CN102441651A - Method for judging and handling steel channeling on junction surface of submerged nozzle - Google Patents

Method for judging and handling steel channeling on junction surface of submerged nozzle Download PDF

Info

Publication number
CN102441651A
CN102441651A CN2011104034785A CN201110403478A CN102441651A CN 102441651 A CN102441651 A CN 102441651A CN 2011104034785 A CN2011104034785 A CN 2011104034785A CN 201110403478 A CN201110403478 A CN 201110403478A CN 102441651 A CN102441651 A CN 102441651A
Authority
CN
China
Prior art keywords
steel
river
mouth
faying face
liquid level
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011104034785A
Other languages
Chinese (zh)
Other versions
CN102441651B (en
Inventor
陈志威
梁凤友
秦海山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Angang Steel Co Ltd
Original Assignee
Angang Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Angang Steel Co Ltd filed Critical Angang Steel Co Ltd
Priority to CN201110403478.5A priority Critical patent/CN102441651B/en
Publication of CN102441651A publication Critical patent/CN102441651A/en
Application granted granted Critical
Publication of CN102441651B publication Critical patent/CN102441651B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a method for judging and handling steel channeling on the junction surface of a submerged nozzle. The method comprises the following steps of: turning down the argon flow according to the overturning condition of the liquid level of molten steel, detecting a submerged nozzle part under the liquid level by using a stick if the overturning variation of the liquid level is unremarkable, and judging that an air sucking phenomenon exists at a junction surface of the submerged nozzle and a down nozzle if no remarkable crack exists on the upper part of the liquid level; when steel channeling appears on the junction surface, decelerating immediately, turning down the argon flow, communicating an argon tube, and cooling the junction surface at high argon flow; closely watching the opening state of a sliding plate, and appropriately adjusting the argon flow; and recovering the argon flow at an upper nozzle simultaneously, and pulling steel at a low speed till casting is finished. Due to the adoption of the method, the problem of steel channeling on the junction surface can be discovered and handled as early as possible, casting stop accidents caused by steel channeling are avoided, heat recovery and cold recovery of the molten steel are reduced, the accident loss is lowered, and successful performance of production is ensured.

Description

A kind ofly immerse the determination processing method that mouth of a river faying face is scurried steel
Technical field
The invention belongs to the continuous casting process field, immerse the emergent determination processing method that steel appears scurrying in the mouth of a river and following mouth of a river faying face in particularly a kind of casting process.
Background technology
Wear out, air-dry crackle etc. arranged if immerse the faying face out-of-flatness or the mouth of a river pad at the mouth of a river and the following mouth of a river, all can cause mouth of a river faying face to scurry steel, in case scurry steel and don't take proper measure in time to save; Will make and scurry the expansion of steel place; Cause and be compelled to stop the accident of watering, thereby cause cold recovery, the recuperation of heat of molten steel, not only cause billet yield to descend and increase molten steel after-treatment amount; Have a strong impact on carrying out smoothly of production; Directly increased production cost, and will bring certain influence, caused great economic loss to enterprise to slab quality.
Summary of the invention
The present invention aims to provide and a kind ofly can find to scurry the steel sign as early as possible and scurry the steel accident with in time handling, and avoids accident to stop watering, and the immersion mouth of a river faying face that reduces cold recovery of molten steel and heat recovery rate is scurried the processing method of steel.
For this reason, the technical solution that the present invention taked is:
A kind ofly immerse the determination processing method that mouth of a river faying face is scurried steel, it is characterized in that:
(1), mouth of a river faying face is scurried the preceding judgement of steel:
Scurry the preceding mouth of a river of steel faying face and inspiratory phenomenon can occur, it is air-breathing to be accompanied by faying face, and molten steel contacts with airborne oxygen, and the molten steel liquid level of an air-breathing side is dug more than the 10mm, and after argon gas closed, liquid level stirred degree and changes little; Whether survey liquid level with wooden stick and immerse mouth of a river part down, observing liquid level top simultaneously has obvious crackle, as does not have obvious crackle or leak eye, can conclude that then immersing the mouth of a river exists inspiratory phenomenon with following mouth of a river faying face;
(2), mouth of a river faying face is scurried the processing of steel:
Occur scurrying steel if immerse the mouth of a river with following mouth of a river faying face, will draw steel speed to reduce to 0.8-1.0 m/min immediately, the argon flow amount of filling pipe end and slide plate is controlled to 10m 3/ h reduces the molten steel flow of mouth of a river passage, and near the following mouth of a river of scurrying the steel place, connects a tunger tube rapidly, and argon flow amount is controlled to 30 ~ 40m 3/ h cools off faying face, makes faying face form cold steel fast; Treat liquid level stabilizing, scurry after steel stops and stablizing 10 ~ 15min, argon gas is adjusted to 10 ~ 20m 3/ h prevents nozzle clogging; Pay close attention to and, suitably adjust argon flow amount according to the aperture state of slide plate; Simultaneously, recover argon flow amount to the 30 ~ 40m of filling pipe end 3/ h, the melting state of assurance covering slag; Take 0.8 ~ 1.0 m/min low speed to draw steel, prevent that excessive steel stream from washing away the cold steel that has solidified, until watering time end.
Beneficial effect of the present invention is:
One aspect of the present invention can be found to immerse the hidden danger that steel appears scurrying in mouth of a river faying face as early as possible, controls so that in time take measures; Simultaneously in case after the steel accident occurring scurrying, also can effectively meet an urgent need and remedy, the accident that prevents enlarges, thereby avoids reducing recuperation of heat, the cold recovery of molten steel owing to scurry the accident of watering of stopping that steel causes, the reduction causality loss, and that guarantees to produce carries out smoothly.The inventive method is simple, is convenient to operation, and can improves the cast effect to a certain extent, improves faying face and scurries the influence of steel to slab quality.
The specific embodiment
Embodiment 1:
Immerse the judgement before mouth of a river faying face is scurried steel:
Mouth of a river faying face has certain sign before scurrying steel; Promptly scurry the preceding mouth of a river of steel faying face and inspiratory phenomenon can occur; And it is air-breathing to be accompanied by faying face, and molten steel contacts with airborne oxygen, will speed up immersing the etch of mouth of a river faying face; If untimely taking measures will be caused the steel accident of scurrying of mouth of a river faying face.The air-breathing main feature of faying face is that after the faying face appearance was air-breathing, bigger stirring will appear in the molten steel liquid level of an air-breathing side.Be that the molten steel liquid level is dug and can be reached more than the 10mm.For confirming whether faying face air-breathing, and its measure is after argon gas is closed, observe liquid level and stir situation, bigger if liquid level still stirs, the size that argon flow amount is described to liquid level to stir influential effect little.Survey liquid level with wooden stick again this moment and immerse mouth of a river part down; Whether observe liquid level top has obvious crackle or leaks eye; As do not have obvious crackle or leak eye; Then there is inspiratory phenomenon in the decidable immersion mouth of a river with following mouth of a river faying face, just should in time take measures to control, and also can handle according to the way of scurrying steel.
Immerse the processing after steel appears scurrying in mouth of a river faying face:
Occur scurrying steel if immerse the mouth of a river with following mouth of a river faying face, will draw steel speed to reduce to 0.9 m/min immediately, the argon flow amount of filling pipe end and slide plate is controlled to 10m 3/ h reduces the molten steel flow of mouth of a river passage, and near the following mouth of a river of scurrying the steel place, connects a tunger tube rapidly, and argon flow amount is controlled to 40m 3/ h adopts argon gas cooling faying face, makes faying face form cold steel fast.Treat liquid level stabilizing, scurry after steel stops, stablizing 14min again, in time turn argon flow amount then down, argon gas is adjusted to 15m 3/ h, preventing the excessive nozzle clogging that causes of intensity of cooling of argon gas from influencing casting condition.Simultaneously, should pay close attention to the aperture situation of slide plate constantly, and the argon flow amount of filling pipe end is returned to 34m 3/ h guarantees the melting state of covering slag.In this process, should take the low speed of 0.8m/min to draw steel all the time, even after in stable condition, also can not improve pulling rate, flow through greatly to prevent steel, wash away the cold steel that has solidified, cause faying face to scurry steel again.Reduction of speed draws steel until originally watering time end, faying face is handled again, and avoids scurrying once more steel.
Embodiment 2:
Immerse the judgement before mouth of a river faying face is scurried steel:
Scurry the preceding mouth of a river of steel faying face and inspiratory phenomenon can occur, and it is air-breathing to be accompanied by faying face, molten steel contacts with airborne oxygen, will speed up immersing the etch of mouth of a river faying face, if untimely taking measures will be caused the steel accident of scurrying of mouth of a river faying face.After the faying face appearance was air-breathing, bigger stirring will appear in the molten steel liquid level of an air-breathing side.Be that the molten steel liquid level is dug and can be reached more than the 10mm.And after argon gas is closed, bigger if liquid level still stirs, the size that argon flow amount is described to liquid level to stir influential effect little.Survey liquid level with wooden stick again this moment and immerse mouth of a river part down; Whether observe liquid level top has obvious crackle or leaks eye; As do not have obvious crackle or leak eye; Then there is inspiratory phenomenon in the decidable immersion mouth of a river with following mouth of a river faying face, just should in time take measures to control, and also can handle according to the way of scurrying steel.
Immerse the processing after steel appears scurrying in mouth of a river faying face:
Occur scurrying steel if immerse the mouth of a river with following mouth of a river faying face, will draw steel speed to reduce to 1.0 m/min immediately, the argon flow amount of filling pipe end and slide plate is controlled to 10m 3/ h reduces the molten steel flow of mouth of a river passage, and near the following mouth of a river of scurrying the steel place, connects a tunger tube rapidly, and argon flow amount is controlled to 30m 3/ h adopts argon gas cooling faying face, makes faying face form cold steel fast.Treat liquid level stabilizing, scurry after steel stops, stablizing 10min again, in time turn argon flow amount then down, argon gas is adjusted to 20m 3/ h, preventing the excessive nozzle clogging that causes of intensity of cooling of argon gas from influencing casting condition.Simultaneously, should pay close attention to the aperture situation of slide plate constantly, and the argon flow amount of filling pipe end is returned to 40m 3/ h guarantees the melting state of covering slag.In this process, should take the low speed of 1.0m/min to draw steel all the time, even after in stable condition, also can not improve pulling rate, flow through greatly to prevent steel, wash away the cold steel that has solidified, cause faying face to scurry steel again.Reduction of speed draws steel until originally watering time end, faying face is handled again, and avoids scurrying once more steel.

Claims (1)

1. one kind immerses the determination processing method that mouth of a river faying face is scurried steel, it is characterized in that:
(1), mouth of a river faying face is scurried the preceding judgement of steel:
Scurry the preceding mouth of a river of steel faying face and inspiratory phenomenon can occur, it is air-breathing to be accompanied by faying face, and molten steel contacts with airborne oxygen, and the molten steel liquid level of an air-breathing side is dug more than the 10mm, and after argon gas closed, liquid level stirred degree and changes little; Whether survey liquid level with wooden stick and immerse mouth of a river part down, observing liquid level top simultaneously has obvious crackle, as does not have obvious crackle or leak eye, can conclude that then immersing the mouth of a river exists inspiratory phenomenon with following mouth of a river faying face;
(2), mouth of a river faying face is scurried the processing of steel:
Occur scurrying steel if immerse the mouth of a river with following mouth of a river faying face, will draw steel speed to reduce to 0.8-1.0 m/min immediately, the argon flow amount of filling pipe end and slide plate is controlled to 10m 3/ h reduces the molten steel flow of mouth of a river passage, and near the following mouth of a river of scurrying the steel place, connects a tunger tube rapidly, and argon flow amount is controlled to 30 ~ 40m 3/ h cools off faying face, makes faying face form cold steel fast; Treat liquid level stabilizing, scurry after steel stops and stablizing 10 ~ 15min, argon gas is adjusted to 10 ~ 20m 3/ h prevents nozzle clogging; Pay close attention to and, suitably adjust argon flow amount according to the aperture state of slide plate; Simultaneously, recover argon flow amount to the 30 ~ 40m of filling pipe end 3/ h, the melting state of assurance covering slag; Take 0.8 ~ 1.0 m/min low speed to draw steel, prevent that excessive steel stream from washing away the cold steel that has solidified, until watering time end.
CN201110403478.5A 2011-12-07 2011-12-07 A kind of soaking water gap faying face alters the determination processing method of steel Active CN102441651B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110403478.5A CN102441651B (en) 2011-12-07 2011-12-07 A kind of soaking water gap faying face alters the determination processing method of steel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110403478.5A CN102441651B (en) 2011-12-07 2011-12-07 A kind of soaking water gap faying face alters the determination processing method of steel

Publications (2)

Publication Number Publication Date
CN102441651A true CN102441651A (en) 2012-05-09
CN102441651B CN102441651B (en) 2015-11-18

Family

ID=46004867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110403478.5A Active CN102441651B (en) 2011-12-07 2011-12-07 A kind of soaking water gap faying face alters the determination processing method of steel

Country Status (1)

Country Link
CN (1) CN102441651B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104001892A (en) * 2014-06-12 2014-08-27 鞍钢股份有限公司 Method for adjusting tundish argon flow
CN106077542A (en) * 2016-06-28 2016-11-09 山东钢铁股份有限公司 A kind of judge to corrode and the method for air-breathing between tundish lower nozzle and submersed nozzle plate
CN113042726A (en) * 2021-03-11 2021-06-29 天津市新天钢钢铁集团有限公司 Method for treating steel channeling between slab continuous casting quick-change water gap plates

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62279059A (en) * 1986-05-26 1987-12-03 Nippon Kokan Kk <Nkk> Submerged nozzle
JPH0390262A (en) * 1989-08-31 1991-04-16 Sumitomo Metal Ind Ltd Method and device for preventing drift stream in discharged flow in mold
JPH0970652A (en) * 1995-09-08 1997-03-18 Nippon Steel Corp Method for preventing uneven flow of molten steel in continuous casting mold
KR20040044001A (en) * 2002-11-20 2004-05-27 주식회사 포스코 Submerged Nozzle for Generating Multi-Flow
CN101602104A (en) * 2009-04-17 2009-12-16 陈红良 A kind of tundish and use this tundish to remove the method for nonmetal impurities
CN201848533U (en) * 2010-10-28 2011-06-01 黄石市火炬科技实业有限责任公司 Device for quick replacing nozzles of continuous casting tundish with argon admission function
CN102764868A (en) * 2012-07-11 2012-11-07 北京科技大学 Blowing and refining device and method used for removing tundish molten steel inclusion

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62279059A (en) * 1986-05-26 1987-12-03 Nippon Kokan Kk <Nkk> Submerged nozzle
JPH0390262A (en) * 1989-08-31 1991-04-16 Sumitomo Metal Ind Ltd Method and device for preventing drift stream in discharged flow in mold
JPH0970652A (en) * 1995-09-08 1997-03-18 Nippon Steel Corp Method for preventing uneven flow of molten steel in continuous casting mold
KR20040044001A (en) * 2002-11-20 2004-05-27 주식회사 포스코 Submerged Nozzle for Generating Multi-Flow
CN101602104A (en) * 2009-04-17 2009-12-16 陈红良 A kind of tundish and use this tundish to remove the method for nonmetal impurities
CN201848533U (en) * 2010-10-28 2011-06-01 黄石市火炬科技实业有限责任公司 Device for quick replacing nozzles of continuous casting tundish with argon admission function
CN102764868A (en) * 2012-07-11 2012-11-07 北京科技大学 Blowing and refining device and method used for removing tundish molten steel inclusion

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104001892A (en) * 2014-06-12 2014-08-27 鞍钢股份有限公司 Method for adjusting tundish argon flow
CN106077542A (en) * 2016-06-28 2016-11-09 山东钢铁股份有限公司 A kind of judge to corrode and the method for air-breathing between tundish lower nozzle and submersed nozzle plate
CN113042726A (en) * 2021-03-11 2021-06-29 天津市新天钢钢铁集团有限公司 Method for treating steel channeling between slab continuous casting quick-change water gap plates

Also Published As

Publication number Publication date
CN102441651B (en) 2015-11-18

Similar Documents

Publication Publication Date Title
CN103586433B (en) A kind of method improving continuous casting steel billet head and tail base flaw detection qualification rate
WO2018077044A1 (en) Control method and apparatus for inhibiting slag entrapment in ladle in last stage of pouring during continuous casting
CN102941323A (en) Method for quickly replacing tundish at low liquid level of medium thin plate blank continuous casting machine crystallizer
CN102441651A (en) Method for judging and handling steel channeling on junction surface of submerged nozzle
CN104889358B (en) Method for controlling surface crack of continuous cast slab
CN109420747B (en) High-yield automatic capping process for slab caster
CN106513616B (en) A kind of wide thickness plate continuous casting machine dry type method for capping
CN102443679A (en) Production method of ultralow oxide inclusion steel
CN104233044B (en) The production method of a kind of high aluminum steel
CN106011388B (en) It is a kind of to improve the smelting process for pouring time the first stove heavy rail fault detection qualification rate
CN105215311A (en) A kind of billet continuous casting open casting operation method
CN109022661B (en) Method for reducing heavy rail steel rail damage rate
CN201735774U (en) Device for eliminating continuous casting tundish bottom eddy
CN103240406B (en) Continuous casting tundish and continuous casting tundish casting control method
CN204700257U (en) A kind of molten steel casting ladle with suspending agent injection device
CN101716659B (en) Method for mold casting of molten steel
CN203960253U (en) Spreader formula line feeding rifle for a kind of steel-making
CN106541122B (en) A kind of method for preventing tundish slag
CN107900302A (en) A kind of method and device for improving slab tail base quality
WO2021203851A1 (en) Method for magnesium and calcium treatments of molten steel by spraying powder using elongated nozzle
JP2018051598A (en) Bottom pouring ingot-making equipment
CN105436451A (en) Method for casting heavy rail steel tail blank through tundish without slag blocking device
CN101745619A (en) Batch water-cooling technology for inhibiting deformation of bottom of aluminum alloy ingot
CN204565069U (en) A kind of vacuum casting device preventing molten steel from splashing
CN215279864U (en) Flow control device for replacing externally hung water gap

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant