CN102444898A - Power station boiler dry slag discharge air infiltration control system and method - Google Patents

Power station boiler dry slag discharge air infiltration control system and method Download PDF

Info

Publication number
CN102444898A
CN102444898A CN2011103872910A CN201110387291A CN102444898A CN 102444898 A CN102444898 A CN 102444898A CN 2011103872910 A CN2011103872910 A CN 2011103872910A CN 201110387291 A CN201110387291 A CN 201110387291A CN 102444898 A CN102444898 A CN 102444898A
Authority
CN
China
Prior art keywords
slag
mod
appearance
bucket
temperature
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103872910A
Other languages
Chinese (zh)
Other versions
CN102444898B (en
Inventor
张锐
衣心亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute Of Jilin Electric Power Co
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jilin Electric Power Co Ltd
Original Assignee
Electric Power Research Institute Of Jilin Electric Power Co
Electric Power Research Institute of State Grid Jilin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute Of Jilin Electric Power Co, Electric Power Research Institute of State Grid Jilin Electric Power Co Ltd filed Critical Electric Power Research Institute Of Jilin Electric Power Co
Priority to CN 201110387291 priority Critical patent/CN102444898B/en
Publication of CN102444898A publication Critical patent/CN102444898A/en
Application granted granted Critical
Publication of CN102444898B publication Critical patent/CN102444898B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

A power station boiler dry slag discharge air infiltration control system and a method belong to the field of power station boiler dry slag discharge. A cold ash bucket is fixedly connected with a dry slag discharge box body. An electric air door is located in the middle of the side face of the dry slag discharge box body. A stainless steel conveying belt is disposed inside the dry slag discharge box body. The tail end of an ascending section of the dry slag discharge box body is connected with the top end of a slag bucket. The upper portion in the slag bucket is fixedly connected with a slag crusher, the bottom portion in the slag bucket is connected with a conveyor which is connected with a bucket conveyor, and the other end of the bucket conveyor is connected with a slag bin. By controlling opening and closing of the electric air door, the air infiltration problem in the power station boiler dry slag discharge air infiltration control system is resolved, the temperature of slag passing through the cold ash bucket is led to keep from 750 DEG C to 800 DEG C, the temperature of discharged smoke is normal, and economical efficiency of boiler operation is maintained.

Description

Dried deslagging leak control system of station boiler and method
Technical field
The invention belongs to the dried deslagging of station boiler field.
Background technology
Closely during the last ten years, be that the survival and development of the power plant of fuel receive an ash occupation of land and water consumption, the wearing and tearing of grey pipeline, the restriction of environmental pollution with the coal; So, all carried out total utilization of PCA, at present flyash is mainly used in and builds the road and as the material of dosing of cement.According to the market demand, in order to keep the activity of ash, each genco all adopts dry ash removal and dry slag disposal basically.When boiler adopted the wet type slagging-off, boiler design furnace bottom air leakage coefficient was 0.05 mostly, because the restriction of slagging-off mode in most cases in early days, leaking out is greater than this value, and the later stage is because the improvement of deashing device mode, generally can be approaching or less than this value.And dry slag disposal, has leaked out into necessary so artificially designed air inlet owing to will chain be cooled off.The increase that the burner hearth furnace bottom leaks out causes boiler efficiency to descend, and exhaust gas temperature raises, and is big to the boiler economic influence, causes the unit generation coal consumption to raise, and exhaust gas temperature exceeds 10 ℃ of design loads, and gross coal consumption rate will increase about 3.5g/kwh.
Summary of the invention
The present invention provides dried deslagging leak control system of a kind of station boiler and method, to solve the problem that dried dreg removing system leaks out and causes exhaust gas temperature to raise, cause boiler efficiency to descend.
The technical scheme that the present invention takes is: furnace hopper is fixedly connected with dried deslagging casing; MOD is positioned at dried dreg discharging box body side surface middle part; In this dried deslagging casing the stainless steel conveyer belt is arranged, the end of dried deslagging casing ascent stage is connected with the slag bucket top, and this slag bucket internal upper part is fixedly connected slag crusher, the bottom connects conveyer; This conveyer is connected with bucket elevator; This bucket elevator other end is connected with the slag storehouse, five/everywhere is fixedly connected slag position measuring point one in the inside of slag bucket far from the bottom, and 3/10ths places are fixedly connected slag position measuring point two far from the bottom in the inside of slag bucket; Horizontal segment terminus inner at dried deslagging casing is fixedly connected infrared thermography appearance one, is fixedly connected infrared thermography appearance two in the ascent stage of dried deslagging casing terminus inner;
The high 40cm of MOD, long 30cm, MOD is at a distance of 100cm;
The wide 2m of dried deslagging casing, long 32m, high 2.5m.
Method:
One, slag drops on the stainless steel chain in the dried deslagging casing from furnace hopper, the wide 1.4 ~ 1.5m of this stainless steel chain, and the speed of service is 1m ~ 9m/ minute, the high 20 ~ 30cm of slag on the stainless steel chain,
Two, when temperature oc>=700 that the terminal infrared thermography appearance one of horizontal segment records ℃, each MOD of horizontal segment is all opened; During the 600 ℃≤α of temperature that records when the terminal infrared thermography appearance one of horizontal segment<700 ℃, each MOD of horizontal segment opens 80%; During the 500 ℃≤α of temperature that records when the terminal infrared thermography appearance one of horizontal segment<600 ℃, each MOD of horizontal segment opens 70%; When the temperature that records when the terminal infrared thermography appearance one of horizontal segment was 400 ℃≤α<500 ℃, each MOD of horizontal segment opened 50%; When the temperature that records when the terminal infrared thermography appearance one of horizontal segment is α<400 ℃, each MOD complete shut-down of horizontal segment;
Three, when temperature oc>=400 that terminal infrared thermography appearance two of ascent stage records ℃, each MOD of ascent stage is all opened; During the 350 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<400 ℃, each MOD of ascent stage opens 80%; During the 300 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<350 ℃, each MOD of ascent stage opens 60%; During the 230 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<300 ℃, each MOD of ascent stage opens 50%; When temperature oc<230 that terminal infrared thermography appearance two of ascent stage records ℃, each MOD Close All of ascent stage;
Four, when slag in the slag bucket is high when surpassing the height of slag position measuring point one, the door of slag bucket bottom is opened slagging, and when the height of slag height measuring point two in the slag position in the slag bucket, the door of slag bucket bottom is closed not slagging;
The slag of five, from slag bucket, emitting gets in the slag storehouse through conveyer, bucket elevator.
Advantage of the present invention is a novel structure, through solving the problem of leaking out in the dried deslagging leak control system of station boiler, makes the slag temperature through the furnace hopper place remain on 750 ℃ ~ 800 ℃, and exhaust gas temperature is normal, keeps the economy of boiler operatiopn.
Description of drawings
Fig. 1 is a structural representation of the present invention.
The specific embodiment
The present invention is an example with 2 * 300MW unit, equally also is fit to 2 * 350MW unit, and fuel is brown coal.
Furnace hopper 1 is fixedly connected with dried deslagging casing 2; MOD 3 is positioned at dried dreg discharging box body side surface middle part; In this dried deslagging casing stainless steel conveyer belt 4 is arranged, the end of dried deslagging casing ascent stage is connected with slag bucket 5 tops, and this slag bucket internal upper part is fixedly connected slag crusher 6, the bottom connects conveyer 7; This conveyer is connected with bucket elevator 8; This bucket elevator other end is connected with slag storehouse 9, five/everywhere is fixedly connected slag position measuring point 1 in the inside of slag bucket far from the bottom, and 3/10ths places are fixedly connected slag position measuring point 2 11 far from the bottom in the inside of slag bucket; Horizontal segment terminus inner at dried deslagging casing is fixedly connected infrared thermography appearance 1, is fixedly connected infrared thermography appearance 2 13 in the ascent stage of dried deslagging casing terminus inner;
The high 40cm of MOD, long 30cm, MOD is at a distance of 100cm;
The wide 2m of dried deslagging casing, long 32m, high 2.5m;
Method:
One, slag drops on the stainless steel chain in the dried deslagging casing from furnace hopper, the wide 1.4 ~ 1.5m of this stainless steel chain, and the speed of service is 1m ~ 9m/ minute, the high 20 ~ 30cm of slag on the stainless steel chain,
Two, when temperature oc>=700 that the terminal infrared thermography appearance one of horizontal segment records ℃, each MOD of horizontal segment is all opened; During the 600 ℃≤α of temperature that records when the terminal infrared thermography appearance one of horizontal segment<700 ℃, each MOD of horizontal segment opens 80%; During the 500 ℃≤α of temperature that records when the terminal infrared thermography appearance one of horizontal segment<600 ℃, each MOD of horizontal segment opens 70%; When the temperature that records when the terminal infrared thermography appearance one of horizontal segment was 400 ℃≤α<500 ℃, each MOD of horizontal segment opened 50%; When the temperature that records when the terminal infrared thermography appearance one of horizontal segment is α<400 ℃, each MOD complete shut-down of horizontal segment;
Three, when temperature oc>=400 that terminal infrared thermography appearance two of ascent stage records ℃, each MOD of ascent stage is all opened; During the 350 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<400 ℃, each MOD of ascent stage opens 80%; During the 300 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<350 ℃, each MOD of ascent stage opens 60%; During the 230 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<300 ℃, each MOD of ascent stage opens 50%; When temperature oc<230 that terminal infrared thermography appearance two of ascent stage records ℃, each MOD Close All of ascent stage;
Four, when slag in the slag bucket is high when surpassing the height of slag position measuring point one, the door of slag bucket bottom is opened slagging, and when the height of slag height measuring point two in the slag position in the slag bucket, the door of slag bucket bottom is closed not slagging;
The slag of five, from slag bucket, emitting gets in the slag storehouse through conveyer, bucket elevator.

Claims (2)

1. dried deslagging leak control system of station boiler; It is characterized in that: furnace hopper is fixedly connected with dried deslagging casing, and MOD is positioned at dried dreg discharging box body side surface middle part, in this dried deslagging casing the stainless steel conveyer belt is arranged; The end of dried deslagging casing ascent stage is connected with the slag bucket top; This slag bucket internal upper part is fixedly connected slag crusher, the bottom connects conveyer, and this conveyer is connected with bucket elevator, and this bucket elevator other end is connected with the slag storehouse; Five/everywhere be fixedly connected slag position measuring point one in the inside of slag bucket far from the bottom; 3/10ths places are fixedly connected slag position measuring point two far from the bottom in the inside of slag bucket, and the horizontal segment terminus inner fixed connection infrared thermography appearance one at dried deslagging casing is fixedly connected infrared thermography appearance two in the ascent stage of dried deslagging casing terminus inner;
The high 40cm of said MOD, long 30cm, MOD is at a distance of 100cm;
The wide 2m of said dried deslagging casing, long 32m, high 2.5m.
2. the dried deslagging of station boiler control method of leaking out is characterized in that comprising the following steps:
One, slag drops on the stainless steel chain in the dried deslagging casing from furnace hopper, the wide 1.4 ~ 1.5m of this stainless steel chain, and the speed of service is 1m ~ 9m/ minute, the high 20 ~ 30cm of slag on the stainless steel chain,
Two, when temperature oc>=700 that the terminal infrared thermography appearance one of horizontal segment records ℃, each MOD of horizontal segment is all opened; During the 600 ℃≤α of temperature that records when the terminal infrared thermography appearance one of horizontal segment<700 ℃, each MOD of horizontal segment opens 80%; During the 500 ℃≤α of temperature that records when the terminal infrared thermography appearance one of horizontal segment<600 ℃, each MOD of horizontal segment opens 70%; When the temperature that records when the terminal infrared thermography appearance one of horizontal segment was 400 ℃≤α<500 ℃, each MOD of horizontal segment opened 50%; When the temperature that records when the terminal infrared thermography appearance one of horizontal segment is α<400 ℃, each MOD complete shut-down of horizontal segment;
Three, when temperature oc>=400 that terminal infrared thermography appearance two of ascent stage records ℃, each MOD of ascent stage is all opened; During the 350 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<400 ℃, each MOD of ascent stage opens 80%; During the 300 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<350 ℃, each MOD of ascent stage opens 60%; During the 230 ℃≤α of temperature that records when terminal infrared thermography appearance two of ascent stage<300 ℃, each MOD of ascent stage opens 50%; When temperature oc<230 that terminal infrared thermography appearance two of ascent stage records ℃, each MOD Close All of ascent stage;
Four, when slag in the slag bucket is high when surpassing the height of slag position measuring point one, the door of slag bucket bottom is opened slagging, and when the height of slag height measuring point two in the slag position in the slag bucket, the door of slag bucket bottom is closed not slagging;
The slag of five, from slag bucket, emitting gets in the slag storehouse through conveyer, bucket elevator.
CN 201110387291 2011-11-29 2011-11-29 Power station boiler dry slag discharge air infiltration control system and method Active CN102444898B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110387291 CN102444898B (en) 2011-11-29 2011-11-29 Power station boiler dry slag discharge air infiltration control system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110387291 CN102444898B (en) 2011-11-29 2011-11-29 Power station boiler dry slag discharge air infiltration control system and method

Publications (2)

Publication Number Publication Date
CN102444898A true CN102444898A (en) 2012-05-09
CN102444898B CN102444898B (en) 2013-01-16

Family

ID=46007646

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110387291 Active CN102444898B (en) 2011-11-29 2011-11-29 Power station boiler dry slag discharge air infiltration control system and method

Country Status (1)

Country Link
CN (1) CN102444898B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104132355A (en) * 2014-07-25 2014-11-05 国家电网公司 Dry-type deslagging system capable of adjusting cooling air

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2616811Y (en) * 2003-04-25 2004-05-19 铁岭市华隆仪表有限公司 Boiler slag-removing failure diagnosis and monitoring system
CN1587815A (en) * 2004-09-13 2005-03-02 中天仕名科技集团有限公司 Cooling system for dry slag of new boiler
JP3827916B2 (en) * 2000-05-18 2006-09-27 株式会社タクマ Detection method of defective molten slag discharge
CN101008492A (en) * 2006-01-24 2007-08-01 北京国电富通科技发展有限责任公司 Dry slag-draining device of coal boiler
CN201053686Y (en) * 2007-06-14 2008-04-30 北京国电富通科技发展有限责任公司 Bucket elevator with cooling function
CN102155743A (en) * 2011-04-15 2011-08-17 山东电力研究院 Ventilation control system and method applicable to dry type slag extractor

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3827916B2 (en) * 2000-05-18 2006-09-27 株式会社タクマ Detection method of defective molten slag discharge
CN2616811Y (en) * 2003-04-25 2004-05-19 铁岭市华隆仪表有限公司 Boiler slag-removing failure diagnosis and monitoring system
CN1587815A (en) * 2004-09-13 2005-03-02 中天仕名科技集团有限公司 Cooling system for dry slag of new boiler
CN101008492A (en) * 2006-01-24 2007-08-01 北京国电富通科技发展有限责任公司 Dry slag-draining device of coal boiler
CN201053686Y (en) * 2007-06-14 2008-04-30 北京国电富通科技发展有限责任公司 Bucket elevator with cooling function
CN102155743A (en) * 2011-04-15 2011-08-17 山东电力研究院 Ventilation control system and method applicable to dry type slag extractor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104132355A (en) * 2014-07-25 2014-11-05 国家电网公司 Dry-type deslagging system capable of adjusting cooling air

Also Published As

Publication number Publication date
CN102444898B (en) 2013-01-16

Similar Documents

Publication Publication Date Title
CN201852085U (en) Coal-fired boiler for waste incineration
CN102052686A (en) Air-cooled dry-type slag discharging system
CN102444898B (en) Power station boiler dry slag discharge air infiltration control system and method
CN201421097Y (en) Dry cooling deslagging device
CN201087201Y (en) Conveyer for energy-saving steel making of electric furnace
CN202807678U (en) Novel horizontal chain type slag remover
CN202265539U (en) Process device for reconstructing coke wet quenching into coke dry quenching
CN202675262U (en) Package boiler with plug reciprocal grate
CN213622335U (en) Coal feeder of coal-fired power plant powder process system
CN104498068B (en) The carbonization furnace of a kind of band air seal set does coke discharging method
CN103723519A (en) Coal ash collecting and delivery method
CN209512034U (en) Bent-tube boiler water cooling self-adapting seal discharging device
CN204388089U (en) A kind of pulverized-coal fired boiler lime-ash cooling conveying system
CN203501772U (en) Environment-friendly hot-blast cupola
CN107300167A (en) A kind of biomass gasification fired technology of integral type and application
CN203682639U (en) Closed pebble coal collecting and discharging system
CN207831370U (en) A kind of small-sized rubbish incineration experiment platform incinerator
CN201104119Y (en) High-efficiency low-leaking low-abrasion inflating beam grate cooler
CN201250202Y (en) Coal port structure of a coke oven carbonized chamber
CN205859973U (en) A kind of integral biomass steam generator
CN201842806U (en) Gas-combustion low temperature dry distillation coking furnace
CN202561769U (en) Leaked slag conveying system of incinerator
CN205481008U (en) Air circulation system is discharged to garbage cracking furnace's nothing
CN103925602A (en) Method for performing deslagging through coal-fired boiler discontinuous dry deslagging system
CN206001484U (en) A kind of fire-gate leakage slag slag conveyer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: JILIN PROV. POWER SCIENCE INST. CO., LTD. STATE EL

Free format text: FORMER OWNER: JILIN ELECTRIC POWER SUPPLY COMPANY CHINA ELECTRIC POWER RESEARCH INSTITUTE

Effective date: 20121008

Owner name: JILIN ELECTRIC POWER SUPPLY COMPANY CHINA ELECTRIC

Free format text: FORMER OWNER: JILIN PROV. POWER SCIENCE INST. CO., LTD.

Effective date: 20121008

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121008

Address after: 130021 Jilin City, Changchun province people's street, No. 4433

Applicant after: Electric Power Research Institute of Jilin Electric Power Company

Applicant after: Jilin Academy of Electric Power Science

Applicant after: State Grid Corporation of China

Address before: 130021 Jilin City, Changchun province people's street, No. 4433

Applicant before: Jilin Academy of Electric Power Science

Applicant before: Electric Power Research Institute of Jilin Electric Power Company

C14 Grant of patent or utility model
GR01 Patent grant