CN102356037A - Clip device for elevator and support device for elevator - Google Patents

Clip device for elevator and support device for elevator Download PDF

Info

Publication number
CN102356037A
CN102356037A CN2009801580995A CN200980158099A CN102356037A CN 102356037 A CN102356037 A CN 102356037A CN 2009801580995 A CN2009801580995 A CN 2009801580995A CN 200980158099 A CN200980158099 A CN 200980158099A CN 102356037 A CN102356037 A CN 102356037A
Authority
CN
China
Prior art keywords
elevator
main part
fixing device
draw
hoistway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2009801580995A
Other languages
Chinese (zh)
Inventor
小泉喜彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Publication of CN102356037A publication Critical patent/CN102356037A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators
    • B66B7/02Guideways; Guides
    • B66B7/023Mounting means therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators
    • B66B7/02Guideways; Guides

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

Provided is a clip device for an elevator which can be applied easily even to a place where the installation cannot be checked visually when a load-lifting beam is installed on top of an elevator shaft, for example, and can hold a member to be held appropriately by simple procedure. A clip device for an elevator which holds a member to be held on a body fixed to the elevator shaft of an elevator is provided, on the surface facing a part of the member to be held, with a protrusion protruding from the surface. When the clip device is fixed, the protrusion is arranged in a recess which is formed in the part of the member to be held.

Description

The fixing device of elevator and the bearing set of elevator
Technical field
The present invention relates to be used in the hoistway of elevator, keeping the fixing device of draw-beam and guide rail etc. and the bearing set that is used to be bearing in the equipment that is provided with in the elevator hoistways.
Background technology
Car that in elevator hoistways, goes up and down and counterweight are through erectting its up-down direction of rail guidance that is provided with in hoistway.Through utilizing bolt or welding to fix, this guide rail is remained on the desired location in the hoistway at the carriage of well enclosure side setting with at the carriage of rail-sides setting.
In addition, the carriage utilization in the rail-sides setting is called the small-sized connecting element of rail clamp and is fixed in guide rail (for example with reference to patent documentation 1~3).
This rail clamp generally in the side of guide rail through bolt in carriage, and this rail clamp and carriage clamp the flange part of guide rail securely, keeps guide rail through its friction force.That is, when the rail clamp that utilizes patent documentation 1~3 to be put down in writing is arranged on the guide rail setting in the hoistway, need not form the fixedly hole of usefulness at the flange part of guide rail.
In addition, guide rail fixedly the time, under the situation that forms the fixing hole of usefulness at its flange part, produce the several problems shown in following.
That is, in the position in the hole that the flange part of guide rail forms according to the erecting stage of each elevator and difference.Therefore, if form the fixedly hole of usefulness, then exist the productivity of guide rail significantly to reduce such problem at above-mentioned flange part.
And, according to the difference of the erecting stage of elevator, its on-the-spot situation of not constructing according to architectural drawing is arranged also.Under this situation, need cut off guide rail at the scene according to the construction state of reality, or before the making of guide rail, carry out field investigation, the result who is based on field measurement carries out the making of guide rail.
In addition, in order at the scene guide rail to be cut off, the installation exercise personnel of elevator need bring the cutting off machine of guide rail into scene.The operability of therefore, exist operating personnel's burden big, installing significantly reduces such problem.On the other hand, when carrying out need guaranteeing to be used to carry out the time of field investigation under the situation of field investigation before the making at guide rail, the installation procedure of elevator can significantly postpone.In addition, in above-mentioned field investigation, need in hoistway, newly scaffold erecting measurement size correctly, required burden, time, the cost of field investigation all significantly increases.
The rail clamp that patent documentation 1~3 is put down in writing is widely used in view of such circumstances.And; Owing to be held the not fixing hole of usefulness of parts (in the above-mentioned example for guide rail); Therefore the unit that fixes is diverted and applied flexibly to this rail clamp, and this fixed cell is used for fixing and can not utilizes bolt directly to carry out fastening position or be difficult to directly fastening position.
Under regard to its concrete example and describe.
Fig. 6 is the main portion front view of the bearing set of the existing elevator of expression; Fig. 7 is the longitudinal section of the bearing set of elevator shown in Figure 6, and it shows the structure of using fixing device 24 with structure identical with above-mentioned rail clamp and draw-beam 25 being set at the top of hoistway 1.Specifically, be provided with carriage 26 at the top of hoistway 1, draw-beam 25 uses fixing device 24 and is fixed in above-mentioned carriage 26.
In addition; The lifting as the various device time-like that works the internal configurations that is hung in hoistway 1 when the installation of elevator of above-mentioned draw-beam 25 is basic; In addition, when the installation of elevator and after installing, above-mentioned draw-beam 25 is applied flexibly the bearing unit of the equipment that acts on the top configuration that is bearing in hoistway 1.Therefore, when the installation of elevator, draw-beam 25 need be provided with in position in the initial stage of installation steps.In addition, near the equipment of ceiling portion that must be configured in hoistway 1 is also arranged in the equipment of elevator, so draw-beam 25 preferably is arranged on the higher positions of hoistway 1 as far as possible.That is,, then when carrying out the installation of the high equipment in installation site, also can use draw-beam 25 to carry out installation exercise, can significantly alleviate the required load of this installation exercise as if the top that draw-beam 25 is arranged on hoistway 1.
Patent documentation 1: Japan opens clear 52-119255 communique in fact
Patent documentation 2: Japan opens clear 52-150168 communique in fact
Patent documentation 3: TOHKEMY 2003-48673 communique
Summary of the invention
The problem that invention will solve
Usually, fixing device 24 has the correct installation direction, if its installation direction mal, then fixing device 24 can not be given full play to hold facility.Therefore,, use fixing device 24 fixedly under the situation of draw-beam 25 like Fig. 6 and shown in Figure 7, must after the installation of fixing device 24 from above bow and see fixing device 24, whether correctly installed with affirmation fixing device 24.
In addition, Fig. 8 is the figure of correct installation mode of the existing fixing device of expression, and Fig. 9 is the figure of mounting means of the mistake of the existing fixing device of expression.Among this Fig. 8 and Fig. 9, the D-D direction of arrow view in left side presentation graphs 6, the E-E direction of arrow view in right side presentation graphs 6.
That is, the installation exercise personnel of elevator confirm fixing device 24 as shown in Figure 8 over against draw-beam 25 through visual from the top, if fixing device 24 sideling fixedly the time, then needs again fixing device 24 is correctly fixing with respect to draw-beam 25 as shown in Figure 9.
Like this, have under the situation with the fixing device 24 of the same structure of above-mentioned rail clamp in use, the application of fixing device 24 is limited to the place that its installing condition can Visual Confirmation.Therefore, because the configuration of draw-beam 25, because of above-mentioned application restriction can not be adopted fixing device 24, draw-beam 25 fixing must adopt that welding is fixing, other method such as bolt.
In addition, Figure 10 is the main portion front view of other examples of the bearing set of the existing elevator of expression, and Figure 11 is the longitudinal section of elevator bearing set shown in Figure 10.Figure 10 and Figure 11 are the fixing situation of draw-beam 25 is carried out in expression through welding figure.
Welding operation can only be undertaken by the people with welding qualification.Therefore, when draw-beam 25 being fixed in carriage 26, existing its operating personnel to receive and limit such problem through welding.In addition, under the situation that draw-beam 25 welding is fixing, also with utilize above-mentioned fixing device 24 to carry out fixing the same, need confirm post-job construction state (that is, weld part 27) through visual.Therefore, the same with the situation of utilizing fixing device 24 to fix, exist its fixed position be limited to can Visual Confirmation local such problem of construction state after the welding.
In addition, when the hole that forms fixing usefulness at draw-beam 25 when utilizing bolt fixedly draw-beam 25, produce and same problem when fixing above-mentioned guide rail.
The present invention accomplishes in order to solve above-mentioned problem; Its purpose is; The fixing device of elevator is provided and has utilized the bearing set of the elevator of this fixing device; The fixing device of said elevator also can easily be used at position that can not its mounting means of Visual Confirmation as the situation at the top that draw-beam is arranged at hoistway, can keep being held parts rightly through simple steps.
Be used to solve the means of problem
The fixing device of elevator of the present invention is to be used for and will to be held the fixing device of elevator that parts remain in the hoistway fixed body of elevator, and the fixing device of this elevator comprises: first press section, and it pushes a face of hoistway fixed body; Second press section, this second press section are clipped in the part that will be held parts under the state between the face of this second press section and hoistway fixed body, with the part that is held parts by a face side of pressing to the hoistway fixed body; Protuberance, it is located at and is held the opposed opposed faces of a part of parts, and outstanding from opposed faces, and is configured in the recess that is formed at a part that is held parts.
In addition, the fixing device of elevator of the present invention is to be used for and will to be held the fixing device of elevator that parts remain in the hoistway fixed body of elevator, and the fixing device of this elevator comprises: main part; Fixed cell, said fixed cell is fixed in the hoistway fixed body with main part; First press section, main part is located in said first press section, is fixed the unit when being fixed in the hoistway fixed body at main part, and this first press section is pressed in a face of hoistway fixed body; Second press section; Main part is located in said second press section; Be fixed the unit when being fixed in the hoistway fixed body at main part, and second press section will be clipped in a part that is held parts between the face of itself and hoistway fixed body by a face side of pressing to the hoistway fixed body; And protuberance; Said protuberance is located at the opposed faces of main part; The opposed faces of this main part is mutually opposed with a part that is held parts when being fixed in the hoistway fixed body in the main part unit that is fixed, and protuberance is outstanding from opposed faces, and is configured in the recess that is formed at a part that is held parts.
The bearing set of elevator of the present invention is the bearing set that is used to be bearing in the elevator of the equipment of setting in the elevator hoistways, and the bearing set of this elevator comprises: fixed body, and said fixed body is located at the top of hoistway; Draw-beam, said draw-beam carries the upper surface that places fixed body, and is formed with recess in the part of this draw-beam; And fixing device, said fixing device remains in fixed body with draw-beam, and fixing device comprises: main part; Fixed cell, said fixed cell is fixed in fixed body with main part; First press section, main part is located in said first press section, and is pressed in the upper surface of fixed body; Second press section, main part is located in said second press section, and second press section will be clipped in the part of the draw-beam between the upper surface of itself and fixed body by the upper surface side of pressing to fixed body; And protuberance, said protuberance is located at main part and the opposed opposed faces of part draw-beam, and outstanding from opposed faces, and is disposed in the recess.
The invention effect
According to the present invention, also can easily use at position that can not its mounting means of Visual Confirmation as the situation at the top that draw-beam is arranged at hoistway, can keep being held parts rightly through simple steps.
Description of drawings
Fig. 1 is the front view of bearing set of the elevator of expression embodiment 1 of the present invention.
Fig. 2 is the longitudinal section of the bearing set of elevator shown in Figure 1.
Fig. 3 is the sectional elevation of the bearing set of elevator shown in Figure 1.
Fig. 4 is the figure of function of fixing device that is used to illustrate the elevator of embodiment 1 of the present invention.
Fig. 5 is the figure of function of fixing device that is used to illustrate the elevator of embodiment 1 of the present invention.
Fig. 6 is the main portion front view of the bearing set of the existing elevator of expression.
Fig. 7 is the longitudinal section of the bearing set of elevator shown in Figure 6.
Fig. 8 is the figure of the correct installation mode of the existing fixing device of expression.
Fig. 9 is the figure of mounting means of the mistake of the existing fixing device of expression.
Figure 10 is the main portion front view of other examples of the bearing set of the existing elevator of expression.
Figure 11 is the longitudinal section of elevator bearing set shown in Figure 10.
Label declaration
1: hoistway; 2: well enclosure; 3: well enclosure; 4: ceiling portion; 5: draw-beam; 6: carriage; 7: fixing device; 8: carriage; 9: fixing device; 10: holding-down bolt; 11: nut; 12: main part; 13: bolt; 14: nut; 15: mounting hole; 16: the press section; 17: the press section; 18: guide portion; 19: opposed faces; 20: protuberance; 21: recess; 22: holding-down bolt; 23: nut; 24: fixing device; 25: draw-beam; 26: carriage; 27: weld part.
The specific embodiment
In order to illustrate in greater detail the present invention, the present invention is described with reference to the accompanying drawings.In addition, to the identical label of identical or cooresponding part mark, and suitably simplify or omit its repeat specification among each figure.
Embodiment 1.
Fig. 1 is the front view of bearing set of the elevator of expression embodiment 1 of the present invention, and Fig. 2 is the longitudinal section of the bearing set of elevator shown in Figure 1, and Fig. 3 is the sectional elevation of the bearing set of elevator shown in Figure 1.In addition, the A-A direction of arrow view of Fig. 2 presentation graphs 1 is among Fig. 3, at the B-B of upside presentation graphs 1 direction of arrow view, at the C-C of downside presentation graphs 1 direction of arrow view.In addition, Fig. 4 and Fig. 5 are the figure of function of fixing device that is used to illustrate the elevator of embodiment 1 of the present invention.
Among Fig. 1~Fig. 5, label 1 is to be the hoistway of the elevator that forms of the inside of the building of firm structure in building structure, and label 2 is side well enclosures of dividing hoistway 1, and label 3 is and well enclosure 2 opposed opposite side well enclosures that label 4 is ceiling portions of hoistway 1.
Top, horizontal at hoistway 1 is provided with the draw-beam 5 with predetermined length.This draw-beam 5 is when the installation of elevator, and as the lifting basis of the various device time-like that works the internal configurations that is hung in hoistway 1, and when the installation of elevator and after installing, this draw-beam 5 is applied flexibly the bearing unit of the equipment that acts on the top configuration that is bearing in hoistway 1.Steel that draw-beam 5 for example is I word shape by cross-sectional plane etc. constitute, this draw-beam 5 in the top-supported of hoistway 1 in well enclosure 2 and 3.In addition, the long limit of draw-beam 5 is disposed at the opposed direction of well enclosure 2 and 3, and the upper surface of this draw-beam 5 disposes near ceiling portion 3.
Specifically, an end of draw-beam 5 is supported on well enclosure 2 via carriage 6 and fixing device 7, and the other end of this draw-beam 5 is supported on well enclosure 3 via carriage 8 and fixing device 9.
Above-mentioned carriage 6 for example forms through plate-shaped member being bent into L word shape, and an avris of above-mentioned L word is fixed in the well enclosure 2 at hoistway 1 top, and another avris of L word is configured to from well enclosure 2 on even keel in hoistway 1 outstanding thus.In addition, label 10 is the holding-down bolt that the well enclosure 2 at the top of hoistway 1 is provided with, and label 11 is a nut.One avris of carriage 6 uses holding-down bolt 10 and nut 11 to be firmly fixed at well enclosure 2.
And the upper surface of another avris that places above-mentioned carriage 6 is carried in an end of draw-beam 5, and remains in carriage 6 through fixing device 7.
This fixing device 7 of maintenance draw-beam 5 possesses main part 12 and is used for main part 12 is fixed in the fixed cell of carriage 6.
In addition, the said fixing unit of this embodiment is made up of 1 group of bolt 13 and nut 14.That is, above-mentioned bolt 13 is applied in mounting hole (through hole) 15 that main part 12 forms and forms at another avris of carriage 6 from the top through hole (not shown) below another avris of carriage 6, is installed nut 14 in the threaded portion of bolt 13 then.Then, under this state, tight a bolt 13, thereby head through bolt 13 and nut 14 are fixed in carriage 6 from clamping another avris of main part 12 and carriage 6 up and down with main part 12.
In addition, the main part 12 at fixing device 7 is provided with press section 16 and 17, guide portion 18.
Press section 16 is the parts of when main part 12 is fixed in carriage 6 upper surface of carriage 6 being pushed downwards.That is, through bolt 13 being tightened and main part 12 being fixed in carriage 6, press section 16 is pressed in the upper surface of carriage 6.At this moment, the nip upper surface of carriage 6 of the bottom of press section 16, main part 12 is firmly held in carriage 6 thus.
Press section 17 is edge portion (upper surface side of the carriage 6) parts of pushing downwards when main part 12 is fixed in carriage 6 carrying in the draw-beam 5 placed the part of carriage 6.Promptly; When using fixing device 7 that draw-beam 5 is remained in carriage 6; The upper surface of the above-mentioned edge portion through press section 17 being connected to draw-beam 5 from the top; The above-mentioned edge portion of draw-beam 5 is clipped between another avris upper surface of press section 17 and carriage 6; Under this state, tight a bolt 13, main part 12 is fixed in carriage 6.Thus, the portion 17 that is pressed of the above-mentioned edge portion of draw-beam 5 presses on the upper surface of carriage 6, and by the maintenance that rubs securely.
Guide portion 18 has the function that when through fixing device 7 draw-beam 5 being remained in carriage 6, is used for main part 12 is disposed at the correct installation direction.Main part 12 has the correct installation direction, if main part 12 is not disposed at its correct installation direction, then fixing device 7 can not be given full play to its hold facility.That is, through the function of this guide portion 18, press section 17 is configured in the correct direction (below be called " reference direction ") of the above-mentioned edge portion that is used to push draw-beam 5 with respect to draw-beam 5.
Specifically; Guide portion 18 possesses the opposed opposed faces 19 of above-mentioned edge portion with draw-beam 5; The end face of the above-mentioned edge portion through making this opposed faces 19 and draw-beam 5 carries out face and contacts; Main part 12 can be disposed at correct direction with respect to draw-beam 5; That is, press section 17 can be disposed at the reference direction with respect to draw-beam 5.In addition, also consider operability when draw-beam 5 is installed etc., the end face of the above-mentioned edge portion of the draw-beam 5 that above-mentioned opposed faces 19 is contacted is set at for example parallel with the long side direction of draw-beam 5 face.
In addition, in the opposed faces 19 of guide sections 18, portion is formed with the protuberance of giving prominence to from opposed faces 19 20 in the central.When having main part 12 (fixing device 7) with respect to the positioning function of draw-beam 5 with through bolt 13 stationary body portions 12 concurrently, this protuberance 20 prevents rotating function.In addition, in order to realize above-mentioned functions,, be formed with the recess 21 chimeric with protuberance 20 in the above-mentioned edge portion that passes through that fixing device 7 keeps of draw-beam 5.And when the end face with the above-mentioned edge portion of opposed faces 19 and draw-beam 5 carried out the strong local stationary body of mode that face contacts portion 12, raised part 20 was chimeric with recess 21 as shown in Figure 3, and is disposed in the recess 21.
In Fig. 3~Fig. 5, show protuberance 20 and appear from the situation of the outstanding triangle of opposed faces 19.Under this situation, recess 21 is made up of the for example otch corresponding to the triangle of the shape of protuberance 20.In addition, protuberance 20 and recess 21 are not limited to these shapes, as long as can realize above-mentioned functions, then can be arbitrary shapes.For example, protuberance 20 can also be semisphere, quadrangle etc. except above-mentioned triangle.In addition, recess 21 also can be made up of the pit (hole) that forms at predetermined face except above-mentioned otch.
On the other hand, keep carriage 8 and the fixing device 9 of the other end side of draw-beam 5 to have the structure identical with above-mentioned carriage 6 and fixing device 7.In addition, the holding-down bolt that label 22 expressions are given prominence in hoistway 1 from well enclosure 3, label 23 expressions use holding-down bolts 22 carriage 8 to be fixed in the nut of the well enclosure 3 at hoistway 1 top.
Step when then, the fixing device 7 and 9 that use is had a said structure is arranged at the top of hoistway 1 with draw-beam 5 describes.
The installation exercise personnel are fixed in carriage 6 and 8 the fixedly top of hoistway 1 in advance.Then, the upper surface that places carriage 6 is carried in an end of draw-beam 5, the upper surface that places carriage 8 is carried in the other end, thereby draw-beam 5 is set up between carriage 6 and 8.
Then, through bolt 13 and nut 14 main part 12 of fixing device 7 is temporarily fixed on carriage 6.At this moment, fixing device 7 is disposed at the both sides of an end of draw-beam 5 as shown in Figure 2, the press section of each main part 12 was placed an end of draw-beam 5 in 17 years.
In addition, likewise fixing device 9 is temporarily fixed on carriage 8, fixing device 9 is disposed at the both sides of the other end of draw-beam 5 with above-mentioned.
After fixing device 7 and 9 working fastenings, keep the situation that fixing device 7 and 9 is configured to above-mentioned state, draw-beam 5 is slided at its long side direction move, draw-beam 5 is disposed at suitable position.Specifically, 1 fixing device 7 or 9 applying light are made draw-beam 5 slide in draw-beam 5, the slip of draw-beam 5 is being stopped at the protuberance 20 and the recess 21 chimeric time points of its main part 12.In addition, owing to fixing device 7 and 9 are arranged, therefore draw-beam 5 is moved at its long side direction in the working fastening of the both sides of draw-beam 5.In addition, about the whether chimeric judgement of protuberance 20, can easily judge from its sense of touch with recess 21.Therefore, even do not carry out Visual Confirmation especially, also can be correctly and the location of implementing draw-beam 5 simply.
Draw-beam 5 is moved behind suitable position, carry out the fixed operation of each fixing device 7 and 9, draw-beam 5 is remained in carriage 6.Specifically, main part 12 is pushed to draw-beam 5 sides, made opposed faces 19 carry out face and contact in that protuberance 20 is embedded under the state of recess 21 with the predetermined face of draw-beam 5.Then, bolt 13 is tightened keeping under the situation of this state, through the head and the nut 14 of bolt 13, from clamping main part 12 and carriage 6 (or 8) up and down.
In addition, in order to tackle the installation site of fixing device 7 and 9 neatly, also can form a plurality of recesses 21 with identical direction at 19 opposed each end faces of opposed faces of draw-beam 5.
In the said fixing operation of fixing device 7 and 9, when carrying out the tightening of bolt 13, have will be to the power of the tightening direction rotation of bolt 13 in 12 effects to main part.But, because protuberance 20 is embedded in recess 21, thus main part 12 even the utmost point fine to the tightening direction rotation of bolt 13, protuberance 20 will contact with the medial surface (the edge portion that also comprises recess 21) of recess 21, and stops its spinning movement.Therefore, fixing device 7 and 9 fixing after, need whether main part 12 correctly be installed through Visual Confirmation, can judge easily that press section 17 is configured in the reference direction with respect to draw-beam 5.
According to the embodiment of the present invention 1, even, also can simply and rightly draw-beam 5 be remained in carriage 6 and 8 being provided with under position height, draw-beam 5 situation such of draw-beam 5 near ceiling portion 4.That is, if the fixing device of said structure 7 (and 9) does not then need Visual Confirmation just can judge draw-beam 5 rightly and has been disposed at appropriate position and has faced draw-beam 5 at the back main part 12 of tightening of bolt 13.
In addition, in this embodiment, as an example of the fixing device 7 of using said structure (and 9), the situation that the top at hoistway 1 is provided with draw-beam 5 is illustrated.But its application is not limited thereto, so long as keep being held parts in order to go up at the parts that are fixed in elevator hoistways 1 (fixed body), then can be applied to various structures.Its use also be not limited to can not the Visual Confirmation installing condition the position.Therefore, also can use above-mentioned fixing device 7 (and 9) to carry out the fixing of guide rail.But,, can become special actv. means for carrying out fixed operation itself and can not carrying out the place of Visual Confirmation.
Utilizability in the industry
The hoistway fixed body that the fixing device of elevator of the present invention can be used at elevator keeps being held parts, can be applied to the maintenance of the draw-beam of elevator, the various situation such as maintenance of guide rail.

Claims (8)

1. the fixing device of an elevator, it is used for and will be held the hoistway fixed body that parts remain in elevator, wherein,
The fixing device of this elevator comprises:
A face of said hoistway fixed body is pushed in first press section, said first press section;
Second press section; Said second press section under the state between the said face that a said part that is held parts is clipped in said second press section and said hoistway fixed body, with a said said part that is held parts by a said face side of pressing to said hoistway fixed body; And
Protuberance, said protuberance are located at and the said opposed opposed faces of a said part that is held parts, and outstanding from said opposed faces, and are configured in the recess that is formed at a said said part that is held parts.
2. the fixing device of an elevator, it is used for and will be held the hoistway fixed body that parts remain in elevator, wherein,
The fixing device of this elevator comprises:
Main part;
Fixed cell, said fixed cell is fixed in said hoistway fixed body with said main part;
First press section, said main part is located in said first press section, and when said main part was fixed in said hoistway fixed body by said fixed cell, this first press section was pressed in a face of said hoistway fixed body;
Second press section; Said main part is located in said second press section; When said main part is fixed in said hoistway fixed body by said fixed cell, said second press section will be clipped in a said part that is held parts between the said face of itself and said hoistway fixed body by a said face side of pressing to said hoistway fixed body; And
Protuberance; Said protuberance is located at the opposed faces of said main part; The said opposed faces of said main part is mutually opposed with a said said part that is held parts when said main part is fixed in said hoistway fixed body by said fixed cell; Said protuberance is outstanding from said opposed faces, and is configured in the recess that is formed at a said said part that is held parts.
3. the fixing device of elevator according to claim 2, wherein,
Said fixed cell comprises bolt, and this bolt is fixed in said hoistway fixed body via the mounting hole that forms at said main part with said main part,
Said main part through being fixed in said hoistway fixed body is to the rotation of the tightening direction of said bolt, and said protuberance contacts with the medial surface of said recess.
4. the fixing device of elevator according to claim 3, wherein,
Said main part only uses a bolt in said hoistway fixed body.
5. according to the fixing device of each described elevator in the claim 1~4, wherein,
Through said protuberance is disposed in the said recess, said opposed faces is configured to parallel with the said long side direction that is held parts.
6. according to the fixing device of each described elevator in the claim 1~5, wherein,
Said second press section have be used to push a said said part that is held parts with respect to the said reference direction that is held parts; Through said opposed faces is contacted with a said said part that is held parts, said second press section is configured in said reference direction.
7. the bearing set of an elevator is used to be bearing in the equipment that is provided with in the elevator hoistways, wherein,
The bearing set of this elevator comprises:
Fixed body, said fixed body is located at the top of said hoistway;
Draw-beam, said draw-beam carries the upper surface that places said fixed body, and is formed with recess in the part of this draw-beam; And
Fixing device, said fixing device remains in said fixed body with said draw-beam,
Said fixing device comprises:
Main part;
Fixed cell, said fixed cell is fixed in said fixed body with said main part;
First press section, said main part is located in said first press section, and is pressed in the upper surface of said fixed body;
Second press section, said main part is located in said second press section, and said second press section will be clipped in the said part of the said draw-beam between the upper surface of itself and said fixed body by the upper surface side of pressing to said fixed body; And
Protuberance, said protuberance are located at said main part and the opposed opposed faces of a said part said draw-beam, and outstanding from said opposed faces, and are disposed in the said recess.
8. the bearing set of elevator according to claim 7, wherein,
Said draw-beam is formed with a plurality of recesses in a said part with equidirectional.
CN2009801580995A 2009-03-17 2009-03-17 Clip device for elevator and support device for elevator Pending CN102356037A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2009/055176 WO2010106641A1 (en) 2009-03-17 2009-03-17 Clip device for elevator and support device for elevator

Publications (1)

Publication Number Publication Date
CN102356037A true CN102356037A (en) 2012-02-15

Family

ID=42739312

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009801580995A Pending CN102356037A (en) 2009-03-17 2009-03-17 Clip device for elevator and support device for elevator

Country Status (5)

Country Link
EP (1) EP2409942A1 (en)
JP (1) JPWO2010106641A1 (en)
KR (1) KR20110113759A (en)
CN (1) CN102356037A (en)
WO (1) WO2010106641A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103395671A (en) * 2013-05-02 2013-11-20 长江润发机械股份有限公司 Leaf plate concave damping anti-sliding guide rail
CN106865382A (en) * 2017-02-22 2017-06-20 张家港奥斯卡电梯部件有限公司 A kind of spacing firm T-shaped cage guide
CN107055258A (en) * 2017-02-22 2017-08-18 张家港奥斯卡电梯部件有限公司 A kind of cage guide of T-shaped

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5714345B2 (en) * 2011-01-27 2015-05-07 東芝エレベータ株式会社 Elevator brake system
JP6293078B2 (en) * 2015-03-02 2018-03-14 株式会社日立ビルシステム Elevator equipment

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5610778Y2 (en) 1976-03-04 1981-03-11
JPS52150168A (en) 1976-06-07 1977-12-13 Matsushita Electric Ind Co Ltd Pressure pan
JPS6124552Y2 (en) * 1981-02-28 1986-07-23
JPS57158659U (en) * 1981-03-31 1982-10-05
JPS6124552A (en) * 1984-07-13 1986-02-03 Kuraray Co Ltd Gamma-aminobutyric acid derivative and its preparation
JP2729017B2 (en) * 1993-01-26 1998-03-18 三菱電機ビルテクノサービス株式会社 Elevator car gantry
JP3058592B2 (en) * 1996-07-01 2000-07-04 東京フアブリック工業株式会社 Rail fastening device with height adjustment function
JP2003027603A (en) * 2001-07-19 2003-01-29 Nippon Light Metal Co Ltd Profile-joining structure
JP2003048673A (en) 2001-08-02 2003-02-21 Mitsubishi Electric Corp Device and method for fixing guide rail of elevator
JP4585228B2 (en) * 2004-05-12 2010-11-24 三菱電機株式会社 Elevator lifting beam fixing device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103395671A (en) * 2013-05-02 2013-11-20 长江润发机械股份有限公司 Leaf plate concave damping anti-sliding guide rail
CN106865382A (en) * 2017-02-22 2017-06-20 张家港奥斯卡电梯部件有限公司 A kind of spacing firm T-shaped cage guide
CN107055258A (en) * 2017-02-22 2017-08-18 张家港奥斯卡电梯部件有限公司 A kind of cage guide of T-shaped

Also Published As

Publication number Publication date
KR20110113759A (en) 2011-10-18
JPWO2010106641A1 (en) 2012-09-20
WO2010106641A1 (en) 2010-09-23
EP2409942A1 (en) 2012-01-25

Similar Documents

Publication Publication Date Title
CN102356037A (en) Clip device for elevator and support device for elevator
US10494233B2 (en) Relocatable fine motion positioner assembly on an overhead crane
EP2524893B1 (en) Lift crane system
KR20170127278A (en) Scaffold apparatus for offshore plant
US20140217050A1 (en) Relocatable fine motion positioner assembly on an overhead crane
KR100947452B1 (en) Jig for dismantal of scaffolding big girder
ATE263113T1 (en) METHOD OF INSTALLING ELEVATORS
KR20100004581A (en) Supporting device for pulling gang form's
JP4203441B2 (en) Tower crane support device and construction method thereof
JP5040202B2 (en) Elevator installation jig
JP4297854B2 (en) Load provision method
JP2016121494A (en) Beam joint jig for automatic work in iron frame construction and automatic plumbing method of an iron frame beam member
CN111170138A (en) Accurate hoisting device and method for precast beam
KR20100059651A (en) Scaffold fixing apparatus
JP2010275709A (en) Method for reinforcing beam
US8935890B2 (en) Apparatus and method for reverse rectification
CN113700280B (en) Overhanging scaffold
CN114380228B (en) Elevator hoist and method for installing elevator hoist
JP4796198B1 (en) Work scaffold equipment
CN214194941U (en) Full-prefabricated assembled balcony beam slab
JP2008169631A (en) Construction member installation hole positioning device
KR200321373Y1 (en) platform equipment for carrying materials between floors
CN104668871A (en) Bogie welding and clamping device and clamping method
CN213539421U (en) Assembled curtain wall
CN219509161U (en) Concrete placement formwork device and wall system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120215