CN102383600A - 一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法 - Google Patents

一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法 Download PDF

Info

Publication number
CN102383600A
CN102383600A CN201110377473XA CN201110377473A CN102383600A CN 102383600 A CN102383600 A CN 102383600A CN 201110377473X A CN201110377473X A CN 201110377473XA CN 201110377473 A CN201110377473 A CN 201110377473A CN 102383600 A CN102383600 A CN 102383600A
Authority
CN
China
Prior art keywords
tower crane
roofing
goes out
construction method
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201110377473XA
Other languages
English (en)
Inventor
王超华
宋连兴
李呈蔚
蔡鸣
李振明
常兆林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN HOUSING GROUP CONSTRUCTION ENGINEERING CONTRACTION Co Ltd
Original Assignee
TIANJIN HOUSING GROUP CONSTRUCTION ENGINEERING CONTRACTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN HOUSING GROUP CONSTRUCTION ENGINEERING CONTRACTION Co Ltd filed Critical TIANJIN HOUSING GROUP CONSTRUCTION ENGINEERING CONTRACTION Co Ltd
Priority to CN201110377473XA priority Critical patent/CN102383600A/zh
Publication of CN102383600A publication Critical patent/CN102383600A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

本发明公开了一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法,它包括以下步骤:(1)首先在塔吊出屋面洞口的四侧分别砌筑四道墙,其中先砌左右两道墙并使左右两道墙高度不同,然后顺左右两道墙的高差砌筑前后两道墙使前后两道墙的顶面形成坡面;(2)在塔吊出屋面洞口内预留的上层楼板钢筋上间隔铺设多条跳板,多条跳板与左右两道墙平行铺设;(3)在每条跳板上间隔安装多个制备好的木方;(4)在四道墙的顶部以及木方顶部支撑铺设竹夹板形成坡面;(5)在所述的竹夹板顶部覆盖彩条布,然后在彩条布上压重物。采用本发明方法操作方便、成本低、安全系数高、防雨适用性强。

Description

一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法
技术领域
本发明涉及一种洞口封闭施工方法,尤其涉及一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法。
背景技术
许多地区夏季施工面临雨多、风大、高温等不利环境因素的影响,并且直接危及生产安全,给企业带来无法估量的损失。因此科学合理组织施工,采取安全技术措施,积极应对雨期施工面临的各种危险状况,对提高抗风险能力、保障企业生产安全,具有重大意义。编制施工组织设计时充分考虑雨期施工的特点,将不宜在雨季施工的工程提前或延后安排,根据天气合理搞好室内外作业安排,风雨天气尽量安排在室内施工作业,搞好工序穿插,提高工效和施工速度,遇到较大的暴风雨天气应停止施工。在雨季对屋面的沉降后浇带、洞口、塔吊出屋面位置、采光天窗等应进行封闭或围护,防止雨水通过这些洞口进入地下室或室内。而目前对于塔吊出屋面位置洞口的临时封闭没有有效的施工办法。
发明内容
本发明的目的在于克服现有技术的不足,提供一种操作方便、成本低、适用性强,可以防止雨水从塔吊出屋面洞口进入室内的一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法。
本发明的一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法,它包括以下步骤:
(1)首先在塔吊出屋面洞口的四侧分别砌筑四道墙,其中先砌左右两道墙并使左右两道墙高度不同,然后顺左右两道墙的高差砌筑前后两道墙使前后两道墙的顶面形成坡面;
(2)在塔吊出屋面洞口内预留的上层楼板钢筋上间隔铺设多条跳板,所述的多条跳板与左右两道墙平行铺设;
(3)在每条跳板上间隔安装多个制备好的木方;
(4)在四道墙的顶部以及木方顶部支撑铺设竹夹板形成坡面;
(5)在所述的竹夹板顶部覆盖彩条布,然后在所述的彩条布上压重物。
采用本发明方法操作方便、成本低、安全系数高、防雨适用性强,尤其是塔吊出屋面洞口的四侧分别砌筑四道墙可以有效的防止屋面雨水从洞口流入室内;另外由于竹夹板形成坡面的铺设,可以使大量雨水顺坡排走,避免形成积水渗流洞内;竹夹板支撑铺设在四道墙顶部和木方顶部牢固安全;本发明方法可以有效的防止在雨季来临时,雨水从塔吊出屋面洞口进入室内,避免了施工生产安全隐患。
附图说明
图1为本发明的一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法的塔吊出屋面洞口施工立面结构示意图;
图2是图1所示的施工结构的俯视图。
具体实施方式
下面结合具体的实施例,并参照附图,对本发明做进一步的说明:
如图所示本发明的一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法,它包括以下步骤:(1)首先在塔吊出屋面洞口10的四侧分别砌筑四道墙8、11、12、14,其中先砌左右两道墙8、11,并使左右两道墙8、11高度不同,然后顺左右两道墙的高差砌筑前后两道墙12、14,使前后两道墙的顶面形成坡面;(2)在塔吊出屋面洞口10内预留的上层楼板钢筋6上间隔铺设多条跳板13,所述的多条跳板13与左右两道墙8、11平行铺设;(3)在每条跳板13上间隔安装多个制备好的木方5;(4)在所述的四道墙8、11、12、14的顶部以及木方5顶部支撑铺设竹夹板7形成坡面;(5)在所述的竹夹板7顶部覆盖彩条布3,然后在所述的彩条布3上压重物2。防止彩条布3被风吹落。
优选的在完成步骤(5)后还包括在所述的塔吊出屋面洞口10四周的四道墙最下一匹砖与屋面9交接处用砂浆4抹成圆弧状。
优选的所述的塔吊出屋面洞口处竹夹板7与塔吊标准节1相交位置错逢拼接保证封闭。
实施例1
(1)首先在塔吊出屋面洞口10的四侧分别砌筑四道墙8、11、12、14,其中先砌左右相对边的两道墙8、11,并使左右相对边的两道墙8、11高度不同,然后顺左右两道墙的高差砌筑前后两道墙12、14,使前后两道墙的顶面形成坡面;(2)在塔吊出屋面洞口10内预留的上层楼板钢筋6上间隔铺设多条跳板13,所述的多条跳板13与左右两道墙8、11平行铺设;(3)在每条跳板13上间隔安装多个制备好的木方5;(4)在所述的四道墙8、11、12、14的顶部以及木方5顶部支撑铺设竹夹板7形成坡面;竹夹板7与塔吊出屋面洞口处的塔吊标准节1相交位置错逢拼接;(5)在所述的竹夹板7顶部覆盖彩条布3,然后在所述的彩条布3上压重物。(6)在所述的塔吊出屋面洞口10四周的四道墙最下一匹砖与屋面9交接处用砂浆4抹成圆弧状。
经使用:施工时正面临夏季多雨季节、采用本发明方法临时封闭的塔吊出屋面洞口,没有雨水从该洞口流入室内,整个系统牢固安全。而且本发明操作方法施工方便、成本低、安全系数高、防雨适用性强,避免了施工生产安全隐患。

Claims (3)

1.一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法,其特征在于:它包括以下步骤:
(1)首先在塔吊出屋面洞口的四侧分别砌筑四道墙,其中先砌左右两道墙并使左右两道墙高度不同,然后顺左右两道墙的高差砌筑前后两道墙使前后两道墙的顶面形成坡面;
(2)在塔吊出屋面洞口内预留的上层楼板钢筋上间隔铺设多条跳板,所述的多条跳板与左右两道墙平行铺设;
(3)在每条跳板上间隔安装多个制备好的木方;
(4)在四道墙的顶部以及木方顶部支撑铺设竹夹板形成坡面;
(5)在所述的竹夹板顶部覆盖彩条布,然后在所述的彩条布上压重物。
2.根据权利要求1所述的防止雨水从塔吊出屋面洞口进入室内的封闭施工方法,其特征在于:在完成所述的步骤(5)后,在所述的塔吊出屋面洞口四周的四道墙最下一匹砖与屋面交接处用砂浆抹成圆弧状。
3.根据权利要求1或2所述的防止雨水从塔吊出屋面洞口进入室内的封闭施工方法,其特征在于:所述的塔吊出屋面洞口处竹夹板与塔吊标准节相交位置采用错逢拼接。
CN201110377473XA 2011-11-24 2011-11-24 一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法 Pending CN102383600A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110377473XA CN102383600A (zh) 2011-11-24 2011-11-24 一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110377473XA CN102383600A (zh) 2011-11-24 2011-11-24 一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法

Publications (1)

Publication Number Publication Date
CN102383600A true CN102383600A (zh) 2012-03-21

Family

ID=45823400

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110377473XA Pending CN102383600A (zh) 2011-11-24 2011-11-24 一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法

Country Status (1)

Country Link
CN (1) CN102383600A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107034A (zh) * 2019-06-13 2019-08-09 中建四局第五建筑工程有限公司 一种塔吊穿结构防水装置及其设置方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001146825A (ja) * 2001-01-30 2001-05-29 Tookoo:Kk 換気棟構造
CN2672195Y (zh) * 2004-02-11 2005-01-19 新乡天丰钢板开发有限公司 钢结构屋面压型板洞口防水结构
CN201184022Y (zh) * 2008-04-10 2009-01-21 沈阳铝镁设计研究院 出屋面高温钢烟囱与砼屋面连接的构造
CN201209299Y (zh) * 2008-09-10 2009-03-18 新乡天丰钢板开发有限公司 一种屋面洞口安装固定结构
JP2009102799A (ja) * 2007-10-19 2009-05-14 Ueno Shoten:Kk 屋根煙突貫通部の施工方法及び屋根煙突貫通部の防水構造

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001146825A (ja) * 2001-01-30 2001-05-29 Tookoo:Kk 換気棟構造
CN2672195Y (zh) * 2004-02-11 2005-01-19 新乡天丰钢板开发有限公司 钢结构屋面压型板洞口防水结构
JP2009102799A (ja) * 2007-10-19 2009-05-14 Ueno Shoten:Kk 屋根煙突貫通部の施工方法及び屋根煙突貫通部の防水構造
CN201184022Y (zh) * 2008-04-10 2009-01-21 沈阳铝镁设计研究院 出屋面高温钢烟囱与砼屋面连接的构造
CN201209299Y (zh) * 2008-09-10 2009-03-18 新乡天丰钢板开发有限公司 一种屋面洞口安装固定结构

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
肖玉杰: "地下室顶板吊车预留施工洞口施工", 《黑龙江科技信息》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107034A (zh) * 2019-06-13 2019-08-09 中建四局第五建筑工程有限公司 一种塔吊穿结构防水装置及其设置方法

Similar Documents

Publication Publication Date Title
KR20200078650A (ko) 가옥 건물 구조
CN108729595A (zh) 一种结构稳固的隔热防渗坡屋面及其建造方法
CN104631713A (zh) 屋顶绿化施工方法
CN113653272B (zh) 高层建筑钢结构仿古屋檐及其施工方法
CN205116580U (zh) 一种平屋面排水系统
CN202324411U (zh) 一种防止雨水从塔吊出屋面洞口进入室内的封闭施工结构
CN102383600A (zh) 一种防止雨水从塔吊出屋面洞口进入室内的封闭施工方法
CN217353235U (zh) 一种建筑群
RU2384667C1 (ru) Способ возведения массивных бетонных плотин в суровых климатических условиях
CN110725424B (zh) 被动式钢结构房屋
CN204238193U (zh) 水电站地下厂房洞室装修结构
CN208668808U (zh) 一种预制成型雨漏口整体安装模块
CN206309126U (zh) 装配式垂直绿化花皿围墙构件
CN108412033B (zh) 建筑体外垂直森林外挑阳台结构及其施工方法
CN208266930U (zh) 海绵城市设计的车库顶板防水结构
CN106193685A (zh) 预制装配式通信机房结构
CN104196178A (zh) 中空双结构层防水屋面及其施工方法
CN102787648A (zh) 一种多功能快速建房模屋板结构体系及其施工方法
CN219840224U (zh) 墙体防流挂压顶构造及墙体
CN209244108U (zh) 一种斜坡屋面整拼式钢龙骨瓦屋面
CN205839962U (zh) 一种绿化节能型建筑外墙结构
CN110130528A (zh) 一种舒适节能全装配土坯房及其建造方法
CN204001469U (zh) 中空双结构层防水屋面
CN108930407A (zh) 绿色屋面系统的施工方法
CN220620749U (zh) 一种建筑物屋顶结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120321