CN102352773B - Sectional filling method of old lane - Google Patents

Sectional filling method of old lane Download PDF

Info

Publication number
CN102352773B
CN102352773B CN 201110346136 CN201110346136A CN102352773B CN 102352773 B CN102352773 B CN 102352773B CN 201110346136 CN201110346136 CN 201110346136 CN 201110346136 A CN201110346136 A CN 201110346136A CN 102352773 B CN102352773 B CN 102352773B
Authority
CN
China
Prior art keywords
filling
old
old working
work plane
working
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110346136
Other languages
Chinese (zh)
Other versions
CN102352773A (en
Inventor
郭德春
王道广
王建沪
孙念昌
田志岭
王伟
王友峰
吴传伟
孙圣明
王永平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yanzhou Mining Group Zouchenghua Construction Design Research Institute Co., Ltd.
Original Assignee
Yankuang Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yankuang Group Corp Ltd filed Critical Yankuang Group Corp Ltd
Priority to CN 201110346136 priority Critical patent/CN102352773B/en
Publication of CN102352773A publication Critical patent/CN102352773A/en
Application granted granted Critical
Publication of CN102352773B publication Critical patent/CN102352773B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention belongs to the field of mining and relates to a sectional filling method of an old lane. The sectional filling method of the old lane comprises the following steps: A) drawing a stratigraphic relation layout diagram of a working face and the old lane and marking the positions of the old lane, the working face and other lanes, the shoring way of the old lane and other parameters in a detailed manner; B) selecting fly ash or slag ash and other radiation-free materials with lower sulfur content as filling materials, screening the filling materials, then bagging and putting into a well; C) filling the old lane in the position which is ahead of the working face 50m at least, and performing stage-by-stage step-by-step filling on the old lane from the working face to a terminal mining line; and D) performing sectional filling construction. The method has the beneficial effects that the sectional filling is adopted, the filling efficiency is high, the recovery and the filling do not affect each other, the filling cost is low, and the consumed time is short, thereby not only solving the problems of ground pressure occurrence of the working face, roof caving, subsidence of a support, loss of coal resources and the like during the recovery period, but also avoiding the defects of waste of the filling materials and long consumed time for filling.

Description

Sectional filling method of old lane
Technical field
The invention belongs to field of mining, relate to a kind of sectional filling method of old lane.
Background technology
For crossing the special mining face of old working in progradation, because old working is various at layer position, the arrangement of work plane, stoping period can cause work plane ground to press to manifest, the advance of the face is sunk, affected in roof fall, support, cause the problem such as coal resources loss, and traditional whole fill method exists that filling cost is high, length consuming time, the shortcoming that easily normal propelling impacted.
Summary of the invention
The present invention provides a kind of sectional filling method of old lane in order to make up the deficiencies in the prior art, not only guarantees filling effect but also avoid the casting resin waste, reduces loading time, effectively solves the contradiction between the normal propelling of filling and work plane.
The present invention is achieved through the following technical solutions:
Sectional filling method of old lane of the present invention, its special character is: comprise the following steps:
A, drawing face old working layer position concerns arrangement diagram, marks in detail position, old working support pattern and other parameter in old working and work plane and other tunnel;
B, select that the sulfur content such as flyash or slag ash are lower, cold material is as casting resin, rear pack is screened in casting resin go into the well;
C, work plane 50m carries out filling to old working at least in advance, to carrying out stage by stage progressively filling from work plane to the old working that stops adopting line;
D, carry out sublevel fill stoping construction.
Sectional filling method of old lane of the present invention, in step D,
(1) be in this layer and the old working parallel with work plane, take intensive sublevel fill stoping mode, be to leave not filling section between every two fillings buttress in old working, distance between every two fillings buttress is not more than span length, during filling, casting resin is filled to apart from old working top board 0.7m-1.0m, stays airspace;
(2) be in old working and the top layer old working of this layer and or oblique vertical with work plane, take general sublevel fill stoping mode, be to leave not filling section between every two fillings buttress, distance between every two fillings buttress, when the old working support pattern falls behind, face pressure is large, when existing the specific positions such as grade separation, usual friendship, oblique to concern with other tunnel, dwindle the distance between the filling buttress, on the contrary the distance of widening;
(3) part bottom old working is that tunnel part is in work plane, part is in the work plane bottom, during filling, first demarcates work plane coal cutting base plate line in old working, and then 0.4m marks fill line under the base plate line, whole fill under fill line.
the invention has the beneficial effects as follows, according to old working top board situation and support pattern, arrangement and length, face pressure, adopt sublevel fill stoping with the factors such as position relationship in other tunnel, there is not filling section in old working (stowboard), by adopting flyash, the casting resin sublevel fill stopings such as slag ash, pack effectiveness is high, back production and filling are independent of each other, filling cost is low, consuming time short, both having solved stoping period work plane ground presses and manifests, roof fall, support sink and the problem such as coal resources loss, the casting resin waste of having avoided again traditional filling method to cause, the shortcoming of filling length consuming time, reached Fast Filling, do not affect the purpose of working face extraction.
Description of drawings
Accompanying drawing is structural representation of the present invention.Fig. 1 is in this layer and the old working parallel with work plane, and Fig. 2 is old working and the top layer old working that is in this layer and or oblique vertical with work plane, and Fig. 3 is the bottom old working, and in Fig. 3, arrow represents advance of the face direction.
In figure, 1 pack portion, 2 old workings, 3 work planes.
The specific embodiment
Sectional filling method of old lane of the present invention comprises the following steps:
A, according to the reality of stope, drawing face old working layer position concerns arrangement diagram in advance, marks in detail position, old working support pattern and other parameter in old working and work plane and other tunnel, for next step filling is constructed ready;
B, according to reality and the prior art situation of stope, the sulfur content such as general selection flyash or slag ash are lower, cold material filling, for guaranteeing that the attal size is unlikely to the excessive filling effect that affects, and screens rear pack to casting resin and goes into the well;
C, according to old working arrangement, top board situation, face propulsion speed, work plane 50m carries out filling (to carrying out stage by stage progressively filling from work plane to the old working that stops adopting line) to old working at least in advance, avoids filling, working face extraction to influence each other;
D, take corresponding sublevel fill stoping method according to the factors such as layer position, arrangement relation of old working and work plane, specifically be divided into following three kinds of situations:
(1) be in this layer and the old working parallel with work plane, take intensive sublevel fill stoping mode, namely leave not filling section between every two fillings buttress in old working, distance between every two fillings buttress is unsuitable excessive, generally can not guarantee filling effect greater than span length, see Fig. 1;
During filling, for preventing that the tunnel drum end from causing the blind lane that ventilates when destroying the roadway support state and preventing the filling construction, casting resin is filled to apart from old working top board 0.7m-1.0m and is advisable, and stays airspace;
(2) be in old working and the top layer old working of this layer and or oblique vertical with work plane, take general sublevel fill stoping mode, be to leave not filling section between every two fillings buttress, distance between every two fillings buttress is according to old working top board situation and support pattern, face pressure, determine with the factors such as position relationship in other tunnel, such as the old working support pattern falls behind, face pressure is large, when existing the specific positions such as grade separation, usual friendship, oblique to concern with other tunnel, should dwindle the distance between the filling buttress, otherwise the distance of widening is seen Fig. 2;
(3) filling method of part bottom old working (tunnel part is in work plane, part is in the work plane bottom), first demarcate work plane coal cutting base plate line in old working, and then when under the base plate line, 0.4m(considers the old working drum end, coal-winning machine coal cutting coal breakage can self-packing fill area not) mark fill line, whole fill under fill line is seen Fig. 3.

Claims (1)

1. sectional filling method of old lane is characterized in that: comprise the following steps:
A, drawing face old working layer position concerns arrangement diagram, marks in detail position, old working support pattern and other parameter in old working and work plane and other tunnel;
B, selection flyash or slag ash screen rear pack to casting resin and go into the well as casting resin;
C, work plane 50m carries out filling to old working at least in advance, to carrying out stage by stage progressively filling from work plane to the old working that stops adopting line;
D, carry out sublevel fill stoping construction:
(1) be in this layer and the old working parallel with work plane, take intensive sublevel fill stoping mode, be to leave not filling section between every two fillings buttress in old working, distance between every two fillings buttress is not more than span length, during filling, casting resin is filled to apart from old working top board 0.7m-1.0m, stays airspace;
(2) be in old working and the top layer old working of this layer and or oblique vertical with work plane, take general sublevel fill stoping mode, be to leave not filling section between every two fillings buttress, distance between every two fillings buttress, when the old working support pattern falls behind, face pressure is large, when having grade separation, usual friendship, oblique position relationship with other tunnel, dwindle the distance between the filling buttress, on the contrary the distance of widening;
(3) part bottom old working is that tunnel part is in work plane, part is in the work plane bottom, during filling, first demarcates work plane coal cutting base plate line in old working, and then 0.4m marks fill line under the base plate line, whole fill under fill line.
CN 201110346136 2011-11-07 2011-11-07 Sectional filling method of old lane Active CN102352773B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110346136 CN102352773B (en) 2011-11-07 2011-11-07 Sectional filling method of old lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110346136 CN102352773B (en) 2011-11-07 2011-11-07 Sectional filling method of old lane

Publications (2)

Publication Number Publication Date
CN102352773A CN102352773A (en) 2012-02-15
CN102352773B true CN102352773B (en) 2013-06-19

Family

ID=45576404

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110346136 Active CN102352773B (en) 2011-11-07 2011-11-07 Sectional filling method of old lane

Country Status (1)

Country Link
CN (1) CN102352773B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104564137B (en) * 2015-01-19 2017-01-18 中国矿业大学 Handling method and device for double-medium stacked supporting and hard top plate type mined-out area
CN109577981A (en) * 2018-11-15 2019-04-05 山西潞安环保能源开发股份有限公司常村煤矿 A kind of high seam pillar recovery method
CN112943243B (en) * 2021-02-08 2023-03-24 中国矿业大学 Method for old hole cutting of oversize section of fully mechanized caving face of shallow-buried extra-thick coal seam

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4377353A (en) * 1978-08-03 1983-03-22 Granges Ab Method of selective underground mining and stabilization of rock cavities
CN1952349A (en) * 2006-11-09 2007-04-25 中国矿业大学 Mining method for replacement of pressed coal under village by waste rock
CN101372891A (en) * 2008-06-10 2009-02-25 沈阳市华祥矿山机械厂 Strip filling integral backstopping coal mining method
CN101737052A (en) * 2009-12-28 2010-06-16 河北邯邢矿冶设计院有限公司 Sublevel fill-mining method
CN101749020A (en) * 2010-01-26 2010-06-23 淄博市王庄煤矿 Forward coal mining by filling method
CN102155226A (en) * 2010-11-30 2011-08-17 淄博市王庄煤矿 Roadway backfill mining method for coal seams with medium-high thickness

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6554368B2 (en) * 2000-03-13 2003-04-29 Oil Sands Underground Mining, Inc. Method and system for mining hydrocarbon-containing materials

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4377353A (en) * 1978-08-03 1983-03-22 Granges Ab Method of selective underground mining and stabilization of rock cavities
CN1952349A (en) * 2006-11-09 2007-04-25 中国矿业大学 Mining method for replacement of pressed coal under village by waste rock
CN101372891A (en) * 2008-06-10 2009-02-25 沈阳市华祥矿山机械厂 Strip filling integral backstopping coal mining method
CN101737052A (en) * 2009-12-28 2010-06-16 河北邯邢矿冶设计院有限公司 Sublevel fill-mining method
CN101749020A (en) * 2010-01-26 2010-06-23 淄博市王庄煤矿 Forward coal mining by filling method
CN102155226A (en) * 2010-11-30 2011-08-17 淄博市王庄煤矿 Roadway backfill mining method for coal seams with medium-high thickness

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
张海波等.评述国内外充填采矿技术发展现状.《中国矿业》.2009,(第12期),
惠功领.我国煤矿充填开采技术现状与发展.《煤炭工程》.2010,(第02期),
我国煤矿充填开采技术现状与发展;惠功领;《煤炭工程》;20101231(第02期);第21-23页 *
评述国内外充填采矿技术发展现状;张海波等;《中国矿业》;20091231(第12期);第59-62页 *

Also Published As

Publication number Publication date
CN102352773A (en) 2012-02-15

Similar Documents

Publication Publication Date Title
CN104405437B (en) A kind of solid filling with combine the hybrid working face mining method of adopting
AU2013358812B2 (en) Solid-filling coal mining method with two pre-excavated tunnels for advancing
CN103016053B (en) Method of local filling to control surface subsidence in gob
CN105298496B (en) Complete adopt of reserved working face coal column is set to fill coal-mining method entirely
CN108952716B (en) Thick coal seam longwall working face multi-lane arrangement method
CN102352773B (en) Sectional filling method of old lane
CN110985058A (en) Grouting reinforcement method for fault fracture zone of coal face
CN202611695U (en) Novel rectangular coal roadway quick driving and bolting all-in-one machine
CN108756882A (en) A kind of district sublevel entry adopts recovery method without the short length of filling of driving formula
CN101457645B (en) Thick coal seam stepwise full-seam coal mining method
CN104533419B (en) Method for partial recovery of residual coal from wide coal pillar
CN109630112B (en) N00 mining method of cut top filling
CN102777185A (en) Inclined well shaft construction technology
CN202391424U (en) Supporting type comprehensive bolter miner
CN102261247B (en) Secondary coal-mining method for reversely filling paste in stripes
CN106907177A (en) A kind of girdle gob side entry retaining roadside packing method for protecting support
CN108204244A (en) The spoil interval method of collecting coal by the means of filling
CN105507947B (en) A kind of networking waste filling method
CN105240012B (en) F-type section coal-mining method allowing commingled mining of coal pillars
CN104343453B (en) Thick mineral deposit filling mining method in a kind of low-angle dip
CN103061767B (en) Lower to horizontal slice Dry-placed fill mining
CN108331580B (en) Clean and efficient coal mining method
CN202132053U (en) VI-level surrounding-rock double track tunnel lining support structure
CN102808624A (en) System and method for simultaneous mining of coal gangue
CN105971607A (en) Method for gob-side entry retaining of medium-thickness coal seam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190328

Address after: 273500 No. 169 Zoucheng Design Institute Road, Shandong Province

Patentee after: Yanzhou Mining Group Zouchenghua Construction Design Research Institute Co., Ltd.

Address before: 273522 No. 40 Fushan Road, Zoucheng City, Jining City, Shandong Province

Patentee before: Yankuang Group Ltd.

TR01 Transfer of patent right