CN102375105A - Simulation test system of substation equipment relay protection system - Google Patents

Simulation test system of substation equipment relay protection system Download PDF

Info

Publication number
CN102375105A
CN102375105A CN2011101781372A CN201110178137A CN102375105A CN 102375105 A CN102375105 A CN 102375105A CN 2011101781372 A CN2011101781372 A CN 2011101781372A CN 201110178137 A CN201110178137 A CN 201110178137A CN 102375105 A CN102375105 A CN 102375105A
Authority
CN
China
Prior art keywords
relay
protection
tested
terminal
protection system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101781372A
Other languages
Chinese (zh)
Inventor
沈炯
范维平
李发良
李磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN2011101781372A priority Critical patent/CN102375105A/en
Publication of CN102375105A publication Critical patent/CN102375105A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a substation protection system, in particular to a test system of a substation equipment protection system. The simulation test system of the substation equipment protection system comprises a tested protection device, a relay protection tester, a junction box, a terminal and a programmable controller, wherein the junction box is used for connecting the tested protection device and the relay protection tester through a wiring cable; the terminal is preassembled with related test software; the terminal is connected with the relay protection tester through a superoxide five wire; and the programmable controller is connected with the terminal through a field bus, is connected with the junction box through a wiring cable and is connected with the tested protection device through a field bus and a wiring cable. The test system disclosed by the invention can be used for carrying out simulation test on the protection system in advance and has the capability of finishing upgrading of the protection system under the condition of not powering off.

Description

Substation facilities relay protection system simulated testing system
Technical field
The present invention relates to the substation protection system, relate in particular to the test macro of substation facilities protection system.
Background technology
The large-scale transformer and distribution station of China is built in the eighties in last century more, can not satisfy the needs of modern power systems management mode far away to its means of relay protection now, therefore must upgrade to original protective device.Be because the power supply object of large-scale electric substation all is some important production unit and places; For the economic loss that house of correction is produced minimizes; Just must in that do not have a power failure or short as far as possible power-off time, upgrade to protective relay; Otherwise just necessary power down process will cause very big influence to worker, civilian electricity.
Summary of the invention
The present invention is intended to address the aforementioned drawbacks, and a kind of substation facilities relay protection system simulated testing system is provided.The present invention can carry out simulation test to protection system in advance, can not accomplish the upgrading of protection system with cutting off the power supply.
A kind of substation facilities relay protection system simulated testing system; It comprises protective device to be tested, relay-protection tester and one couple together protective device to be tested and relay-protection tester through the wire harness cable junction box, and said test macro also comprises:
A prepackage has the terminal of dependence test software, and this terminal connects said relay-protection tester through CAT5E UTP cable;
A Programmable Logic Controller, it is connected with described terminal through fieldbus, is connected with the wire harness cable with the junction box, is connected with the wire harness cable through fieldbus with protective device to be tested.
The present invention can simulate the practical operation situation behind the protective device upgrading truly, be convenient to find in advance to design and equipment in the problem that exists, and solve.
Description of drawings
Below, in conjunction with accompanying drawing, the present invention is further described
Fig. 1 is a synoptic diagram of the present invention.
Embodiment
As shown in Figure 1; A kind of substation facilities relay protection system of the present invention simulated testing system; It comprises protective device to be tested 1, relay-protection tester 2 and one couple together protective device 1 to be tested and relay-protection tester 2 through wire harness cable 10 junction box 3, and said test macro also comprises:
A prepackage has the terminal 4 of dependence test software, and this terminal connects said relay-protection tester 2 through CAT5E UTP cable 11; A Programmable Logic Controller 5, it is connected with described terminal 4 through fieldbus 12, is connected with wire harness cable 10 with junction box 3, is connected with wire harness cable 10 through fieldbus 12 with protective device 1 to be tested.Described test macro also comprises a power supply of supplying power to test macro incessantly.
Embodiment
Simulator program is write
Combined floodgate logic and the separating brake logic of using Programmable Logic Controller (S7-300) to come analog switch; According to actual switch once with secondary hardware device, and its branch, closing locking condition; Establishment one cover soft logic program, thus reach purpose to the emulation of relay protection logic testing signal system.Below provided " branch, the combined floodgate logical design thinking of isolating switch commonly used ".
The establishment of MI picture
Through Siemens SIMATIC WINCC human interface software; Write the pictures such as status surveillance, fault alarm, Data Detection of cover electric substation each equipment in conjunction with electric substation's actual motion state, simulation realizes internal data communication tests such as the remote control, remote measurement, remote signalling of electric substation.
Analogue means inserts
After having accomplished work such as programming in logic and the establishment of HMI picture, just can carry out the access test of analogue means, whether the test simulation loop can true(-)running, and detects the degree of compatibility of tested device for original system.Fig. 4 is the line chart of analogue means.
Realistic simulation signal for high-voltage switch gear one action condition, secondary singal and operating power etc. passes through the simulation test junction box, realizes the switching value simulation.Each section busbar voltage, line voltage distribution, electric current and signals such as meritorious and reactive power are realized the analog quantity simulation through the relay protection tester.
The network signal test
Through the S7-300 programming software, detect the correctness of protective relay to HMI picture signal, and the consistance of each protective relay terminal address and the corresponding station of picture.
The present invention improves substation protection system update upgrading safety of construction; Substation protection system upgrade in the past; Only do the monomer test of protection equipment early stage; Chain and internal data communication all must be tested after equipment replacement to the logic between the protection system, if run into design mistake or with the unmatched situation of legacy system interface signal, very easily cause electric substation's tripping operation accident.Our this cover simulation device; Can under off-line case, accomplish complete analog simulation test to protection equipment; And all signal transfer of the device that can be replaced needs through the bypass switching way can improve online construction to greatest extent and transform accuracy and safety coefficient to the model test device.
The present invention shortens the power off time that substation protection system update upgrading construction is transformed; Because signal testing must carry out at the construction field (site) in the past; The transformation time of such covering device need be used 3~5 days; Use the analogue means test signal, the renewal update time of single cover facility only just can be accomplished with 2~3 days at present.

Claims (2)

1. substation facilities relay protection system simulated testing system; It comprises protective device to be tested, relay-protection tester and one couple together protective device to be tested and relay-protection tester through the wire harness cable junction box; Said test macro also comprises: a prepackage has the terminal of dependence test software, and this terminal connects said relay-protection tester through CAT5E UTP cable; A Programmable Logic Controller, it is connected with described terminal through fieldbus, is connected with the wire harness cable with the junction box, is connected with the wire harness cable through fieldbus with protective device to be tested.
2. substation facilities relay protection system simulated testing system as claimed in claim 1 is characterized in that, described test macro also comprises a power supply of supplying power to test macro incessantly.
CN2011101781372A 2010-07-22 2011-06-29 Simulation test system of substation equipment relay protection system Pending CN102375105A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101781372A CN102375105A (en) 2010-07-22 2011-06-29 Simulation test system of substation equipment relay protection system

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN2010202680990U CN201892726U (en) 2010-07-22 2010-07-22 Simulation test system for protective relaying system of electric power substation equipment
CN201020268099.0 2010-07-22
CN2011101781372A CN102375105A (en) 2010-07-22 2011-06-29 Simulation test system of substation equipment relay protection system

Publications (1)

Publication Number Publication Date
CN102375105A true CN102375105A (en) 2012-03-14

Family

ID=44222198

Family Applications (2)

Application Number Title Priority Date Filing Date
CN2010202680990U Expired - Lifetime CN201892726U (en) 2010-07-22 2010-07-22 Simulation test system for protective relaying system of electric power substation equipment
CN2011101781372A Pending CN102375105A (en) 2010-07-22 2011-06-29 Simulation test system of substation equipment relay protection system

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN2010202680990U Expired - Lifetime CN201892726U (en) 2010-07-22 2010-07-22 Simulation test system for protective relaying system of electric power substation equipment

Country Status (1)

Country Link
CN (2) CN201892726U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103364663A (en) * 2013-07-16 2013-10-23 上海毅昊自动化有限公司 Intelligent device for simulating transformer substation primary equipment behavior
CN104467182A (en) * 2014-12-05 2015-03-25 国家电网公司 Substation control layer device non-power-outage remote control system and method
CN105548742A (en) * 2015-12-04 2016-05-04 国家电网公司华东分部 Remote relay protection test system
CN109541353A (en) * 2018-11-30 2019-03-29 广州供电局有限公司 Power distribution automation detection system

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103544104B (en) * 2013-10-22 2017-01-11 珠海许继电气有限公司 Testing method for power distribution terminal remote control functional software module

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0365664A (en) * 1989-08-02 1991-03-20 Kansai Electric Power Co Inc:The Apparatus and method for testing transformer protecting relay apparatus
US20060014585A1 (en) * 2004-07-15 2006-01-19 Raja Neogi Dynamic insertion of personalized content in online game scenes
CN2826453Y (en) * 2004-11-30 2006-10-11 湖南大学 Multifunctional microcomputer protection and converting station integrated automation experiment training system
CN101482602A (en) * 2008-11-25 2009-07-15 甘肃电力科学研究院 Detection analysis system of relay-protection tester
CN201319063Y (en) * 2008-11-25 2009-09-30 甘肃电力科学研究院 Detecting and analyzing device of relay protection testing device
CN201449436U (en) * 2009-06-08 2010-05-05 南京工业职业技术学院 Failure diagnosing and positioning system for power system earthing net
CN201518052U (en) * 2009-10-26 2010-06-30 江西省电力科学研究院 Portable all-digital relay protection transient closed-loop tester

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0365664A (en) * 1989-08-02 1991-03-20 Kansai Electric Power Co Inc:The Apparatus and method for testing transformer protecting relay apparatus
US20060014585A1 (en) * 2004-07-15 2006-01-19 Raja Neogi Dynamic insertion of personalized content in online game scenes
CN2826453Y (en) * 2004-11-30 2006-10-11 湖南大学 Multifunctional microcomputer protection and converting station integrated automation experiment training system
CN101482602A (en) * 2008-11-25 2009-07-15 甘肃电力科学研究院 Detection analysis system of relay-protection tester
CN201319063Y (en) * 2008-11-25 2009-09-30 甘肃电力科学研究院 Detecting and analyzing device of relay protection testing device
CN201449436U (en) * 2009-06-08 2010-05-05 南京工业职业技术学院 Failure diagnosing and positioning system for power system earthing net
CN201518052U (en) * 2009-10-26 2010-06-30 江西省电力科学研究院 Portable all-digital relay protection transient closed-loop tester

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张沛云等: "继电保护的模拟试验", 《电气应用》, vol. 25, no. 07, 31 July 2006 (2006-07-31) *
王力军等: "数字仿真系统振荡在继电保护测试中的应用", 《湖北电力》, vol. 23, no. 04, 31 December 1999 (1999-12-31) *
陈振宇等: "数字仿真技术在继电保护测试中的应用", 《河南电力》, no. 03, 31 March 1997 (1997-03-31) *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103364663A (en) * 2013-07-16 2013-10-23 上海毅昊自动化有限公司 Intelligent device for simulating transformer substation primary equipment behavior
CN103364663B (en) * 2013-07-16 2015-06-17 上海毅昊自动化有限公司 Intelligent device for simulating transformer substation primary equipment behavior
CN104467182A (en) * 2014-12-05 2015-03-25 国家电网公司 Substation control layer device non-power-outage remote control system and method
CN105548742A (en) * 2015-12-04 2016-05-04 国家电网公司华东分部 Remote relay protection test system
CN105548742B (en) * 2015-12-04 2018-11-09 国家电网公司华东分部 System is tested in a distant place for relay protection
CN109541353A (en) * 2018-11-30 2019-03-29 广州供电局有限公司 Power distribution automation detection system

Also Published As

Publication number Publication date
CN201892726U (en) 2011-07-06

Similar Documents

Publication Publication Date Title
CN103123758B (en) A kind of dispatching automation numeral physical mixed simulation training system
CN202159106U (en) Intelligent tester with intelligent power grid self-healing control technology
CN103713214A (en) Intelligent transformer station relay protection closed loop test system
CN105445601A (en) Current transformer interface testing device and method
CN104242472B (en) A kind of railway station low buckling distribution intelligent monitor system
CN102375105A (en) Simulation test system of substation equipment relay protection system
CN105094120B (en) Simulate the test device of primary equipment action behavior
CN106329720A (en) Detecting and debugging method for reconstruction and extension project secondary system for intelligent substation
CN103425847B (en) Based on circuit anticipation modernization system and the method for work thereof of dispatching of power netwoks anti-error system
CN105548742A (en) Remote relay protection test system
CN103746304B (en) The remodeling method of Intelligent transformer station
CN205354423U (en) Intelligent substation emulation training system
CN102426309A (en) Method for testing area spare power automatic switching system in engine room environment of master station
CN103236362A (en) PLC-based (programmable logic controller-based) knife switch control method and system
CN105680441A (en) Simulated replacement technique-based simulated point-alignment device
CN109149766A (en) A kind of automatic monitoring system of transformer substation and its connection type with secondary device
CN201230204Y (en) Logic test device for microcomputer type protection monitoring module in power supply and distribution system
CN109374994A (en) A kind of detection system suitable for protective relaying device
CN109768619B (en) Automatic debugging system and debugging method for monitoring information
CN205484589U (en) Overload protection device checkback auxiliary and monitoring system
CN102508052A (en) Test method for field band channel operation of automatic bus transfer system of area network
CN105162254A (en) Digitalized transformation method for transformer substation
CN206099520U (en) Intelligent substation debugging is with digital mimic -disconnecting switch
CN113643596B (en) Power distribution demonstration method and device, electronic equipment and computer readable storage medium
CN113990132A (en) Power transformation and distribution operation and maintenance integrated practical training system and practical training method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120314