CN102465529A - Automatically extended large-head wavy edge jet grouting anchor pile for pile end anchor bar, and construction method thereof - Google Patents

Automatically extended large-head wavy edge jet grouting anchor pile for pile end anchor bar, and construction method thereof Download PDF

Info

Publication number
CN102465529A
CN102465529A CN2010105351434A CN201010535143A CN102465529A CN 102465529 A CN102465529 A CN 102465529A CN 2010105351434 A CN2010105351434 A CN 2010105351434A CN 201010535143 A CN201010535143 A CN 201010535143A CN 102465529 A CN102465529 A CN 102465529A
Authority
CN
China
Prior art keywords
pile
anchor cable
anchor
churning
dowel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105351434A
Other languages
Chinese (zh)
Inventor
邹荣
邹宗煊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2010105351434A priority Critical patent/CN102465529A/en
Publication of CN102465529A publication Critical patent/CN102465529A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to an automatically extended large-head wavy edge jet grouting anchor pile for a pile end anchor bar, and a construction method thereof, which are similar to the traditional anchor pile and the construction method thereof. An anchor pile rig is used for construction, the anchor pile has a jet grouting cement soil pile body, and two to four anchor cables are arranged at the center of the pile body. The automatically extended large-head wavy edge jet grouting anchor pile for the pile end anchor bar is characterized in that: an automatically extended radial anchor bar is arranged at the end part of the jet grouting cement soil pile body, the diameter of the end part of the pile body is 10-120cm larger than that of the pile body, the jet grouting cement soil pile body is in a spirally cylindrical shape, and the major axis around the pile is in a wavy shape. Compared with the prior art, the invention has the following obvious advantages that: the pullout resistance is increased by 40-70% compared with the current anchor pile, the construction process is simple, the number of anchor piles can be reduced, and the cost of foundation pit support is reduced.

Description

Hold dowel automatic expansion major part rippled edge churning anchoring pile and worker's method thereof for a kind of
Technology neck city
The present invention relates to building engineering field, relate in particular to a kind of end dowel automatic expansion major part rippled edge churning anchoring pile and worker's method thereof.
Background technology
At present, the building foundation pit supporting that oneself knows is used the churning anchoring pile, is successively successively to be constructed simultaneously in the mining process at foundation ditch by the anchoring pile rig; Creep into to hole wall soil layer water filling on the foundation ditch limit earlier by the three-wing bit on the rig (bore 12-18cm), until the design hole depth, bore draw the hole after; Withdraw from three-wing bit; Change guniting drilling bit, the steel strand (also claiming anchor cable) of 2-3 root Φ 14-20 are fixed on the anchor cable dish, head on anchor cable disk center hole by guniting drilling bit and anchor cable is delivered to the bottom of drawing the hole; The spout of being resprayed by two-fold or three while advancing is whitewashed at the bottom of aperture to hole; Shotcrete pipe withdraws from Shi Zaicong and draws hole bottom upwards at the uniform velocity churning water and cement paste (triple churnings are gas, water and cement paste) are to the aperture, and the long anchor cable of 1.5-2m is reserved in the aperture, makes and the later stage anchorage cable stretching as foundation ditch concrete Guan Liang.The cylindric cement soil body such as this kind uplift resistance is not high, and 2-3 root anchor cable passes diameter 10-12cm, and behind the hole of the anchor cable dish of thick 8-14mm, bending is fixed on the anchor cable dish; To the aperture, the anchor cable overcoat rubber plastic pipe (sharp later stage stretch-draw), when the bigger or single anchorage cable stretching tonnage of excavation slope downslide soil body gravity is big from the anchor cable dish; Anchor cable will spur from the cement soil body, reduce uplift resistance, therefore; For excavation slope stable, must the anchoring piles of beating more, increase and invest.
Summary of the invention
The object of the present invention is to provide a kind of end dowel automatic expansion major part rippled edge churning anchoring pile and worker's method thereof, have high tonnage, high uplift resistance, can reduce the pattern foundation pit supporting structure expense.
The objective of the invention is to realize: hold dowel automatic expansion major part rippled edge churning anchoring pile and worker's method thereof for a kind of through following technical scheme; The same with existing anchoring pile and worker's method thereof, all by the anchoring pile drilling machine construction, all have the churning cement soil pile; 2-4 root anchor cable is all arranged at the pile body center; It is characterized in that at churning cement earth pile end of body the dowel of radial automatic expansion being arranged, the pile body end diameter is than the big 10-120cm of pile body diameter; The churning cement soil pile is cylindric in the shape of a spiral, and all major axis of stake are wavy.Dowel automatic expansion described herein is behind the three-wing bit drilling to completion, from draw the hole, withdraws from three-wing bit, changes reaming bit into; Be pushed into 1-3m place water filling reaming at the bottom of the hole, reaming bit is made up of 1-3 layer steel chain or steel throw away tip, and dowel one end electric welding is on the anchor cable dish; The other end is crooked or be welded with and increase sear sheet or reinforcing bar, and dowel selects the elasticity reinforcing bar, outside radial splitting out after the electric welding; With band slip-knot rope dowel is tied up bunchy; Again 2-4 root anchor cable is passed hole on the anchor cable dish respectively, every anchor cable separately, is also twisted the curved little steel wire of forming anchor cable at the anchor cable dish back side, head on the anchor cable center hole by the churning drilling rod anchor cable is pushed into the hole depth portion of drawing; Spur and take out the slip-knot rope then, the elasticity reinforcing bar automatically springs open and is extended to radial.The all major axis of stake described herein are wavy, are to adopt the theoretical gravitational sliding face of enlarged footing to foundation ditch from the bottom, and (triple churnings then are gas, water and cement paste churning with uprising the pressure rotary-spraying cement paste; The stake footpath can reach 800-1200mm); Because high pressure batch, churning body diameter intermittently becomes greatly, and pile body also just forms the spiral circle column; The all major axis of stake also are wavy fluctuating, increase uplift resistance; To the aperture, adopt the mesolow churning from gravitational sliding face, dwindle the stake footpath, alleviate gravitational sliding soil body weight, reduce the horizontal thrust of the outer soil body in hole in the hole.
The present invention compared with prior art has following remarkable advantage: a kind of end dowel automatic expansion major part rippled edge churning anchoring pile, improve uplift resistance 40-70% than existing anchoring pile, and construction technology is simple, can reduce anchoring pile quantity, and reduce the pattern foundation pit supporting structure cost.
Description of drawings
Fig. 1 is a churning anchoring pile sketch map of the present invention.
Among the figure: 1. miscellaneous fill, 2. sprayed mortar, 3. soil nailing, 4. mud, 5. foundation ditch; 6. concrete Guan Liang, 7. churning cement-soil pile body, 8. anchor cable, 9. anchor cable positioning disk; 10. argillic horizon, 11. boring supporting castinplace piles, 12. contain the sand clay layer, 13. anchor cable dishes; 14. the elasticity reinforcing bar, 15. increase sear sheet or reinforcing bar, 16. enlarged footings, the theoretical soil body gravitational sliding face of 17. foundation ditches.
Fig. 2 is a reaming bit sketch map of the present invention.
Among the figure: 1. drilling rod, 2. reaming blade, 3. spring is 4. hinged, 5. the jetting hole.
The specific embodiment
An exemplary embodiments of the present invention such as Fig. 1; When the building foundation pit excavation depth reaches under design concrete Guan Liang (6) absolute altitude 0.5m; Go up laying spacing 150 * 150 Φ 6 steel mesh reinforcements in side slope soil layer (1), (4), (10), insert Φ 16 reinforcing bars (3) of long 3m by 1200 * 1200 spacings and make soil nailing.Three-wing bit (bore 12-18cm) by the anchoring pile rig creeps into to projected depth to hole wall soil layer on the foundation ditch limit again, as the hole of drawing of anchor cable (8), withdraws from three-wing bit then; Change reaming bit (Fig. 2), the beginning water filling is crept at 1-3m place at the bottom of the hole, holds soil layer to get enlarged footing (16) stake; With (14) the one end electric welding of elasticity reinforcing bar on anchor cable dish (13), elasticity reinforcing bar (14) other end burn-on 50 * 50 increase sear sheet (15), and outwards be radial splitting out to elasticity reinforcing bar (14); With band slip-knot rope elasticity reinforcing bar (14) is tied up bunchy; Anchor cable (8) with 3 Φ 16 passes upward hole of anchor cable dish (13) respectively again, and every anchor cable (8) separately, is also twisted the little steel wire of curved composition anchor cable (8) at anchor cable dish (13) back side, head on anchor cable dish (13) centre bore by the churning drilling rod anchor cable (8) is pushed into the hole depth portion of drawing; The cement paste of churning simultaneously; Then, pulling is also taken out the slip-knot rope, and elasticity reinforcing bar (14) automatically springs open and be extended to radial.When withdrawing from the churning pipe, the theoretical gravitational sliding face (17) of enlarged footing to foundation ditch from the bottom, employing uprises the pressure rotary-spraying cement paste, and (triple churnings then are gas, water and cement paste churning; The stake footpath can reach 800-1200mm); High pressure batch is interrupted churning body diameter and becomes big, forms the spiral circle column; The all major axis of stake also are wavy, increase the uplift resistance of pile body (7); To the aperture, adopt the mesolow churning from gravitational sliding face (17), purpose is dwindled the stake footpath, alleviates gravitational sliding soil body weight, reduces the horizontal thrust of the outer soil body in hole in the hole.Making and later stage anchor cable (8) the traction stretch-draw of 1.5-2m anchor cable (8) as foundation ditch concrete Guan Liang (6) is reserved in the aperture.After waiting to be preced with concrete Guan Liang (6) construction and concrete strength thereof and reaching; Reach builder's tonnage with special-purpose jack tension anchor cable (8); Put anchor cable positioning disk (9), the anchor cable of the unnecessary length of oxyacetylene metal-cutting (8), a kind of end dowel automatic expansion major part rippled edge churning anchoring pile promptly completes; Go round and begin again, accomplish the construction of other piles.

Claims (3)

1. a stake end dowel automatic expansion major part rippled edge churning anchoring pile and worker's method thereof are the same with existing anchoring pile and worker's method thereof, all by the anchoring pile drilling machine construction; All have the churning cement soil pile, 2-4 root anchor cable is all arranged at the pile body center, it is characterized in that; The dowel that radial automatic expansion is arranged at churning cement earth pile end of body; The pile body end diameter is than the big 10-120cm of pile body diameter, and the churning cement soil pile is cylindric in the shape of a spiral, and all major axis of stake are wavy.
2. according to claim 1, dowel automatic expansion described herein is behind the three-wing bit drilling to completion, from draw the hole, withdraws from three-wing bit; Change reaming bit into, be pushed into 1-3m place water filling reaming at the bottom of the hole, reaming bit is made up of 1-3 layer steel chain or steel throw away tip; Dowel one end electric welding is on the anchor cable dish, and the other end is crooked or be welded with and increase sear sheet or reinforcing bar, and dowel selects the elasticity reinforcing bar; Outside radial splitting out after the electric welding tied up bunchy with band slip-knot rope with dowel, again 2-4 root anchor cable passed hole on the anchor cable dish respectively; Every anchor cable separately, is also twisted the curved little steel wire of forming anchor cable at the anchor cable dish back side; Head on the anchor cable center hole by the churning drilling rod anchor cable is pushed into the hole depth portion of drawing, spur and take out the slip-knot rope then, the elasticity reinforcing bar automatically springs open and is extended to radial.
3. according to claim 1; The all major axis of stake described herein are wavy; Be to adopt the theoretical gravitational sliding face of enlarged footing to foundation ditch, with uprising pressure rotary-spraying cement paste (triple churnings then are gas, water and cement paste churning, and the stake footpath can reach 800-1200mm) from the bottom; Make pile body form the spiral circle column, all major axis of stake also are wavy fluctuating; To the aperture, adopt the mesolow churning from gravitational sliding face.
CN2010105351434A 2010-11-08 2010-11-08 Automatically extended large-head wavy edge jet grouting anchor pile for pile end anchor bar, and construction method thereof Pending CN102465529A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105351434A CN102465529A (en) 2010-11-08 2010-11-08 Automatically extended large-head wavy edge jet grouting anchor pile for pile end anchor bar, and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105351434A CN102465529A (en) 2010-11-08 2010-11-08 Automatically extended large-head wavy edge jet grouting anchor pile for pile end anchor bar, and construction method thereof

Publications (1)

Publication Number Publication Date
CN102465529A true CN102465529A (en) 2012-05-23

Family

ID=46069617

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105351434A Pending CN102465529A (en) 2010-11-08 2010-11-08 Automatically extended large-head wavy edge jet grouting anchor pile for pile end anchor bar, and construction method thereof

Country Status (1)

Country Link
CN (1) CN102465529A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4411557A (en) * 1977-03-31 1983-10-25 Booth Weldon S Method of making a high-capacity earthbound structural reference
CN1095781A (en) * 1993-05-27 1994-11-30 卢锡焕 In order to promote the spacing ground anchor side grouting construction method of anchoring force
JP2003003467A (en) * 2001-06-21 2003-01-08 Nihonkai Gijutsu Consultants:Kk Ground anchor work using bellmouthed pipe, and bellmouthed pipe
CN1615385A (en) * 2002-01-22 2005-05-11 亨宁·巴尔策·拉斯马森 Reinforcement unit for reinforcing a footing element and method for placing a foundation pile and reinforcement of a footing element
CN101205719A (en) * 2007-12-05 2008-06-25 中国科学院地质与地球物理研究所 Deep-thick earth-rock aggregate pawl type blasting anchor device
CN201137069Y (en) * 2007-11-09 2008-10-22 王国奋 Impact force resistant friction pile for high-rise building
CN101575854A (en) * 2009-06-10 2009-11-11 陕西中机岩土工程有限责任公司 High-pressure jet grouting enlarged footing anchor rod and construction method thereof
CN101649614A (en) * 2008-08-14 2010-02-17 刘全林 Variable-diameter multi-direction anchor pile

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4411557A (en) * 1977-03-31 1983-10-25 Booth Weldon S Method of making a high-capacity earthbound structural reference
CN1095781A (en) * 1993-05-27 1994-11-30 卢锡焕 In order to promote the spacing ground anchor side grouting construction method of anchoring force
JP2003003467A (en) * 2001-06-21 2003-01-08 Nihonkai Gijutsu Consultants:Kk Ground anchor work using bellmouthed pipe, and bellmouthed pipe
CN1615385A (en) * 2002-01-22 2005-05-11 亨宁·巴尔策·拉斯马森 Reinforcement unit for reinforcing a footing element and method for placing a foundation pile and reinforcement of a footing element
CN201137069Y (en) * 2007-11-09 2008-10-22 王国奋 Impact force resistant friction pile for high-rise building
CN101205719A (en) * 2007-12-05 2008-06-25 中国科学院地质与地球物理研究所 Deep-thick earth-rock aggregate pawl type blasting anchor device
CN101649614A (en) * 2008-08-14 2010-02-17 刘全林 Variable-diameter multi-direction anchor pile
CN101575854A (en) * 2009-06-10 2009-11-11 陕西中机岩土工程有限责任公司 High-pressure jet grouting enlarged footing anchor rod and construction method thereof

Similar Documents

Publication Publication Date Title
CN203756203U (en) Self-drilling type full-thread bolt grouting anchor rod
CN107905224B (en) Anchoring structure for improving anti-pulling force of anchor rod by expanding head of expansion cement in perforated steel pipe and construction method
CN101906977A (en) Method for preventing and treating large deformation and collapse of softrock tunnel
CN103993611A (en) Anti-floating piled raft structure combining deep-layer jet-grouting cement-soil board and anchor and construction method
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN101761074A (en) Method for improving bearing capacity and tensile capacity of tubular pile end
CN203741820U (en) Cast-in-situ bored pile structure for karst area
CN109930609A (en) A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground
CN104141305A (en) Multi-layer spiral blade self-drilling-type soil anchor rod and constructing method thereof
CN104895057A (en) Big diameter steel pipe protective wall artificial digging-hole bottom expanding pile and building foundation reinforcement method
CN205712122U (en) A kind of truss-like double-row pile associating suspension roof support system
CN211898463U (en) Reinforcing device combining micro-steel pipe pile and anchor rod
CN102535458A (en) Reinforced cement-soil anchor bolt and construction method thereof
CN113668525A (en) Construction method of anti-floating anchor rod with water-drop-shaped enlarged head based on PSB finish-rolled deformed steel bar
CN107489144B (en) Reinforcing tubular pile
CN206521873U (en) A kind of reducing steel reinforcement cage and its enlarging anchor rod or pile foundation
CN112726627B (en) Bored pile structure in karst region and construction method
CN203866852U (en) Anti-floating pile structure composited by deep spiral-spraying cement soil plate and anchor rod
CN204040041U (en) A kind of front close rear thin Double-row Piles Support system being provided with vertical anchor pole
CN112112159A (en) Electromagnetic gun pile head hole guiding device of large-diameter overlong static pressure anchor pile
CN106988327A (en) A kind of upright controling slip casting steel floral tube pile base beam barrier wall structure and its construction method
CN215482928U (en) Fill and silt district pressure-bearing type anti-floating anchor rod
CN214169107U (en) Cast-in-situ bored pile structure in area with intense karst
CN102465529A (en) Automatically extended large-head wavy edge jet grouting anchor pile for pile end anchor bar, and construction method thereof
CN206693256U (en) A kind of upright controling slip casting steel floral tube pile base beam barrier wall structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 26, building 325000, railway building, Wenzhou Avenue, Lucheng District, Zhejiang, Wenzhou

Applicant after: Zou Zongxuan

Address before: 350000, Fujian, Fuzhou province Cangshan district on the cross Liansheng District, building 4, 301

Applicant before: Zou Zongxuan

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120523