CN102287052A - Construction method of ecological wall - Google Patents
Construction method of ecological wall Download PDFInfo
- Publication number
- CN102287052A CN102287052A CN201110137493XA CN201110137493A CN102287052A CN 102287052 A CN102287052 A CN 102287052A CN 201110137493X A CN201110137493X A CN 201110137493XA CN 201110137493 A CN201110137493 A CN 201110137493A CN 102287052 A CN102287052 A CN 102287052A
- Authority
- CN
- China
- Prior art keywords
- wall
- geotextiles
- plaster
- main part
- form removal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Curing Cements, Concrete, And Artificial Stone (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses a construction method of an ecological wall. The construction method comprises the steps of processing materials, erecting a formwork and configuring reinforcement, feeding the materials, removing the formwork, applying a geotextile, brushing asphalt and the like. The construction method has the following beneficial effects: the wall is convenient to construct and has good quality and the wall per m<3> can save electrical energy by 4 degrees, cement amount by over 30kg and clay by 0.6m<3> compared with the brick body.
Description
Technical field
The present invention relates to a kind of job practices of ecological wall.
Background technology
The construction of ecological wall generally adopts mud wall to pile up, and its stack manner has two kinds: a kind of is that water is folded: earth and water are are fully mixed and stirred, and its water content is about 20%, and with the special-purpose wall instrument of beating, the shovel mound is folded then; Another kind of for non-irrigated folded: as to be to draft body of wall width formwork erection, to add folded dried mud compacting.Tradition mud wall technology subject matter is to utilize problems such as clay resource is many, the body of wall life-span is short.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, the job practices of the ecological wall that wall quality is good.
Technical solution of the present invention is:
A kind of job practices of ecological wall is characterized in that: comprise the following steps:
(1) material processed: material of main part pulverized be the particle of particle diameter for≤1cm; Fibrous material is processed into fineness less than 0.15mm, and length mixes material of main part, fibrous material, cementitious materials and the water part by weight by 6:2:1:1 then less than the particle of 10mm; Described material of main part is one or more in earth, cinder, the building waste; Described fibrous material is one or more in stalk, wood chip, the foam; Described cementitious materials is cement, lime or gypsum;
(2) formwork erection, configuration reinforcement: carry out formwork erection and configuration reinforcement by designing requirement;
(3) feed intake: the material that step (1) is prepared feeds intake, and the thickness that feeds intake is 30cm, tamps then or vibrates, and makes compactness greater than 98%;
(4) form removal: after body of wall forms 3d, carry out form removal;
(5) geotextiles of applying ointment or plaster: after the form removal, after the time body of wall more than 3 months is metalled run out, the geotextiles of on body of wall, applying ointment or plaster;
(6) brushing pitch: after geotextiles is applied ointment or plaster, be 0.5cm pitch, form the waterproofing course surface layer at the even brushing thickness of geotextiles.
Easy construction of the present invention, wall quality is good, and every cubic metre of body of wall is compared with the brick body and can be saved 4 degree electric energy, saves more than the cement consumption 30kg, saves 0.6 cubic metre of clay.
The specific embodiment
The invention will be further described below in conjunction with embodiment.
The specific embodiment
A kind of job practices of ecological wall comprises the following steps:
(1) material processed: material of main part pulverized be the particle of particle diameter for≤1cm; Fibrous material is processed into fineness less than 0.15mm, and length mixes material of main part, fibrous material, cementitious materials and the water part by weight by 6:2:1:1 then less than the particle of 10mm; Described material of main part is one or more in earth, cinder, the building waste; Described fibrous material is one or more in stalk, wood chip, the foam; Described cementitious materials is cement, lime or gypsum;
(2) formwork erection, configuration reinforcement: carry out formwork erection and configuration reinforcement by designing requirement;
(3) feed intake: the material that step (1) is prepared feeds intake, and the thickness that feeds intake is 30cm, tamps then or vibrates, and makes compactness greater than 98%;
(4) form removal: after body of wall forms 3d, carry out form removal;
(5) geotextiles of applying ointment or plaster: after the form removal, after the time body of wall more than 3 months or 3 months is metalled run out, the geotextiles of on body of wall, applying ointment or plaster;
(6) brushing pitch: after geotextiles is applied ointment or plaster, be 0.5cm pitch, form the waterproofing course surface layer at the even brushing thickness of geotextiles.
Claims (1)
1. the job practices of an ecological wall is characterized in that: comprise the following steps:
(1) material processed: material of main part pulverized be the particle of particle diameter for≤1cm; Fibrous material is processed into fineness less than 0.15mm, and length mixes material of main part, fibrous material, cementitious materials and the water part by weight by 6:2:1:1 then less than the particle of 10mm; Described material of main part is one or more in earth, cinder, the building waste; Described fibrous material is one or more in stalk, wood chip, the foam; Described cementitious materials is cement, lime or gypsum;
(2) formwork erection, configuration reinforcement: carry out formwork erection and configuration reinforcement by designing requirement;
(3) feed intake: the material that step (1) is prepared feeds intake, and the thickness that feeds intake is 30cm, tamps then or vibrates, and makes compactness greater than 98%;
(4) form removal: after body of wall forms 3d, carry out form removal;
(5) geotextiles of applying ointment or plaster: after the form removal, after the time body of wall more than 3 months is metalled run out, the geotextiles of on body of wall, applying ointment or plaster;
(6) brushing pitch: after geotextiles is applied ointment or plaster, be 0.5cm pitch, form the waterproofing course surface layer at the even brushing thickness of geotextiles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110137493XA CN102287052A (en) | 2011-05-26 | 2011-05-26 | Construction method of ecological wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110137493XA CN102287052A (en) | 2011-05-26 | 2011-05-26 | Construction method of ecological wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102287052A true CN102287052A (en) | 2011-12-21 |
Family
ID=45333781
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110137493XA Pending CN102287052A (en) | 2011-05-26 | 2011-05-26 | Construction method of ecological wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102287052A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103922655A (en) * | 2014-04-09 | 2014-07-16 | 葛加君 | Method for preparing ecological thermal insulating wall brick |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1134403A (en) * | 1995-04-24 | 1996-10-30 | 上海三井·英凡特工艺品有限公司 | Concrete made of clay, sea sand, dregs and dust produced in course of building and other material |
JPH08302858A (en) * | 1995-05-02 | 1996-11-19 | Hazama Gumi Ltd | Rc wall construction method |
CN1374267A (en) * | 2002-04-08 | 2002-10-16 | 单国民 | Light mortar and its production process |
CN1451827A (en) * | 2002-04-15 | 2003-10-29 | 王西 | Building of regenerated resource walling |
CN1704539A (en) * | 2004-06-02 | 2005-12-07 | 陈田平 | Construction method for one-time pouring molding of light solid wall |
CN1922117A (en) * | 2004-02-06 | 2007-02-28 | 代尔夫特岩土基金会 | Construction material based upon a sludge or sludged waste material |
CN101298371A (en) * | 2007-05-01 | 2008-11-05 | 李东升 | Light insulating brick prepared from fly ash, boiler slag, construction garbage and straw and preparation thereof |
US20090166267A1 (en) * | 2007-12-27 | 2009-07-02 | Beijing Hengyecun S&T Co., Ltd | Method which turns construction wastes into building materials |
-
2011
- 2011-05-26 CN CN201110137493XA patent/CN102287052A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1134403A (en) * | 1995-04-24 | 1996-10-30 | 上海三井·英凡特工艺品有限公司 | Concrete made of clay, sea sand, dregs and dust produced in course of building and other material |
JPH08302858A (en) * | 1995-05-02 | 1996-11-19 | Hazama Gumi Ltd | Rc wall construction method |
CN1374267A (en) * | 2002-04-08 | 2002-10-16 | 单国民 | Light mortar and its production process |
CN1451827A (en) * | 2002-04-15 | 2003-10-29 | 王西 | Building of regenerated resource walling |
CN1922117A (en) * | 2004-02-06 | 2007-02-28 | 代尔夫特岩土基金会 | Construction material based upon a sludge or sludged waste material |
CN1704539A (en) * | 2004-06-02 | 2005-12-07 | 陈田平 | Construction method for one-time pouring molding of light solid wall |
CN101298371A (en) * | 2007-05-01 | 2008-11-05 | 李东升 | Light insulating brick prepared from fly ash, boiler slag, construction garbage and straw and preparation thereof |
US20090166267A1 (en) * | 2007-12-27 | 2009-07-02 | Beijing Hengyecun S&T Co., Ltd | Method which turns construction wastes into building materials |
Non-Patent Citations (1)
Title |
---|
刘艳红: "生态墙体材料的应用与发展研究", 《山西建筑》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103922655A (en) * | 2014-04-09 | 2014-07-16 | 葛加君 | Method for preparing ecological thermal insulating wall brick |
CN103922655B (en) * | 2014-04-09 | 2016-01-06 | 葛加君 | Ecological heat preservation wall brick preparation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104609814B (en) | Anti-aqueous dispersion synchronous grouting material with large specific gravity and low consistence | |
CN101581093B (en) | Composite high performance soil cement mortar pile construction method | |
CN103922647B (en) | Heat insulation house surface construction ecological glue and uses thereof | |
CN104529333A (en) | Waste sintered brick recycled C30 concrete and preparation method thereof | |
CN103086619B (en) | The preparation method of building waste micro-powder composite admixture | |
CN103496896A (en) | Non-sintered slag soil wall body block and preparation process thereof | |
CN102815909B (en) | Gangue ready mixed mortar and preparation method thereof | |
CN104177015A (en) | Baking-free brick mainly prepared from river/lake dredging sediment and natural-curing manufacturing method thereof | |
CN107176812A (en) | High intensity contraction-free grouting concrete and its production method | |
CN101845830B (en) | Open caisson deviation rectification construction method | |
CN104230237A (en) | Ceramic tile ready-mixed mortar and production method thereof | |
CN103265239A (en) | Method for preparing sludge concrete | |
CN107344822A (en) | One kind is containing bentonitic premixing mortar water-keeping thickening material and preparation method thereof | |
CN106045424A (en) | Method for producing prefabricated member of concrete ditch by using construction waste | |
CN104790565B (en) | A kind of cast-in-place phosphogypsum bearing wall Temperature Variation In Buildings of Mixed Structures main body construction method | |
CN103113078A (en) | Pre-mixed building mortar making full use of solid wastes | |
CN101234874B (en) | Cement-base rigidity water-proofing material and preparing method thereof | |
CN102287052A (en) | Construction method of ecological wall | |
CN101704645A (en) | Water-holding thickening agent of mortar | |
CN105753387A (en) | Stone powder waste material regeneration easy plaster and preparation method thereof | |
CN102936964A (en) | Construction method of high elongation concrete embedded constructional column | |
CN109053105A (en) | Modified rammed earth material of a kind of gypsum and preparation method thereof | |
CN103030354A (en) | Cement and lava composite concrete manufacturing method | |
CN202482897U (en) | Concrete structure | |
CN105439518B (en) | A kind of patching additive of cement concrete and preparation method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20111221 |
|
RJ01 | Rejection of invention patent application after publication |