CN102409788A - Pcm现浇钢筋混凝土大尺寸夹芯楼板及其施工工法 - Google Patents
Pcm现浇钢筋混凝土大尺寸夹芯楼板及其施工工法 Download PDFInfo
- Publication number
- CN102409788A CN102409788A CN2011102396851A CN201110239685A CN102409788A CN 102409788 A CN102409788 A CN 102409788A CN 2011102396851 A CN2011102396851 A CN 2011102396851A CN 201110239685 A CN201110239685 A CN 201110239685A CN 102409788 A CN102409788 A CN 102409788A
- Authority
- CN
- China
- Prior art keywords
- core
- floor
- reinforced concrete
- large scale
- buried pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明涉及一种PCM现浇钢筋混凝土大尺寸夹芯楼板及其施工工法,所述夹芯楼板其内间隔设置有暗梁,由芯模、上层钢筋、下层钢筋和外包混凝土组成,所述芯模为实心聚苯块,其顶面绑扎有上层钢筋、其底面绑扎有下层钢筋,并通过外包混凝土包裹形成整体。浇筑过程中内模上浮,将下层钢筋和下层钢筋通过抗浮钢丝与底部模板的龙骨绑扎。本发明所述夹芯楼板具有自重轻,抗震隔音效果好,施工过程预埋管线不受限等优点。可广泛应用于跨度和荷载较大、楼板较厚的多层和高层建筑的楼板。
Description
技术领域
本发明涉及一种楼板及其施工工法,特别是一种夹芯楼板及其施工工法。
背景技术
PCM现浇空心楼盖结构技术是国内第三代空心板结构技术,为了提高建筑净高降低建筑成本,在大跨度的车库或高层建筑中采用了现浇钢筋混凝土夹芯楼板,与传统的实心楼板相比,具有:减轻结构自重、利于抗震、提高净空、隔音效果好等主要优点。现有的芯模为矩形空心水泥箱体内模,存在空心箱体无法开槽穿管,管线只能沿梁布置问题以及外包混凝土不易流动到板底,导致板底混凝土浇捣不密实,浇筑质量难以保证等缺陷。
发明内容
本发明的目的是提供一种PCM现浇钢筋混凝土大尺寸夹芯楼板及其施工工法,要解决现有的现浇钢筋混凝土夹芯楼板预埋管线无法穿越芯模,需另行沿梁布置,板底混凝土浇筑质量无法保证的技术问题。
为实现上述目的,本发明采用如下技术方案:
一种PCM现浇钢筋混凝土大尺寸夹芯楼板,其内间隔设置有暗梁,由芯模、上层钢筋、下层钢筋和外包混凝土组成,所述芯模为实心聚苯块,其顶面绑扎有上层钢筋、其底面绑扎有下层钢筋,并通过外包混凝土包裹形成整体。
所述芯模包由四个侧面、四个折向本体内的折面、一个底面和一个顶面围合成的实心斗状本体,其中每个侧面均通过折面与底面连接,所述检查孔至少为1个。
所述检查孔的直径为100mm~150mm。
所述折面与底面的夹角α为30°~60°。
所述的PCM现浇钢筋混凝土大尺寸夹芯楼板的施工工法,步骤如下:
步骤一,复核框架柱轴线,并准确控制主梁轴线;
步骤二,安装夹芯楼板底部模板;
步骤三,在底部模板上对芯模、下层水电管线预埋管和暗梁预留孔放线定位;
步骤四,按事先放好的边线进行绑扎下层钢筋和安装暗梁,并检查;
步骤五,检查合格后将下层钢筋通过抗浮钢丝A与底部模板的龙骨绑扎,并在下层钢筋底面放置钢筋垫块;
步骤六,下层水电管线预埋管安装;
步骤七,按照步骤三放线位置进行芯模的安装;
步骤八,按照步骤三放线位置进行下层水电管线预埋管安装;
步骤九,在芯模顶面安装上层钢筋;
步骤十,将上层钢筋通过抗浮钢丝B与底部模板的龙骨绑扎;
步骤十一,浇筑外包混凝土;
步骤十二,外包混凝土养护。
所述步骤五中,抗浮钢丝A的间距不大于1200mm。
所述步骤六中,下层水电管线预埋管与芯模相交的采用钢管,预埋管与预埋管的交叉点设置在芯模的检查孔之间的实体上。
所述步骤七中,芯模的安装过程中遇下层水电管线预埋管,现场采用热风枪在内模块材上开槽,让出下层水电管线预埋管的位置。
所述步骤十中,抗浮钢丝B穿过芯模的中心位置处的检查孔。
所述步骤十一中浇筑混凝土采用“赶浆法”,沿芯模纵向单侧浇筑混凝土,在暗梁部位进行振捣。
与现有技术相比本发明具有以下特点和有益效果:
混凝土楼板中间部分混凝土被PCM内模取代,与等厚度实心楼板相比楼板自重减轻了约50%。被取代的混凝土位于楼板中部,这部分混凝土对楼板抗弯没有贡献,所以夹芯楼板与同厚度实心楼板相比抗弯能力没有降低。虽然被取代的混凝土对抗剪、抗冲切有影响,但楼板抗剪、抗冲切能力通常远远大于其受到的剪力、冲切力,再加上夹芯楼板自重大幅减少,楼板内剪力、冲切力也相应减少,所以夹芯楼板抗剪、抗冲切能力仍然大于其受到的剪力、冲切力。夹芯楼盖受拉区混凝土减少,按有效受拉混凝土截面面积计算的纵向受拉钢筋配筋率增大,夹芯楼盖与同厚度实心楼盖相比裂缝减小,同时也减轻了柱和基础的荷载。
本发明中的芯模为实心聚苯内模,解决一般空心箱体因无法开槽穿管,管线只能沿梁布置问题,管线叠合的位置也可以轻松开槽,预埋管线不受限。
本发明所述芯模的侧面为45度斜立面,保证混凝土更易于流动到板下;设置多个检查孔,便于观察内模下各部位混凝土的密实情况;以上改进有效的保证了混凝土的浇筑质量。
本发明可广泛应用于跨度和荷载较大、楼板较厚的多层和高层建筑的楼板。
附图说明
下面结合附图对本发明做进一步详细的说明。
图1是夹芯楼板平面布置图。
图2是图1A-A剖视图。
图3是芯模详图。
图4是图3俯视图。
图5是图4B-B剖视图。
图6是抗浮点设置详图。
图7是本发明施工流程图。
附图标记:1-上层钢筋、2-下层钢筋、3-外包混凝土、4-芯模、4.1-侧面、4.2-底面4.3-折面、4.4-顶面、5-检查孔、6-抗浮钢丝A、7-底部模板的龙骨、8-暗梁、9-钢筋垫块、10-抗浮钢丝B、11-框架柱、12-主梁。
具体实施方式
实施例参见图1~图5所示,一种PCM现浇钢筋混凝土大尺寸夹芯楼板,其内间隔设置有暗梁8,由芯模4、上层钢筋1、下层钢筋2和外包混凝土3组成,所述芯模4为实心聚苯块,其顶面绑扎有上层钢筋1、其底面绑扎有下层钢筋2,并通过外包混凝土3包裹形成整体。所述芯模4包由四个侧面4.1、四个折向本体内的折面4.3、一个底面4.2和一个顶面4.4围合成的实心斗状本体,其中每个侧面4.1均通过折面4.3与底面4.2连接,所述检查孔5至少为1个。所述检查孔5的直径为100mm~150mm。所述折面4.3与底面4.2的夹角α为30°~60°。所述芯模平面尺寸为1000mm×1000mm。
所述的PCM现浇钢筋混凝土大尺寸夹芯楼板的施工工法,参见图6和图7,步骤如下:
步骤一,复核框架柱轴线,并准确控制主梁轴线;
步骤二,安装夹芯楼板底部模板;
步骤三,在底部模板上对芯模4、下层水电管线预埋管和暗梁预留孔放线定位;
步骤四,按事先放好的边线进行绑扎下层钢筋2和安装暗梁8,并检查;
步骤五,检查合格后将下层钢筋2通过抗浮钢丝A6与底部模板的龙骨7绑扎,并在下层钢筋2底面放置钢筋垫块9;抗浮钢丝A6的间距不大于1200mm。
步骤六,下层水电管线预埋管安装;下层水电管线预埋管与芯模相交的采用钢管,预埋管与预埋管的交叉点设置在芯模4的检查孔5之间的实体上。
步骤七,按照步骤三放线位置进行芯模4的安装;芯模4的安装过程中遇下层水电管线预埋管,现场采用热风枪在内模块材上开槽,让出下层水电管线预埋管的位置。
步骤八,按照步骤三放线位置进行下层水电管线预埋管安装;
步骤九,在芯模4顶面安装上层钢筋1;
步骤十,将上层钢筋1通过抗浮钢丝B10与底部模板的龙骨7绑扎;所述抗浮钢丝B10穿过芯模4的中心位置处的检查孔5。
步骤十一,浇筑外包混凝土3;所述步骤十一中浇筑混凝土采用“赶浆法”,沿芯模纵向单侧浇筑混凝土,在暗梁部位进行振捣。
步骤十二,外包混凝土3养护。所述混凝土养护在浇筑完12小时内加以覆盖并保湿养护,且养护时间不少于7天。
Claims (10)
1.一种PCM现浇钢筋混凝土大尺寸夹芯楼板,其内间隔设置有暗梁(8),由芯模(4)、上层钢筋(1)、下层钢筋(2)和外包混凝土(3)组成,其特征在于:所述芯模(4)为实心聚苯块,其顶面绑扎有上层钢筋(1)、其底面绑扎有下层钢筋(2),并通过外包混凝土(3)包裹形成整体。
2.根据权利要求1所述的PCM现浇钢筋混凝土大尺寸夹芯楼板,其特征在于:所述芯模(4)包由四个侧面(4.1)、四个折向本体内的折面(4.3)、一个底面(4.2)和一个顶面(4.4)围合成的实心斗状本体,其中每个侧面(4.1)均通过折面(4.3)与底面(4.2)连接,所述检查孔(5)至少为1个。
3.根据权利要求1所述的PCM现浇钢筋混凝土大尺寸夹芯楼板,其特征在于:所述检查孔(5)的直径为100mm~150mm。
4.根据权利要求1所述的PCM现浇钢筋混凝土大尺寸夹芯楼板,其特征在于:所述折面(4.3)与底面(4.2)的夹角α为30°~60°。
5.根据权利要求1~4任意一项所述的PCM现浇钢筋混凝土大尺寸夹芯楼板的施工工法,其特征在于:步骤如下:
步骤一,复核框架柱(11)的轴线,并准确控制主梁(12)的轴线;
步骤二,安装夹芯楼板底部模板;
步骤三,在底部模板上对芯模(4)、下层水电管线预埋管和暗梁预留孔放线定位;
步骤四,按事先放好的边线进行绑扎下层钢筋(2)和安装暗梁(8),并检查;
步骤五,检查合格后将下层钢筋(2)通过抗浮钢丝A(6)与底部模板的龙骨(7)绑扎,并在下层钢筋(2)底面放置钢筋垫块(9);
步骤六,下层水电管线预埋管安装;
步骤七,按照步骤三放线位置进行芯模(4)的安装;
步骤八,按照步骤三放线位置进行下层水电管线预埋管安装;
步骤九,在芯模(4)顶面安装上层钢筋(1);
步骤十,将上层钢筋(1)通过抗浮钢丝B(10)与底部模板的龙骨(7)绑扎;
步骤十一,浇筑外包混凝土(3);
步骤十二,外包混凝土(3)养护。
6.根据权利要求1~5所述的PCM现浇钢筋混凝土大尺寸夹芯楼板的施工工法,其特征在于:所述步骤五中,抗浮钢丝A(6)的间距不大于1200mm。
7.根据权利要求1~5所述的PCM现浇钢筋混凝土大尺寸夹芯楼板的施工工法,其特征在于:所述步骤六中,下层水电管线预埋管与芯模相交的采用钢管,预埋管与预埋管的交叉点设置在芯模(4)的检查孔(5)之间的实体上。
8.根据权利要求1~5所述的PCM现浇钢筋混凝土大尺寸夹芯楼板的施工工法,其特征在于:所述步骤七中,芯模(4)的安装过程中遇下层水电管线预埋管,现场采用热风枪在内模块材上开槽,让出下层水电管线预埋管的位置。
9.根据权利要求1~5所述的PCM现浇钢筋混凝土大尺寸夹芯楼板的施工工法,其特征在于:所述步骤十中,抗浮钢丝B(10)穿过芯模(4)的中心位置处的检查孔(5)。
10.根据权利要求1~5所述的PCM现浇钢筋混凝土大尺寸夹芯楼板的施工工法,其特征在于:所述步骤十一中浇筑混凝土采用“赶浆法”,沿芯模纵向单侧浇筑混凝土,在暗梁部位进行振捣。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102396851A CN102409788A (zh) | 2011-08-19 | 2011-08-19 | Pcm现浇钢筋混凝土大尺寸夹芯楼板及其施工工法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102396851A CN102409788A (zh) | 2011-08-19 | 2011-08-19 | Pcm现浇钢筋混凝土大尺寸夹芯楼板及其施工工法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102409788A true CN102409788A (zh) | 2012-04-11 |
Family
ID=45912098
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102396851A Pending CN102409788A (zh) | 2011-08-19 | 2011-08-19 | Pcm现浇钢筋混凝土大尺寸夹芯楼板及其施工工法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102409788A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102979233A (zh) * | 2012-09-06 | 2013-03-20 | 山东聊建集团有限公司 | 车库顶板结构及施工方法和砼结构空腔内膜 |
CN103243849A (zh) * | 2013-05-07 | 2013-08-14 | 中国十七冶集团有限公司 | 现浇空心楼板埋入式内模安装方法 |
DE102014100448A1 (de) | 2014-01-16 | 2015-07-16 | Anton Falkeis | Fassadenelemente mit Latentwärmespeicher |
CN105908885A (zh) * | 2016-06-27 | 2016-08-31 | 青岛建集团有限公司 | 一种大幅面多孔洞轻质芯模及其施工方法 |
CN111794447A (zh) * | 2020-06-19 | 2020-10-20 | 中国十七冶集团有限公司 | 固定钢筋保护层抗浮构件及其施工方法和拆卸方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1584766A2 (en) * | 2004-04-01 | 2005-10-12 | Assounisol S.r.l. | Prefabricated modular element for lightening floors with lattice beams |
CN1975032A (zh) * | 2005-11-30 | 2007-06-06 | 邱则有 | 一种现浇砼空心板 |
CN201074373Y (zh) * | 2007-08-21 | 2008-06-18 | 张香梨 | 具有加高型垫块的pcm空心楼盖结构 |
CN201103180Y (zh) * | 2007-07-09 | 2008-08-20 | 张香梨 | Pcm现浇钢筋砼双向空心内模 |
CN201158891Y (zh) * | 2007-12-07 | 2008-12-03 | 张延卫 | Pcm带硬质加强层的轻质发泡材料内模 |
CN102071808A (zh) * | 2011-01-13 | 2011-05-25 | 中建四局第三建筑工程有限公司 | 一种芯模管抗浮定位方法及结构 |
CN201883585U (zh) * | 2010-12-24 | 2011-06-29 | 中国华冶科工集团有限公司 | 现浇混凝土空心楼板 |
-
2011
- 2011-08-19 CN CN2011102396851A patent/CN102409788A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1584766A2 (en) * | 2004-04-01 | 2005-10-12 | Assounisol S.r.l. | Prefabricated modular element for lightening floors with lattice beams |
CN1975032A (zh) * | 2005-11-30 | 2007-06-06 | 邱则有 | 一种现浇砼空心板 |
CN201103180Y (zh) * | 2007-07-09 | 2008-08-20 | 张香梨 | Pcm现浇钢筋砼双向空心内模 |
CN201074373Y (zh) * | 2007-08-21 | 2008-06-18 | 张香梨 | 具有加高型垫块的pcm空心楼盖结构 |
CN201158891Y (zh) * | 2007-12-07 | 2008-12-03 | 张延卫 | Pcm带硬质加强层的轻质发泡材料内模 |
CN201883585U (zh) * | 2010-12-24 | 2011-06-29 | 中国华冶科工集团有限公司 | 现浇混凝土空心楼板 |
CN102071808A (zh) * | 2011-01-13 | 2011-05-25 | 中建四局第三建筑工程有限公司 | 一种芯模管抗浮定位方法及结构 |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102979233A (zh) * | 2012-09-06 | 2013-03-20 | 山东聊建集团有限公司 | 车库顶板结构及施工方法和砼结构空腔内膜 |
CN102979233B (zh) * | 2012-09-06 | 2014-12-24 | 山东聊建集团有限公司 | 车库顶板结构和砼结构空腔内膜 |
CN105839824A (zh) * | 2012-09-06 | 2016-08-10 | 山东聊建集团有限公司 | 车库顶板结构施工方法 |
CN105839824B (zh) * | 2012-09-06 | 2018-05-15 | 山东聊建集团有限公司 | 车库顶板结构施工方法 |
CN103243849A (zh) * | 2013-05-07 | 2013-08-14 | 中国十七冶集团有限公司 | 现浇空心楼板埋入式内模安装方法 |
DE102014100448A1 (de) | 2014-01-16 | 2015-07-16 | Anton Falkeis | Fassadenelemente mit Latentwärmespeicher |
EP2896898A2 (de) | 2014-01-16 | 2015-07-22 | Falkeis, Anton | Fassadenelement mit latentwärmespeicher, latentwärmespeichermodul und verfahren zum klimatisieren eines gebäudes. |
CN105908885A (zh) * | 2016-06-27 | 2016-08-31 | 青岛建集团有限公司 | 一种大幅面多孔洞轻质芯模及其施工方法 |
CN111794447A (zh) * | 2020-06-19 | 2020-10-20 | 中国十七冶集团有限公司 | 固定钢筋保护层抗浮构件及其施工方法和拆卸方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11085186B2 (en) | Thermal-insulated exterior wall boards, dedicated molds and making methods thereof | |
CN106703269A (zh) | 一种带钢桁架的预应力混凝土叠合板及制作方法 | |
CN107322768A (zh) | 预制预应力保温外墙板、专用模具及其制作方法 | |
CN202081546U (zh) | 一种夹心带肋预应力混凝土叠合楼盖 | |
CN104762871A (zh) | 一种预应力混凝土-钢槽梁结合梁连续梁桥 | |
CN108104284B (zh) | 剪力墙钢臂嵌入楼板的墙板连接结构及装配方法 | |
CN104895230A (zh) | 一种预制叠合楼板的后浇带及其施工方法 | |
CN106988477A (zh) | 装配式双向预应力空心板及其制作方法 | |
CN102409788A (zh) | Pcm现浇钢筋混凝土大尺寸夹芯楼板及其施工工法 | |
CN206352357U (zh) | 一种带钢桁架的预应力混凝土叠合板 | |
CN105649249A (zh) | 内置空心圆钢管的压型钢板混凝土双向组合楼板 | |
CN112324037A (zh) | 一种钢筋桁架预应力混凝土叠合板及制作方法 | |
CN113653235A (zh) | 叠合板、叠合板与组合梁的连接结构及施工方法 | |
CN110005109A (zh) | 一种开槽式预应力混凝土叠合板 | |
CN103195259A (zh) | 一种泡沫混凝土预制板及用其加固混凝土结构的方法 | |
CN103966953A (zh) | 基于无粘结钢绞线预应力后张的大跨度混凝土梁施工方法 | |
CN114059699A (zh) | 集成桁架钢筋及预应力钢丝网的预制混凝土底板 | |
CN209353550U (zh) | 一种夹心减重叠合板 | |
CN114482400A (zh) | 一种与预制竖向构件相连的叠合梁 | |
CN207812307U (zh) | 斜拉桥主塔及钢锚梁的施工系统 | |
CN213806067U (zh) | 一种钢筋桁架预应力混凝土叠合板 | |
CN206953253U (zh) | 预制预应力保温外墙板及专用模具 | |
CN107254930A (zh) | 一种宽幅空心叠合板 | |
CN107012986A (zh) | 多层外包钢混凝土组合连梁 | |
CN205776898U (zh) | 整体装配式钢筋混凝土剪力墙结构体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120411 |