lower floor's step is installed a plurality of left and right pillar 5-1,5-2 respectively successively at interval; The left side side girder steel 8-1 of elongated setting is installed at least on described two left tray pillars and a plurality of left pillar; The right side girder steel 8-2 of elongated setting is installed at least on described two right carriage pillars and a plurality of right pillar; The centre of the upper strata step between described left and right avris girder steel and the end face of lower floor's step is installed a plurality of left and right intermediate studdle 7-1,7-2 respectively successively at interval; The middle girder steel 6-1 in a left side of elongated setting is installed on described a plurality of left intermediate studdles; The right middle girder steel 6-2 of elongated setting is installed on described a plurality of right intermediate studdles, and described left and right avris girder steel and left and right middle girder steel along continuous straight runs each other laterally arrange; (b) will assemble the sliding machine lifting of accomplishing (like the A side among the figure) to the main orbit of the assistance platform of forming by left and right avris girder steel; (c) cylindrical shell is lifted to sliding machine; (d) adopt bottle gouard moved by hands traction sliding machine to stop until arriving the plant bottom case top by a side direction plant bottom case side shifting of main orbit; (e) fixing sliding machine adopts adjustable hold-down support to support the outwardly directed crossbeam 12 in the sliding machine left and right sides respectively; (f) remove the left and right avris girder steel of plant bottom case position, adjustable hold-down support 11 and utilize jack that sliding machine and cylindrical shell integral body are dropped on the device carrier then gradually descends; (g) remove sliding machine; (h) with inspection trolley be installed in left and right in the middle of on the Auxiliary Track of the assistance platform formed of girder steel; (i) grinding roller is lifted to inspection trolley and penetrate cylindrical shell by a side direction plant bottom case side shifting of Auxiliary Track until inspection trolley and grinding roller integral body, connect grinding roller, extract inspection trolley out cylindrical shell at last by pulling equipment traction inspection trolley.Said cylindrical shell is installed in that the grinding machine center discrepancy in elevation is 730mm behind center and the installation in position on the sliding machine.
The cylindrical shell of roller mill, grinding roller are installed, and implementation result is good.Cause the grinding mill barrel centre deviation can be controlled at 0.02mm in the installation process.
Embodiment 2
In the cylindrical shell of slag micro powder production line 3800mm horizontal roll grinder, grinding roller installation:
(a) assistance platform is installed, the installation process of described assistance platform is following: (1) makes up ground, the stepped footing of described ground for being made up of upper strata step 1 and lower floor's step 2; (2) erection unit base 3 on described upper strata step 1; Left and right side at the end face of described plant bottom case is installed at least two left and right carriage pillar 4-1,4-2 respectively; Left and right side at the end face of described upper strata step and lower floor's step is installed a plurality of left and right pillar 5-1,5-2 respectively successively at interval; The left side side girder steel 8-1 of elongated setting is installed at least on described two left tray pillars and a plurality of left pillar; The right side girder steel 8-2 of elongated setting is installed at least on described two right carriage pillars and a plurality of right pillar; The centre of the upper strata step between described left and right avris girder steel and the end face of lower floor's step is installed a plurality of left and right intermediate studdle 7-1,7-2 respectively successively at interval; The middle girder steel 6-1 in a left side of elongated setting is installed on described a plurality of left intermediate studdles; The right middle girder steel 6-2 of elongated setting is installed on described a plurality of right intermediate studdles, and described left and right avris girder steel and left and right middle girder steel along continuous straight runs each other laterally arrange; (b) will assemble the sliding machine lifting of accomplishing (like the A side among the figure) to the main orbit of the assistance platform of forming by left and right avris girder steel; (c) cylindrical shell is lifted to sliding machine; (d) adopt bottle gouard moved by hands traction sliding machine to stop until arriving the plant bottom case top by a side direction plant bottom case side shifting of main orbit; (e) fixing sliding machine adopts adjustable hold-down support to support the outwardly directed crossbeam 12 in the sliding machine left and right sides respectively; (f) remove the left and right avris girder steel of plant bottom case position, adjustable hold-down support 11 and utilize jack that sliding machine and cylindrical shell integral body are dropped on the device carrier then gradually descends; (g) remove sliding machine; (h) with inspection trolley be installed in left and right in the middle of on the Auxiliary Track of the assistance platform formed of girder steel; (i) grinding roller is lifted to inspection trolley and penetrate cylindrical shell by a side direction plant bottom case side shifting of Auxiliary Track until inspection trolley and grinding roller integral body, connect grinding roller, extract inspection trolley out cylindrical shell at last by pulling equipment traction inspection trolley.Said cylindrical shell is installed in that the grinding machine center discrepancy in elevation is 720mm behind center and the installation in position on the sliding machine.
The cylindrical shell of roller mill, grinding roller are installed, and implementation result is good.Cause the grinding mill barrel centre deviation can be controlled at 0.02mm in the installation process.
Embodiment 3
In the cylindrical shell of slag micro powder production line 3800mm horizontal roll grinder, grinding roller installation:
(a) assistance platform is installed, the installation process of described assistance platform is following: (1) makes up ground, the stepped footing of described ground for being made up of upper strata step 1 and lower floor's step 2; (2) erection unit base 3 on described upper strata step 1; Left and right side at the end face of described plant bottom case is installed at least two left and right carriage pillar 4-1,4-2 respectively; Left and right side at the end face of described upper strata step and lower floor's step is installed a plurality of left and right pillar 5-1,5-2 respectively successively at interval; The left side side girder steel 8-1 of elongated setting is installed at least on described two left tray pillars and a plurality of left pillar; The right side girder steel 8-2 of elongated setting is installed at least on described two right carriage pillars and a plurality of right pillar; The centre of the upper strata step between described left and right avris girder steel and the end face of lower floor's step is installed a plurality of left and right intermediate studdle 7-1,7-2 respectively successively at interval; The middle girder steel 6-1 in a left side of elongated setting is installed on described a plurality of left intermediate studdles; The right middle girder steel 6-2 of elongated setting is installed on described a plurality of right intermediate studdles, and described left and right avris girder steel and left and right middle girder steel along continuous straight runs each other laterally arrange; (b) will assemble the sliding machine lifting of accomplishing (like the A side among the figure) to the main orbit of the assistance platform of forming by left and right avris girder steel; (c) cylindrical shell is lifted to sliding machine; (d) adopt bottle gouard moved by hands traction sliding machine to stop until arriving the plant bottom case top by a side direction plant bottom case side shifting of main orbit; (e) fixing sliding machine adopts adjustable hold-down support to support the outwardly directed crossbeam 12 in the sliding machine left and right sides respectively; (f) remove the left and right avris girder steel of plant bottom case position, adjustable hold-down support 11 and utilize jack that sliding machine and cylindrical shell integral body are dropped on the device carrier then gradually descends; (g) remove sliding machine; (h) with inspection trolley be installed in left and right in the middle of on the Auxiliary Track of the assistance platform formed of girder steel; (i) grinding roller is lifted to inspection trolley and penetrate cylindrical shell by a side direction plant bottom case side shifting of Auxiliary Track until inspection trolley and grinding roller integral body, connect grinding roller, extract inspection trolley out cylindrical shell at last by pulling equipment traction inspection trolley.Said cylindrical shell is installed in that the grinding machine center discrepancy in elevation is 740mm behind center and the installation in position on the sliding machine.
The cylindrical shell of roller mill, grinding roller are installed, and implementation result is good.Cause the grinding mill barrel centre deviation can be controlled at 0.02mm in the installation process.

Claims (2)

1. a horizontal roll grinder cylindrical shell, grinding roller installation method is characterized in that it may further comprise the steps:
(a) assistance platform is installed, the installation process of described assistance platform is following: (1) makes up ground, the stepped footing of described ground for being made up of upper strata step and lower floor's step; (2) erection unit base on the step of described upper strata; Left and right side at the end face of described plant bottom case is installed at least two left and right carriage pillars respectively; Left and right side at the end face of described upper strata step and lower floor's step is installed a plurality of left and right pillars respectively successively at interval; The left side side girder steel of elongated setting is installed at least on described two left tray pillars and a plurality of left pillar; The right side girder steel of elongated setting is installed at least on described two right carriage pillars and a plurality of right pillar; The centre of the upper strata step between described left and right avris girder steel and the end face of lower floor's step is installed a plurality of left and right intermediate studdles respectively successively at interval; The middle girder steel in a left side of elongated setting is installed on described a plurality of left intermediate studdles, the right middle girder steel of elongated setting is installed on described a plurality of right intermediate studdles, described left and right avris girder steel and left and right middle girder steel along continuous straight runs each other laterally arrange;
(b) will assemble the sliding machine of accomplishing lifts to the main orbit of the assistance platform of being made up of left and right avris girder steel;
(c) cylindrical shell is lifted to sliding machine;
(d) adopt pulling equipment traction sliding machine to stop until arriving the plant bottom case top by a side direction plant bottom case side shifting of main orbit;
(e) fixing sliding machine adopts adjustable hold-down support to support the outwardly directed crossbeam in the sliding machine left and right sides respectively;
(f) remove the left and right avris girder steel of plant bottom case position, adjustable hold-down support and utilize jack that sliding machine and cylindrical shell integral body are dropped on the plant bottom case then gradually descends;
(g) remove sliding machine;
(h) with inspection trolley be installed in left and right in the middle of on the Auxiliary Track of the assistance platform formed of girder steel;
(i) grinding roller is lifted to inspection trolley and penetrate cylindrical shell by a side direction plant bottom case side shifting of Auxiliary Track until inspection trolley and grinding roller integral body, connect grinding roller, extract inspection trolley out cylindrical shell at last by pulling equipment traction inspection trolley.
2. horizontal roll grinder cylindrical shell according to claim 1, grinding roller installation method is characterized in that: described cylindrical shell is installed in that the grinding machine center discrepancy in elevation is 700~800mm behind center and the installation in position on the sliding machine.
CN 201210028686 2012-02-09 2012-02-09 Method for assembling barrel body and grinding roller of horizontal roller mill Active CN102527467B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201210028686 CN102527467B (en) 2012-02-09 2012-02-09 Method for assembling barrel body and grinding roller of horizontal roller mill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201210028686 CN102527467B (en) 2012-02-09 2012-02-09 Method for assembling barrel body and grinding roller of horizontal roller mill

Publications (2)

Publication Number Publication Date
CN102527467A true CN102527467A (en) 2012-07-04
CN102527467B CN102527467B (en) 2013-10-23

Family

ID=46336208

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201210028686 Active CN102527467B (en) 2012-02-09 2012-02-09 Method for assembling barrel body and grinding roller of horizontal roller mill

Country Status (1)

Country Link
CN (1) CN102527467B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111495492A (en) * 2020-04-27 2020-08-07 五冶集团上海有限公司 Installation method of high-pressure roller mill

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102049335A (en) * 2009-11-06 2011-05-11 中冶成工上海五冶建设有限公司 Installation and construction method of large-sized ball mill
WO2011161583A1 (en) * 2010-06-24 2011-12-29 Metso Brasil Indústria E Comércio Ltda Roller for high pressure roller grinder, roller grinder, and method for assembling a roller for a roller grinder
JP4865285B2 (en) * 2005-09-14 2012-02-01 バブコック日立株式会社 Crusher installation method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4865285B2 (en) * 2005-09-14 2012-02-01 バブコック日立株式会社 Crusher installation method
CN102049335A (en) * 2009-11-06 2011-05-11 中冶成工上海五冶建设有限公司 Installation and construction method of large-sized ball mill
WO2011161583A1 (en) * 2010-06-24 2011-12-29 Metso Brasil Indústria E Comércio Ltda Roller for high pressure roller grinder, roller grinder, and method for assembling a roller for a roller grinder

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
李朝宾等: "磨机安装中应注意的几个问题", 《矿山机械》, no. 10, 31 October 2005 (2005-10-31), pages 128 *
杨顺昌等: "JSX型系列磨用的减速机安装与调试", 《建材发展导向》, no. 1, 31 January 2008 (2008-01-31), pages 28 - 30 *
王蒲初: "MQY5585溢流型球磨机安装", 《安装》, no. 11, 30 November 2007 (2007-11-30), pages 29 - 31 *
蒋为镜等: "世界最大型磨机预组装施工", 《上海建设科技》, no. 2, 28 February 2011 (2011-02-28), pages 43 - 45 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111495492A (en) * 2020-04-27 2020-08-07 五冶集团上海有限公司 Installation method of high-pressure roller mill
CN111495492B (en) * 2020-04-27 2024-01-30 五冶集团上海有限公司 Installation method of high-pressure roller mill

Also Published As

Publication number Publication date
CN102527467B (en) 2013-10-23

Similar Documents

Publication Publication Date Title
CN101672011B (en) Steel tube arch rib vertical lifting method
CN201943007U (en) Constant amplitude frame beam crane capable of being used in combination with movable support frame
CN105625195A (en) Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket
CN102912736A (en) Vertical assembling construction method for trussed arch bridge
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN105239514A (en) Stepless-adjustment ball-hinge type multi-support-leg forward transverse shifting track system of bridge girder erection machine
CN113846575B (en) Automatic operation method for internal mold of cradle cantilever construction
CN103993745A (en) Integral transfer girder hoisting device and hoisting method thereof
CN205184745U (en) Operation platform for airplane assembling
CN101806162B (en) Inner and outer barrel type free-standing steel chimney
CN2866514Y (en) Blast furnace body frame
CN102527467B (en) Method for assembling barrel body and grinding roller of horizontal roller mill
CN109812021A (en) A kind of installation method of large span welding ball grid
CN202881858U (en) Jig frame used for vertical assembly construction of truss arc bridge
CN203959689U (en) A kind of large-type sinterer depositing dust pipeline is installed and is adjusted with operation car
CN201671393U (en) Inner-outer tubular self-supporting steel chimney
CN202185966U (en) Novel hydraulic internal mold for U-shaped beam
CN201688421U (en) Elevated flare system with online maintaining and expansion properties
CN102145353B (en) O-forming machine mounting method
CN101956372B (en) Quick construction method for No. 0 section of prestressed concrete beam type bridge
CN110252823A (en) The steering gliding method of heavy mill housing under restricted clearance
CN201943006U (en) Main tower zone movable bracket for assisting non-variable amplitude girder erecting crane to erect steel box girders
CN212799260U (en) Converter steam pocket hoisting device based on hydraulic lifter
CN204727536U (en) A kind of overhead traveling crane transmission shaft up-down movable support
CN105002829A (en) Integral manufacturing method for cable wire tower

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant