CN102347613A - Method for automatically selecting on-line strategy and off-line strategy of transient security and stability emergency control of electrical power system - Google Patents

Method for automatically selecting on-line strategy and off-line strategy of transient security and stability emergency control of electrical power system Download PDF

Info

Publication number
CN102347613A
CN102347613A CN2011102799477A CN201110279947A CN102347613A CN 102347613 A CN102347613 A CN 102347613A CN 2011102799477 A CN2011102799477 A CN 2011102799477A CN 201110279947 A CN201110279947 A CN 201110279947A CN 102347613 A CN102347613 A CN 102347613A
Authority
CN
China
Prior art keywords
line
control strategy
strategy
transient
security
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011102799477A
Other languages
Chinese (zh)
Other versions
CN102347613B (en
Inventor
徐泰山
方勇杰
薛禹胜
李碧君
鲍颜红
罗剑波
余文杰
汪马翔
王胜明
郑亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nari Technology Co Ltd
Original Assignee
Nanjing NARI Group Corp
State Grid Electric Power Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing NARI Group Corp, State Grid Electric Power Research Institute filed Critical Nanjing NARI Group Corp
Priority to CN201110279947.7A priority Critical patent/CN102347613B/en
Publication of CN102347613A publication Critical patent/CN102347613A/en
Application granted granted Critical
Publication of CN102347613B publication Critical patent/CN102347613B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention belongs to the technical field of electrical power system security and stability control and is suitable for a transient security and stability emergency control system to automatically select an on-line strategy or an off-line strategy. On the basis of a transient security and stability quantitative analysis method, the invention provides the index of influence of running state change on transient security and stability for judging the adaptability of the on-line control strategy to the running state change. The invention comprises the following two parts: (1) issuance of the on-line strategy and confirmation of the effectiveness thereof, i.e. checking the security of the on-line strategy to judge whether issuing the on-line strategy to a control device, and judging the effectiveness of the issued on-line strategy constantly; and (2) selection of the on-line strategy and the off-line strategy during failure, i.e. selecting the on-line strategy when 'form characters' detected by the control device are as same as 'form characters' of the on-line strategy, the time for generating the on-line strategy is not long, and the influence degree of the running state change calculated on the basis of measured data of the control device on the transient security and stability meets the requirement; and otherwise, selecting the off-line strategy.

Description

Temporarily steady emergency control strategy of on-line of electric power system and off-line strategy automatic selecting method
Technical field
The invention belongs to power system safety and stability control technology field, be applicable to how the transient safe and stable emergency control system selects strategy of on-line or off-line strategy automatically.
Background technology
Changeable along with the expansion of electric power system scale and operational mode; Transient safe and stable (being called for short: the steady temporarily) emergency control policy of formulating through off-line analysis is difficult to realize optimal control; Even be difficult to guarantee the security and stability of electric power system; Need take online calculation mode to calculate the strategy of on-line of temporarily steady emergency control according to the actual motion state of electric power system.However, to determine transient stability control strategy requires a certain online computing time, assuming an average period
Figure 305633DEST_PATH_IMAGE001
(usually a few minutes), which requires online control strategy
Figure 541442DEST_PATH_IMAGE001
to 2
Figure 552123DEST_PATH_IMAGE001
time to adapt to changes in the state power system operation, in order to truly realize the control strategy according to the control line to ensure the safety of the power system transient stability.In fact, the running status of electric power system is constantly to change, and the temporarily steady characteristic variations of electric power system maybe be bigger within several minutes, and the On-line Control strategy of formulating based on the operation states of electric power system before several minutes possibly not satisfy temporarily steady requirement.For this reason; Patent " the power system safety stabilization emergency control policy automatically matching method " (patent No.: ZL200710135095.8) the give chapter and verse definition of " mode word " (for example equipment is thrown/moved back) in the safety and stability control device (be called for short: peace control device); Confirm that the Operation of Electric Systems section corresponding with being created on the line traffic control strategy (is called for short: " the mode word " of data section); When forecast failure takes place; By " the mode word " and peace control device nearest " mode word " of actual measurement constantly before fault of coupling On-line Control strategy, avoid the incompatibility problem of On-line Control strategy.In fact, in the electric power system of safety and stability characteristic complicacy, be difficult to (be called for short: propose suitable " mode word " peace control system), guarantee the reliability that On-line Control strategy and off-line control strategy are selected at safety stabilization control system.
Three links such as the validity check of the present invention's On-line Control strategy from On-line Control policy distribution, peace control device and control strategy selection improve the reliability of On-line Control strategy and the selection of off-line control strategy.In On-line Control policy distribution link, increased the adaptability judgement of carrying out this control strategy after the On-line Control strategy generates immediately based on current profile data,, be not issued in the peace control device for not guaranteeing steady On-line Control strategy temporarily; For the On-line Control strategy that is issued to peace control device, increased and constantly carried out the flow process that On-line Control strategy validity is checked based on new profile data; Select link at On-line Control strategy and off-line control strategy; Propose POWER SYSTEM STATE based on temporarily steady quantification theory and change computational methods temporarily steady nargin influence degree; Increased under the condition that the estimated value of considering temporarily steady nargin behind the peace control system real measured data need meet the demands, just possibly be chosen in the line traffic control strategy.
Summary of the invention
The present invention seeks to: accurately judge the adaptability that temporarily steady emergency control On-line Control strategy changes operation states of electric power system, improve the reliability that On-line Control strategy and off-line control strategy are selected.
The present invention adopts following technical scheme to realize, comprises the steps:
1) On-line Control policy calculation flow process: integrated application EMS state estimation real time data, WAMS real time data and peace control system real time data are carried out section data integration in the control centre, and calculate the temporarily steady emergency control strategy of on-line of the forecast failure that peace control system covered based on this profile data.
2) the On-line Control strategy is checked and is issued flow process: the integrated application EMS state estimation real time data in the control centre; WAMS real time data and peace control system real time data are carried out section data integration again; And based on this profile data; Consider the On-line Control strategy implement after the temporarily steady quantitative evaluation of this forecast failure; If surely can guarantee temporarily; Then with forecast failure information; On-line Control strategy and relevant information thereof (temporarily steady quantitative information; Section constantly; The generator and the information on load of peace control system monitoring in " mode word " and the profile data) (be called for short: peace control device), " significance bit " with this On-line Control strategy is changed to " effectively " simultaneously to flush to corresponding safety and stability control device; Otherwise, abandon this On-line Control strategy, do not carry out the On-line Control strategy and refresh.
3) validity of On-line Control strategy is checked flow process in the peace control device: the integrated application EMS state estimation real time data in the control centre; WAMS real time data and peace control system real time data are carried out section data integration again; And based on this profile data; Consider to pacify the temporarily steady quantitative evaluation after the On-line Control strategy of controlling in the device is implemented; If surely can guarantee temporarily; Information that will be relevant (temporarily steady quantitative information then with this forecast failure; Section constantly; The generator and the information on load of peace control system monitoring in " mode word " and the profile data) flush in the corresponding peace control device, " significance bit " with this On-line Control strategy is changed to " effectively " simultaneously; Otherwise, " significance bit " of this On-line Control strategy is changed to engineering noise.
4)? Envisioned after a failure in the security control devices and offline strategies online strategy selection process: When the security control unit detects a fault has occurred envisioned, security control device if the fault-line control strategy of the "significant" to " effective ", the corresponding cross-section moment at failure time data length of time than the set value, the" way of the word "security control device with the most recent time before failure measured" way the word "same, and security control system based on measured data to calculate the operating state of the power system transient stability changes in the degree of influence meet the requirements, then choose the appropriate control strategies online; otherwise, with the corresponding offline control strategy.
Effect and advantage:
One aspect of the present invention effectively reduces peace control device and selects the probability that does not satisfy the On-line Control strategy that surely requires temporarily for use through based on new profile data the On-line Control strategy being carried out steady temporarily check; Pass through on the other hand in On-line Control strategy and off-line control strategy link; Theoretical based on temporarily steady quantitative analysis; Estimated and considered to pacify the generator output of control system monitoring in real time and the temporarily steady nargin after the load variations, can significantly improve the reliability of control strategy selection.The present invention is with the practical applications of the temporarily steady emergency control technology of big force urges scale grid line.
Description of drawings
Fig. 1-Fig. 4 is the flow chart of the inventive method.
Embodiment
Below in conjunction with accompanying drawing 1-Fig. 4, the inventive method is described in detail.
Fig. 1-Fig. 4 is 4 independently circular treatment flow processs; Fig. 1 is an On-line Control policy calculation flow process; Fig. 2 is that flow process is checked and issued to the On-line Control strategy; Fig. 3 checks flow process to the validity of On-line Control strategy in the peace control device, and Fig. 4 is the selection flow process that On-line Control strategy and off-line control strategy in the back peace control device take place forecast failure.About the check flow process of Fig. 3, need explanation 2 points, the one, as long as in the peace control device On-line Control strategy is arranged, even without refreshing, the execution that still need circulate of this check flow process; The 2nd, controlling to peace in the validity check process of On-line Control strategy in the device; If detecting new On-line Control strategy has flushed in the peace control device; Then end the ongoing validity that refreshes preceding On-line Control strategy immediately and check, start to the validity of new On-line Control strategy and check.
Be that example describes below,, then take the parallel processing mode for a plurality of forecast failures by a forecast failure.
What step 1 was described among Fig. 1 is that integrated application EMS state estimation real time data, WAMS real time data and peace control system real time data are carried out section data integration in the control centre.
Step 2 is described among Fig. 1 is based on the profile data after step 1 is integrated, and the forecast failure that is covered to peace control system calculates corresponding temporarily steady emergency control strategy of on-line.
What step 1 was described among Fig. 2 is the On-line Control strategy generation that whether forecast failure has a new round in cycle detection Fig. 1 On-line Control policy calculation flow process; If the On-line Control strategy of forecast failure generates; Even the On-line Control strategy also gets into step 2 with last round of identical; Otherwise, continue to detect.
What step 2 was described among Fig. 2 is to obtain up-to-date EMS state estimation real time data, WAMS real time data and peace control system real time data, merges the section data integration of peace control system real time data again, obtains new profile data.
Step 3 is described among Fig. 2 is based on new profile data, carries out steady temporarily check of the On-line Control strategy that Fig. 1 step 2 generates and calculates.
What step 4 was described among Fig. 2 is if the temporarily steady check result of step 3 is safety and stability, then gets into step 5; Otherwise, return step 1.
What step 5 was described among Fig. 2 is according to surely checking result of calculation temporarily; Forecast failure information, On-line Control strategy and relevant information thereof (generator and the information on load of peace control system monitoring in temporarily steady quantitative information, the section moment, " mode word " and the profile data) are flushed in the corresponding peace control device, and " significance bit " with this On-line Control strategy is changed to " effectively " simultaneously.Wherein, temporarily steady quantitative information comprises that the transient state angle stability dominant pattern relevant with the element of peace control system monitoring and a plurality of dominant patterns and nargin, transient voltage fall load collection and nargin and transient frequency of safe weak node collection and nargin, the stable weakness of transient voltage and be offset safe weak node/generator collection and nargin.
Step 1 is described among Fig. 3 is certain forecast failure existing On-line Control strategy whether in the cycle detection peace control device, if having, gets into step 2; Otherwise, continue to detect.
What step 2 was described among Fig. 3 is to obtain up-to-date EMS state estimation real time data, WAMS real time data and peace control system real time data, merges the section data integration of peace control system real time data again, obtains new profile data.
Step 3 is described among Fig. 3 is based on new profile data, carries out steady temporarily check of this On-line Control strategy and calculates.
What step 4 was described among Fig. 3 is if the temporarily steady check result of step 3 is safety and stability, then gets into step 5; Otherwise, get into step 6.
What step 5 was described among Fig. 3 is according to surely checking result of calculation temporarily; To flush in the corresponding peace control device with the generator and the information on load of peace control system monitoring in this forecast failure and the temporarily steady quantitative information of On-line Control policy-related (noun), the section moment, " mode word " and the profile data, " significance bit " with this On-line Control strategy is changed to " effectively " simultaneously.
Step 6 is described among Fig. 3 is that " significance bit " with this On-line Control strategy is changed to engineering noise.
What step 1 was described among Fig. 4 is whether the cycle detection forecast failure takes place, if detecting forecast failure takes place, then gets into step 2; Otherwise, continue to detect.
What step 2 was described among Fig. 4 is if " significance bit " of this On-line Fault control strategy is " effectively " in the peace control device; Duration constantly takes place less than set point apart from fault in corresponding profile data constantly; And " the mode word " of On-line Control strategy is identical with " mode word " that peace control device is surveyed before fault recently constantly, then gets into step 3; Otherwise, get into step 6.
Described in step 3 in Figure 4 is how the security control device and stored in the fault-line transient stability control strategy relevant quantitative information security control system monitors the generator load the appropriate information in the data section, and the fault occurred before the most recent measured time generators, load data, to estimate the fault-line control strategy implemented under the transient angle stability margin
Figure 83861DEST_PATH_IMAGE002
, transient voltage drop margin of safety
Figure 179993DEST_PATH_IMAGE003
, transient voltage stability margin and transient frequency deviation shift safety margin .Concrete computing formula is seen formula (1)-(4).
Figure 957959DEST_PATH_IMAGE006
Figure 603704DEST_PATH_IMAGE007
(1)
Figure 853420DEST_PATH_IMAGE008
Figure 838693DEST_PATH_IMAGE009
(2)
Figure 210769DEST_PATH_IMAGE010
Figure 281493DEST_PATH_IMAGE011
(3)
Figure 898681DEST_PATH_IMAGE012
Figure 738461DEST_PATH_IMAGE013
(4)
Formula (1), N is the security control system to monitor the number of generator sets, m-line control measures for the implementation of fault transient angle stability of the dominant model, as well as a number of stability margin and margin of difference is less than dominant mode setting value of the total number of sub-dominant pattern of patterns,
Figure 219121DEST_PATH_IMAGE014
i-th generator clustering mode stability margin,?
Figure 573879DEST_PATH_IMAGE015
i-th generator grouping mode j-generator participation factor, critical group generator participation factor is positive, the remaining group generator participation factor is negative,
Figure 430977DEST_PATH_IMAGE016
for the security control system in recent times measured before the failure of the j generator active power output,
Figure 187580DEST_PATH_IMAGE017
control strategy for online data in the corresponding section of the generator active power output,
Figure 839141DEST_PATH_IMAGE018
for the generator active power output Max, a is the coefficient set,
Figure 884458DEST_PATH_IMAGE002
is
Figure 341984DEST_PATH_IMAGE019
( ) a minimum.
Formula (2), n is the security control system monitors the load transient voltage drop insecurity total number of nodes,
Figure 536741DEST_PATH_IMAGE020
is weak nodes of node i transient voltage drop margin of safety,
Figure 803774DEST_PATH_IMAGE021
,
Figure 737095DEST_PATH_IMAGE022
for the security control system in recent time before failure node i is the measured load apparent power, control strategy for the online section data corresponding node in the load apparent power, if and are 0, then calculate the load nodes removed, if
Figure 280892DEST_PATH_IMAGE023
is not 0, then the is taken as
Figure 30859DEST_PATH_IMAGE023
Otherwise
Figure 836267DEST_PATH_IMAGE024
is taken as
Figure 376969DEST_PATH_IMAGE022
, b is the coefficient set,
Figure 817178DEST_PATH_IMAGE003
is
Figure 417924DEST_PATH_IMAGE025
(
Figure 943583DEST_PATH_IMAGE009
) the minimum.
Formula (3), k is the security control system to monitor the total load transient voltage stability is weak,
Figure 287977DEST_PATH_IMAGE026
is weak load in the i-th load transient voltage stability margin,
Figure 785954DEST_PATH_IMAGE027
,
Figure 354339DEST_PATH_IMAGE028
for the security control system in recent times measured before the failure load i is the apparent power,
Figure 570556DEST_PATH_IMAGE029
control strategy for online data in the corresponding section of the load apparent power,
Figure 16843DEST_PATH_IMAGE029
control strategy for online data in the corresponding section of the load apparent power, if
Figure 369327DEST_PATH_IMAGE029
and
Figure 46296DEST_PATH_IMAGE028
are 0, then the calculation to remove The load, if
Figure 546548DEST_PATH_IMAGE029
is not 0, then
Figure 232744DEST_PATH_IMAGE030
is taken as
Figure 502051DEST_PATH_IMAGE029
, or
Figure 615501DEST_PATH_IMAGE030
is taken as
Figure 540731DEST_PATH_IMAGE028
, c is the set coefficient, is
Figure 154432DEST_PATH_IMAGE031
(
Figure 2565DEST_PATH_IMAGE011
) the minimum.
Formula (4) in, l the security control system to monitor the frequency offset weak transient generators and loads total,
Figure 149513DEST_PATH_IMAGE032
generator is weak, the load in the generator or the i-th frequency offset of the transient load margin, , is security control system in recent time before failure measured active power generator or load i,
Figure 876663DEST_PATH_IMAGE035
control strategy for online data in the corresponding section of the active power generator or load, if
Figure 776486DEST_PATH_IMAGE035
and
Figure 404913DEST_PATH_IMAGE034
are 0, then remove the power calculation machine or the load, if is not 0, then
Figure 129473DEST_PATH_IMAGE036
is taken as
Figure 251013DEST_PATH_IMAGE035
, or
Figure 620814DEST_PATH_IMAGE036
is taken as
Figure 358349DEST_PATH_IMAGE034
, d is the set coefficient,
Figure 155403DEST_PATH_IMAGE005
is
Figure 764239DEST_PATH_IMAGE037
(
Figure 734469DEST_PATH_IMAGE013
) the minimum.
Figure 4 is described in Step 4 If the estimate of the transient angle stability margin, transient voltage drop margin of safety, transient voltage stability margin and transient frequency offset safety margins were greater than the corresponding setting that
Figure 745151DEST_PATH_IMAGE038
,
Figure 775424DEST_PATH_IMAGE039
,
Figure 871556DEST_PATH_IMAGE040
,
Figure 583160DEST_PATH_IMAGE041
, the process proceeds to step 5; otherwise, go to step 6.
What step 5 was described among Fig. 4 is to select the corresponding online control strategy for use.
What step 6 was described among Fig. 4 is to select corresponding off-line control strategy for use.

Claims (4)

1. temporarily steady emergency control strategy of on-line of electric power system and off-line strategy automatic selecting method may further comprise the steps:
On-line Control policy calculation flow process: integrated application EMS state estimation real time data, WAMS real time data and safety stabilization control system in the control centre (be called for short: peace control system) real time data is carried out the power system operation section, and (be called for short: section) data are integrated, and calculate transient safe and stable (being called for short: steady temporarily) the emergency control strategy of on-line of the forecast failure that peace control system covered based on this profile data;
The On-line Control strategy is checked and is issued flow process: the integrated application EMS state estimation real time data in the control centre; WAMS real time data and peace control system real time data are carried out section data integration again; And based on this profile data; Consider the On-line Control strategy implement after the temporarily steady quantitative evaluation of this forecast failure; If surely can guarantee temporarily; Then with forecast failure information; On-line Control strategy and relevant information thereof (temporarily steady quantitative information; Section constantly; The generator and the information on load of peace control system monitoring in " mode word " and the profile data) (be called for short: peace control device), " significance bit " with this On-line Control strategy is changed to " effectively " simultaneously to flush to corresponding safety and stability control device; Otherwise, abandon this On-line Control strategy, do not carry out the On-line Control strategy and refresh;
The validity of On-line Control strategy is checked flow process in the peace control device: the integrated application EMS state estimation real time data in the control centre; WAMS real time data and peace control system real time data are carried out section data integration again; And based on this profile data; Consider to pacify the temporarily steady quantitative evaluation after the On-line Control strategy of controlling in the device is implemented; If surely can guarantee temporarily; Information that will be relevant (temporarily steady quantitative information then with this forecast failure; Section constantly; The generator and the information on load of peace control system monitoring in " mode word " and the profile data) flush in the corresponding peace control device, " significance bit " with this On-line Control strategy is changed to " effectively " simultaneously; Otherwise, " significance bit " of this On-line Control strategy is changed to engineering noise;
Expected after the failure security control device online and offline strategies strategy selection process: When the security control unit detects a fault has occurred envisioned, security control device if the fault-line control strategy of the "significant" to "active", the corresponding sectional data from the moment of failure time duration is less than the set value, the "way of the word" security control device with the most recent time before failure measured "way the word" same, and security control system based on measured data to calculate the operating state of the power system changes in the degree of influence on the transient stability to meet the requirements, the selection of the appropriate line control strategy; Otherwise, use the appropriate line control strategy.
2. require temporarily steady emergency control strategy of on-line of described electric power system and off-line strategy automatic selecting method according to right 1; It is characterized in that; Step 2) check of On-line Control strategy is independently a cycle calculations and judgement flow process with issuing flow process; Generated the On-line Control strategy in case detect step 1) On-line Control policy calculation flow process; Then carry out section data integration again; And carry out surely checking temporarily of On-line Control strategy based on this profile data and calculate; If this On-line Control strategy; Under new running status, still can guarantee the transient safe and stable of corresponding forecast failure; Then according to surely checking result of calculation temporarily; With forecast failure information; On-line Control strategy and relevant information thereof (temporarily steady quantitative information; Section constantly; The generator and the information on load of peace control system monitoring in " mode word " and the profile data) flush in the corresponding peace control device, " significance bit " with this On-line Control strategy is changed to " effectively " simultaneously; Otherwise, abandon this On-line Control strategy, do not carry out the On-line Control strategy and refresh; Wherein, temporarily steady quantitative information comprises that the transient state angle stability dominant pattern relevant with the element of peace control system monitoring and a plurality of dominant patterns and nargin, transient voltage fall load collection and nargin and transient frequency of safe weak node collection and nargin, the stable weakness of transient voltage and be offset safe weak node/generator collection and nargin.
3 claimed in claim 1 wherein the power system transient stability emergency control strategies online and offline strategies automatic selection method, wherein the step 3)? Security control device online checking the validity of the process control strategy is also a separate cycle calculation and judgment process, upon detection of the security control device stored in the line control strategy, the re-integration section data and section data based on the on-line transient stability control policy checking calculation, if stored in the security control line control apparatus strategy in the new operating conditions able to ensure appropriate security and stability expected transient faults, then check the results based on the information associated with the fault (transient stability quantitative information, the cross section moment, "the word means," and Section data security control system monitors the generator and load information) flushed to the corresponding security control device, while the online control strategy of the "significant" is set to "active"; Otherwise, the line control strategy of the "significant" is set to "invalid."
As claimed in claim 1 wherein the power system transient stability emergency control strategies online and offline strategies automatic selection method, wherein step 4)? Expected after a failure in the security control unit control strategies online and offline control strategy selection process is an independent loop calculation and selection processes, security control device upon detection of expected failure has occurred, immediately following judgments: If the security control unit the fault-line control strategy of the "significant" to "active", the corresponding cross-section moments of failure time data from the length of time less than the set value, the "way of the word" security control device with the most recent time before failure measured "way the word" same, and security control system based on measured data, according to the formula (1) - ( 4) to calculate the transient angle stability margin, transient voltage drop margin of safety, transient voltage stability margin and transient frequency offset safety margins were greater than the corresponding set value, then use online control strategies; otherwise , the use of off-line control strategy;
Figure 790892DEST_PATH_IMAGE001
Figure 929749DEST_PATH_IMAGE002
(1)
Figure 326675DEST_PATH_IMAGE004
(2)
Figure 311948DEST_PATH_IMAGE005
Figure 684024DEST_PATH_IMAGE006
(3)
Figure 489169DEST_PATH_IMAGE007
Figure 542576DEST_PATH_IMAGE008
(4)
Formula (1), N is the security control system to monitor the number of generator sets, m-line control measures for the implementation of fault transient angle stability of the dominant model, as well as a number of stability margin and margin of difference is less than dominant mode setting value of the total number of sub-dominant pattern of patterns,
Figure 444673DEST_PATH_IMAGE009
i-th generator clustering mode stability margin,
Figure 925332DEST_PATH_IMAGE010
i-th generator grouping mode j-generator participation factor, critical group generator participation factor is positive, and the remaining group generator participation factor is negative, for the security control system in recent times measured before the failure of the j generator active power output,
Figure 137188DEST_PATH_IMAGE012
for online control strategy in the corresponding section data generator active power output,
Figure 97054DEST_PATH_IMAGE013
maximum value for the generator active power output, a is the set of coefficients;
Formula (2), n is the security control system monitors the load transient voltage drop weak total number of nodes,
Figure 312397DEST_PATH_IMAGE014
is weak nodes of node i transient voltage drop margin of safety, ,
Figure 487343DEST_PATH_IMAGE016
is the security control system in the last moments before the failure load of node i is the measured apparent power,
Figure 364032DEST_PATH_IMAGE017
control strategy for the online section data corresponding node in the load apparent power, if
Figure 186495DEST_PATH_IMAGE017
is not 0,
Figure 453528DEST_PATH_IMAGE018
is taken as
Figure 714745DEST_PATH_IMAGE017
, or is taken as
Figure 439304DEST_PATH_IMAGE016
, b is the set coefficient;
Formula (3), k is the security control system to monitor the total load transient voltage stability is weak,
Figure 193634DEST_PATH_IMAGE019
is weak load in the i-th load transient voltage stability margin, ,
Figure 283392DEST_PATH_IMAGE021
for the security control system in recent time before failure load i is the measured apparent power, control strategy for online data in the corresponding section of the load apparent power, if
Figure 751599DEST_PATH_IMAGE022
Not is 0, is taken as
Figure 670194DEST_PATH_IMAGE022
, or
Figure 333256DEST_PATH_IMAGE023
is taken as
Figure 796599DEST_PATH_IMAGE021
, c is the set coefficient;
Formula (4) in, l the security control system to monitor the frequency offset weak transient generators and loads total,
Figure 140992DEST_PATH_IMAGE024
is weak generators, load in the i-th generator or load transient frequency offset margin,
Figure 435708DEST_PATH_IMAGE025
,
Figure 207354DEST_PATH_IMAGE026
for the security control system malfunction before the most recent time i measured active power generator or load,
Figure 739353DEST_PATH_IMAGE027
control strategy for the online data of the corresponding sections active power generator or load, if
Figure 621858DEST_PATH_IMAGE027
is not 0,
Figure 974342DEST_PATH_IMAGE028
is taken as
Figure 979207DEST_PATH_IMAGE027
, or
Figure 417142DEST_PATH_IMAGE028
is taken as
Figure 103338DEST_PATH_IMAGE026
, d is the set factor.
CN201110279947.7A 2011-09-21 2011-09-21 Method for automatically selecting on-line strategy and off-line strategy of transient security and stability emergency control of electrical power system Active CN102347613B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110279947.7A CN102347613B (en) 2011-09-21 2011-09-21 Method for automatically selecting on-line strategy and off-line strategy of transient security and stability emergency control of electrical power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110279947.7A CN102347613B (en) 2011-09-21 2011-09-21 Method for automatically selecting on-line strategy and off-line strategy of transient security and stability emergency control of electrical power system

Publications (2)

Publication Number Publication Date
CN102347613A true CN102347613A (en) 2012-02-08
CN102347613B CN102347613B (en) 2015-05-13

Family

ID=45545990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110279947.7A Active CN102347613B (en) 2011-09-21 2011-09-21 Method for automatically selecting on-line strategy and off-line strategy of transient security and stability emergency control of electrical power system

Country Status (1)

Country Link
CN (1) CN102347613B (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102638040A (en) * 2012-04-16 2012-08-15 中国南方电网有限责任公司 Online setting method of safety and stability emergency control fixed value of electric power system
CN102664463A (en) * 2012-05-16 2012-09-12 北京四方继保自动化股份有限公司 Realization method for online control strategies of security control device with self-adaption running modes
CN102662663A (en) * 2012-03-28 2012-09-12 国网电力科学研究院 Realization method for configurable decision software of stability control device
CN102664464A (en) * 2012-05-16 2012-09-12 北京四方继保自动化股份有限公司 On-line control strategy switching method for security control device by using strategy effective conditions
CN104809512A (en) * 2014-12-18 2015-07-29 国电南瑞科技股份有限公司 Rapid assessment method for performance indexes of different emergency control measures in electric power system
CN105098763A (en) * 2014-05-16 2015-11-25 国家电网公司 Transient voltage stable on-line assessment method based on WAMS and EMS
CN105141029A (en) * 2015-06-19 2015-12-09 国电南瑞科技股份有限公司 Power system security and stability adaptive emergency control system and method
CN105139075A (en) * 2015-05-04 2015-12-09 国电南瑞科技股份有限公司 Electric power system safety stabilization prevention control rolling decision method in consideration of real-time plan
CN106100918A (en) * 2016-08-30 2016-11-09 国网山东省电力公司滨州供电公司 A kind of substation data based on EMS system does not refresh detection method
CN107069699A (en) * 2016-11-23 2017-08-18 国电南瑞科技股份有限公司 A kind of optimal emergency control policy method for fast searching of power system
CN107342588A (en) * 2017-07-18 2017-11-10 国电南瑞科技股份有限公司 The adaptive emergency control method of mains frequency of meter and transmission cross-section limit
CN107832915A (en) * 2017-10-12 2018-03-23 国网安徽省电力公司 A kind of E formatted file automatic generation methods of stability control strategy
CN106033888B (en) * 2015-03-19 2018-10-09 国家电网公司 Alternating current circuit failure based on prompt drop DC sensitivities pacifies control amount online evaluation method
CN112039074A (en) * 2020-09-25 2020-12-04 贵州电网有限责任公司 Online safety and stability emergency control strategy mode word generation method
CN114156934A (en) * 2021-11-04 2022-03-08 云南电网有限责任公司 Wind-water coordination active real-time control method based on online dynamic quota adjustment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3677668B2 (en) * 1997-12-12 2005-08-03 株式会社日立製作所 Power system stabilization system and power system stability monitoring system
JP2007189840A (en) * 2006-01-13 2007-07-26 Toshiba Corp Power system stabilizing apparatus
CN101299533A (en) * 2007-11-08 2008-11-05 国网南京自动化研究院 Reliability design method for large electric network safety steady cooperativeness defensive system
CN101299539A (en) * 2007-11-08 2008-11-05 国网南京自动化研究院 Large electric network on-line preventing control method based on static state and transient safety steady mode
CN101807798A (en) * 2010-04-20 2010-08-18 国网电力科学研究院 Section data integration method for power system safety and stability online analysis

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3677668B2 (en) * 1997-12-12 2005-08-03 株式会社日立製作所 Power system stabilization system and power system stability monitoring system
JP2007189840A (en) * 2006-01-13 2007-07-26 Toshiba Corp Power system stabilizing apparatus
CN101299533A (en) * 2007-11-08 2008-11-05 国网南京自动化研究院 Reliability design method for large electric network safety steady cooperativeness defensive system
CN101299539A (en) * 2007-11-08 2008-11-05 国网南京自动化研究院 Large electric network on-line preventing control method based on static state and transient safety steady mode
CN101807798A (en) * 2010-04-20 2010-08-18 国网电力科学研究院 Section data integration method for power system safety and stability online analysis

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周良松等: "电力系统暂态稳定控制策略表的应用研究", 《电网技术》 *
薛禹胜等: "暂态电压稳定性及电压跌落可接受性", 《电力系统自动化》 *

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102662663A (en) * 2012-03-28 2012-09-12 国网电力科学研究院 Realization method for configurable decision software of stability control device
CN102638040B (en) * 2012-04-16 2014-07-02 中国南方电网有限责任公司 Online setting method of safety and stability emergency control fixed value of electric power system
CN102638040A (en) * 2012-04-16 2012-08-15 中国南方电网有限责任公司 Online setting method of safety and stability emergency control fixed value of electric power system
CN102664463A (en) * 2012-05-16 2012-09-12 北京四方继保自动化股份有限公司 Realization method for online control strategies of security control device with self-adaption running modes
CN102664464A (en) * 2012-05-16 2012-09-12 北京四方继保自动化股份有限公司 On-line control strategy switching method for security control device by using strategy effective conditions
CN102664464B (en) * 2012-05-16 2014-09-17 北京四方继保自动化股份有限公司 On-line control strategy switching method for security control device by using strategy effective conditions
CN102664463B (en) * 2012-05-16 2015-02-25 北京四方继保自动化股份有限公司 Realization method for online control strategies of security control device with self-adaption running modes
CN105098763B (en) * 2014-05-16 2018-01-19 国家电网公司 A kind of Transient Voltage Stability online evaluation method based on WAMS and EMS
CN105098763A (en) * 2014-05-16 2015-11-25 国家电网公司 Transient voltage stable on-line assessment method based on WAMS and EMS
CN104809512A (en) * 2014-12-18 2015-07-29 国电南瑞科技股份有限公司 Rapid assessment method for performance indexes of different emergency control measures in electric power system
CN106033888B (en) * 2015-03-19 2018-10-09 国家电网公司 Alternating current circuit failure based on prompt drop DC sensitivities pacifies control amount online evaluation method
CN105139075B (en) * 2015-05-04 2019-07-05 国电南瑞科技股份有限公司 Consider that the power system security planned in real time stablizes prevention and control Rolling decision method
CN105139075A (en) * 2015-05-04 2015-12-09 国电南瑞科技股份有限公司 Electric power system safety stabilization prevention control rolling decision method in consideration of real-time plan
WO2016201840A1 (en) * 2015-06-19 2016-12-22 国电南瑞科技股份有限公司 Security and stability adaptive emergency control system and method for power system
CN105141029A (en) * 2015-06-19 2015-12-09 国电南瑞科技股份有限公司 Power system security and stability adaptive emergency control system and method
CN106100918A (en) * 2016-08-30 2016-11-09 国网山东省电力公司滨州供电公司 A kind of substation data based on EMS system does not refresh detection method
CN107069699A (en) * 2016-11-23 2017-08-18 国电南瑞科技股份有限公司 A kind of optimal emergency control policy method for fast searching of power system
CN107069699B (en) * 2016-11-23 2020-05-19 国电南瑞科技股份有限公司 Rapid search method for optimal emergency control strategy of power system
CN107342588A (en) * 2017-07-18 2017-11-10 国电南瑞科技股份有限公司 The adaptive emergency control method of mains frequency of meter and transmission cross-section limit
CN107342588B (en) * 2017-07-18 2020-05-19 国电南瑞科技股份有限公司 Power grid frequency self-adaptive emergency control method considering power transmission section quota
CN107832915A (en) * 2017-10-12 2018-03-23 国网安徽省电力公司 A kind of E formatted file automatic generation methods of stability control strategy
CN107832915B (en) * 2017-10-12 2021-06-11 国网安徽省电力公司 E-format file automatic generation method of stability control strategy
CN112039074A (en) * 2020-09-25 2020-12-04 贵州电网有限责任公司 Online safety and stability emergency control strategy mode word generation method
CN112039074B (en) * 2020-09-25 2022-01-18 贵州电网有限责任公司 Online safety and stability emergency control strategy mode word generation method
CN114156934A (en) * 2021-11-04 2022-03-08 云南电网有限责任公司 Wind-water coordination active real-time control method based on online dynamic quota adjustment
CN114156934B (en) * 2021-11-04 2024-01-26 云南电网有限责任公司 Wind-water coordination active real-time control method based on online dynamic quota adjustment

Also Published As

Publication number Publication date
CN102347613B (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN102347613A (en) Method for automatically selecting on-line strategy and off-line strategy of transient security and stability emergency control of electrical power system
CN105656024B (en) Electric power system operation standby margin of safety online evaluation method
CN101557110B (en) On-line analysis and aid decision making method for low-frequency oscillation of electric power system
CN102324743B (en) Screening method for expected fault in online transient safety and stability assessment of power system
CN104678264B (en) The online Insulation monitoring of AUV DC power-supply systems and fault treating apparatus and method
CN102638041B (en) Method forquickly checking safety and stability of scheduling operation of power system on line
CN106549425B (en) A kind of failure isolated island fast control method containing flexible direct current
CN103514364B (en) The grid equipment overload aid decision computational methods of meter and load transfer measure
CN103107544B (en) On-line pre-deciding method for offshore oilfield group power grid emergency control
CN105207196B (en) A kind of power grid critical circuits discrimination method based on effective power flow betweenness
CN106099906B (en) A kind of power system security stablizes online integrated campaign method
CN104112076B (en) Operation risk assessment method and assessment system based on fuzzy mathematics
CN101419267A (en) Electric network fault on-line rapid diagnosis and analysis method
CN101969202A (en) Method for recognizing transmission section power limit interval of power system transient stability
CN107732906B (en) Cutter cutting control method for dynamically tracking transient power angle weak stability mode
JP6047425B2 (en) Isolated operation detection device and isolated operation detection method
CN103577698B (en) A kind of on-Line Voltage stabilizing determination method of alternating current-direct current combined hybrid system
CN102185291B (en) Island detection method and island detection system
CN108599225A (en) A kind of commutation failure forecast Control Algorithm and its device based on direct current tolerance
CN108037387A (en) The equipment fault analysis method and device collected based on cluster
Voropai et al. A suite of intelligent tools for early detection and prevention of blackouts in power interconnections
CN105139075B (en) Consider that the power system security planned in real time stablizes prevention and control Rolling decision method
Zhang et al. Detection and isolation of sensor faults of wind turbines using sliding mode observers
CN206673564U (en) A kind of pump-storage generator accident standby trip protection device
RU2530836C2 (en) Automated distributed control for electrical devices capable to regulate their longitudinal resistance in order to unload components of power pool system in case of their overloading

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: NANJING NARI CO., LTD.

Free format text: FORMER OWNER: STATE GRID ELECTRIC POWER RESEARCH INSITITUTE

Effective date: 20130312

Free format text: FORMER OWNER: NANJING NARI CO., LTD.

Effective date: 20130312

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20130312

Address after: Nan Shui Road Gulou District of Nanjing city of Jiangsu Province, No. 8 210003

Applicant after: Nanjing Nari Co., Ltd.

Address before: Nan Shui Road Gulou District of Nanjing city of Jiangsu Province, No. 8 210003

Applicant before: State Grid Electric Power Research Insititute

Applicant before: Nanjing Nari Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: NARI TECHNOLOGY DEVELOPMENT CO., LTD.

Free format text: FORMER OWNER: NANJING NARI CO., LTD.

Effective date: 20131225

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 210003 NANJING, JIANGSU PROVINCE TO: 210061 NANJING, JIANGSU PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20131225

Address after: 210061 D10, Nanjing high tech Industrial Development Zone, Jiangsu, China

Applicant after: NARI Technology Development Co., Ltd.

Address before: Nan Shui Road Gulou District of Nanjing city of Jiangsu Province, No. 8 210003

Applicant before: Nanjing Nari Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant