CN102332695B - Lifting method of submarine cable terminal landing platform - Google Patents

Lifting method of submarine cable terminal landing platform Download PDF

Info

Publication number
CN102332695B
CN102332695B CN 201110254417 CN201110254417A CN102332695B CN 102332695 B CN102332695 B CN 102332695B CN 201110254417 CN201110254417 CN 201110254417 CN 201110254417 A CN201110254417 A CN 201110254417A CN 102332695 B CN102332695 B CN 102332695B
Authority
CN
China
Prior art keywords
cable
extra large
steel wire
wire rope
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110254417
Other languages
Chinese (zh)
Other versions
CN102332695A (en
Inventor
李士涛
朱绍华
李鹏
商涛
前德门
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cnooc Shenzhen Ocean Engineering Technology Service Co ltd
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, Offshore Oil Engineering Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN 201110254417 priority Critical patent/CN102332695B/en
Publication of CN102332695A publication Critical patent/CN102332695A/en
Application granted granted Critical
Publication of CN102332695B publication Critical patent/CN102332695B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention relates to a lifting method of a submarine cable terminal landing platform, which comprises the following steps: 1) drawing a steel wire rope of a hoist of the platform onto a deck of a cable laying ship; 2) connecting a lute head short rope on a submarine cable dragging head; 3) mounting a clamp on a submarine cable; 4) connecting the steel wire rope of the hoist of the platform with the clamp, and laying and fixing the steel wire rope on the submarine cable through a plurality of binding bands; 5) connecting the steel wire rope of the hoist with the short rope into a whole in the position of the end of the submarine cable; 6) performing smooth treatment on all connecting points; 7) starting a cable laying machine on the cable laying ship of the hoist of the platform to synchronously send out the submarine cable, removing a steel wire rope clip after the head of the submarine cable is out of a submarine cable protecting pipe, untying the binding bands one by one, and separating the steel wire rope from the submarine cable; and 8) placing the submarine cable on the deck till the clamp is out of the submarine cable protecting pipe, and enabling the submarine cable to land the platform. The whole process adopts the continuous operation almost, the head of the submarine cable is rapidly lifted in place, the operation is time-saving and labor-saving, operation ship days are reduced, and the working efficiency is improved.

Description

Land the method for improving of the submarine cable terminal of platform
Technical field
The present invention relates to method for improving, relate in particular to the method for improving that a kind of submarine cable terminal is landed platform, belong to the offshore oil field of engineering technology.
Background technology
The exploitation of new forms of energy such as offshore oilfield construction and Oversea wind power generation all needs a large amount of extra large cables to be used for connecting center control platform between each production platform or each windmill, is used for the support of energising, communication.The pattern of sea cable mainly comprises: power cable, optical cable, optoelectronic composite cable and Long-distance Control umbilical cables.These extra large cables lay the difference very big with the laying existence of overland cable, and extra large cable laying task is comparatively complicated.
In extra large cable laid processes, need employ specialty shop cable ship and corresponding specialty shop cable equipment, these shop cable equipment comprise: a whole set of system of burying cable machine, diving, underwater robot (ROV), global differential positioning system (DGPS) etc. supports that facility are huge, and cost is higher.Especially under the situation of carrying out deep water shop cable operation and sea situation environmental condition difference, needing large-scale shop cable ship as support, is the industry of excessive risk, high investment.Therefore, extra large cable lays the height of quality, the efficient of worker's method, skill and technique, directly has influence on the cost of engineering.
The sea cable lays and comprises: the seabed of extra large cable is laid and extra large cable terminal is landed platform and laid.
At present, vertically to land the platform operations method as follows for extra large cable terminal:
⑴ adopt hoist engine as the power source of the extra large cable walking of traction, need be installed in advance on the platform; The wire rope pulley of hoist engine is hung above the oral top of cable pillar, platform sea (annotate: be subjected to the influence of the restriction of platform small space, platform production equipment, general suspension height is only about 2 meters) as turning point; Shop cable ship is located near the platform.
⑵ the steel wire penetrating pulley of hoist engine, enter extra large cable pillar, go out pillar bottom horn mouth, turn back to the eye splice shackle that the water surface arrives shop cable ship, steel wire rope again and connect the dilatory head of extra large cable.
⑶ platform hoist engine scrolling haulage cable, shop cable ship discharges extra large cable synchronously, and steel wire rope pulls extra large cable end entry, enters pillar, goes out pillar arrival pillar crown pulley.
So far, extra large cable is taken out and is dragged lifting work and be far from finishing, generally speaking, even the junction box is positioned near the pillar, the length that extra large cable also need be pulled out 12 meters to 15 meters of pillars could satisfy the requirement that terminal is made; In particular cases, the extra large cable that has need be extracted 40 meters just can arrive at the junction box position to 50 meters.
Because extra large cable end arrives pillar top pulley and is obstructed, the hoist engine dynamic failure, traditional method of dragging of taking out is:
⑴ time-out is taken out and is dragged, and temporary fixed extra large cable prevents from gliding;
⑵ untie being connected of steel wire rope and extra large cable end, manually utilizes chain block (jack) to substitute hoist engine and take out piecemeal by rice and drag, and it is intermittent to take out the process of dragging, until pulling out the length of enough advancing junction box's wiring.
Above-mentioned whole operation process not only wastes time and energy, and, when expending engineering shop cable boatman.
Be subjected to the restriction of environmental working condition, marine engineering not only must be provided support to implement by " working ship ", and " working ship " could work and restricted by weather conditions, and the operating time window is very valuable.In extra large cable laying project, especially in the relatively poor marine site of sea situation, shop cable ship mostly is large-scale operation boats and ships, and daily cost is high.Therefore, one save time, work skill and technique in labour-saving can reduce hundreds of thousands even engineering cost up to a million; Sometimes carry previous hour, engineering just might be kept away public attention and be caught up with safety, completion smoothly before a weather window.Based on this kind situation, improve worker's method of the individual work link in the extra large cable laying process, shorten the operating time, increase work efficiency, reduce the operation ship sky, be the target that engineers and technicians lay siege to.And extra large cable terminal is landed the method for improving of platform, namely is one of innovation and creation in this process.
Summary of the invention
Main purpose of the present invention is to overcome the above-mentioned shortcoming that prior art exists, and provide a kind of method for improving that lands the submarine cable terminal of platform, its steel wire rope with hoist engine directly is strapped on the extra large cable, by lockset steel wire rope and extra large cable are connected as a single entity, land in the process of pulling at extra large cable poling, when extra large cable does not arrive at pulley, the cable walking of hoist engine rope traction sea; Treat that extra large cable end arrives pulley, progressively untie the lockset between steel wire rope and the extra large cable, extra large cable is separated with steel wire rope, steel wire rope walks on and passes pulley and arrive at hoist engine, extra large cable is followed steel wire rope, and to go out pillar then be by manually being placed on the deck, whole process is almost works continuously, and extra large cable end is lifted to put in place fast, time saving and energy saving; Reduce the operation ship sky, improved operating efficiency.
The objective of the invention is to be realized by following technical scheme:
A kind of method for improving that lands the submarine cable terminal of platform is characterized in that: adopt following steps:
The first step: start the hoist engine on the cable ship of shop, the steel wire rope of platform hoist engine is dragged on the deck of shop cable ship;
Second step: connect the short rope of an eye splice at the dilatory head of extra large cable;
The 3rd step: one anchor clamps are installed at extra large cable;
The 4th step: the steel wire rope of platform hoist engine is connected with anchor clamps, and, steel wire rope sticked with several bandages be fixed on the extra large cable extremely extra large cable and draw a position;
The 5th step: in extra large cable-end head position, utilize rope cramp that the steel wire rope of hoist engine and short rope are connected as one;
The 6th step: smooth treatment is carried out on each surface, tie point position;
The 7th step: start the platform hoist engine and involve in steel wire rope, the cable laying machine that is located on the cable ship of shop is sent extra large cable synchronously, after extra large cable end goes to sea the cable pillar, remove rope cramp, and when being accompanied by extra large cable and going to sea the cable pillar, untie bandage one by one, steel wire rope is separated with extra large cable;
The 8th step: the steel wire penetrating pulley enters the cylinder of hoist engine, and extra large cable is placed on the deck, and until the anchor clamps cable pillar that goes to sea, extra large cable lands the platform end-of-job.
In the described first step, the steel wire rope of platform hoist engine is to be dragged on the deck of spreading the cable ship by the messenger that is contained in advance in the extra large cable pillar.
In described second step, the dilatory head of extra large cable is gone up the short rope of the eye splice that connects and is: with the same diameter specifications of the steel wire rope of hoist engine, length be: the short rope of 0.6 meter eye splice.
Anchor clamps in described the 3rd step are: the net anchor clamps.
In described the 4th step, bandage adopts the binding of steel strap fixing, and the binding spacing of bandage is: 1 meter.
Each tie point position smooth surface processing mode in described the 6th step is: adopt the PVC plastic adhesive tape to wrap up in around processing.
Beneficial effect of the present invention: the present invention is owing to adopt technique scheme, its steel wire rope with hoist engine directly is strapped on the extra large cable, by lockset steel wire rope and extra large cable are connected as a single entity, land in the process of pulling at extra large cable poling, when extra large cable does not arrive at pulley, the cable walking of hoist engine rope traction sea; Treat that extra large cable end arrives pulley, progressively untie the lockset between steel wire rope and the extra large cable, extra large cable is separated with steel wire rope, steel wire rope walks on and passes pulley and arrive at hoist engine, extra large cable is followed steel wire rope, and to go out pillar then be by manually being placed on the deck, and whole process is almost works continuously, and extra large cable end is lifted to put in place fast, time saving and energy saving, save 6-7 hour man-hour; Reduce the operation ship sky, improved operating efficiency.
Description of drawings:
Fig. 1 lands the poling schematic diagram for the present invention sea cable terminal.
Fig. 2 is steel wire rope and the extra large cable connection diagram of hoist engine of the present invention.
Fig. 3 is the operational mode schematic diagram after the present invention sea cable goes out J-shape pipe.
Major label description in figure:
1 hoist engine, 2, pulley, 3 steel wire ropes, 4 rope cramps, the short rope of 5 eye splices, the dilatory head of 6 extra large cables, 7 bandages, 8 extra large cables, 9 net anchor clamps, 10 J-shapes pipe, 11 shop cable ships, 12 production platforms.
Embodiment
Hoist engine 1 is installed in locus available on the production platform 12 in advance, in the overhead of extra large cable pillar one sliding opinion 2 is installed, the steel wire rope 3 of hoist engine 1 is passed this pulley 2 and be connected with a messenger in being contained in extra large cable pillar in advance; Shop cable ship 11 is located near the production platform 12.The extra large cable pillar of present embodiment is: J-shape pipe 10.
As Fig. 1, Fig. 2, shown in Figure 3, the present invention adopts following steps:
The first step: start the hoist engine on the shop cable ship 11, by being contained in extra large cable pillar in advance namely: the messenger in the J-shape pipe 10 is dragged to the steel wire rope 3 of platform hoist engine 1 on the deck of shop cable ship 11;
Second step: connect the short rope of an eye splice on dilatory 6 on extra large cable; The short rope of present embodiment is: with steel wire rope 3 same diameter specifications, the length of hoist engine 1 be: the short rope 5 of 0.6 meter eye splice.
The 3rd step: go out the active length of pillar according to extra large cable 8, at the extra large cable apart from extra large this extension position of cable end one anchor clamps are installed; Present embodiment is: net anchor clamps 9 are installed.
The 4th step: the steel wire rope 3 of platform hoist engine 1 directly is connected with net anchor clamps 9, and, several bandages of steel wire rope 3 usefulness are sticked be fixed on the extra large cable 8 to dilatory 6 position of extra large cable, present embodiment is: bandage adopts 7 bindings of steel strap fixing, and the binding spacing of bandage is: 1 meter.
The 5th step: in extra large cable 8 tip position, utilize rope cramp 4 that the steel wire rope 3 of hoist engine 1 and short rope 5 locks are one;
The 6th step: each surface, tie point position is wrapped up in around handling smooth with the wide adhesive tape of PVC plastics 5cm;
The 7th step: start platform hoist engine 1 and involve in steel wire rope 3, the cable laying machine that is located on the shop cable ship 11 is sent extra large cable 8 synchronously, after extra large cable end goes out J-shape pipe 10, remove rope cramp 4, and when being accompanied by extra large cable 8 and going out J-shape pipe, untie bandage 7 one by one, steel wire rope 3 separates with extra large cable 8;
The 8th step: steel wire rope 3 passes the cylinder that pulley 2 enters hoist engine 1, and 8 on extra large cable manually is placed on the deck, goes out J-shape pipe 10 until net anchor clamps 9, and extra large cable 8 lands the platform end-of-job.
Above-mentioned hoist engine, pulley, steel wire rope, rope cramp, the short rope of eye splice, the dilatory head of extra large cable, bandage, net anchor clamps, shop cable ship are known technology.
The above, it only is preferred embodiment of the present invention, be not that the present invention is done any pro forma restriction, every foundation technical spirit of the present invention all still belongs in the scope of technical solution of the present invention any simple modification, equivalent variations and modification that above embodiment does.

Claims (5)

1. method for improving that lands the submarine cable terminal of platform is characterized in that: adopt following steps:
The first step: start the hoist engine on the cable ship of shop, the steel wire rope of platform hoist engine is dragged on the deck of shop cable ship;
Second step: connect the short rope of an eye splice at the dilatory head of extra large cable;
The 3rd step: one net anchor clamps are installed at extra large cable;
The 4th step: the steel wire rope of platform hoist engine is connected with anchor clamps, and, steel wire rope sticked with several bandages be fixed on the extra large cable extremely extra large cable and draw a position;
The 5th step: in extra large cable-end head position, utilize rope cramp that the steel wire rope of hoist engine and short rope are connected as one;
The 6th step: smooth treatment is carried out on each surface, tie point position;
The 7th step: start the platform hoist engine and involve in steel wire rope, the cable laying machine that is located on the cable ship of shop is sent extra large cable synchronously, after extra large cable end goes to sea the cable pillar, remove rope cramp, and when being accompanied by extra large cable and going to sea the cable pillar, untie bandage one by one, steel wire rope is separated with extra large cable;
The 8th step: the steel wire penetrating pulley enters the cylinder of hoist engine, and extra large cable is placed on the deck, and until the anchor clamps cable pillar that goes to sea, extra large cable lands the platform end-of-job.
2. the method for improving that lands the submarine cable terminal of platform according to claim 1 is characterized in that: in the described first step, the steel wire rope of platform hoist engine is to be dragged on the deck of shop cable ship by being contained in messenger in the extra large cable pillar in advance.
3. the method for improving that lands the submarine cable terminal of platform according to claim 1, it is characterized in that: in described second step, the dilatory head of extra large cable is gone up the short rope of the eye splice that connects and is: with the same diameter specifications of the steel wire rope of hoist engine, length be: the short rope of 0.6 meter eye splice.
4. the method for improving that lands the submarine cable terminal of platform according to claim 1 is characterized in that: in described the 4th step, bandage adopts the binding of steel strap fixing, and the binding spacing of bandage is: 1 meter.
5. the method for improving that lands the submarine cable terminal of platform according to claim 1 is characterized in that: each the tie point position smooth surface processing mode in described the 6th step is: adopt the PVC plastic adhesive tape to wrap up in around processing.
CN 201110254417 2011-08-31 2011-08-31 Lifting method of submarine cable terminal landing platform Active CN102332695B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110254417 CN102332695B (en) 2011-08-31 2011-08-31 Lifting method of submarine cable terminal landing platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110254417 CN102332695B (en) 2011-08-31 2011-08-31 Lifting method of submarine cable terminal landing platform

Publications (2)

Publication Number Publication Date
CN102332695A CN102332695A (en) 2012-01-25
CN102332695B true CN102332695B (en) 2013-10-09

Family

ID=45484357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110254417 Active CN102332695B (en) 2011-08-31 2011-08-31 Lifting method of submarine cable terminal landing platform

Country Status (1)

Country Link
CN (1) CN102332695B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103399386B (en) * 2013-07-30 2015-07-15 江苏通光海洋光电科技有限公司 Submarine sensing assembly and messenger wire online binding device and construction method thereof
US9896896B2 (en) * 2013-12-18 2018-02-20 Aker Solutions As Hinged cable termination
WO2015158367A1 (en) * 2014-04-15 2015-10-22 Abb Technology Ltd A method for a subsea power cable installation procedure
CN104037707B (en) * 2014-06-05 2017-10-10 龙源电力集团股份有限公司 Extra large cable lays protection device and installation method at offshore wind farm jacket basis
CN104092153B (en) * 2014-07-29 2016-09-14 中国海洋石油总公司 A plurality of sea cable shares the pipe penetration method of a J-shaped pipe
CN104594319B (en) * 2014-12-29 2016-05-11 中国海洋石油总公司 The lifting installation method of integral of deep water ocean platform pump pillar
CN105866913A (en) * 2016-04-28 2016-08-17 江苏亨通海洋光网系统有限公司 Armored submarine optical cable landing fixing device and installation method thereof
DK3257738T3 (en) * 2016-06-14 2020-09-21 Fundacion Tecnalia Res & Innovation Procedure for installing a submarine cable
CN107247320A (en) * 2017-05-16 2017-10-13 天津亿利科能源科技发展股份有限公司 A kind of method that seabed armored optical cable steps on ocean platform
CN108083007B (en) * 2018-01-05 2023-07-07 合肥神马科技集团有限公司 High-altitude cable laying machine for conveying submarine cables at wharf
CN108462117B (en) * 2018-03-02 2024-04-12 北京利华消防工程有限公司 High-rise building cable laying device and application method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1083193A (en) * 1992-04-07 1994-03-02 科夫莱克希普公司 Device with installation flexible cable of curvature limiter
CN101036016A (en) * 2004-08-13 2007-09-12 伊特雷科公司 Marine J-type pipeline laying system

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0656076A (en) * 1992-08-12 1994-03-01 Seki Kaiji Kogyosho:Kk Submarine cable laying construction method and laying work ship thereof
JPH07298441A (en) * 1994-04-22 1995-11-10 Fujikura Ltd Laying and burying method for long element in shallow sea
JP2000308228A (en) * 1999-04-19 2000-11-02 Sumitomo Electric Ind Ltd Submarine cable laying method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1083193A (en) * 1992-04-07 1994-03-02 科夫莱克希普公司 Device with installation flexible cable of curvature limiter
CN101036016A (en) * 2004-08-13 2007-09-12 伊特雷科公司 Marine J-type pipeline laying system

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
JP特开2000-308228A 2000.11.02
JP特开平6-56076A 1994.03.01
JP特开平7-298441A 1995.11.10
埕岛浅海海底电缆敷设工艺浅谈;张小明等;《科技资讯》;20110423(第12期);第132页 *
张小明等.埕岛浅海海底电缆敷设工艺浅谈.《科技资讯》.2011,(第12期),

Also Published As

Publication number Publication date
CN102332695A (en) 2012-01-25

Similar Documents

Publication Publication Date Title
CN102332695B (en) Lifting method of submarine cable terminal landing platform
CN113148030B (en) Laying and installing method for deepwater submarine cable side launching
CN203584490U (en) Submarine cable or soft pipe burying device and workboat
CN203129178U (en) Ultra-large type immersed tube stranded cable undock system
CN102586784B (en) Method for assembling direct current cathode protection system outside platform
Wang et al. Latest progress in deepwater installation technologies
CN105672138A (en) Through type stayed cable installation circulation system and cable threading construction method thereof
JP2018039475A (en) Method for extension of mooring cable, method for mooring floating body structure and method for construction of floating body type offshore wind power generation facility
CN102221128A (en) Seabed oil and gas transportation hose line fixed on the basis of anchor pier
CN102213085A (en) Installation method of vertical pipe of guide pipe rack
CN106786157A (en) Transmission line of electricity Great span above the navigation water surface tears aging method open
CN103407548A (en) Quick release method and device of anchor chain for permanently mooring on-water floating type platform
CN103410477B (en) Offshore oil platform underwater cable disconnecting and reconnecting method and equipment
CN105782568A (en) Mounting method of stand tube and protection tube
CN103255775B (en) Method for installing cofferdam
CN109901273B (en) Construction method for laying optical cable junction boxes on sea in ultra-deep water
CN112025232B (en) Method for installing remote jacket impressed current cathodic protection integrated device
CN104092153B (en) A plurality of sea cable shares the pipe penetration method of a J-shaped pipe
CN101797966B (en) Method for refloating deeply-buried cable by utilizing three-meter deeply-buried cable mechanical refloatation anchor
RU2676927C1 (en) Installation method of a drilling ship with a turret on an anchor-mooring system in ice conditions
CN210529503U (en) Positioning device for beam-transporting ship of suspension bridge
CN202578652U (en) In-place auxiliary bracket for vertical pipe
CN107140129A (en) Submerged wreck tether system
CN113212656A (en) Pipe cable lifting method for single-point cabin
CN108613663B (en) Ocean vertical profile automatic observation system and method based on ocean oil platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee after: CHINA NATIONAL OFFSHORE OIL Corp.

Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee before: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee before: CHINA NATIONAL OFFSHORE OIL Corp.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240716

Address after: 100010 No. 25 North Main Street, Dongcheng District, Beijing, Chaoyangmen

Patentee after: CHINA NATIONAL OFFSHORE OIL Corp.

Country or region after: China

Patentee after: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee after: CNOOC Shenzhen Ocean Engineering Technology Service Co.,Ltd.

Address before: No. 25 Chaoyangmen North Street, Dongzhimen, Beijing 100010

Patentee before: CHINA NATIONAL OFFSHORE OIL Corp.

Country or region before: China

Patentee before: OFFSHORE OIL ENGINEERING Co.,Ltd.