CN102359126A - 碎石垫层压实密度的测定方法 - Google Patents
碎石垫层压实密度的测定方法 Download PDFInfo
- Publication number
- CN102359126A CN102359126A CN2011102577486A CN201110257748A CN102359126A CN 102359126 A CN102359126 A CN 102359126A CN 2011102577486 A CN2011102577486 A CN 2011102577486A CN 201110257748 A CN201110257748 A CN 201110257748A CN 102359126 A CN102359126 A CN 102359126A
- Authority
- CN
- China
- Prior art keywords
- sample block
- rubble
- hardcore bed
- slurries
- compacted density
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Investigating Or Analyzing Non-Biological Materials By The Use Of Chemical Means (AREA)
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
Abstract
本发明公开了一种碎石垫层压实密度的测定方法。该测定方法是采用灌浆法在待检测区域取出试样,然后用排水法求得试坑体积,之后去浆后测得试样质量,最后根据公式求得干密度,进而获得压实系数。与传统方法相比,本测定方法测试结果精确,而且现场更容易操作。
Description
技术领域
本发明属于路基基础施工技术领域,特别是涉及一种碎石垫层压实密度的测定方法。
背景技术
目前地基处理中常采用桩基处理,桩顶设置桩帽和碎石垫层结构。其中碎石垫层的厚度一般为400mm-600mm,粒径20-50mm,施工质量以压实系数进行控制。压实系数为填料压实后的干密度与击实试验得出的最大干密度的比值。根据《铁路工程土工试验规程》TB10102-2010的规定,现场填料压实后干密度ρ=mp/Vp的测定采用灌水法或灌砂法进行测量。步骤如下:1.按确定的试坑直径画出坑口轮廓线,在轮廓线内下挖至要求深度,边挖边将坑内的试样装入盛土容器内,称得质量mp;2.试坑挖好后,将略大于试坑容积的塑料薄膜袋沿坑底、坑壁紧密相贴,到地面后翻开袋口,将袋口周围用重物压牢固定,通过灌水法求得试坑体积Vp;3.根据公式ρ=mp/Vp得出干密度,进而求得压实系数。
目前这种方法是测量挖出试样的质量和试坑体积,以试坑体积来代替挖出试样的体积,这样就存在难以克服的问题:标准试坑很难挖成,容易塌孔,而且灌水时塑料薄膜袋不能完全与坑壁密贴,这样就会使测得的试坑体积偏小,误差大,从而导致计算的干密度误差大。
发明内容
为了解决上述问题,本发明的目的在于提供一种测试结果精确、现场容易操作的碎石垫层压实密度的测定方法。
为了达到上述目的,本发明提供的碎石垫层压实密度的测定方法包括按顺序进行的下列步骤:
1)在完成铺设和碾压后的碎石垫层上选择待检测区域并画出轮廓线;
2)将浆液均匀浇灌在整个待检测区域的表面,浆液将通过碎石之间的缝隙渗透到所需要的深度;
3)待浆液与该区域内的碎石凝固成试样块体后,将轮廓线外未凝固碎石挖至试样块体深度,然后取出试样块体;
4)在试样块体的外部包裹一层塑料薄膜以形成防水层,在此过程中应使塑料薄膜紧贴在试样块体的外表面上;
5)将上述带有防水层的试样块体放入水中,测量其排水量,从而得出试样块体的体积Vp;
6)将试样块体砸碎,然后利用水洗的方法除去浆体;
7)将碎石烘干并测量出碎石的干质量mp;
8)将上述干质量mp和试样块体的体积Vp代入公式ρ=mp/Vp即可求出填料压实后的干密度,进而获得压实系数,至此整个测定过程结束。
所述的步骤2)中的浆液为水泥浆或石灰浆。
本发明提供的碎石垫层压实密度的测定方法是采用灌浆法在待检测区域取出试样,然后用排水法求得试坑体积,之后去浆后测得试样质量,最后根据公式求得干密度,进而获得压实系数。与传统方法相比,本测定方法测试结果精确,而且现场更容易操作。
具体实施方式
下面结合具体实施例对本发明提供的碎石垫层压实密度的测定方法进行详细说明。
本发明提供的碎石垫层压实密度的测定方法包括按顺序进行的下列步骤:
1)在完成铺设和碾压后的碎石垫层上选择待检测区域并画出轮廓线;
2)将浆液均匀浇灌在整个待检测区域的表面,浆液将通过碎石之间的缝隙渗透到所需要的深度;
3)待浆液与该区域内的碎石凝固成试样块体后,将轮廓线外未凝固碎石挖至试样块体深度,然后取出试样块体;
4)在试样块体的外部包裹一层塑料薄膜以形成防水层,在此过程中应使塑料薄膜紧贴在试样块体的外表面上;
5)将上述带有防水层的试样块体放入水中,测量其排水量,从而得出试样块体的体积Vp;
6)将试样块体砸碎,然后利用水洗的方法除去浆体;
7)将碎石烘干并测量出碎石的干质量mp;
8)将上述干质量mp和试样块体的体积Vp代入公式ρ=mp/Vp即可求出填料压实后的干密度,进而获得压实系数,至此整个测定过程结束。
所述的步骤2)中的浆液为诸如水泥浆或石灰浆等可使碎石凝固成试样块体的浆液。
Claims (2)
1.一种碎石垫层压实密度的测定方法,其特征在于:所述的碎石垫层压实密度的测定方法包括按顺序进行的下列步骤:
1)在完成铺设和碾压后的碎石垫层上选择待检测区域并画出轮廓线;
2)将浆液均匀浇灌在整个待检测区域的表面,浆液将通过碎石之间的缝隙渗透到所需要的深度;
3)待浆液与该区域内的碎石凝固成试样块体后,将轮廓线外未凝固碎石挖至试样块体深度,然后取出试样块体;
4)在试样块体的外部包裹一层塑料薄膜以形成防水层,在此过程中应使塑料薄膜紧贴在试样块体的外表面上;
5)将上述带有防水层的试样块体放入水中,测量其排水量,从而得出试样块体的体积Vp;
6)将试样块体砸碎,然后利用水洗的方法除去浆体;
7)将碎石烘干并测量出碎石的干质量mp;
8)将上述干质量mp和试样块体的体积Vp代入公式ρ=mp/Vp即可求出填料压实后的干密度,进而获得压实系数,至此整个测定过程结束。
2.根据权利要求1所述的碎石垫层压实密度的测定方法,其特征在于:所述的步骤2)中的浆液为水泥浆或石灰浆。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110257748 CN102359126B (zh) | 2011-09-02 | 2011-09-02 | 碎石垫层压实密度的测定方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110257748 CN102359126B (zh) | 2011-09-02 | 2011-09-02 | 碎石垫层压实密度的测定方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102359126A true CN102359126A (zh) | 2012-02-22 |
CN102359126B CN102359126B (zh) | 2013-08-28 |
Family
ID=45584501
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110257748 Expired - Fee Related CN102359126B (zh) | 2011-09-02 | 2011-09-02 | 碎石垫层压实密度的测定方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102359126B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105403481A (zh) * | 2015-10-27 | 2016-03-16 | 中国电力工程顾问集团中南电力设计院有限公司 | 适用于粗颗粒土的土壤密度测量方法 |
CN108387482A (zh) * | 2018-04-27 | 2018-08-10 | 新疆维吾尔自治区产品质量监督检验研究院 | 一种胶凝材料浆体表观密度快速测试装置 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5426972A (en) * | 1993-04-20 | 1995-06-27 | Gas Research Institute | Monitoring soil compaction |
CN101368933A (zh) * | 2008-05-30 | 2009-02-18 | 重庆交通大学 | 一种压实度测试方法及基于该方法的压实度测试仪 |
-
2011
- 2011-09-02 CN CN 201110257748 patent/CN102359126B/zh not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5426972A (en) * | 1993-04-20 | 1995-06-27 | Gas Research Institute | Monitoring soil compaction |
CN101368933A (zh) * | 2008-05-30 | 2009-02-18 | 重庆交通大学 | 一种压实度测试方法及基于该方法的压实度测试仪 |
Non-Patent Citations (1)
Title |
---|
杜长学: "压实碎石填土工后检测方法的试验研究", 《湖南地质》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105403481A (zh) * | 2015-10-27 | 2016-03-16 | 中国电力工程顾问集团中南电力设计院有限公司 | 适用于粗颗粒土的土壤密度测量方法 |
CN108387482A (zh) * | 2018-04-27 | 2018-08-10 | 新疆维吾尔自治区产品质量监督检验研究院 | 一种胶凝材料浆体表观密度快速测试装置 |
Also Published As
Publication number | Publication date |
---|---|
CN102359126B (zh) | 2013-08-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104404838B (zh) | 速度200km以上铁路湿陷性黄土路基基底处理方法 | |
CN106049557B (zh) | 采用模拟灌注桩桩端后注浆的室内试验装置的试验方法 | |
CN106840086A (zh) | 超低位真空预压法快速固结软土试验装置 | |
CN102323396B (zh) | 大体积混凝土实体模拟试验装置及其试验施工方法 | |
CN107299650B (zh) | 一种远距离沉井排土纠偏方法 | |
CN106149673B (zh) | 湿陷性黄土深部预浸水强夯法 | |
CN101413261A (zh) | 双层低位真空预压加固装置及软土地基加固方法 | |
CN107489164A (zh) | 一种在役钢筋混凝土挡土墙的加高加固结构及方法 | |
CN108277795B (zh) | 一种加酸预浸水法处理非自重湿陷性黄土地基的方法 | |
CN207331739U (zh) | 一种在役钢筋混凝土挡土墙的加高加固结构 | |
CN201305846Y (zh) | 双层低位真空预压加固装置 | |
CN217542800U (zh) | 一种水泥土复合桩侧摩阻力及桩土应力比的试验装置 | |
CN102359126B (zh) | 碎石垫层压实密度的测定方法 | |
CN106013267B (zh) | 一种竖向抗拉拔混凝土模型桩及其建造方法及应用 | |
CN106149751A (zh) | 利用生石灰砖碴挤密桩加固房屋建筑地基的方法 | |
CN206971247U (zh) | 一种置于卸荷岩体上的混凝土趾板基础加固结构 | |
CN101591906A (zh) | 一次插管、多遍真空井点降水动力固结的地基处理方法 | |
CN106958239A (zh) | 降水联合轻夯软土地基加固方法 | |
CN101886384A (zh) | 真空强夯同步法 | |
CN107326765A (zh) | 处理岛状冻土地基石灰桩及其施工方法 | |
CN206540536U (zh) | 超低位真空预压法快速固结软土试验装置 | |
CN105386448A (zh) | 一种堆石坝坝坡处理中倒坡的填筑施工方法 | |
CN206220108U (zh) | 膨胀土路堑边坡加筋土反压防渗支护结构 | |
CN109696391A (zh) | 一种排水土工格栅排水性能试验装置和测试方法 | |
CN106703013A (zh) | 用于处治已建黄土路基沉陷病害的隔水帷幕 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 300141 No. 10, Hebei District, Tianjin, Zhongshan Road Patentee after: CHINA RAILWAY DESIGN Corp. Address before: 300141 No. 10, Hebei District, Tianjin, Zhongshan Road Patentee before: THE THIRD RAILWAY SURVEY AND DESIGN INSTITUTE Group Corp. |
|
CP01 | Change in the name or title of a patent holder | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130828 Termination date: 20210902 |
|
CF01 | Termination of patent right due to non-payment of annual fee |