CN102297932A - Water quality comprehensive simulation test system with replacement pipe sections for circulating pipe network - Google Patents

Water quality comprehensive simulation test system with replacement pipe sections for circulating pipe network Download PDF

Info

Publication number
CN102297932A
CN102297932A CN2011101305893A CN201110130589A CN102297932A CN 102297932 A CN102297932 A CN 102297932A CN 2011101305893 A CN2011101305893 A CN 2011101305893A CN 201110130589 A CN201110130589 A CN 201110130589A CN 102297932 A CN102297932 A CN 102297932A
Authority
CN
China
Prior art keywords
water
water tank
pipe network
pipeline
branch road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011101305893A
Other languages
Chinese (zh)
Other versions
CN102297932B (en
Inventor
张土乔
邵煜
邵卫云
毛欣炜
黄煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University ZJU
Original Assignee
Zhejiang University ZJU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University ZJU filed Critical Zhejiang University ZJU
Priority to CN2011101305893A priority Critical patent/CN102297932B/en
Publication of CN102297932A publication Critical patent/CN102297932A/en
Application granted granted Critical
Publication of CN102297932B publication Critical patent/CN102297932B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pipeline Systems (AREA)

Abstract

The invention discloses a water quality comprehensive simulation test system with replacement pipe sections for a circulating pipe network. The system comprises a water supply subsystem and independent circulating pipe network subsystems. The water supply subsystem includes a first water supply tank and a second water supply tank communicated with the first water supply tank through a pipeline with a second valve. Each independent circulating pipe network subsystem includes a main circulating pump, a multichannel flow switch calibration device, a visible pipe section and a loop of a high water supplement and exhaust tank that are connected in series by a pipeline. The loop is in connection with a first pipeline branch for realizing closed circulation, a water supplement system, a blowdown branch, a water quality on-line monitoring system, a temperature control system and replacement pipe section branches. Meanwhile, the pipeline of the independent circulating pipe network subsystem is also connected to a reagent filling system. Making use of the interaction among all parts, the water quality comprehensive simulation test system for a circulating pipe network has the advantages of high simulation degree and ability to simulate the working conditions of a plurality of municipal water supply pipe networks.

Description

A kind of circulation pipe network water quality comprehensive simulation test system with the displacement pipeline section
Technical field
The present invention relates to the test simulation systems technology field of potable water water supply network, particularly a kind of circulation pipe network water quality comprehensive simulation test system with the displacement pipeline section.
Background technology
Water supply network is the important component part in the water supply system, and its effect is that the water that meets national Drinking Water water quality standard after purifying through water factory is delivered to user terminal.Every index of China's most waterworks effluent quality can both reach or be better than national water quality standard for drinking water, but when being delivered to the user by pipe network, often not reaching standard even jeopardize user's body health.Data shows, the water of waterworks is from the user of dispatching from the factory, and water quality presents the trend of obvious reduction, shows that mainly the content in water such as iron, manganese, colourity, turbidity, total number of bacteria increases, even surpassing national standard, this much all finds in the actual motion of water factories at home to some extent.In addition, although the develop rapidly of water technology has fully guaranteed to handle safety, the health of back water quality, but the secondary pollution problem in the pipe network has become influences the principal element that effluent quality can't be up to standard, is water quality research work and water treatment main research work.
Water supply network is just as a sensitivity, dynamic and have a huge reactor of self-characteristic, water is owing to the hold-up time in pipeline is long, itself constantly be subjected to polluting once more, complicated physics, chemistry and biology taking place in pipeline changing, cause the decline of sanitary condition in the pipeline.According in " urban water supply industry technical progress development plan in 2000 " domestic 34 main cities ductwork water quality data being added up, what surface water water factory output water was basicly stable accounts for 21%, corrosively accounts for 50%, slight fouling accounts for 29%.What underground water water factory output water was basicly stable accounts for 50%, mordantly accounts for 30%, slight corrosively accounts for 20%.To accounting for 36 urban surveys of national total supply 42.44%, the output water average turbidity is 1.3 degree, and pipe network water is increased to 1.6 degree; Colourity is increased to 6.7 degree by 5.2 degree; Iron is increased to 0.11mg/l by 0.09mg/l; Total number of bacteria is increased to 29.2cfu/ml by 6.6cfu/ml.Certain city finds that the thickness of pipe scale in the feed pipe reaches 16~20mm, redness of the skin or complexion, fishy smell is arranged, contain 16 kinds of metallic elements, detect 6 kinds of microorganisms such as iron bacteria, dust Xi Shi Escherichia coli and (see Qin Qiuli, Chen Jingyan for details, China's urban water supply safety case is analyzed and the guarantee countermeasure, water conservancy economy, 2001.5).According to city's results of regular determination pipe network coefficient of roughness statistics such as Shanghai, Tianjin, find that the pipeline water delivery ability of no anti-corrosion measure has reduced more than 1/3.Pipeline scale, water delivery water quality deterioration, pipeline water delivery ability drop have become the ubiquitous phenomenon of public supply mains.
Expansion and propelling and the progress of society and the raising of living standards of the people fast of town and country one way of supplying water along with China completed region of the city, the resident no longer only has been confined to the guarantee of the pressure and the water yield for the requirement of potable water, but the more concern quality problem, the water stabilization of public supply mains and safety problem are urgent day by day.Drinking water quality is not only up to standard when dispatching from the factory, and need be up to standard at user's water swivel place, meets water quality standard for drinking water.And most important in carrying as potable water, also be that the health of the most responsive link-water supply network then is prerequisite and the basis that ensures final leading effluent quality safety.Change of water quality mechanism in the research pipe network proposes and the relevant reply of checking technical measures, is the key point of guaranteeing the inner health of pipe network and ensureing final pipe network tip effluent quality safety.
Carry out above research work, the pipe network experimental study is a basic means, can realize by the research technique of three levels.The most direct is to carry out site test, but exists external condition uncontrollable, is difficult to carry out the problem of quantitative examination targetedly, and more crucial is that the test pipe network relates to huge numbers of families, can not add the medicament of test easily; The simplest is to carry out indoor beaker test or build simple local reaction device test, but this class test water sample is few, can not do long-time cyclic test, and there is serious test problem of dtmf distortion DTMF in the real working condition ratio with actual pipeline.Therefore both at home and abroad many research institutions all are inclined to and adopt the test unit of circulation pipe network model that true pipe network is carried out high analogue simulation, provide panorama to show and analyze.
In the prior art, circulation pipe network simulation of water quality pilot system both domestic and external all adopts the open circulation mode, promptly is connected with a low level cistern in the circulating line loop, and current back by the road flow into cistern, pass through lift pump then, water is risen in the pipe system circulate.This cistern promptly is that the former water allotment of test pond has scavenging action again concurrently, but the general scale of building up of open circulation pipe network pilot system is less, cyclic design is all very simple, and closed circuit is shorter, can not calculate the circulation pipe network water quality comprehensive simulation test system of high emulation on the essential meaning.Specifically mainly exist following a lot of technical matters in design:
1, flow condition emulation is poor
Each circulation water sample all contacts with the air large tracts of land when flowing through cistern, can influence cycle water; And the Yuan Shui pond participates in the pipe network cyclic test, and there is some difference for flow condition and actual pipe network.
2, condition control is not enough
Can't be to full-section pipe-flow pressurized control in the circulation line, can not water main pipe network that is virtually reality like reality pressure running environment arranged; The test water temperature is subject to the influence of environment temperature in four seasons in the circulation line, can't temperature control be embedded in the running temperature of underground true water main pipe network with simulation; Can't when circulation pipe network is tested initialization, confirm the inner air tube emptying to reach " full-section pipe-flow " fully, can't the Real Time Observation pipe in the change of fluidised form, biological and chemical environment, understand the situation of change of water quality.
3, simulated condition is single
Can't realize the simulation that multi-water resources character is switched, double water source mixes all kinds of complex working conditions such as water supply, external source contaminative water quality mutation, pipe network secondary chlorination; Can't can't carry out sampling analysis to pipe scale, biological membrane bacterium not influencing long-time continue observation pipeline internal corrosion fouling and biological membrane bacterial growth situation under the cyclic test operating mode; Can't investigate the tubing tenure of use of the influence to ductwork water quality, different feedwater piping foulings and biological membrane bacterium that research reality has been moved for many years come off to the influence of water quality.
4, analog distortion is bigger
The chlorine residue decay maximum effect factor that influences actual pipe network is the pipe network water temperature, if pilot system can't then will exist than mistake with actual pipe network operation result by temperature control; Adopting single electromagnetic flowmeter to detect as the flow control of system for the test water flow in the circulation pipe network feeds back, single electromagnetic flowmeter can not accurately detect in the gamut scope, when test needs the low discharge operating condition of the actual water supply network of simulation as circulation pipe network, its flow detection error will improve greatly, thereby the flow control accuracy of influence test produces bigger flow simulation distortion.
Summary of the invention
The invention provides a kind of circulation pipe network water quality comprehensive simulation test system with the displacement pipeline section, in the circulation pipe network water quality comprehensive simulation test system of entire belt displacement pipeline section, each parts cooperatively interacts, and the fidelity height, can simulate actual water main pipe network system.
A kind of circulation pipe network water quality comprehensive simulation test system with the displacement pipeline section comprises water supply subsystem and the independent loops pipe network subsystem that is connected with the water supply subsystem by the pipeline with first valve;
Described water supply subsystem comprises first water tank and second water tank that is communicated with first water tank by the pipeline with second valve, and described first water tank and second water tank are equipped with water inlet, water delivering orifice and medicament inlet;
Described independent loops pipe network subsystem is to comprise the main circulation pump by the pipeline series connection, the loop that multichannel flow switches calibrating installation, visual pipeline section and high-order moisturizing exhaust water tank; Described loop is provided with water inlet, and the water inlet in described loop is communicated with the water supply subsystem;
Described multichannel flow switches calibrating installation and comprises the first passage traffic alignment branch road that is composed in series by the 3rd valve and first electromagnetic flowmeter in parallel, second channel traffic alignment branch road that is composed in series by the 4th valve and second electromagnetic flowmeter and the third channel traffic alignment branch road that is composed in series by the 5th valve and the 3rd electromagnetic flowmeter, described independent loops pipe network subsystem, first passage traffic alignment branch road, the ratio of the pipe diameter in second channel traffic alignment branch road and the third channel traffic alignment branch road is 3: 3: 2: 1, and the range of the range of the range of described first electromagnetic flowmeter>second electromagnetic flowmeter>the 3rd electromagnetic flowmeter;
The penetrability of described visual pipeline section is greater than 90%, and the caliber of visual pipeline section equates with the caliber of the pipeline of independent loops pipe network subsystem;
The position of the water inlet of the close high-order moisturizing exhaust water tank in described loop and the water delivering orifice of close high-order moisturizing exhaust water tank is respectively equipped with the 6th valve and the 7th valve;
Described loop is connected with the first pipeline branch road with eight valve in parallel with the branch road that is composed in series by the 6th valve, high-order moisturizing exhaust water tank and the 7th valve, is used to the water charging system of loop supplementing water, is used for discharging the emptying branch road of loop water, the water quality monitoring system that is used for the water quality of monitoring circuit water, the temperature control system that is used for the regulating loop water temperature and displacement pipeline section branch road;
Described water charging system comprises the experiment water filling jar and the experiment water dispenser pump of series connection, described experiment water filling delivery side of pump and circuit communication, and the inlet of described experiment water filling jar is communicated with the water supply subsystem;
Described displacement pipeline section branch road comprises that two ends are connected with the displacement pipeline section of the 9th valve and the tenth valve respectively, the two ends of described displacement pipeline section branch road are in parallel with the ducted any section of independent loops pipe network subsystem by tee pipe fitting, and described any section is provided with the 11 valve;
The end face of described first water tank, second water tank and high-order moisturizing exhaust water tank approaches same surface level, described surface level is positioned at the horizontal extreme higher position of the circulation pipe network water quality comprehensive simulation test system of described band displacement pipeline section, and the placement location of described main circulation pump is lower than the placement location of first water tank, second water tank and high-order moisturizing exhaust water tank;
Described high-order moisturizing exhaust water tank comprises casing and is positioned at the piston-like floating head of casing, leaves the space between described piston-like floating head and the cabinet wall; The density of described piston-like floating head is less than the density of water.
In order to reach the better invention effect of the present invention, the present invention is carried out further preferred:
Described first water tank and second water tank provide the water source for the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section, the water delivering orifice of the water delivering orifice of described first water tank and second water tank lays respectively at the bottom of first water tank and second water tank, the i.e. basal surface position of first water tank or near the sidewall of first water tank of bottom surface, the sidewall of second water tank of the basal surface position of second water tank or close bottom surface, like this, water in first water tank and second water tank can flow in the independent loops pipe network subsystem better, is that independent loops pipe network subsystem supplies water better.The water source of first water tank and second water tank, water inlet by first water tank and second water tank after general employing tap water ships by direct water supply of the water inlet of first water tank and second water tank or water storage vehicle directly pours into first water tank and second water tank, also can be according to the test needs, the medicament inlet by first water tank and the medicament inlet of second water tank add medicament and carry out distributed in demand, obtain required resource of water supply.
In order not make water in the water tank contaminated and successfully the gas in the water tank is discharged, the first water tank dust cap that area is slightly larger than the first water tank end face is stamped at the top of described first water tank; The top side wall of described first water tank is provided with the through hole that is used for exhaust; The second water tank dust cap that area is slightly larger than the second water tank end face is stamped at the top of described second water tank; The top side wall of described second water tank is provided with the through hole that is used for exhaust.
Described first water tank is connected with the second pipeline branch road with the first mixing circulation pump, and the two ends of the described second pipeline branch road are communicated with first water tank respectively; Described second water tank is connected with the 3rd pipeline branch road with the second mixing circulation pump, and the two ends of described the 3rd pipeline branch road are communicated with second water tank respectively; The described second pipeline branch road is communicated with by the pipeline that has the 12 valve with the 3rd pipeline branch road.Difference in height is all arranged between the two ends of the described second pipeline branch road and between the two ends of the 3rd pipeline branch road; Be located at the first water tank bottom surface or near the first water tank sidewall of the first water tank bottom surface as an end of the second pipeline branch road, the other end of the second pipeline branch road is located at the first water tank end face or near the first water tank sidewall of the first water tank end face.Like this, just there is certain height poor between the two ends of the second pipeline branch road of first water tank, under the effect of the first mixing circulation pump, water in first water tank comes out from an end (i.e. the low side of the second pipeline branch road) of the second pipeline branch road, enter from the other end (promptly the second pipeline branch road is high-end) of the second pipeline branch road again, make the water in the water tank after dosing, can fully stir, finally mix that second water tank carries out mixing circulation based on same principle.
Switching by second valve can realize that the water source of first water tank mixes (the former water of test that two kinds of water sources can dispose the different proportion water yield by the experimental study requirement) with the different water sources of second water tank, the second pipeline branch road is communicated with by having the 12 valve pipe with the 3rd pipeline branch road, just can make water in first water tank and the water in second water tank under the effect of the first mixing circulation pump or the second mixing circulation pump, fully mix.The present invention can realize the test of the single water quality in a plurality of loops, simulates single character water source flow operating mode in pipe network; Also can realize heterogeneity water source, single loop switching tests, simulation is switched the heterogeneity water source and is used to study that the heterogeneity water source causes the change mechanism of the biochemical environment in pipe network inside and to the influence of water quality through operation back after a while.
Described main circulation pump provides power for the ducted water cycle operation of independent loops pipe network subsystem, make the ducted water of independent loops pipe network subsystem that stable flow velocity can be arranged, preferably, the bottom surface of main circulation pump is positioned at the floor level face of the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section, so that when being full of the test water from the water supply subsystem in the pipeline of independent loops pipe network subsystem, the main circulation pump inner chamber body also can be full of water, and the startup main circulation pump provides power for the ducted water of independent loops pipe network subsystem.The control of flow velocity adopts the variable frequency control of main circulation pump to finish.
The measurement of flow velocity can adopt multichannel flow to switch calibrating installation, and described first electromagnetic flowmeter, second electromagnetic flowmeter and the 3rd electromagnetic flowmeter adopt the electromagnetic flowmeter of range from big to small successively according to place branch road caliber size; First electromagnetic flowmeter, second electromagnetic flowmeter and the preferred range ratio of the 3rd electromagnetic flowmeter are 9: 4: 1.During test, according to different flow velocity (flow) requirement, multichannel flow switches calibrating installation and can be the traffic alignment pipeline that independent loops pipe network subsystem switches different tube diameters, select the electromagnetic flowmeter monitoring feedback cycle flow (can calculate corresponding flow velocity) of corresponding best range section, so that the high-precision adjusting control of main circulation pump test flow velocity by known caliber cross section.Under the bigger situation of flow, select big caliber path and the big electromagnetic flowmeter of range ability on it, under the less situation of flow, select tubule footpath path and the less electromagnetic flowmeter of range ability on it.Branch road by the series connection of valve and electromagnetic flowmeter can many in parallel.As required, can also select three, four, five etc., comparatively speaking, the selector bar number is many more, and the error between detected value and the actual value will be littler, but the bar number is more, increase the cost of equipment for a moment, the 2nd, in practical operation, need frequent switching, cause operation too loaded down with trivial details, there is no need, preferably, can select three, accurate control that can dependable flow can guarantee the simplicity of operating again.
The penetrability of described visual pipeline section is greater than 90%, the caliber of visual pipeline section equates with the caliber of the pipeline of independent loops pipe network subsystem, the tubing of visual pipeline section can select for use the high light transmittance organic glass (as polymethylmethacrylate, transmissivity is up to 92~93%, can see through visible light 99%, ultraviolet light 72%), because visual pipeline section has certain requirement to penetrability, with may have difference on the material of the pipeline of independent loops pipe network subsystem, for the existence that reduces visual pipeline section influence to simulation test, and can make the fluidised form that reaches in the Real Time Observation pipe intuitively, biological, the change of chemical environment, understand the situation of change of water quality, grasp polluter (iron rust, sediment etc.) depositional phenomenon and the rule in pipe, visual pipeline section is generally unsuitable long, be about independent loops pipe network subsystem the pipeline pipe range 1/40, when the pipeline of independent loops pipe network subsystem was the 80m left and right sides, the pipe range of visual pipeline section was about 2m.
Can adopt the experiment water filling jar and the experiment water dispenser pump of series connection in the described water charging system, simultaneously electromagnetic flowmeter can also be set feeds back rate of water make-up, this water charging system mainly is can provide power when initialization, make the former water liquid level of test that enters in the high-order exhaust replenishing water tank of water of circulation pipe network subsystem be higher than the water tank liquid level, but the former water major part of the test in the water supply subsystem enters independently in the circulation pipe network subsystem like this, saves former damage by water consumption.When the needs of water quality monitoring system owing to the monitoring sampling, when causing the ducted water of independent loops pipe network subsystem to reduce, in view of the water of sampling is considerably less, can finish moisturizing by the participation round-robin retaining in the high-order exhaust replenishing water tank of water, when the water flow of pipeline rate of water make-up of circulation pipe network subsystem is bigger, be that the pipeline of circulation pipe network subsystem needing after the exhaust to carry out replenishing the water table ratio of relatively large water or high-order exhaust replenishing water tank of water when low, can adopt water charging system to carry out moisturizing, making has retaining all the time at high-order exhaust replenishing water tank of water, remain on suitable level, prevent that air from entering into the pipeline of circulation pipe network subsystem.
The route atmospheric valve is propped up in described emptying and the system blow-down pipe is formed, and the circulation pipe network water of finishing after the simulation test is all discharged, and pours water again by water tank then again, begins new test.
Though be provided with water tank both at home and abroad in the pipe network simulation system to get rid of the air in the pipeline, avoid occurring in the closed circuit vacuum and then produce unstability and vibration.But existing water tank is uncovered casing, the water tank of this structure will make unavoidably that water sample has the chance that contacts with air in cyclic process, cause the change of water quality character in each circulation, cause the fidelity of pipe network simulation to descend, make result of study bigger deviation occur.For this reason, in the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section of the present invention, high-order moisturizing exhaust water tank in the independent loops pipe network subsystem is provided with the piston-like floating head identical with bottom shape, described piston-like floating head is placed horizontally in the high-order moisturizing exhaust water tank, and and high-order moisturizing exhaust tank inner wall between leave the space, the density of described piston-like floating head is less than the density of water, the piston-like floating head just can be done the piston type motion in rising of the water level in the high-order moisturizing exhaust water tank or decline like this, in guaranteeing the emptying pipeline, reduce circulating water flow and the chance that the pipe outer air contacts in the gas as much as possible, guarantee that simulation pipeline water quality is consistent with true pipe network.Requirement to density mainly is for the piston-like floating head can be floated, described density is meant the density of piston-like floating head integral body, be not to be the density of the material of piston-like floating head, can adopt the centre of making to be full of the closed piston type floating head of air as the piston-like floating head by thin corrosion resistant plate, such piston type floating head also can float on the water, and satisfies the density requirements of the present invention for the piston-like floating head.
Described high-order moisturizing exhaust water tank, its wall is vertical with the bottom surface, is the shape of an arbitrary xsect and the solid that area all equates.The piston-like floating head that more convenient like this shape is similar to xsect, area is slightly less than xsect can be done the piston motion by in the vertical direction, simultaneously, the high-order moisturizing exhaust water tank dust cap that area is slightly larger than high-order moisturizing exhaust water tank end face is stamped at the top of described high-order moisturizing exhaust water tank, and described high-order moisturizing exhaust water tank dust cap can obtain effective support by high-order moisturizing exhaust tank box.The top side wall of described high-order moisturizing exhaust water tank is provided with the through hole that is used for exhaust, like this, can significantly reduce the chance that water sample contacts with air in cyclic process, the air in the recirculated water in the independent loops pipe network subsystem can be discharged smoothly again.Preferably, it is cylindrical can selecting the casing of high-order moisturizing exhaust water tank.
In order to get rid of the bubble in the water in the independent loops pipe network subsystem circulation line, the water delivering orifice of described high-order moisturizing exhaust water tank is positioned at the bottom of high-order moisturizing exhaust water tank, promptly be positioned at high-order moisturizing exhaust water tank sidewall or high-order moisturizing exhaust water tank bottom surface near high-order moisturizing exhaust water tank bottom surface, the water inlet of described high-order moisturizing exhaust water tank is higher than the water delivering orifice of high-order moisturizing exhaust water tank and is lower than high-order moisturizing exhaust water tank case Senior Two/one position.Like this, the water inlet of high-order moisturizing exhaust water tank just is higher than the water delivering orifice of high-order moisturizing exhaust water tank, and the ducted water of independent loops pipe network subsystem just has certain drop when flowing through, and bubble will rise because density is little like this, easily discharges.
The position of the water inlet of the close high-order moisturizing exhaust water tank in described loop and the water delivering orifice of close high-order moisturizing exhaust water tank is respectively equipped with the 6th valve and the 7th valve; Described loop is connected with the first pipeline branch road with eight valve in parallel with the branch road that is composed in series by the 6th valve, high-order moisturizing exhaust water tank and the 7th valve; Based on above-mentioned design, the present invention just can realize switching between accurate closed circulation and the closed circulation by the switching between each valve, when closing the 6th valve and the 7th valve, open the 8th valve, just can realize closed circulation completely, and, the 8th valve is the process variable valve, can be under the constant situation of main circulation pump frequency, regulate " full-section pipe-flow " pressure in the control closed circulation loop by aperture, can simulate the different hydraulic pressure of the water quality transportation of actual pipe network transportation.
The pipeline that described independent loops pipe network subsystem is a plurality of and a plurality of independent loops pipe network subsystems is identical or different; The pipeline of described independent loops pipe network subsystem is ductile iron pipe, polyethylene pipe (PE pipe), copper pipe or stainless-steel tube.The pipeline of independent loops pipe network subsystem is exactly the carrier that the water in the circulation pipe network flows, it also is transportation environment, because the pipeline of unlike material is to the degree varies sample of the secondary pollution of water, the concrete chemistry that takes place, physics also can be different with biological the variation, therefore, the present invention has chosen ductile iron pipe commonly used in actual pipeline, the PE pipe, copper pipe, stainless-steel tubes etc. are as the pipeline of independent loops pipe network subsystem, to study of the influence of different pipelines to change of water quality in the transportation pipe network, relevant reply technical measures are proposed, and the validity of the relevant reply of checking technical measures.
Water supply subsystem among the present invention can link to each other with a plurality of independent loops pipe network subsystems, a plurality of independent loops pipe network subsystems all can independently be tested, link to each other with four independent loops pipe network subsystems as a water supply subsystem, promptly the pipeline of a water supply subsystem connection independent loops pipe network subsystem is the independent loops pipe network subsystem of ductile iron pipe, the pipeline of independent loops pipe network subsystem is the independent loops pipe network subsystem of PE pipe, the pipeline of independent loops pipe network subsystem is that the independent loops pipe network subsystem of stainless-steel tube and the pipeline of independent loops pipe network subsystem are the independent loops pipe network subsystem of copper pipe.
In order to monitor the ducted water quality situation of independent loops pipe network subsystem, the pipeline of independent loops pipe network subsystem is connected to the water quality monitoring system of the water quality that is used for monitoring circuit water, sampling is used for the water yield of water quality monitoring on the pipeline of independent loops pipe network subsystem, be considerably less, almost can ignore, generally just can finish moisturizing (under the special test situation by the retaining in the high-order exhaust replenishing water tank of water, moisturizing demand in the pipeline of independent loops pipe network subsystem surpasses the available maximum rate of water make-up in the high-order exhaust water supply tank, can also pass through water charging system moisturizing in time).Under the bigger situation of moisturizing demand, can pass through water charging system moisturizing in time.Therefore, generally speaking, water sample can directly enter trench through water quality monitoring system.But reduce of the influence of the water yield of collection water sample in order to try one's best to water in the pipeline of independent loops pipe network subsystem; Described water quality monitoring system can not be made up of by the circulating line branch road water quality monitoring circulating line branch road and water quality monitoring; Described water quality monitoring circulating line branch road comprises conductivity meter, pH instrument and dissolved oxygen DO tester in parallel, and the two ends of described water quality monitoring circulating line branch road are communicated with the pipeline of independent loops pipe network subsystem respectively.Because monitored conductivity, water body pH monitoring and dissolved oxygen DO monitoring do not relate to chemical change, just can monitor, therefore, the water quality of water is basic identical in the water quality of the water sample of above-mentioned process monitoring and the pipeline of independent loops pipe network subsystem, water sample after the monitoring can be got back in the pipeline of independent loops pipe network subsystem by the water quality monitoring closed circuit once more, for the foregoing reasons, monitored conductivity, water body pH monitoring and dissolved oxygen DO monitoring can be adopted real-time monitoring, promptly monitor at any time, can not cause the unstability of the ducted current of monitoring independent loops pipe network subsystem, wherein, described monitored conductivity, water body pH monitoring and dissolved oxygen DO monitoring can be adopted commercially available instrument and equipment.
Described water quality monitoring can not comprise residual chlorine detecting instrument, turbidity detector and granule content detector in parallel by the circulating line branch road, described water quality monitoring can not the circulating line branch road an end be communicated with the pipeline of independent loops pipe network subsystem, the other end inserts trench.Because chlorine residue monitoring, turbidity monitoring and granule content monitoring need to add medicament, changed test water water quality in the circulating line, or diversion come out to detect the back decompression can't get back in the pipeline of independent loops pipe network subsystem by pressure differential again, therefore, can only enter in the trench, wherein chlorine residue monitoring, turbidity monitoring and granule content monitoring can adopt commercially available instrument to monitor, and in order to reduce the loss of water sample, the intermittently mode of periodic monitor is taked in the test of these three indexs.But the people for open, shutoff operation, also can open automatically according to initial time, the interval time set, after reaching stable testing required time and transmission and showing read signal, close automatically.
For various working such as the secondary sterilization (as chloramines, chlorine dioxide, ozone, sodium hypochlorite etc.) of simulating actual water supply network, xenobiotic pollutants invasion, water quality mutations, study its change of water quality rule, be connected with the medicament loading system on the pipeline of described independent loops pipe network subsystem, described medicament loading system comprises the medicament filling jar and the medicament dispenser pump of series connection.Can optionally add medicament by the medicament loading system, wherein, the medicament dispenser pump is selected the delicate metering dispenser pump for use, and the delicate metering dispenser pump can be according to the amount of setting that adds the medicament of setting working time, thereby realizes the accurately joining day and the dosage of control medicament.The number of described medicament loading system can increase or reduce as required.When the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section carries out simulation test, need the water quality result that monitors according to water quality monitoring system sometimes, select medicament to add, preferably the number of medicament loading system is 1~5.Can also be according to the water quality result behind the water quality monitoring system monitoring adding medicament, as the monitoring of the DBPs after the sterilization.In addition, tracer agent also can add by the medicament loading system, can control the amount of the tracer agent of filling by the medicament dispenser pump exactly, the basis that guarantees each test condition is consistent, before test by adding tracer agent, guarantee that flushing of pipeline is clean, thereby can not cause interference to the result of test, the warranty test result's is accurate.
Actual water main pipe network generally all is embedded in underground or the soil, the circulation pipe network that is used for test simulation generally is indoor, can there be difference on the temperature in both in different spaces, also have, also can there be difference in the temperature of the actual water supply network between the different places, this just need be used in water temperature and actual underground, the soil of circulation pipe network of test simulation or other places are consistent, and so just can better simulate actual pipe network, obtains test findings more accurately.Consistent and different water temperatures of research are to the ductwork water quality in the transportation pipe network for coolant-temperature gage under the actual condition in the water temperature that makes simulation test and the transportation pipe network, the influence of structural pipe wall etc., the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section of the present invention, also comprised temperature control system, described temperature control system comprises the 13 valve by series connection, the temperature controlling plumbing fixtures branch road that plate type heat exchanger and temperature control system ebullator are formed, first temperature transmitter and second temperature transmitter, the two ends of described temperature controlling plumbing fixtures branch road are communicated with the pipeline of the independent loops pipe network subsystem that has the 14 valve respectively; Described temperature controlling plumbing fixtures branch road is in parallel with the 14 valve; Described first temperature transmitter is positioned at temperature controlling plumbing fixtures branch road inflow point, and described second temperature transmitter is positioned at temperature controlling plumbing fixtures branch road exit.The flow through temperature of the test water before the temperature control branch road of the pipeline that first temperature transmitter is used for detecting independent loops pipe network subsystem, second temperature transmitter is used for detecting the temperature that secondary water (water after the plate type heat exchanger heat interchange of excess temperature control branch road is called secondary water at this, and corresponding to it to plate type heat exchanger provides the water of Cooling and Heat Source to be called water one time at this) after the heat interchange of excess temperature control branch road passes back into the mixed test water of pipeline of independent loops pipe network subsystem.First temperature transmitter and second temperature transmitter in time feed back to control system with detected temperature data, control system is provided with temperature according to the pipeline recirculated water test of independent loops pipe network subsystem, the temperature control system ebullator start and stop on the control temperature control branch road and the switching of the 13 valve.The medium of the cold and hot exchange of described plate type heat exchanger can adopt multiple, it is also a lot of to originate, consider from many-sided factor such as effect, comfort level, can select for use the central air conditioner source pump to provide cold and hot water source for plate type heat exchanger, plate type heat exchanger is furnished with special-purpose temperature controller, special-purpose temperature controller can specifically be selected Honeywell-T9275A1002 for use, continuing, stopping and speed by cold and hot exchange in the Honeywell temperature controller control plate type heat exchanger.
Because actual water main pipe network is difficult to regular dismounting, observes the change process of tube wall proterties, especially also otherwise influence the operating mode that it continues cyclic test for a long time, therefore the present invention has designed the displacement pipeline section, by routine observation and measurement to it, can understand the corrosion development of material pipe network tube wall, grasp generation, the rule of development of layer of scale, the forming process of all kinds of bacterial mass of research biological membrane; Simultaneously, by periodic sampling, applying X-ray diffraction (XRD, it is the abbreviation of X-ray diffraction,), the proterties of sweep electron microscope methods analyst different times tube wall incrustation layers such as (SEM), sum up the characteristic changing rule and the trend of layer of scale, have crucial meaning.Described displacement pipeline section branch road comprises that two ends are connected with the displacement pipeline section of the 9th valve and the tenth valve respectively, the two ends of described displacement pipeline section branch road are in parallel with the ducted any section of independent loops pipe network subsystem by tee pipe fitting, and described any section is provided with the 11 valve; Preferably, the caliber of displacement pipeline section is identical with the caliber of independent loops pipe network subsystem pipeline, when the length of independent loops pipe network subsystem pipeline is 60~100m, displacement pipeline section duct length can be 5~6 meters, and, displacement pipeline section branch road can be provided with many covers as requested, and the displacement pipeline section below in the displacement pipeline section branch road is furnished with the support structure platform, is easy to put the displacement pipeline section.Close the 9th valve and the tenth valve, open the 11 valve and the displacement pipeline section can be taken off, observe and detect displacement pipeline section internal corrosion fouling situation, simultaneously pipe scale, biological membrane are carried out sampling analysis, research pipe scale composition, structure and microbial population distribution etc.To replace pipeline section takes off, can also change the old pipeline section (pipeline section that intercepting is fit to the displacement installation length is connected with the tenth valve flanges liquid sealing with the 9th valve by the auxiliary right-angle bend that connects in two ends) under the actual city municipal water supply pipe network dismounting, open the 9th valve and the tenth valve, close the 11 valve, the circulation pipe network simulation experiment system of band of the present invention displacement pipeline section just can be investigated the tubing tenure of use of the influence to ductwork water quality, studies different feedwater piping foulings and the biological membrane bacterium that reality moved for many years and comes off to the influence of water quality.
The pipeline of described independent loops pipe network subsystem is provided with the outlet that is used for artificial water intaking sampling, and be provided with the 15 valve in the exit position, when water sampling not, close the 15 valve, when the needs water sampling, open the 15 valve, can adopt the method for chemical reaction or the water-quality guideline of instrumental method analytical sampling water directly from this outlet water sampling.
The present invention has following advantage:
The present invention's water supply subsystem that subsystem adopts double water source to supply water that supplies water, and design has single circulation to stir and whole circulation stirring system, single circulation stirring system can guarantee the even of water quality in each water tank; Whole circulation stirring system can stir the water cycle in two water tanks, guarantees that different former water can fully mix in proportion in two water tanks.The water supply subsystem can provide the tap water of various water quality for circulation pipe network water quality comprehensive simulation test system, and provide heterogeneity water source switching tests, can satisfy of the research requirement of circulation pipe network water quality comprehensive simulation test system to the different quality water source, the different quality that occurs in the pipe network transportation with the tap water that dispatches from the factory of tackling the local different quality of current difference changes and different secondary pollution problems, the problem that output water that can higher analogue simulation reality occurs in the pipe network transportation can also satisfy the assessment before urban water resource is changed and detect needs.
Bubble in the good emptying circulation pipe network of the high-order moisturizing exhaust of the present invention water tank energy, and can be with the water that is lost in the rapid complementary testing of actual participation round-robin retaining in the high-order moisturizing exhaust water tank, when the liquid level in the high-order moisturizing exhaust water tank is low, can carry out moisturizing by water charging system, the water that makes circulation pipe network water quality comprehensive simulation test more be similar in actual and the circulation pipe network is mobile stable, thereby has guaranteed accuracy of experimental results.
The present invention is used to realize that the first pipeline branch road of closed circulation just can realize switching between accurate closed circulation and the closed circulation by the switching between the related valve, guarantee requiring under the prerequisite of the every index monitoring of water quality, make the present invention realize that the closed circulation loop simulates actual water supply line.And, regulate by the process control valve opening on the closed circulation branch road, can be under the constant situation of main pump frequency, " full-section pipe-flow " pressure in the control closed circulation loop, every result that feasible circulation pipe network water quality comprehensive simulation test system by band displacement pipeline section of the present invention carries out test simulation manages the transportation of feeding water near actual pressing dry to greatest extent, help the correlative study of causative mechanism that ductwork water quality pollutes, influence factor, control method, help better to be familiar with physical change, biological change and chemical change of potable water in pipe network.
Multichannel flow of the present invention switches calibrating installation can be by selecting the flow instrument and the ducted discharge of different big or small caliber path calibration independent loops pipe network subsystems of corresponding range when the different flow, improved the flow velocity controllable precision of system's gamut scope when low discharge (especially) greatly, thereby guaranteed that at utmost the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section of the present invention carries out the accuracy of analog reslt.
Visual pipeline section of the present invention make testing crew can the Real Time Observation pipe in the change of coenocorrelation, chemical environment, running environment and change of water quality in the Real Time Observation pipe, understand the situation of change of water quality, grasp depositional phenomenon and the rule of polluter (iron rust, sediment etc.) in pipe.The design of visual pipeline section can help testing crew to get information about test process and dynamic, carry out that water quality flows in the circulation pipe network, variation and pollutant thereof be in the researchs such as deposition rule of tube wall, raising has embodied the practicality of the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section to the understanding of circulation pipe network internal operation state.
Water quality monitoring system of the present invention and electromagnetic flowmeter can be realized the chlorine residue monitoring well, the turbidity monitoring, the granule content monitoring, the chlorine residue monitoring, the turbidity monitoring, granule content monitoring and flow monitoring, the parameter of water quality and the monitoring of running status in the circulation pipe network have been guaranteed, thereby the operating mode in the circulation pipe network there is comprehensive grasp, thereby more help studying clear physical change wherein, chemical change and biological the variation, as chlorine residue attenuation law and dynamic analysis, the Biochemical Mechanism of the formation of DBPs migration in the pipe network, the biological stability of water supply network and chemical stability, basic research such as microhabital provides the analog hardware platform of high emulation in pipe scale electrochemical mechanism and the pipe, for the prevention and control of water supply network secondary pollution provide the basic theory data.
Medicament loading system of the present invention can accurately be controlled filling time and filling dosage, can carry out circulation pipe network water quality comprehensive simulation test secondary system chlorination, three chlorinations, the xenobiotic pollutants invasion, the simulation of operating modes such as water quality mutation, be used to study the medicament filling time, change of water quality rule after filling dosage and xenobiotic pollutants are invaded and potential hazard etc., and the validity of checking counter-measure, promoted the adaptability of the circulation pipe network water quality comprehensive simulation test system of band band displacement pipeline section, to transforming existing drinking water treatment flow process, development new technologies and new technology, set up the method and the strategy of drinking water quality pollution control in the pipe network, provide safe and Wholesome Drinking Water to have important theory directive significance and engineering using value.
Temperature control system precise dose of the present invention control can simulate the temperature conditions with the more approaching Various Seasonal water quality transportation of actual condition as required, thereby has improved the accuracy and the confidence level of test figure, the emulation that has improved pilot system.Simultaneously, also make the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section of the present invention can carry out more extensive studies, particularly can carry out the influence of temperature ductwork water quality, structural pipe wall etc.
The design of a plurality of displacement pipeline sections of the present invention can be guaranteed in the process of the test: regular opposed replace tubes section is dismantled under the prerequisite that does not influence the cyclic test operating mode, the fouling situation and the biological membrane bacterial growth situation of observation, analyzer tube inwall; When the multiple flow velocity operating mode of simulation, can analyze hydraulics under the identical water quality situation and change influence the tube wall biochemical reaction; Can carry out the replacing test of realistic objective pipeline section, after municipal water supply pipeline section in city is dismantled, install and replace displacement pipeline section pipeline of the present invention, can investigate the tubing tenure of use of the influence to ductwork water quality, different feedwater piping foulings and biological membrane bacterium that assay research reality has been moved for many years come off to the influence of water quality.This design has also improved the expansibility of the interaction and the pilot system of pilot system of the present invention and testing crew greatly, make pilot system of the present invention can carry out simulation test wider, object is more, to the feedwater quality problem research have strategic meaning.
The circulation pipe network water quality comprehensive simulation test system of band of the present invention displacement pipeline section provides a good platform for the correlative study of the causative mechanism carrying out ductwork water quality and pollute, influence factor, control method, to transforming existing treatment scheme, setting up method and strategy that ductwork water quality pollutes control.The circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section of the present invention is to water quality stabilizer, antiseptic, pharmaceutical preparations such as sterilization sustained release agent, give novel disinfection technology of water treatment and means, new technologies such as novel tube application, new method, new tool, the hardware place that provides security and efficiency evaluation to detect, be new technology, new method provides the influence of ductwork water quality and identifies and the evaluating standard ways and means, has crucial meaning and provides safe and Wholesome Drinking Water to have important theory directive significance and engineering using value for the research of feedwater quality problem.
Description of drawings
Fig. 1 is the structural representation of the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section of the present invention.
Embodiment
As shown in Figure 1, circulation pipe network water quality comprehensive simulation test system for band displacement pipeline section of the present invention, by the independent loops pipe network subsystem that 1 water supply subsystem and 4 pipelines 2 by the water supply subsystem (hereinafter to be referred as pipeline 2) are connected with the water supply subsystem, four independent loops pipe network subsystems are the first independent loops pipe network subsystem, the second independent loops pipe network subsystem, the 3rd independent loops pipe network subsystem and the 4th independent loops pipe network subsystem.
The water supply subsystem comprises first water tank 1, second water tank 22, pipeline 2, the first mixing circulation pump 3, valve 4, valve 5, valve 19, the second mixing circulation pump 23, valve 24, valve 25, valve 26, second valve 27, the 12 valve 28, valve 29, valve 30, valve 31, valve 32, valve 33 and pipeline 6, first water tank 1 is cylindrical, volume is 6000L, first water tank 1 comprises the water delivering orifice 101 of first water tank 1, the water inlet 102 of first water tank 1, the medicament inlet 103 of first water tank 1, the outlet 104 of first water tank 1, the import 105 of first water tank 1 and the first water tank dust cap 106, the water delivering orifice 101 of first water tank 1 is positioned at the sidewall near first water tank 1 of first water tank, 1 bottom surface, and the water delivering orifice 101 of first water tank 1 is connected with valve 19; The medicament inlet 103 of the water inlet 102 of first water tank 1 and first water tank 1 is positioned at the end face of first water tank 1, the outlet 104 of first water tank 1 is positioned at the sidewall near first water tank 1 of first water tank, 1 bottom surface, the import 105 of first water tank 1 is positioned at the sidewall near first water tank 1 of first water tank, 1 end face, the first water tank dust cap 106 covers on the casing of first water tank 1, and the top sidewall of first water tank 1 is provided with exhaust hole (not mark).The outlet 104 of first water tank 1 is communicated with the import of the first mixing circulation pump 3 by the pipeline 6 that is serially connected with valve 5, the outlet of the first mixing circulation pump 3 links to each other with the import 105 of first water tank by the pipeline 6 that is serially connected with valve 4, the internal diameter of pipeline 2 is 150mm, and the internal diameter of pipeline 6 is 80mm.
Second water tank 22 is cylindrical, volume is 6000L, second water tank 22 comprises the water delivering orifice 2201 of second water tank 22, the water inlet 2202 of second water tank 22, the medicament inlet 2203 of second water tank 22, the outlet 2204 of second water tank 22, the import 2205 of second water tank 22 and and the second water tank dust cap 2206, the water delivering orifice 2201 of second water tank 22 is positioned at the sidewall near second water tank 22 of second water tank, 22 bottom surfaces, and the water delivering orifice 2201 of second water tank 22 is connected with independent loops pipe network subsystem by the pipeline 2 that is serially connected with valve 26; The medicament inlet 2203 of the water inlet 2202 of second water tank 22 and second water tank 22 is positioned at the end face of second water tank 22, the outlet 2204 of second water tank 22 is positioned at the sidewall near second water tank 22 of second water tank, 22 bottom surfaces, and the import 2205 of second water tank 22 is positioned at the sidewall near second water tank 22 of second water tank, 22 end faces.The second water tank dust cap 2206 covers on the casing of second water tank 22, and the top sidewall of second water tank 22 is provided with exhaust small through hole (not mark).The outlet 2204 of second water tank 22 is communicated with the import of the second mixing circulation pump 23 by the pipeline 6 that is serially connected with valve 25, and the outlet of the second mixing circulation pump 23 links to each other with the import 2205 of second water tank by the pipeline 6 that is serially connected with valve 24.First water tank 1 and second water tank 22 pipeline 6 by being serially connected with second valve 27 is communicated with, and is communicated with by the pipeline 6 that is connected to the 12 valve 28 between the outlet of valve 4 and the second mixing circulation pump 3 with between the outlet of valve 24 and the second mixing circulation pump 23.
The water delivering orifice 101 of first water tank 1 is by the pipeline 2 and the first independent loops pipe network subsystem, the second independent loops pipe network subsystem, the 3rd independent loops pipe network subsystem and the 4th independent loops pipe network subsystem are communicated with, pipeline 2 and the first independent loops pipe network subsystem of the water delivering orifice 2201 of second water tank 22 by being serially connected with valve 26, the second independent loops pipe network subsystem, the 3rd independent loops pipe network subsystem and the 4th independent loops pipe network subsystem are communicated with, be provided with valve 29 on the pipeline 2 respectively successively, valve 30, valve 31, valve 32 and valve 33, make no matter be the single water source of first water tank 1 and second water tank 22, or the double water source that first water tank 1 mixes with second water tank 22 can both successfully arrive the first independent loops pipe network subsystem, the second independent loops pipe network subsystem, the 3rd independent loops pipe network subsystem and the 4th independent loops pipe network subsystem.
The first independent loops pipe network subsystem comprises main circulation pump 7, multichannel flow switches calibrating installation 8, visual pipeline section 36, high-order moisturizing exhaust water tank 9, the pipeline 10 of independent loops pipe network subsystem, water charging system 11, emptying branch road 12, water quality monitoring system 13, the first medicament loading system 15, the second medicament loading system 16, temperature control system 34, displacement pipeline section 38, the 6th valve 18, valve 19, the 7th valve 20, the 8th valve 21, the 9th valve 39, the tenth valve 40 and the 11 valve 37.Main circulation pump 7, visual pipeline section 36, multichannel flow switching calibrating installation 8 and high-order moisturizing exhaust water tank 9 are connected successively by the pipeline 10 of independent loops pipe network subsystem and are formed the loop, the total length of the pipeline 10 of independent loops pipe network subsystem is 78m, and the internal diameter of the pipeline 10 of independent loops pipe network subsystem is 150mm.
Multichannel flow switches calibrating installation 8 and comprises first passage traffic alignment branch road in parallel, second channel traffic alignment branch road and third channel traffic alignment branch road, the first passage traffic alignment is propped up first electromagnetic flowmeter 801 and the 3rd valve 802 of route series connection and is formed, the second channel traffic alignment is propped up second electromagnetic flowmeter 803 and the 4th valve 804 of route series connection and is formed, the third channel traffic alignment is propped up the 3rd electromagnetic flowmeter 805 and the 5th valve 806 of route series connection and is formed, the 3rd valve 802, the 4th valve 804 and the 5th valve 806 all adopt motorized valve, first passage traffic alignment branch road is serially connected on the pipeline 10 of circulation pipe network subsystem, and the two ends after second channel traffic alignment branch road and the parallel connection of third channel traffic alignment branch road are in parallel with first passage traffic alignment branch road.Pipe interior diameter in the first passage traffic alignment branch road is 150mm, pipe interior diameter in the second channel traffic alignment branch road is 100mm, pipe interior diameter in the third channel traffic alignment branch road is 50mm, the range maximum of electromagnetic flowmeter 801, the range minimum of electromagnetic flowmeter 805, the range ratio of first electromagnetic flowmeter 801, second electromagnetic flowmeter 803, the 3rd electromagnetic flowmeter 805 is 9: 4: 1.The penetrability of visual pipeline section 36 is 99%, and the selection of material is polymethylmethacrylate (being commonly called as organic glass), and internal diameter of the pipeline is 150mm, and pipe range is 2m.
High-order moisturizing exhaust water tank 9 is cylindrical, volume is 400L, height is highly consistent with water tank 1, high-order moisturizing exhaust water tank 9 is built-in with circular piston-like floating head 903, area is slightly less than high-order moisturizing exhaust water tank 9, make and to leave certain space with the inwall of high-order moisturizing exhaust water tank 9 when piston-like floating head 903 levels are put into, the density of piston-like floating head 903 is less than the density of water, when high-order moisturizing exhaust water tank 9 is water-filled, piston-like floating head 903 under the effect of buoyancy of water along the rising of high-order moisturizing exhaust water tank 9 water levels or reduce and do piston up and down and move.Dust cap 904 is stamped at the top of high-order moisturizing exhaust water tank 9, the area of dust cap 904 is slightly larger than the end face of high-order moisturizing exhaust water tank 9, obtain effectively to support by high-order moisturizing exhaust water tank 9 casings, be provided with the small through hole (not marking) that is used for exhaust at sidewall, can successfully the air in the water in the circulation line be discharged near the high-order moisturizing exhaust water tank 9 of high-order moisturizing exhaust water tank 9 end faces.High-order moisturizing exhaust water tank 9 is provided with the water inlet 901 of high-order moisturizing exhaust water tank and the water delivering orifice 902 of high-order moisturizing exhaust water tank, the water inlet 901 of high-order moisturizing exhaust water tank is positioned at high-order moisturizing exhaust water tank case Senior Three/one position, and the water delivering orifice 902 of high-order moisturizing exhaust water tank is positioned at the position of high-order moisturizing exhaust water tank sidewall near high-order moisturizing exhaust water tank bottom surface.The water inlet 901 of high-order moisturizing exhaust water tank and the water delivering orifice 902 of high-order moisturizing exhaust water tank insert the loop by the pipeline 10 of independent loops pipe network subsystem, the pipeline 10 of the independent loops pipe network subsystem of the water inlet 901 of close high-order moisturizing exhaust water tank 9 is provided with the 6th valve 18, the pipeline 10 of the independent loops pipe network subsystem of the water delivering orifice 902 of close high-order moisturizing exhaust water tank 9 is provided with the 7th valve 20, the 6th valve 18 is a motorized valve, promptly adopt the industrial process operation valve, adopt the industrial process operation valve, can adjust aperture, under the constant situation of main circulation pump 7 frequencies, the flow of the water of the aperture by adjusting the 6th valve 18 in also can controlling plumbing fixtures.Can be by adjusting the flow of the water in the more accurate control loop of aperture.The 8th valve 21 inserts independent loops pipe network subsystem by the pipeline 10 of independent loops pipe network subsystem, is serially connected with the pipeline 10 and the branch road parallel connection of by six valve 18, high-order moisturizing exhaust water tank 9 and seven valve 20 being connected formed of the first pipeline branch road of the 8th valve 21 by independent loops pipe network subsystem.Can be under the constant situation of main circulation pump 7 frequencies, flow by the water in the aperture controlling plumbing fixtures of adjusting the 8th valve 21, thereby realize ducted pressure control, for pressure monitoring, can adopt on the pipeline 10 of independent loops pipe network subsystem the 8th valve 21 vicinity that the size that tensimeter is monitored hydraulic pressure in the pipeline 10 of independent loops pipe network subsystem is housed, aperture by the 8th valve 21 is regulated " full-section pipe-flow " pressure of controlling in the closed circulation loop, thereby makes the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section of the present invention can simulate the actual water quality that press dry the transportation of pipe pipe network that has.
The end face of first water tank 1, second water tank 22 and high-order moisturizing exhaust water tank 9 is positioned at the horizontal highest level face of the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section; The placement location of main circulation pump 7 is positioned at the extreme lower position of the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section.
The pipeline 10 of independent loops pipe network subsystem is provided with first outlet 1001 of the pipeline 10 of independent loops pipe network subsystem, second outlet 1002 of the pipeline 10 of independent loops pipe network subsystem, the triple feed inlet 1003 (water inlet in loop) of the pipeline 10 of independent loops pipe network subsystem, the 4th outlet 1004 of the pipeline 10 of independent loops pipe network subsystem, the 5th outlet 1008 of the pipeline 10 of independent loops pipe network subsystem, first import 1005 of the pipeline 10 of independent loops pipe network subsystem, second import 1006 of the pipeline 10 of independent loops pipe network subsystem, the 4th import 1009 of the triple feed inlet 1007 of the pipeline 10 of independent loops pipe network subsystem and the pipeline 10 of independent loops pipe network subsystem.
Water quality monitoring system 13 can not be made up of by circulating line branch road 1302 water quality monitoring circulating line branch road 1301 and water quality monitoring, water quality monitoring circulating line branch road 1301 is by online conductivity meter (not marking), pH instrument (not marking) and dissolved oxygen DO tester (not marking) three is in parallel is communicated with, and water quality monitoring circulating line branch road 1301 is first import 1005 of the pipeline of first outlet 1001 of the pipeline of the 20mm pipeline that inserts independent loops pipe network subsystem and independent loops pipe network subsystem by internal diameter.Water quality monitoring can not be composed in parallel by residual chlorine detecting instrument (not marking), turbidity detector (not marking) and granule content detector (not marking) three by circulating line branch road 1302, water quality monitoring can not closed circuit 1302 an end be first outlet 1001 that the pipeline of 20mm inserts the pipeline of independent loops pipe network subsystem by internal diameter, the other end inserts trench.
Second outlet 1002 of the pipeline 10 of independent loops pipe network subsystem is connected to the emptying branch road 12 that atmospheric valve 1201 and system's blow-down pipe 1202 are composed in series, the 4th outlet 1004 of the pipeline 10 of independent loops pipe network subsystem is connected to the intake with the 15 valve (not mark), when gathering water sample, open the 15 valve, carry out required test after gathering water sample, close the 15 valve at other times, second import 1006 of the pipeline 10 of independent loops pipe network subsystem is connected to the first medicament loading system 15 that first medicament filling jar 1501 and first delicate metering dispenser pump 1502 is composed in series, and the triple feed inlet 1007 of the pipeline 10 of independent loops pipe network subsystem is connected to the second medicament loading system 16 that second medicament filling jar 1601 and second delicate metering dispenser pump 1602 is composed in series.
Temperature control system 34 comprises by temperature control system ebullator 3401, plate type heat exchanger 3402, the temperature controlling plumbing fixtures branch road that the 13 valve 3403 is formed, first temperature transmitter 3405 and second temperature transmitter 3406, the 13 valve 3403 adopts motorized valve, temperature control system ebullator 3401, plate type heat exchanger 3402 and the 13 valve 3403 are the 4th import 1009 of the pipeline 10 of the 5th outlet 1008 of the pipeline series connection back of the 50mm pipeline 10 that inserts independent loops pipe network subsystem and independent loops pipe network subsystem by bore, the pipeline 10 of the independent loops pipe network subsystem between the 4th import 1009 of the 5th outlet 1008 of the pipeline 10 of independent loops pipe network subsystem and the pipeline 10 of independent loops pipe network subsystem is provided with the 14 valve 35, temperature controlling plumbing fixtures branch road is in parallel with the 14 valve 35, is respectively equipped with first temperature transmitter 3405 and second temperature transmitter 3406 near the 4th import 1009 of the pipeline 10 of the 5th outlet 1008 of the pipeline 10 of independent loops pipe network subsystem and independent loops pipe network subsystem and the pipeline 10 away from the independent loops pipe network subsystem of the 14 valve 35.The two ends that plate type heat exchanger 3402 is used to connect Cooling and Heat Source are connected with the central air conditioner source pump respectively, and the Cooling and Heat Source water in the plate type heat exchanger 3402 (water) comes from the refrigeration of central air conditioner source pump or heats water output.In addition, plate type heat exchanger 3402 also is furnished with special-purpose temperature controller Honeywell-T9275A1002, is used for controlling the secondary coolant-temperature gage through after the plate type heat exchanger heat interchange.
Displacement pipeline section branch road comprises the 9th valve 39, displacement pipeline section 38 and the tenth valve 40, the two ends of displacement pipeline section 38 are connected with the 9th valve 39 and the tenth valve 40 respectively, the two ends of displacement pipeline section branch road are in parallel by any section in the pipeline 10 of tee pipe fitting (not marking) and independent loops pipe network subsystem, and any section is provided with the 11 valve 37; The caliber of displacement pipeline section 38 is consistent with the caliber of the pipeline 10 of independent loops pipe network subsystem, and displacement pipeline section 38 belows in the displacement pipeline section branch road are furnished with support structure platform (not marking), are easy to put displacement pipeline section 38.Displacement pipeline section branch road can be arranged side by side three covers at the pipeline 10 of independent loops pipe network subsystem.
Be communicated with by the pipeline 2 that is provided with first valve 14 between the triple feed inlet 1003 of water supply subsystem and the pipeline of the first independent loops pipe network subsystem; First valve 14 is in parallel with the water charging system 11 that annotated by pipeline 1101, the experiment water of water charging system jar 1102, experiment water dispenser pump 1103 and electromagnetic flowmeter 1104 are composed in series, the outlet of electromagnetic flowmeter 1104 is communicated with the pipeline 10 of independent loops pipe network subsystem by the pipeline 1101 of water charging system, and the inlet of experiment water filling jar 1102 is communicated with pipeline 2 by the pipeline 1101 of water charging system; The internal diameter of the pipeline 1101 of water charging system is 50mm, and the volume of experiment water filling jars 1102 is 100L, in a ball float water intaking valve is arranged.
The water supply subsystem links to each other with the second independent loops pipe network subsystem, the 3rd independent loops pipe network subsystem and the 4th independent loops pipe network subsystem by above-mentioned connected mode, and the second independent loops pipe network subsystem, the 3rd independent loops pipe network subsystem and the 4th independent loops pipe network subsystem are communicated with the water supply subsystem by B end, C end, D end on the pipeline 2 respectively.
Each independent loops pipe network subsystem pipeline is all the same with equipment, difference, just be: the pipeline of independent loops pipe network subsystem is different, the pipeline of the independent loops pipe network subsystem of the first independent loops pipe network subsystem is a ductile iron pipe, the pipeline of the independent loops pipe network subsystem of the second independent loops pipe network subsystem is the PE pipe, the pipeline of the independent loops pipe network subsystem of the 3rd independent loops pipe network subsystem is a stainless-steel tube, and the pipeline of the independent loops pipe network subsystem of the 4th independent loops pipe network subsystem is a ductile iron pipe.Ductile iron pipe is comparatively commonly used, the physics that the water quality of simulating in ductile iron pipe for water at circulation pipe network water quality comprehensive simulation test takes place in transportation, chemistry and biological variation, meaning is very great, because the time that some circulation pipe network water quality comprehensive simulation test needs is long, and it is also many to utilize ductile iron pipe to do circulation pipe network water quality comprehensive simulation test, in order to satisfy the needs of test, the pipeline of the independent loops pipe network subsystem of the pipeline of the independent loops pipe network subsystem of the first independent loops pipe network subsystem and the 4th independent loops pipe network subsystem has all adopted ductile iron pipe in the test, to satisfy the test demand.
The concrete workflow of circulation pipe network water quality comprehensive simulation test system of band of the present invention displacement pipeline section is as follows: at first, the water inlet 102 by water tank 1 adds the former water of waiting to enter the pipe network cyclic test more than 2000 liters and needing study its change of water quality rule in water tank 1.This goes on foot available 2 kinds of modes, and first kind is the output water that directly ships waterworks to be studied with water storage vehicle, and the water inlet 102 by water tank 1 directly pours into water tank 1.Second kind is the tap water that adds pipe network end more than 2000 liters by the water inlet 102 of water tank 1 toward water tank 1, again according to testing the main water-quality guideline that to study, to prepare the medicament of concentration (as adding the chlorination before sodium hypochlorite simulation tap water output water enters pipe network by the medicament inlet 103 of water tank 1, the change of water quality physics law of the tap water that research contains the variable concentrations chlorion after long-time long distance running flows in pipe network), pour into water tank 1 to realize the former water of artificial allotment test.Secondly, as required, can open valve 4 and valve 5, start mixing circulation pump 3, make that the water in the water tank 1 comes out from the outlet 104 of water tank 1, return the import 105 of water tank 1, make the water in the water tank 1 and the soup of injection mix.
Water inlet 2202 by water tank 22 adds the former water of waiting to enter the pipe network cyclic test more than 2000 liters and needing its change of water quality rule of research in water tank 22.This goes on foot available 2 kinds of modes, and first kind is the output water that directly ships waterworks to be studied with water storage vehicle, and the water inlet 2202 by water tank 22 directly pours into water tank 22.Second kind is the tap water that adds pipe network end more than 2000 liters by the water inlet 2202 of water tank 22 toward water tank 22, again according to testing the main water-quality guideline that to study, to prepare the medicament of concentration (as adding the chlorination before sodium hypochlorite simulation tap water output water enters pipe network by the medicament inlet 2203 of water tank 22, the change of water quality physics law of the tap water that research contains the variable concentrations chlorion after long-time long distance running flows in pipe network), pour into water tank 22 to realize the former water of artificial allotment test.Secondly, as required, can open valve 24 and valve 25, start mixing circulation pump 23, make the water in the water tank 22 come out, return the import 2205 of water tank 22, make the water in the water tank 22 and the soup of injection mix from the outlet 2204 of water tank 22.
Can also be as required, water in the water in first water tank 1 and second water tank 22 is mixed, as Open valve 5, the 12 valve 28, the valve 24 and second valve 27, valve-off 4 and valve 25, start the first mixing circulation pump 3, under the effect of the first mixing circulation pump 3, water in first water tank 1 comes out from the outlet 105 of first water tank 1, through the first mixing circulation pump 3, through the 12 valve 28, reach second water tank 22 through valve 24, water in second water tank 22 reaches first water tank through second valve 27, water cycle in this way, reach the purpose that water in first water tank and the water in second water tank mix, another kind of embodiment is an Open valve 25, the 12 valve 28 and valve 4, valve-off 5 and valve 24 start the second mixing circulation pump 23.
Open first valve 14, the 3rd valve 802, the 6th valve 18 and the 7th valve 20, selectively opened valve 19, valve 26, valve 29, valve 30, valve 31, the keying combination of valve 32 and valve 33, make the water tank 1 of winning, second water tank 22 or first water tank 1 and second water tank, 22 mixed water pour into pipeline 10 (being the pipeline 10 of independent loops pipe network subsystem) under the effect of gravity, treat that high-order exhaust replenishing water tank of water 9 is with invariable during for same surface level with the liquid level of first water tank 1 of its pipeline connection or second water tank 22, can assert in the pipeline 10 and be full of water, close first valve 14 then (when simulation heterogeneity water source switching tests, can in process of the test, open first valve 14 once more, and on one side open atmospheric valve 1201 and discharge water, the selectively opened valve 19 in one side, valve 26, valve 29, valve 30, valve 31, the keying combination of valve 32 and valve 33, close the water tank supply channel of initial selected, being communicated with another water tank pipeline pours water in pipeline 10), open water charging system 11, under the effect of water charging system 11, the circulation pipe network subsystem is carried out moisturizing, make the former water liquid level of test in the high-order exhaust replenishing water tank of water reach the higher liquid level in 3/4 place (allows this water tank accumulate the former water of more test as far as possible, can be higher than the water tank liquid level), water charging system 11 is closed afterwards, can open once more according to the needs of moisturizing.Former water in the water supply subsystem can be transported to experiment water filling jar 1102 by the pipeline 2 that is communicated with it under gravitional force, the ball-cock assembly that the water level rising drives in it in jar is closed this jar water inlet, and the retaining in the filling jar 1102 can be injected in the pipeline 10 of independent loops pipe network subsystem under the effect of the experiment water dispenser pump 1103 of water charging system 11, electromagnetic flowmeter 1104 can show the refill flow of testing water, and the accumulation refill flow.
Begin to start main circulation pump 7, main circulation pump 7 is the frequency conversion ebullator, the closed circuit flow is realized by the frequency of regulating main circulation pump 7, water in the pipeline 10 is under the effect of main circulation pump 7, circulate, bubble in the pipeline 10 can be recycled water and take in the high-order moisturizing exhaust water tank 9 and drain: because it is poor to exist certain height between the water delivering orifice 902 of the water inlet 901 of high-order moisturizing exhaust water tank 9 and high-order moisturizing exhaust water tank 9, water is come in from the water inlet 901 of high-order moisturizing exhaust water tank 9, water delivering orifice 902 from high-order moisturizing exhaust water tank 9 is sucked away again, running orbit in high-order moisturizing exhaust water tank 9 from top to bottom, and after being recycled bubble that water brings into and coming in from the water inlet 901 of high-order moisturizing exhaust water tank 9, though can under inertia effect, can move to water delivering orifice 902 directions of high-order moisturizing exhaust water tank 9 from top to bottom at the beginning with the recirculated water running orbit, but because its density is very little, be subjected to very big rising buoyancy, can rise, difference in height enough big between the water inlet 901 of high-order moisturizing exhaust water tank 9 and the water delivering orifice 902 apart from buffering under, can be again by water delivering orifice 902 upstream lines, but can exist certain space discharge by the inwall by piston-like floating head 903 and high-order moisturizing exhaust water tank 9 after come-up, and the through hole that is used for exhaust that final casing by high-order moisturizing exhaust water tank 9 is provided with is discharged.When the water level in the high-order moisturizing exhaust water tank 9 hangs down owing to the exhaust water level, can adopt water charging system 11 that it is carried out moisturizing, make high-order moisturizing exhaust water tank 9 keep certain high liquid level, prevent that air from entering into independent loops pipe network subsystem again.Electromagnetic flowmeter in the multichannel flow switching calibrating installation 8 can feed back the interior circular flow of pipe of the pipeline 10 of main circulation pump variable frequency control, the independent loops pipe network subsystem of Gou Chenging can make the former water of test within the pipeline 10 circulate at a relative environment that relatively seals like this, closed circulation promptly is as the criterion, can also be by opening the 8th valve 21, close the 6th valve 18 and the 7th valve 20, make recirculated water switch to closed circulation from the standard sealing, after switching to closed circulation, can directly utilize water charging system 11 to carry out moisturizing, thereby utilization band multichannel flow switch various situations and the more approaching reality of resulting result that the simulated experiment of the circulation pipe network water quality integrated simulation experiment system of calibration simulates.
Visual pipeline section 36 makes testing crew in test during initialization, can Real Time Observation change of flow state overall process in the pipe of independent loops pipe network subsystem filling test water and circulating exhaust, and the test water exhaust totally reaches completely " full-section pipe-flow " in confirming when to manage; Fluidised form operation conditionss such as turbulent flow, laminar flow in pipe during can Real Time Observation different control flow velocity; The change of coenocorrelation, chemical environment in all right Real Time Observation pipe, running environment and change of water quality in the Real Time Observation pipe, the situation of understanding change of water quality is grasped depositional phenomenon and the rule of polluter (iron rust, sediment etc.) in managing.
Above-mentioned circulation pipe network multichannel flow switches calibrating installation 8 can be according to the difference of the flow in the pipeline 10 (by first electromagnetic flowmeter 801, the flow detection summation of second electromagnetic flowmeter 803 and the 3rd electromagnetic flowmeter 805 can be fed back and obtain), by motorized valve the 3rd valve 802 in the multichannel flow switching calibrating installation 8, the 4th valve 804, the automatic open close of the 5th valve 806 switches, can realize that test water in the pipeline 10 can select the first passage traffic alignment branch road of different big or small calibers automatically when different small-large flow, second channel traffic alignment branch road and third channel traffic alignment branch road are to realize high-precision flow control.As working as ducted discharge at 0~15m 3During/h, select to switch to the third channel traffic alignment branch road of caliber minimum, when ducted discharge at 15~60m 3During/h, select to switch to caliber second channel traffic alignment branch road placed in the middle, when ducted discharge at 60~110m 3(the available pipeline circulation of pipeline main circulation pump maximum flow is 110m to/h 3/ h) time, selection switches to the first passage traffic alignment branch road of caliber maximum, the flow of the different sizes of circulating line can be selected the pipeline by way of the big or small caliber of difference like this, and corresponding flowmeter detection flow by the big or small range of difference, thereby the flow detection accuracy when improving low discharge greatly provides the calibration of gamut for the flow High Accuracy Control of system.
Water quality monitoring system 13 can not be made up of by circulating line branch road 1302 water quality monitoring circulating line branch road 1301 and water quality monitoring, water quality monitoring circulating line branch road 1301 is not by online conductivity meter (marking), PH instrument (not marking) and dissolved oxygen DO tester (not marking) three are in parallel to be communicated with, water quality monitoring circulating line branch road 1301 is first import 1005 of the pipeline of first outlet 1001 of the pipeline of the 20mm pipeline that inserts water quality monitoring independent loops pipe network subsystem and independent loops pipe network subsystem by the pipe interior diameter, can monitor at any time, because at monitored conductivity, water body pH monitoring and dissolved oxygen DO monitoring do not need to add reagent, do not relate to chemical change, the water quality of monitoring can be regarded as substantially and not change, can decompression yet, therefore, above-mentioned water sample can also be got back in the pipeline 10 by water quality monitoring circulating line branch road 1301 after monitoring, and monitoring can be carried out in the pipeline operational process at any time.Water quality monitoring can not be composed in parallel by online residual chlorine detecting instrument (not marking), turbidity detector (not marking) and granule content detector (not marking) three by circulating line branch road 1302, water quality monitoring can not closed circuit 1302 an end be first outlet 1001 that the pipeline of 20mm inserts the pipeline 10 of independent loops pipe network subsystem by the pipe interior diameter, the other end inserts trench.Because the loop of this design relates to add medicament, changed test water water quality in the circulating line, or diversion comes out to detect the back decompression, can't get back in the circulation person in charge by pressure differential again, in order not influence, do not pollute the water quality in the pipeline 10, to be used for the chlorine residue monitoring, the water of the decompression of water sample after monitoring of turbidity monitoring and granule content monitoring, directly enter trench, like this, water in the pipeline 10 can reduce thereupon, though it is very little to be used for the water yield of the water sample that on-line monitoring sampling discharges, but open sampling continuously always, integration loss also can be very big, thereby influence test accuracy, therefore, in order to reduce the loss of water sample, the chlorine residue monitoring, can set as required the interval time of turbidity monitoring and granule content monitoring, and generally be used for chlorine residue, being captured in of the water sample of turbidity and granule content on-line monitoring should not be too frequent on the basis of satisfying the test figure requirement.Simultaneously, participation round-robin retaining meeting in the high-order moisturizing exhaust water tank 9 replenishes (under the special test situation at any time, moisturizing demand in the pipeline 10 surpasses the available maximum rate of water make-up in the high-order exhaust water supply tank 9, can also pass through water charging system 11 moisturizing in time rapidly), thus make the recirculated water operation in the pipeline 10 keep stable.
Conductivity, water body pH, dissolved oxygen DO, chlorine residue, turbidity and the granule content in the pipeline 10 of monitoring independent loops pipe network subsystems with water quality monitoring system 13, can also be by the 4th outlet 1004 that has the 15 valve of pipeline 10, open and close by the 15 valve, carry out artificial sample water intaking, and then the water sample that collects transferred to carry out offline inspection in the analytical instrument.
Conductivity in the pipeline 10 of the independent loops pipe network subsystem that monitors for water quality monitoring system 13, water body pH, dissolved oxygen DO, chlorine residue, outside the variation of turbidity and granule content, the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section of the present invention can also directly add medicament in the former water of test in pipeline 10 by the first medicament loading system 15 and the second medicament loading system 16, can simulate the change of water quality process after secondary in the actual water supply network way adds sanitizer (as the secondary chlorination), medicament delivery is advanced first medicament filling jar 1501 and second medicament delivery and is advanced medicament filling jar 1601, then (as required at the first delicate metering dispenser pump 1502 and the second delicate metering dispenser pump 1602, the interval time that set to add and each addition) effect under, render in the pipeline 10 of independent loops pipe network subsystem.
At present, domestic waterworks all is the disposable disinfection by chlorine agent that adds capacity in output water, still can keep water quality preferably when the tap water of water quality reaching standard is carried arrival user fire hose head end through the long distance of pipe network when dispatching from the factory with maintenance.But output water has the long weak point that has to the conveyance conduit of pipe network user water swivel end, for the tap water that makes long pipeline retention time can keep water quality, may just need when dispatching from the factory, add more sanitizer, the harm that will bring a lot of user's disinfection of tap water accessory substances that connect than the short tube net to exceed standard, if add few, the user's tap water that connects than the long tube net might have bacterium, the organism water quality that exceeds standard again can't keep harm up to standard, and this is a problem of facing a difficult choice.Therefore, external a lot of advanced cities are analyzed by pipe network optimization, set up the equipment of secondary chlorination (also can add other sanitizers) in the appropriate node midway that connects than the long tube net,, can significantly reduce the residual harm of DBPs in the tap water to reduce output water chlorine dosage once.And the first medicament loading system 15 of the present invention and the second medicament loading system 16 can be simulated the secondary of pipe network, the test that adds sanitizer three times.By the 4th outlet 1004 the intakes that are connected to of water quality monitoring system 13 and the pipeline by independent loops pipe network subsystem the water quality in the pipeline 10 of independent loops pipe network subsystem is monitored again with the 15 valve, thus its Disinfection Effect of the analysis that can quantize, the situation of sterilization back water quality and the attenuation change rule of sterilization product and DBPs.
The first medicament loading system 15 and the second medicament loading system 16 of the present invention's configuration, also can be by the test of the former water simulation of the different exogenous pollution of their filling water supply network exogenous pollution, the research external source is polluted the problem that enters caused pipe network environmental change behind the pipe network, water quality impact degree etc. is still located to study blank field both at home and abroad.
Temperature control system 34 can change and controlling plumbing fixtures 10 in the temperature of water.When needs change the temperature of the water in the pipeline 10 of independent loops pipe network subsystem, can open the 13 valve 3403, open temperature control system ebullator 3401, part test water in pipeline 10 is under 3401 effects of temperature control system ebullator, enter plate type heat exchanger 3402, the caliber of temperature controlling plumbing fixtures branch road is less, caliber is 50mm, part test water in the pipeline 10 will enter plate type heat exchanger 3402 and carry out cold and hot exchange, the water of getting back in the pipeline 10 after 3402 heat exchange of process plate type heat exchanger is secondary water, after being back to pipeline 10 by secondary water, can heat or cooling duct 10 in test water, thereby change the temperature of test water in the pipeline 10.The Cooling and Heat Source of plate type heat exchanger 3402 is provided by the central air conditioner source pump, the central air conditioner source pump provides a water of different temperatures, water by the different temperatures that provides in the central air conditioner source pump and the part test water in the temperature controlling plumbing fixtures branch road by cold and hot exchange after, obtain the heat exchange secondary water of different temperatures.By the special-purpose temperature controller Honeywell-T9275A1002 that is furnished with in the plate type heat exchanger 3402, can control the secondary coolant-temperature gage after the heat exchange, too high or too low as the secondary coolant-temperature gage, the Honeywell temperature controller can be with information feedback, will stop a water to enter plate type heat exchanger 3402 by valve-off, thereby realize control, prevent that the secondary coolant-temperature gage is too high or too low the secondary coolant-temperature gage.Second temperature transmitter 3406 is used to detect the temperature of the preliminary mixed test water after the secondary water of excess temperature control branch road passes back into pipeline 10.First temperature transmitter 3405 is used for detecting secondary water and passes back into nearly circle and the abundant mixed water temperature of test loop water that circulate again behind the pipeline 10, and this has reflected the actual pipe network test water temperature after independent loops pipe network subsystem is through the temperature control system temperature control.
Displacement pipeline section branch road can be provided with 3 covers in each independent loops pipe network subsystem, every cover all has displacement pipeline section 38.Whenever the cyclic test operating mode that is nested with replace tubes section branch road participation pipe network is: the 9th valve 39 and the tenth valve 40 full-gears, and the 11 valve 37 closed conditions, test water can be by way of hyperphoric replace tubes section 38 operation circulations.And under this operating condition, open the 11 valve 37, close the 9th valve 39 and the tenth valve 40 again, can realize: continue under the operating mode of cyclic test for a long time at the independent loops pipe network that does not influence its place, to replace pipeline section 38 takes off, water in the displacement pipeline section 38 can enter in tank or the container, and opposed replace tubes section 38 internal corrosion foulings and biological membrane bacterium carry out sampling analysis, research pipe scale component, structure and bacterial population distribution etc.To replace after pipeline section 38 takes off, can also change the old pipeline section of same caliber under the operation city municipal water supply pipe network dismounting for many years, and intercept suitable length, auxiliary connection by the two ends right-angle bend again with the 9th valve 39 with the tenth valve 40 flange fluid-tights close and be connected, open the 9th valve 39 and the tenth valve 40 again, close the 11 valve 37, the circulation pipe network simulation experiment system of band of the present invention displacement pipeline section just can be investigated the tubing tenure of use of the influence to ductwork water quality, studies different feedwater piping foulings and the biological membrane bacterium that reality moved for many years and comes off to the influence of water quality.

Claims (10)

1. the circulation pipe network water quality comprehensive simulation test system with the displacement pipeline section is characterized in that, comprises water supply subsystem and the independent loops pipe network subsystem that is connected with the water supply subsystem by the pipeline with first valve;
Described water supply subsystem comprises first water tank and second water tank that is communicated with first water tank by the pipeline with second valve, and described first water tank and second water tank are equipped with water inlet, water delivering orifice and medicament inlet;
Described independent loops pipe network subsystem is to comprise the main circulation pump by the pipeline series connection, the loop that multichannel flow switches calibrating installation, visual pipeline section and high-order moisturizing exhaust water tank; Described loop is provided with water inlet, and the water inlet in described loop is communicated with the water supply subsystem;
Described multichannel flow switches calibrating installation and comprises the first passage traffic alignment branch road that is composed in series by the 3rd valve and first electromagnetic flowmeter in parallel, second channel traffic alignment branch road that is composed in series by the 4th valve and second electromagnetic flowmeter and the third channel traffic alignment branch road that is composed in series by the 5th valve and the 3rd electromagnetic flowmeter, described independent loops pipe network subsystem, first passage traffic alignment branch road, the ratio of the pipe diameter in second channel traffic alignment branch road and the third channel traffic alignment branch road is 3: 3: 2: 1, and the range of the range of the range of described first electromagnetic flowmeter>second electromagnetic flowmeter>the 3rd electromagnetic flowmeter;
The penetrability of described visual pipeline section is greater than 90%, and the caliber of visual pipeline section equates with the caliber of the pipeline of independent loops pipe network subsystem;
The position of the water inlet of the close high-order moisturizing exhaust water tank in described loop and the water delivering orifice of close high-order moisturizing exhaust water tank is respectively equipped with the 6th valve and the 7th valve;
Described loop is connected with the first pipeline branch road with eight valve in parallel with the branch road that is composed in series by the 6th valve, high-order moisturizing exhaust water tank and the 7th valve, is used to the water charging system of loop supplementing water, is used for discharging the emptying branch road of loop water, the water quality monitoring system that is used for the water quality of monitoring circuit water, the temperature control system that is used for the regulating loop water temperature and displacement pipeline section branch road;
Described water charging system comprises the experiment water filling jar and the experiment water dispenser pump of series connection, described experiment water filling delivery side of pump and circuit communication, and the inlet of described experiment water filling jar is communicated with the water supply subsystem;
Described displacement pipeline section branch road comprises that two ends are connected with the displacement pipeline section of the 9th valve and the tenth valve respectively, the two ends of described displacement pipeline section branch road are in parallel with the ducted any section of independent loops pipe network subsystem by tee pipe fitting, and described any section is provided with the 11 valve;
The end face of described first water tank, second water tank and high-order moisturizing exhaust water tank approaches same surface level, described surface level is positioned at the horizontal extreme higher position of the circulation pipe network water quality comprehensive simulation test system of described band displacement pipeline section, and the placement location of described main circulation pump is lower than the placement location of first water tank, second water tank and high-order moisturizing exhaust water tank;
Described high-order moisturizing exhaust water tank comprises casing and is positioned at the piston-like floating head of casing, leaves the space between described piston-like floating head and the cabinet wall; The density of described piston-like floating head is less than the density of water.
2. the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section according to claim 1 is characterized in that the water delivering orifice of described first water tank is positioned at the bottom of first water tank;
The first water tank dust cap that area is slightly larger than the first water tank end face is stamped at the top of described first water tank;
The top side wall of described first water tank is provided with the through hole that is used for exhaust;
Described first water tank is connected with the second pipeline branch road with the first mixing circulation pump, and the two ends of the described second pipeline branch road are communicated with first water tank respectively;
The water delivering orifice of described second water tank is positioned at the bottom of second water tank;
The second water tank dust cap that area is slightly larger than the second water tank end face is stamped at the top of described second water tank;
The top side wall of described second water tank is provided with the through hole that is used for exhaust;
Described second water tank is connected with the 3rd pipeline branch road with the second mixing circulation pump, and the two ends of described the 3rd pipeline branch road are communicated with second water tank respectively;
Difference in height is all arranged between the two ends of the described second pipeline branch road and between the two ends of the 3rd pipeline branch road;
The described second pipeline branch road is communicated with by the pipeline that has the 12 valve with the 3rd pipeline branch road.
3. the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section according to claim 1 is characterized in that the wall of described high-order moisturizing exhaust water tank is vertical with the bottom surface;
The high-order moisturizing exhaust water tank dust cap that area is slightly larger than high-order moisturizing exhaust water tank end face is stamped at the top of described high-order moisturizing exhaust water tank;
The top of described high-order moisturizing exhaust water tank is provided with the through hole that is used for exhaust.
4. according to the circulation pipe network water quality comprehensive simulation test system of claim 1 or 3 described band displacement pipeline sections, it is characterized in that the casing of described high-order moisturizing exhaust water tank is cylindrical.
5. the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section according to claim 1, it is characterized in that, the water delivering orifice of described high-order moisturizing exhaust water tank is positioned at the bottom of high-order moisturizing exhaust water tank, and the water inlet of described high-order moisturizing exhaust water tank is higher than the water delivering orifice of high-order moisturizing exhaust water tank and is lower than high-order moisturizing exhaust water tank case Senior Two/one position.
6. the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section according to claim 1 is characterized in that the pipeline that described independent loops pipe network subsystem is a plurality of and a plurality of independent loops pipe network subsystems is identical or different;
The pipeline of described independent loops pipe network subsystem is ductile iron pipe, polyethylene pipe, copper pipe or stainless-steel tube.
7. the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section according to claim 1 is characterized in that described water quality monitoring system can not be made up of by the circulating line branch road water quality monitoring circulating line branch road and water quality monitoring;
Described water quality monitoring circulating line branch road comprises conductivity meter, pH instrument and dissolved oxygen DO tester in parallel, and the two ends of described water quality monitoring circulating line branch road are communicated with the pipeline of independent loops pipe network subsystem respectively;
Described water quality monitoring can not comprise residual chlorine detecting instrument, turbidity detector and granule content detector in parallel by the circulating line branch road, described water quality monitoring can not the circulating line branch road an end be communicated with the pipeline of independent loops pipe network subsystem, the other end inserts trench.
8. the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section according to claim 1, it is characterized in that, be connected with the medicament loading system on the pipeline of described independent loops pipe network subsystem, described medicament loading system comprises the medicament filling jar and the medicament dispenser pump of series connection.
9. the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section according to claim 1, it is characterized in that, described temperature control system comprises temperature controlling plumbing fixtures branch road, first temperature transmitter and second temperature transmitter of being made up of the 13 valve, plate type heat exchanger and the temperature control system ebullator of series connection, and the two ends of described temperature controlling plumbing fixtures branch road are communicated with the pipeline of the independent loops pipe network subsystem that has the 14 valve respectively; Described temperature controlling plumbing fixtures branch road is in parallel with the 14 valve;
Described first temperature transmitter is positioned at temperature controlling plumbing fixtures branch road inflow point, and described second temperature transmitter is positioned at temperature controlling plumbing fixtures branch road exit.
10. the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section according to claim 1 is characterized in that, the bottom surface of described main circulation pump is positioned at the floor level face of the circulation pipe network water quality comprehensive simulation test system of band displacement pipeline section;
The pipeline of described independent loops pipe network subsystem is provided with the outlet that is used for artificial water intaking sampling with the 15 valve.
CN2011101305893A 2011-05-19 2011-05-19 Water quality comprehensive simulation test system with replacement pipe sections for circulating pipe network Expired - Fee Related CN102297932B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101305893A CN102297932B (en) 2011-05-19 2011-05-19 Water quality comprehensive simulation test system with replacement pipe sections for circulating pipe network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101305893A CN102297932B (en) 2011-05-19 2011-05-19 Water quality comprehensive simulation test system with replacement pipe sections for circulating pipe network

Publications (2)

Publication Number Publication Date
CN102297932A true CN102297932A (en) 2011-12-28
CN102297932B CN102297932B (en) 2012-11-21

Family

ID=45358492

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101305893A Expired - Fee Related CN102297932B (en) 2011-05-19 2011-05-19 Water quality comprehensive simulation test system with replacement pipe sections for circulating pipe network

Country Status (1)

Country Link
CN (1) CN102297932B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103868559A (en) * 2014-03-28 2014-06-18 中冶南方工程技术有限公司 Parallel installation and segmental measurement flow measurement method with large measurement range ratio and device thereof
CN104316664A (en) * 2014-10-31 2015-01-28 北京市自来水集团有限责任公司技术研究院 Method for measuring in-situ simulated water quality in pipe network under water source switching condition
CN104316665A (en) * 2014-10-31 2015-01-28 北京市自来水集团有限责任公司技术研究院 Equipment for studying pipe network water quality stability under condition of simulating water source switch in situ
CN105300722A (en) * 2015-11-24 2016-02-03 清华大学 Water transport and distribution pipe network test platform and test method
US11125658B2 (en) 2018-12-19 2021-09-21 Blue-Water Management Solutions, Inc. Fluid sampling unit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4897022A (en) * 1988-07-25 1990-01-30 Hudson Carl E Multi-tank/multi-pump water pressure booster system
JP2004060970A (en) * 2002-07-26 2004-02-26 Rajiant:Kk Piping structure of heating system
JP3510604B2 (en) * 2001-05-09 2004-03-29 新洋技研工業株式会社 Cooling water supply system
CN201723978U (en) * 2010-07-15 2011-01-26 宝钢工程技术集团有限公司 Automatic water power balancing device for industrial circulating water pipe grid
CN201836651U (en) * 2010-09-27 2011-05-18 河南理工大学 Water make-up and constant pressure system for multi-heat source ring-shaped heating pipe network

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4897022A (en) * 1988-07-25 1990-01-30 Hudson Carl E Multi-tank/multi-pump water pressure booster system
JP3510604B2 (en) * 2001-05-09 2004-03-29 新洋技研工業株式会社 Cooling water supply system
JP2004060970A (en) * 2002-07-26 2004-02-26 Rajiant:Kk Piping structure of heating system
CN201723978U (en) * 2010-07-15 2011-01-26 宝钢工程技术集团有限公司 Automatic water power balancing device for industrial circulating water pipe grid
CN201836651U (en) * 2010-09-27 2011-05-18 河南理工大学 Water make-up and constant pressure system for multi-heat source ring-shaped heating pipe network

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103868559A (en) * 2014-03-28 2014-06-18 中冶南方工程技术有限公司 Parallel installation and segmental measurement flow measurement method with large measurement range ratio and device thereof
CN104316664A (en) * 2014-10-31 2015-01-28 北京市自来水集团有限责任公司技术研究院 Method for measuring in-situ simulated water quality in pipe network under water source switching condition
CN104316665A (en) * 2014-10-31 2015-01-28 北京市自来水集团有限责任公司技术研究院 Equipment for studying pipe network water quality stability under condition of simulating water source switch in situ
CN104316665B (en) * 2014-10-31 2016-01-13 北京市自来水集团有限责任公司技术研究院 A kind of equipment studying ductwork water quality stability under original position simulation water source switching condition
CN104316664B (en) * 2014-10-31 2016-08-24 北京市自来水集团有限责任公司技术研究院 A kind of measure the method for ductwork water quality under the conditions of in situ simulation water source switching
CN105300722A (en) * 2015-11-24 2016-02-03 清华大学 Water transport and distribution pipe network test platform and test method
CN105300722B (en) * 2015-11-24 2018-06-15 清华大学 Water distributing network pilot test platform and test method
US11125658B2 (en) 2018-12-19 2021-09-21 Blue-Water Management Solutions, Inc. Fluid sampling unit

Also Published As

Publication number Publication date
CN102297932B (en) 2012-11-21

Similar Documents

Publication Publication Date Title
CN102288736B (en) Circulating pipe network water quality integrative simulation test system with visible pipe sections
CN102288737B (en) Circulating pipe network water quality integrative simulation test system with multichannel flow switching and calibrating devices
CN102278599B (en) Circulating pipe network water quantity integrated simulation test system with temperature control system
CN102230577B (en) Comprehensive water quality simulation test system for quasi-closed circulation pipe network
CN102297932B (en) Water quality comprehensive simulation test system with replacement pipe sections for circulating pipe network
CN102297933B (en) Circulation pipe network water quality comprehensive simulation test system with stationary water pipe section
CN104316665B (en) A kind of equipment studying ductwork water quality stability under original position simulation water source switching condition
CN102288738B (en) Circulating pipe network water quality integrative simulation test system
CN103698487A (en) Intelligent building water quality multi-parameter monitoring system
CN108585226A (en) A kind of system and method for the circulating water quality stability contorting based on remote control
CN102289979B (en) Double water source water supply circulating pipe network water quality integrative simulation test system
CN202082620U (en) Water quality comprehensive simulation test system for circulating pipe network
CN102399036B (en) Movable test guiding water plant for emergency treatment
CN103937660B (en) A kind of water supply network microbiological test small testing device
CN202083686U (en) Water quality comprehensive simulation test system of double-water source water supply circulating pipe network
CN203630124U (en) Intelligent building water quality multi-parameter monitoring system
CN202082621U (en) Quasi-closed circulation pipe network water quality comprehensive simulation test system
CN102289977B (en) Comprehensive pipeline disinfection effect testing apparatus
CN204188602U (en) A kind of equipment studying ductwork water quality stability under original position simulation water source switching condition
CN216377563U (en) Novel ultraviolet sterilization water purifier
CN104316664B (en) A kind of measure the method for ductwork water quality under the conditions of in situ simulation water source switching
CN105301187A (en) Sewage pipeline simulation device
Alemu et al. Assessment of urban water quality and hydraulic performance of the distribution pipe network system
Lemke et al. Effects of Storage Tank Mixing on Water Quality
CN105905954B (en) The adding method thereof of the automatic mobile sewage disposal device for calculating dosing dosage and frequency

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121121