CN102419155A - 冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法 - Google Patents

冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法 Download PDF

Info

Publication number
CN102419155A
CN102419155A CN201110256497XA CN201110256497A CN102419155A CN 102419155 A CN102419155 A CN 102419155A CN 201110256497X A CN201110256497X A CN 201110256497XA CN 201110256497 A CN201110256497 A CN 201110256497A CN 102419155 A CN102419155 A CN 102419155A
Authority
CN
China
Prior art keywords
radius
barrel
creeping formwork
guide rail
cylindrical shell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201110256497XA
Other languages
English (en)
Other versions
CN102419155B (zh
Inventor
彭晓月
程景栋
吴敏
彭建锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Group Jiangsu Co ltd
China Construction Third Engineering Bureau Second Construction And Installation Co ltd
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
China Construction Third Bureau Green Industry Investment Co Ltd
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN201110256497.XA priority Critical patent/CN102419155B/zh
Publication of CN102419155A publication Critical patent/CN102419155A/zh
Application granted granted Critical
Publication of CN102419155B publication Critical patent/CN102419155B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明涉及冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法,以筒体中心在水平面上的投影为圆心,根据爬模导轨数量N将圆分成N等份并用墨线和红油漆在底板上作标记即为辐射线,且爬模导轨中心线与辐射线相对应;在圆心架设全站仪沿辐射线测量出圆心至架设垂准仪基准点的距离L1和读出在筒壁上爬模导轨内边缘挑出的有机玻璃测量尺的读数L2,筒壁内半径R=L1+L2,检查R与R是否相等,如有偏差则调整爬模导轨直至R与R相等为止,用相同的方法确定每节筒体半径;根据筒壁内半径和筒壁厚度之和为筒壁外半径来控制筒体混凝土半径。本发明安全可靠、操作简单、精确度高,大大降低了测量人员劳动强度、提高了测量效率。

Description

冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法
技术领域:
本发明属于建筑工程领域,特别涉及在双曲线冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法,保证筒壁混凝土外观尺寸精确。
背景技术:
现有的冷却塔及大型构筑物筒体混凝土半径测量控制技术是:在高空平台上或脚手架上用经纬仪测角度,再用50m或者100m尺子测量距离,用于控制筒壁半径。此项技术的缺点是:一、由于半径较大,而且在高空作业,测量精度不易控制。二、由于在高空,操作非常不便,给现场测量人员带来安全隐患。此项技术已不适应现代建筑的需要。
发明内容:
本发明的目的是提供一种冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法,保证安全、精确、快捷地测量冷却塔及大型构筑物筒体半径。
本发明解决其技术问题所采用的技术方案是:
冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法,其特征在于按以下步骤进行:(1)、以冷却塔及大型构筑物筒体中心在水平面上的投影为圆心,根据爬模导轨数量N,将圆分成N等份,用墨线和红油漆在底板上作标记即为辐射线,且每条爬模导轨中心线对应一条辐射线;(2)、在圆心架设全站仪沿辐射线测量出每节爬模导轨半径的临时控制基准点,作为垂准仪架设的临时基准点;(3)、将垂准仪安放在底板的临时基准点上,在筒壁上爬模导轨内边缘挑出有机玻璃测量尺,利用垂准仪的激光光斑在有机玻璃测量尺上进行读数,临时基准点的数值L1加上测量尺读数L2即为筒壁内半径R=L1+L2,检查R与R是否相等,R为设计的筒壁内半径,如有偏差则通过爬模导轨进行调整,直至R与R相等为止,则该节筒体半径已确定,用相同的方法确定每节筒体半径;根据筒壁内半径和筒壁厚度之和为筒壁外半径来控制冷却塔及大型构筑物筒体混凝土半径。
所述爬模导轨数量N按以下方法计算得到:依据冷却塔风筒或大型构筑物筒体底部最大周长和喉部最小周长及爬模平台板的尺寸确定爬模导轨数量,保证爬模平台板在冷却塔风筒及大型构筑物筒体的底部能够连接,在筒体喉部能够顺利通过,底部周长除以平台板拉伸至极限位置的长度得一整数N1,喉部周长除以平台板收缩至极限位置的长度得一整数N2,从N1和N2中选出最大数为爬模导轨数N。
本发明使用先进全站仪测角、测距可以同时测量,而且连续复测,提高了测量精度。全站仪在底板上测量,操作方便、安全可靠。本发明使用激光垂准仪进行铅垂线的点位传递,下对点激光光斑无须调焦,测量快捷。本发明使用有机玻璃测量尺,立尺人员根据激光光斑直接读数,快捷简单。
本发明安全可靠、操作简单、精确度高。解决了大直径、高耸冷却塔及大型构筑物筒体半径施工测量的难题,特别是双曲线冷却塔及大型筒体构筑物,大大降低了测量人员劳动强度、提高了测量效率。
全站仪、激光垂准仪、有机玻璃测量尺均从市场购买得到。
此技术同样适用于其他变直径圆弧形高耸构筑物半径的施工测量控制。
附图说明:
图1是本发明冷却塔爬模导轨中心线在基础底板上水平投影线图;
图2是本发明全站仪及激光垂准仪测量布置图;
图3是本发明全站仪及激光垂准仪测量筒壁半径的立体示意图。
图4是本发明有机玻璃测量尺示意图。
图中1是全站仪、2是激光垂准仪、3是有机玻璃测量尺、4是风筒筒壁、5是爬模导轨、6是爬升模架、7是基准点、8是筒壁钢筋、9是导轨中心线在水平面上投影线、10是风筒底部外径在水平面上投影线、11是风筒半径最小处筒壁在水平面上投影线。
具体实施方式:
下面结合附图对本发明进一步说明。
参照图1,依据冷却塔风筒底部最大周长和喉部最小周长及爬模平台板的尺寸确定爬模导轨数量,保证爬模平台板在风筒底部能够连接,在风筒喉部能够顺利通过,底部周长除以平台板拉伸至极限位置的长度得一整数N1,喉部周长除以平台板收缩至极限位置的长度得另一整数N2,从N1和N2中选出最大数为爬模导轨数N;以圆形底板中心为圆心把底板等分成N等分,用墨线和红油漆在底板上作标记,得到N条辐射线,即为测量控制辐射线。安装爬模导轨时使爬模导轨中心线在底板上的投影与辐射线重合。
参照图2全站仪1与激光垂准仪2平面位置布置图,在冷却塔基础底板圆心上架设全站仪1,反复调平全站仪1三爪基座的脚螺旋,使基座上的圆水准泡居中,仪器处于水平位置;
在爬模导轨水平投影线上架设激光垂准仪2,调节激光垂准仪2三爪基座的脚螺旋,使基座上的圆水准泡居中,开动仪器的激光发动器,将激光光斑向下投射到底板上,松开仪器与脚架的连接螺栓,将仪器缓慢移动到地面测量基准点7的上方,观察激光光斑是否与底板上基准点7重合,反复调整,直至激光光斑中心正好落在基准点7上为止;对中精确、效率高。
参照图3是利用全站仪1和激光垂准仪2测量筒壁半径示意图,按下全站仪POWER键启动仪器,瞄准基准方向点,锁定仪器,按OSET/TRK键两下,角度HR归零,松开目镜转动锁定键,轻松转动目镜几图,按MODE键一下,进入距离测量模式,按V%键,选择距离测量类型,松开仪器转动锁定键,转动仪器,通过目镜上的瞄准器,大致对准目标点,锁定仪器,通过角度微调螺旋,精确定位目标点,通过目镜照准目标点的棱镜,听到响声观察屏幕,按HOLD/MEAS键自动计算出目标点到仪器的距离L1,同时自动显示出目标点与基准方向点的角度;在筒壁上爬模导轨5内边缘挑出有机玻璃测量尺3,开启激光垂准仪2将激光投至有机玻璃测量尺3上,旋转仪器360度,其光斑在接收测量尺3上的运行轨迹为一个小圆形,取其圆心对应的刻度作为测量导轨半径的依据,基准点7的数值加上测量尺3读数L2即为筒壁内半径读数(即R=L1+L2),如果R与R相等,则半径准确,如果R与R不相等,则需调整爬模导轨5斜率使R与R相等,用同样方法测量完该节筒壁所有N个爬模导轨5的半径,则该节筒壁的半径就确定了,也用相同的方法测定每节筒壁的半径,则整个冷却塔风筒的半径就确定了。根据筒壁内半径和筒壁厚度即可控制筒壁外半径。筒壁外半径为R=R+H,H为筒壁厚度。
参照图4是有机玻璃测量尺3详图,尺长2m,宽20cm,前端是格网,接收和调整激光光斑,后面有刻度,可直接读取读数。
通过以上的说明,本领域的技术人员理解了本发明的实质特征,并且可在此基础上对本发明进行修改、完善、或改进,然而,这样做都将落入本发明的保护范围。

Claims (2)

1.冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法,其特征在于按以下步骤进行:(1)、以冷却塔及大型构筑物筒体中心在水平面上的投影为圆心,根据爬模导轨数量N,将圆分成N等份,用墨线和红油漆在底板上作标记即为辐射线,且每条爬模导轨中心线对应一条辐射线;(2)、在圆心架设全站仪沿辐射线测量出每节爬模导轨半径的临时控制基准点,作为垂准仪架设的临时基准点;(3)、将垂准仪安放在底板的临时基准点上,在筒壁上爬模导轨内边缘挑出有机玻璃测量尺,利用垂准仪的激光光斑在有机玻璃测量尺上进行读数,临时基准点的数值L1加上测量尺读数L2即为筒壁内半径R=L1+L2,检查R与R是否相等,R为设计的筒壁内半径,如有偏差则通过爬模导轨进行调整,直至R与R相等为止,则该节筒体半径已确定,用相同的方法确定每节筒体半径;根据筒壁内半径和筒壁厚度之和为筒壁外半径来控制冷却塔及大型构筑物筒体混凝土半径。
2.根据权利要求1所述的冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法,其特征在于:所述爬模导轨数量N按以下方法计算得到:依据冷却塔风筒或大型构筑物筒体底部最大周长和喉部最小周长及爬模平台板的尺寸确定爬模导轨数量,保证爬模平台板在冷却塔风筒及大型构筑物筒体的底部能够连接,在筒体喉部能够顺利通过,底部周长除以平台板拉伸至极限位置的长度得一整数N1,喉部周长除以平台板收缩至极限位置的长度得一整数N2,从N1和N2中选出最大数为爬模导轨数N。
CN201110256497.XA 2011-09-01 2011-09-01 冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法 Active CN102419155B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110256497.XA CN102419155B (zh) 2011-09-01 2011-09-01 冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110256497.XA CN102419155B (zh) 2011-09-01 2011-09-01 冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法

Publications (2)

Publication Number Publication Date
CN102419155A true CN102419155A (zh) 2012-04-18
CN102419155B CN102419155B (zh) 2014-05-07

Family

ID=45943684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110256497.XA Active CN102419155B (zh) 2011-09-01 2011-09-01 冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法

Country Status (1)

Country Link
CN (1) CN102419155B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103217149A (zh) * 2013-03-11 2013-07-24 浙江省建工集团有限责任公司 一种双曲线钢筋混凝土冷却塔筒壁施工测量方法
CN103644891A (zh) * 2013-11-26 2014-03-19 中冶天工集团有限公司 超高柱子顶部标高的测量方法
CN104973810A (zh) * 2015-06-24 2015-10-14 天津二十冶建设有限公司 一种双膛石灰窑窑膛砌筑测量定位方法
CN107860376A (zh) * 2017-11-07 2018-03-30 中国化学工程第三建设有限公司 一种大型间冷塔锥体段的三角架的测量定位方法
CN112556673A (zh) * 2020-12-07 2021-03-26 北京市测绘设计研究院 超高层建筑的轴线竖向传递测量方法及自动接收装置
CN114577128A (zh) * 2022-05-09 2022-06-03 广东电网有限责任公司佛山供电局 一种线缆验收方法和装置
CN118274771A (zh) * 2024-06-04 2024-07-02 江苏双辉环境科技有限公司 一种冷却塔厚度检测设备

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2040128U (zh) * 1988-01-11 1989-06-28 孙国栋 混凝土建筑物用分段滑模装置
CN101864818A (zh) * 2009-04-14 2010-10-20 武汉建工股份有限公司 现浇倾斜悬弧混凝土剪力墙施工方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2040128U (zh) * 1988-01-11 1989-06-28 孙国栋 混凝土建筑物用分段滑模装置
CN101864818A (zh) * 2009-04-14 2010-10-20 武汉建工股份有限公司 现浇倾斜悬弧混凝土剪力墙施工方法

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
《工业建筑》 19841031 黄明生 80米钢筋混凝土烟囱液压滑模施工的纠偏 第二页右侧第三段,第五页左侧最后一段以及图22 1-2 , 第10期 *
张正禄: "《工程测量学》", 31 July 2002, 武汉大学出版社 *
徐剑佩: "大型冷却塔筒体施工新技术的应用", 《浙江电力》 *
李亮: "冷却塔筒壁混凝土外观的施工过程控制", 《安徽建筑》 *
贺跃光,高成发: "《工程测量》", 28 February 2007, 北京市:人民交通出版社 *
黄明生: "80米钢筋混凝土烟囱液压滑模施工的纠偏", 《工业建筑》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103217149A (zh) * 2013-03-11 2013-07-24 浙江省建工集团有限责任公司 一种双曲线钢筋混凝土冷却塔筒壁施工测量方法
CN103217149B (zh) * 2013-03-11 2016-02-24 浙江省建工集团有限责任公司 一种双曲线钢筋混凝土冷却塔筒壁施工测量方法
CN103644891A (zh) * 2013-11-26 2014-03-19 中冶天工集团有限公司 超高柱子顶部标高的测量方法
CN103644891B (zh) * 2013-11-26 2016-08-17 中冶天工集团有限公司 超高柱子顶部标高的测量方法
CN104973810A (zh) * 2015-06-24 2015-10-14 天津二十冶建设有限公司 一种双膛石灰窑窑膛砌筑测量定位方法
CN104973810B (zh) * 2015-06-24 2017-01-18 中冶天工集团天津有限公司 一种双膛石灰窑窑膛砌筑测量定位方法
CN107860376A (zh) * 2017-11-07 2018-03-30 中国化学工程第三建设有限公司 一种大型间冷塔锥体段的三角架的测量定位方法
CN112556673A (zh) * 2020-12-07 2021-03-26 北京市测绘设计研究院 超高层建筑的轴线竖向传递测量方法及自动接收装置
CN114577128A (zh) * 2022-05-09 2022-06-03 广东电网有限责任公司佛山供电局 一种线缆验收方法和装置
CN114577128B (zh) * 2022-05-09 2022-07-19 广东电网有限责任公司佛山供电局 一种线缆验收方法和装置
CN118274771A (zh) * 2024-06-04 2024-07-02 江苏双辉环境科技有限公司 一种冷却塔厚度检测设备
CN118274771B (zh) * 2024-06-04 2024-10-18 江苏双辉环境科技有限公司 一种冷却塔厚度检测设备

Also Published As

Publication number Publication date
CN102419155B (zh) 2014-05-07

Similar Documents

Publication Publication Date Title
CN102419155B (zh) 冷却塔及大型构筑物筒体混凝土半径的施工测量控制方法
CN108680103B (zh) 一种斜拉桥超高桥塔墩锚固结构快速精密定位测量方法
CN205333053U (zh) 一种自动扶正式水准仪测量标尺
CN105698776A (zh) 一种二维基准垂直传递装置及其测量方法
CN103308030A (zh) 超高层标高高精度自动传递工艺方法
CN103115610A (zh) 适用于复合水准仪的水准测量方法
CN107130809A (zh) 一种超高层核心筒墙体施工测量定位方法及系统
CN105735145A (zh) 一种桥梁转体施工精确对中控制施工方法及其结构
CN103217149A (zh) 一种双曲线钢筋混凝土冷却塔筒壁施工测量方法
CN204881624U (zh) 超高层建筑核心筒模板定位测量控制装置
CN103741945A (zh) 超高层建筑核心筒轴网外控施工方法
CN104164984B (zh) 一种带肋的大型冷却塔筒壁空间几何定位方法
CN114964189A (zh) 一种支撑胎架和桁架的安装测量方法
CN115387221A (zh) 高海拔地区高墩线型控制方法
CN101464146B (zh) 将地面水准点高程精确传递到高架桥上的测量方法及其装置
CN102435179A (zh) 核岛内部微网基准点的建立方法及其测量观测平台
CN114136226A (zh) 超高层建筑竖向压缩变形的高精度测量方法
CN110631550B (zh) 一种围堰封底倾斜度的测量方法及测量装置
CN206971771U (zh) 一种超高层核心筒墙体施工测量定位系统
CN203053430U (zh) 激光电子全站仪照相接收装置
CN206695780U (zh) 一种建筑工程管理用测量工具
CN110411423A (zh) 应用于预制立柱定位测量装置
CN112161611B (zh) 一种海上风电导向架导向框的厂内同心度定位方法
CN109596093B (zh) 用于盾构发射基座放样的测量装置及方法
CN106150479B (zh) 便捷重力式激光垂直度、孔径检测仪的使用方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221221

Address after: Room 2105, 21st Floor, Tongda Plaza, No. 111 Wenhua Avenue, Jiangxia District, Wuhan City, Hubei Province 430000

Patentee after: THE SECOND CONSTRUCTION Co.,Ltd. OF CHINA CONSTRUCTION THIRD ENGINEERING BUREAU

Patentee after: China Construction Third Engineering Bureau Group (Jiangsu) Co.,Ltd.

Patentee after: China Construction Third Engineering Bureau second construction and installation Co.,Ltd.

Patentee after: CHINA CONSTRUCTION THIRD ENGINEERING BUREAU GREEN INDUSTRY INVESTMENT Co.,Ltd.

Address before: 430074 No. 306 Lu Lu, Hongshan District, Hubei, Wuhan

Patentee before: THE SECOND CONSTRUCTION Co.,Ltd. OF CHINA CONSTRUCTION THIRD ENGINEERING BUREAU