CN102409697A - Prefabricated tower and mast structure foundation - Google Patents

Prefabricated tower and mast structure foundation Download PDF

Info

Publication number
CN102409697A
CN102409697A CN2011102833321A CN201110283332A CN102409697A CN 102409697 A CN102409697 A CN 102409697A CN 2011102833321 A CN2011102833321 A CN 2011102833321A CN 201110283332 A CN201110283332 A CN 201110283332A CN 102409697 A CN102409697 A CN 102409697A
Authority
CN
China
Prior art keywords
inner core
prefabricated
foundation
counterweight ring
mast structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102833321A
Other languages
Chinese (zh)
Inventor
范力
王凯
王京
赵祥碧
尹利茹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU JIUDING GLOBAL CONSTRUCTION TECHNOLOGY GROUP Co Ltd
Original Assignee
JIANGSU JIUDING GLOBAL CONSTRUCTION TECHNOLOGY GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU JIUDING GLOBAL CONSTRUCTION TECHNOLOGY GROUP Co Ltd filed Critical JIANGSU JIUDING GLOBAL CONSTRUCTION TECHNOLOGY GROUP Co Ltd
Priority to CN2011102833321A priority Critical patent/CN102409697A/en
Publication of CN102409697A publication Critical patent/CN102409697A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a prefabricated foundation, in particular to a prefabricated tower and mast structure foundation, belonging to the technical field of construction engineering. The prefabricated tower and mast foundation comprises an inner cylinder, a bottom plate and a counterweight ring, and all the components are prefabricated in a factory and assembled into a whole at the construction field, wherein the inner cylinder is placed on the bottom plate, and the counterweight ring is sleeved outside the inner cylinder and self-locked on the inner cylinder by self weight to form a whole foundation. The prefabricated foundation is assembled without the aid of pre-stressed tendons or bolts and other traditional assembling means, but is assembled by a gravity self-locking effect generated by the self weights of the components, therefore, installation of the prefabricated foundation is more convenient, quicker and lower in cost compared with the traditional prefabricated foundations, and the foundation can be conveniently disassembled to realize repeated use.

Description

Prefabricated assembled tower mast structure basis
Technical field
The present invention relates to a kind of prefabricated assembled basis, particularly relate to a kind of prefabricated assembled tower mast structure basis, belong to construction engineering technical field.
Background technology
Along with the Chinese society expanding economy, in construction project, all kinds of tower mast structures as: the application of tall and slender structures such as communications tower, high lamp stand, billboard constantly increases.The main cast-in-situ steel reinforced concrete base form that adopts in the basis of present domestic tower mast structure.The cast-in-situ steel reinforced concrete basis needs formwork, bundle muscle, fluid concrete at the construction field (site), and can install portion's structure after needing the base concrete maintenance to reach design strength.The cast-in-situ concrete foundation construction cycle is long, and is big to the job site ambient influnence, and the basis can only disposablely use, and is prone to produce building waste, causes the wasting of resources, do not meet the requirement of environmental protection and civilized construction.Therefore, need the prefabricated basis that exploitation is suitable for to tower mast structure, with satisfy the special construction environment as: construction can not influence scene and surrounding enviroment and special construction condition like the requirement of duration anxiety in the urban district.Prefabricated basis is prefabricated in the factory, and quality is guaranteed; Generally do not need wet trade, quick construction at the construction field (site); Prefabricated basis can also be reused, and meets the requirement of environmental protection and civilized construction.But when prefabricated basis was used for bigger structure, the basic scale of construction was huge, if integral manufacturing is then made, transports, installs all inconvenient.Therefore, the necessary precast block in large scale prefabricated basis is assembled into integral body again to the job site.The erection method on present prefabricated basis mainly contains: back pouring concrete assembly unit, presstressed reinforcing steel assembly unit, bolt assembly unit.Back pouring concrete assembly unit needs the cast on-site concrete, can cause claim for eot; Presstressed reinforcing steel assembly unit and bolt assembly unit meeting make basic mounting technique complicacy and cause basic cost to rise.Therefore seek the basic piecemeal of advantages of simple and a key and the difficult problem that erection method is prefabricated assembled basis.
Summary of the invention
The objective of the invention is for overcoming the weak point of above-mentioned prior art, a kind of prefabricated assembled tower mast structure basis is provided, this prefabricated assembled tower mast basis includes inner core, base plate and counterweight ring, and each member is assembled into integral body at the construction field (site) by prefabrication.Inner core is shelved on the base plate; The side dependence outer tube of counterweight ring set is self-locking on the inner core, forms base integral.The assembly unit on this prefabricated basis need be by traditional assembly unit means such as presstressed reinforcing steel or bolts; But " the gravity self-locking effect " of leaning on member dead weight to produce realizes basic assembly unit; Therefore the more traditional prefabricated basis of the installation on this prefabricated basis is more convenient, quick; Expense is lower, and the basis can be dismantled the realization repeated use easily.
The present invention realizes with following technical scheme: a kind of prefabricated assembled tower mast structure basis; It includes inner core (1), base plate (2) and counterweight ring (3); Inner core is seated on the base plate; It is characterized in that: described inner tank theca is up-small and down-big truncated cone, is with some counterweight rings on the inner tank theca from top to bottom; The inwall of described counterweight ring is up-small and down-big truncated cone, and the counterweight ring relies on deadweight to form integral body from locking on the inner core with inner core, between each counterweight ring and between counterweight ring and the base plate vertical gap is arranged.
Described inner core is a hollow shape, the sealing of inner core end face, and there is circular open the bottom surface, and connecting bolt is arranged at the inner core top, and inner core is fixed through connecting bolt and top tower mast structure.
The shear key that truncated cone is arranged in the middle of the described plate upper surface.
The invention has the beneficial effects as follows: the assembly unit on this prefabricated assembled basis does not need cast-in-place concrete, need be by traditional assembly unit means such as presstressed reinforcing steel or bolts yet, but " the gravity self-locking effect " that rely on member dead weight to produce realizes the assembly unit on basis.The assembly unit simple and fast on basis, cost is low, and is safe and reliable.Basic requirement to different loading conditions and different ground situation can realize through the quantity of adjustment counterweight ring and the size of counterweight ring, helps realizing the standardization and the modularization production on prefabricated basis.The basis convenient disassembly, the situation that basic presstressed reinforcing steel that can not occur being prone in traditional erection method or bolt rust are waited indefinitely and be difficult to dismantle, the basis is reusable, meets the building requirements of environmental protection.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the present invention is explained further details:
Fig. 1 is a structure sectional view of the present invention:
Fig. 2 is the inner core floor map:
Fig. 3 is the base plate plane sketch map:
Fig. 4 is a counterweight plane of a loop sketch map:
Among the figure, 1, inner core, 2, base plate, 3, the counterweight ring, 4, bolt, 5, shear key.
The specific embodiment
As shown in the figure: a kind of prefabricated assembled tower mast structure basis, it includes inner core 1, base plate 2 and counterweight ring 3, and inner core is seated on the base plate 2, and described inner core 1 outer wall is up-small and down-big truncated cone, is with some counterweight rings 3 on the inner tank theca from top to bottom; The inwall of described counterweight ring is up-small and down-big truncated cone, and the counterweight ring relies on deadweight to form integral body from locking on the inner core with inner core, between each counterweight ring and between counterweight ring and the base plate vertical gap is arranged.
Described inner core 1 is a hollow shape, the sealing of inner core end face, and there is circular open the bottom surface, and connecting bolt 4 is arranged at the inner core top, and inner core is fixed through connecting bolt and top tower mast structure.
The shear key 5 that truncated cone is arranged in the middle of described base plate 2 upper surfaces.
Described each member can be made in the factory for prefabrication, and inner core, base plate and counterweight ring can adopt Reinforced Concrete Materials to make, and wherein inner core also can adopt steel to make, and steel surface need carry out preservative treatment.
The course of work: according to basic part size excavation pit; The bed course levelling is done in the foundation ditch bottom, puts into base plate; Sit slurry back mounting inner cylinder on the base plate, the shear key interlock that inner core bottom surface circular hole and base plate are protruding; The counterweight ring is installed on inner core; Pit backfill soil and compacting; The top tower mast structure is installed.This basic part can be dismantled repeated use, and disassembly sequence and erection sequence are opposite.

Claims (3)

1. a prefabricated assembled tower mast structure is basic; It includes inner core (1), base plate (2) and counterweight ring (3); Inner core is seated on the base plate (2), it is characterized in that: described inner core (1) outer wall is up-small and down-big truncated cone, is with some counterweight rings (3) on the inner tank theca from top to bottom; The inwall of described counterweight ring is up-small and down-big truncated cone, and the counterweight ring relies on deadweight to form integral body from locking on the inner core with inner core, between each counterweight ring and between counterweight ring and the base plate vertical gap is arranged.
2. a kind of prefabricated assembled tower mast structure according to claim 1 basis; It is characterized in that: described inner core (1) is hollow shape, the sealing of inner core end face, and there is circular open the bottom surface; Connecting bolt (4) is arranged at the inner core top, and inner core is fixed through connecting bolt and top tower mast structure.
3. a kind of prefabricated assembled tower mast structure according to claim 1 basis is characterized in that: the shear key (5) that truncated cone is arranged in the middle of described base plate (2) upper surface.
CN2011102833321A 2011-09-15 2011-09-15 Prefabricated tower and mast structure foundation Pending CN102409697A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102833321A CN102409697A (en) 2011-09-15 2011-09-15 Prefabricated tower and mast structure foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102833321A CN102409697A (en) 2011-09-15 2011-09-15 Prefabricated tower and mast structure foundation

Publications (1)

Publication Number Publication Date
CN102409697A true CN102409697A (en) 2012-04-11

Family

ID=45912016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102833321A Pending CN102409697A (en) 2011-09-15 2011-09-15 Prefabricated tower and mast structure foundation

Country Status (1)

Country Link
CN (1) CN102409697A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877483A (en) * 2012-09-11 2013-01-16 天津大学 Foundation structure capable of being prefabricated and assembled and construction method thereof
CN103147454A (en) * 2013-03-01 2013-06-12 江苏九鼎环球建设科技集团有限公司 Pre-fabricated foundation structure of steel structure factory building
CN105971004A (en) * 2016-06-30 2016-09-28 三重型能源装备有限公司 Offshore support foundation and fan system
CN106907045A (en) * 2017-04-25 2017-06-30 周俊麟 A kind of gravity type ocean anemometer tower
CN107724407A (en) * 2017-10-24 2018-02-23 江苏建研建设工程质量安全鉴定有限公司 A kind of concrete stepped footing module and its joining method
CN108396764A (en) * 2018-04-28 2018-08-14 广东电网有限责任公司 Stringing pole prefabricated foundation base and stringing pole assembly
CN112878355A (en) * 2021-01-25 2021-06-01 北京天罡星机械设备租赁有限公司 Tower crane foundation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101255700A (en) * 2008-01-22 2008-09-03 赵正义 Vertical combined novel foundation of mast mechanical equipment
CN101539096A (en) * 2008-03-18 2009-09-23 歌美飒创新技术公司 Foundation for a wind turbine
CN201459752U (en) * 2009-06-29 2010-05-12 河南省电力公司开封供电公司 Electric pole prefabricated foundation
CN201746861U (en) * 2010-07-29 2011-02-16 吴春英 Fibre concrete protection shell
CN201794312U (en) * 2010-09-28 2011-04-13 香港华艺设计顾问(深圳)有限公司 Column foot positioning device for precast concrete column
CN102144091A (en) * 2008-09-05 2011-08-03 马克斯·博格建筑两合公司 Offshore station, foundation for an offshore station, and method for building an offshore station

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101255700A (en) * 2008-01-22 2008-09-03 赵正义 Vertical combined novel foundation of mast mechanical equipment
CN101539096A (en) * 2008-03-18 2009-09-23 歌美飒创新技术公司 Foundation for a wind turbine
CN102144091A (en) * 2008-09-05 2011-08-03 马克斯·博格建筑两合公司 Offshore station, foundation for an offshore station, and method for building an offshore station
CN201459752U (en) * 2009-06-29 2010-05-12 河南省电力公司开封供电公司 Electric pole prefabricated foundation
CN201746861U (en) * 2010-07-29 2011-02-16 吴春英 Fibre concrete protection shell
CN201794312U (en) * 2010-09-28 2011-04-13 香港华艺设计顾问(深圳)有限公司 Column foot positioning device for precast concrete column

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中国建筑标准涉及研究院组织编: "《国家建筑标准设计图集.多、高层民用建筑钢结构节点构造详图》", 31 March 2009 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877483A (en) * 2012-09-11 2013-01-16 天津大学 Foundation structure capable of being prefabricated and assembled and construction method thereof
CN103147454A (en) * 2013-03-01 2013-06-12 江苏九鼎环球建设科技集团有限公司 Pre-fabricated foundation structure of steel structure factory building
CN105971004A (en) * 2016-06-30 2016-09-28 三重型能源装备有限公司 Offshore support foundation and fan system
CN106907045A (en) * 2017-04-25 2017-06-30 周俊麟 A kind of gravity type ocean anemometer tower
CN107724407A (en) * 2017-10-24 2018-02-23 江苏建研建设工程质量安全鉴定有限公司 A kind of concrete stepped footing module and its joining method
CN108396764A (en) * 2018-04-28 2018-08-14 广东电网有限责任公司 Stringing pole prefabricated foundation base and stringing pole assembly
CN108396764B (en) * 2018-04-28 2024-02-13 广东电网有限责任公司 Wire pole prefabricated foundation seat and wire pole assembly
CN112878355A (en) * 2021-01-25 2021-06-01 北京天罡星机械设备租赁有限公司 Tower crane foundation

Similar Documents

Publication Publication Date Title
CN102409697A (en) Prefabricated tower and mast structure foundation
CN108643221B (en) Offshore wind power assembled bearing platform foundation and construction method thereof
CN205152976U (en) Marine precast concrete cushion cap wind turbine foundation
CN100595395C (en) Static pressure pile process for construction of existing building basement
CN103114604B (en) Prestressed concrete tubular type wind generating set foundation
WO2010121519A1 (en) Inner support pile for supporting sinking well structure during construction
CN102400469A (en) Secant pile drum type foundation and construction method thereof
CN102864943A (en) Brick and concrete reinforcement structure for shock insulation support and mounting and underpinning method thereof
CN113338451A (en) Assembly type structure adaptive to deformed steel pipe column and construction method thereof
CN202227362U (en) Prefabricated assembly type tower mast structural foundation
CN105714678B (en) A kind of combined type gravity anchorage
CN102704505A (en) Onshore wind generating set foundation
CN104878786A (en) Inclined-straight alternating group piles-soil-structure interaction experiment model
CN110593303A (en) Heat distribution pipeline prefabricated reinforced concrete fixed buttress and construction method
CN112575789A (en) Diagonal space truss foundation pit inner support system
CN111197319A (en) Multidirectional prestress prefabricated assembled beam slab foundation of wind power generation tower
CN203782738U (en) Prefabricated type communication base station foundation
CN2921109Y (en) Mast type machinery equipment combined foundation
CN108532625A (en) A kind of foundation of wind-driven generator unit
CN205046569U (en) Annular wind -powered electricity generation foundation structure based on shaping of two ripple steel cylinder
CN211229781U (en) Novel prefabricated hollow enclosure
CN210946874U (en) Heat distribution pipeline prefabricated reinforced concrete fixed buttress
CN215594097U (en) Fan foundation reinforcing structure
CN206815366U (en) A kind of prefabricated assembled basis
CN205557548U (en) Transmission line is from weight formula steel pipe pile foundation of pole setting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120411