CN102278063A - Water-mill drilling construction process for Karst terrain - Google Patents

Water-mill drilling construction process for Karst terrain Download PDF

Info

Publication number
CN102278063A
CN102278063A CN2011101231635A CN201110123163A CN102278063A CN 102278063 A CN102278063 A CN 102278063A CN 2011101231635 A CN2011101231635 A CN 2011101231635A CN 201110123163 A CN201110123163 A CN 201110123163A CN 102278063 A CN102278063 A CN 102278063A
Authority
CN
China
Prior art keywords
tube
target hole
hole
core
bore
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101231635A
Other languages
Chinese (zh)
Inventor
范晓静
杨洪
罗骥
马俊
王杰
王远才
叶贵红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN NO3 CONSTRUCTION ENGINEERING Co
Original Assignee
SICHUAN NO3 CONSTRUCTION ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN NO3 CONSTRUCTION ENGINEERING Co filed Critical SICHUAN NO3 CONSTRUCTION ENGINEERING Co
Priority to CN2011101231635A priority Critical patent/CN102278063A/en
Publication of CN102278063A publication Critical patent/CN102278063A/en
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention discloses a water-mill drilling construction process for Karst terrains, relates to the technical field of construction engineering, and aims to solve the technical problems in the conventional basal hole drilling process for hard rock foundations, such as difficulty in breaking hard rock, slow construction progress, large noise and poor basal hole forming effect. The water-mill drilling construction process for Karst terrains comprises the following steps of: (a) according to the position and size of a target hole, marking a peripheral line and two mutually-perpendicular diameter lines of the target hole on a ground surface required for construction; (b) performing core-drilling operation along the peripheral line of the target hole; (c) repeating the step (b) until all the core-drilling operations along the peripheral line of the target hole is completing completed; (d) performing core-drilling operation along the two diameter lines formed in the step (a) in the same way as the steps (b) to (c), and ensuring that the central axis of a drill tube is perpendicularly crossed with the diameter lines; and (e) crushing and removing stones in the target hole.

Description

The karst landform water mill bores construction technology
Technical field
The present invention relates to construction engineering technical field, particularly a kind of hard karst landform water mill of basic rock that is applied to bores construction technology.
Background technology
In the karst landform district, basic rock is hard, carries out datum hole excavation in this type of area and adopts dual mode usually, and one is slow for adopting pneumatic pick to carry out datum hole excavation progress, and big degree of depth perforate is then more difficult; It is bigger to the destruction of hole wall two for adopting bursting work, is not suitable for the effect of many places pore-forming in the small size, and influence is bigger between the adjacent datum hole.
Carrying out the datum hole excavation with pneumatic pick is example, and the principle of its construction is that diesel compressor is the pneumatic pick power source, rotates broken stone by air compression impelling pneumatic pick drill bit; Processing step is: preparation of construction, and------the broken stone of pneumatic pick smashes the cubic meter of stone in the hole, and---it is broken again that the dark cubic meter of stone of every broken 300mm is cleared a hole slag---cleans datum hole to measure unwrapping wire (location and sideline); The shortcoming that this technology exists is that foundation stone is hard just very difficult broken, and progress is slow, and noise is big, and is bigger to the destruction of hole wall, is not suitable for the harder cubic meter of stone.
Summary of the invention
The present invention be intended to solve in the hard datum hole drilling construction technology of traditional basic rock exist be difficult to broken solid rock, technical problems such as construction speed is slow, noise is big, datum hole forming effect difference, with provide have can the efficiency crushing solid rock, the karst landform water mill brill construction technology of good, the construction control precision height of datum hole forming effect, advantages such as construction speed is fast, noise is little.
The objective of the invention is to be achieved through the following technical solutions.
Karst landform water mill of the present invention bores construction technology, comprises the steps:
A) position and the size according to target hole calibrates the target hole outer peripheral lines on the face of land that need are constructed, and is that intersection point calibrates two orthogonal diameter lines with the center of circle of target hole;
B) bore the core operation along above-mentioned target hole outer peripheral lines: bore tube and be placed on the guide rail that is vertically to the face of land, the central axis and the target hole outer peripheral lines of boring tube intersect vertically, and brill tube upper end connects motor, and the delivery port of water pipe is communicated with the brill tube inner chamber; Motor drives is bored tube and is bored movingly during operation, and water is annotated in boring tube inner chamber via water pipe simultaneously, when bore tube down drilling depth reach when boring tube length and spending, mention and bore tube, will bore tube, motor and water pipe and move to next target outer peripheral lines brill core job position;
C) repeating step b bores the core operation until all that finish along the target hole outer peripheral lines;
D) the brill core operating type of employing step b~c bores the core operation along two diameter lines described in the step a, and the central axis and the diameter line that bore tube during operation intersect vertically;
E) broken and clear stone in the target hole.
Karst landform water mill of the present invention bores construction technology, uses chisel and pneumatic pick to impact stone in the target hole from side among the wherein said step e, makes the broken apart one-tenth fritter of stone in its hole.
Karst landform water mill of the present invention bores construction technology, after wherein said step e finishes target hole is picked dozen finishing.
Karst landform water mill of the present invention bores construction technology, and wherein said brill tube diameter is 50mm, or 100mm, or 150mm, and boring barrel thick is 6mm, and boring the tube length degree is 500~700mm.
 
Karst landform water mill of the present invention bores the beneficial effect of construction technology:
1. at karst landform solid rock efficiency of construction height, average advance can reach 100cm/ days, and progress is fast;
2. it is little to use water mill to bore noise, is beneficial to environmental protection;
3. the construction of water mill brill also has the precision height, periphery and hole wall is influenced characteristics such as little,, in 10mm hole wall and adjacent datum hole is not almost influenced for center line, limit, hole size Control precision.
 
The specific embodiment
Detailed structure of the present invention, application principle, effect and effect are illustrated by following embodiment.
Karst landform water mill of the present invention bores construction technology, comprises the steps:
A) position and the size according to target hole calibrates the target hole outer peripheral lines on the face of land that need are constructed, and is that intersection point calibrates two orthogonal diameter lines with the center of circle of target hole;
B) bore the core operation along above-mentioned target hole outer peripheral lines: bore tube and be placed on the guide rail that is vertically to the face of land, the central axis and the target hole outer peripheral lines of boring tube intersect vertically, and brill tube upper end connects motor, and the delivery port of water pipe is communicated with the brill tube inner chamber; Motor drives is bored tube and is bored movingly during operation, and water is annotated in boring tube inner chamber via water pipe simultaneously, when bore tube down drilling depth reach when boring tube length and spending, mention and bore tube, will bore tube, motor and water pipe and move to next target outer peripheral lines brill core job position;
C) repeating step b bores the core operation until all that finish along the target hole outer peripheral lines;
D) the brill core operating type of employing step b~c bores the core operation along two diameter lines described in the step a, and the central axis and the diameter line that bore tube during operation intersect vertically;
E) use chisel and pneumatic pick to impact stone in the target hole, make the broken apart one-tenth fritter of stone in its hole, and clear stone in the target hole from side;
F) target hole is picked dozen finishing.
Above-mentioned technological process can be reduced to: preparation of construction, and------around the datum hole and middle part original position is bored core---gets core and smashes the cubic meter of stone hole in that------picking at the bottom of perforated wall and the hole the unnecessary cubic meter of stone---repeats to bore core and get core---and clean datum hole to clear the datum hole cubic meter of stone and hole slag to measure unwrapping wire (location and sideline).
Karst landform water mill of the present invention bores construction technology, wherein the water mill rig is by motor, bore tube, guide rail, the water pipe main member is formed, the diameter that bores tube divides 50mm, 100mm, 150mm, three kinds of specifications, bore the thick 6mm that is generally of barrel, bore the tube length degree and be generally 600mm, rotation by motor drives a brill tube high speed rotating, water flows out along boring barrel, water of hydration is bored the tube high speed in situ and is rotated, boring tube is placed on the upright guide rail, artificial downward force of brill tube of giving high speed rotating, thereby reaching first step purpose---original position is bored core, adopts this method to bore core to around the datum hole, makes the cubic meter of stone separation all around of its datum hole, bore a cross hole with rig again at the datum hole middle part in addition, make the interior cubic meter of stone of its datum hole be divided into four fritters, get core then, adopt chisel and pneumatic pick to carry out stone in the punching hole from side, make that stone is separated into fritter in its hole, in conjunction with hoist engine and tower crane with the datum hole cubic meter of stone, the hole slag goes out clearly.Each brill core can only drill through the degree of depth of tube length degree, and circulation repeats said process, and the datum hole degree of depth until satisfying the design drawing requirement finally forms datum hole.
The main material that the present invention uses is flitch, steel pipe, steel cable, cubic chisel; Capital equipment is water mill rig (process assembling voluntarily by operation troop, mainly comprise motor, bore tube, the straight steel guide rail of zigzag, switchbox etc.), pneumatic pick, hoist engine.

Claims (4)

1. the karst landform water mill bores construction technology, it is characterized in that this technology comprises the steps:
A) position and the size according to target hole calibrates the target hole outer peripheral lines on the face of land that need are constructed, and is that intersection point calibrates two orthogonal diameter lines with the center of circle of target hole;
B) bore the core operation along above-mentioned target hole outer peripheral lines: bore tube and be placed on the guide rail that is vertically to the face of land, the central axis and the target hole outer peripheral lines of boring tube intersect vertically, and brill tube upper end connects motor, and the delivery port of water pipe is communicated with the brill tube inner chamber; Motor drives is bored tube and is bored movingly during operation, and water is annotated in boring tube inner chamber via water pipe simultaneously, when bore tube down drilling depth reach when boring tube length and spending, mention and bore tube, will bore tube, motor and water pipe and move to next target outer peripheral lines brill core job position;
C) repeating step b bores the core operation until all that finish along the target hole outer peripheral lines;
D) the brill core operating type of employing step b~c bores the core operation along two diameter lines described in the step a, and the central axis and the diameter line that bore tube during operation intersect vertically;
E) broken and clear stone in the target hole.
2. karst landform water mill as claimed in claim 1 bores construction technology, it is characterized in that: use chisel and pneumatic pick to impact stone in the target hole from side among the described step e, make the broken apart one-tenth fritter of stone in its hole.
3. karst landform water mill as claimed in claim 1 bores construction technology, it is characterized in that: after described step e finishes target hole is picked dozen finishing.
4. karst landform water mill as claimed in claim 1 bores construction technology, it is characterized in that: described brill tube diameter is 50mm, or 100mm, or 150mm, and boring barrel thick is 6mm, and boring the tube length degree is 500~700mm.
CN2011101231635A 2011-05-13 2011-05-13 Water-mill drilling construction process for Karst terrain Pending CN102278063A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101231635A CN102278063A (en) 2011-05-13 2011-05-13 Water-mill drilling construction process for Karst terrain

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101231635A CN102278063A (en) 2011-05-13 2011-05-13 Water-mill drilling construction process for Karst terrain

Publications (1)

Publication Number Publication Date
CN102278063A true CN102278063A (en) 2011-12-14

Family

ID=45103752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101231635A Pending CN102278063A (en) 2011-05-13 2011-05-13 Water-mill drilling construction process for Karst terrain

Country Status (1)

Country Link
CN (1) CN102278063A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147687A (en) * 2013-02-21 2013-06-12 北京鑫实路桥建设有限公司 Ring-type cutting method for excavating rocks at bottom part of pit shaft of bored pile
CN104775438A (en) * 2015-04-08 2015-07-15 国家电网公司 Method for carrying out tower site foundation pit construction on karst landform foundation in rainy season
CN107059847A (en) * 2017-06-20 2017-08-18 中国华西企业有限公司 A kind of competent bed water mill bores pouring pile hole structure and its construction from the bottom of one's heart
CN107269288A (en) * 2017-08-11 2017-10-20 曹丽召 The non-explosion water mill of hard stone section push pipe bores two-way drilling construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1047550A (en) * 1989-06-21 1990-12-05 英格索尔-兰德公司 The method and apparatus of rock-boring
CN1730895A (en) * 2005-09-12 2006-02-08 陈月辉 Automatic boring device for hand-held drill
JP2006233748A (en) * 2005-01-26 2006-09-07 Kato Construction Co Ltd Hole drilling device
WO2006121386A1 (en) * 2005-05-09 2006-11-16 Sandvik Intellectual Property Ab Rock drilling element, drill string and method for transferring impact energy from a top hammer unit to a drill bit
CN1869395A (en) * 2006-07-11 2006-11-29 陈月辉 Automatic hole drilling apparatus for hand water drill
JP2007247199A (en) * 2006-03-15 2007-09-27 Eito Kogyo Kk Vertical hole excavation unit, vertical hole excavation subsystem, and vertical hole excavation system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1047550A (en) * 1989-06-21 1990-12-05 英格索尔-兰德公司 The method and apparatus of rock-boring
JP2006233748A (en) * 2005-01-26 2006-09-07 Kato Construction Co Ltd Hole drilling device
WO2006121386A1 (en) * 2005-05-09 2006-11-16 Sandvik Intellectual Property Ab Rock drilling element, drill string and method for transferring impact energy from a top hammer unit to a drill bit
CN1730895A (en) * 2005-09-12 2006-02-08 陈月辉 Automatic boring device for hand-held drill
JP2007247199A (en) * 2006-03-15 2007-09-27 Eito Kogyo Kk Vertical hole excavation unit, vertical hole excavation subsystem, and vertical hole excavation system
CN1869395A (en) * 2006-07-11 2006-11-29 陈月辉 Automatic hole drilling apparatus for hand water drill

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
《中小企业管理与科技(上旬刊)》 20100205 汪家全 "水钻法"在城市人工挖孔桩施工中的应用分析 第121页 1-4 , 第02期 *
曹鑫锋: "锚固桩水磨钻施工工艺及技术经济分析", 《山西建筑》, no. 13, 1 May 2010 (2010-05-01), pages 111 *
杨成宏等: "公路桩基小孔水钻成孔施工工艺与质量控制", 《公路交通技术》, no. 02, 25 April 2010 (2010-04-25) *
汪家全: ""水钻法"在城市人工挖孔桩施工中的应用分析", 《中小企业管理与科技(上旬刊)》, no. 02, 5 February 2010 (2010-02-05), pages 121 *
黄司: "超大直径岩石桩水钻取芯成孔的施工技术", 《交通标准化》, no. 19, 8 October 2009 (2009-10-08) *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147687A (en) * 2013-02-21 2013-06-12 北京鑫实路桥建设有限公司 Ring-type cutting method for excavating rocks at bottom part of pit shaft of bored pile
CN104775438A (en) * 2015-04-08 2015-07-15 国家电网公司 Method for carrying out tower site foundation pit construction on karst landform foundation in rainy season
CN104775438B (en) * 2015-04-08 2016-06-29 国家电网公司 The method of tower position foundation pit construction in karst landform basis rainy season
CN107059847A (en) * 2017-06-20 2017-08-18 中国华西企业有限公司 A kind of competent bed water mill bores pouring pile hole structure and its construction from the bottom of one's heart
CN107269288A (en) * 2017-08-11 2017-10-20 曹丽召 The non-explosion water mill of hard stone section push pipe bores two-way drilling construction method

Similar Documents

Publication Publication Date Title
CN108729924B (en) Quick construction method for mechanical excavation of urban hard rock tunnel
CN104295239A (en) Method for using rotary drilling rig to drill into hard rock stratum
CN105714783A (en) Arc splicing equipment for Y-shaped piles and rectangular piles
CN106836204A (en) The device and method of pouring pile bearing capacity under a kind of lifting Soft Soil
CN102278063A (en) Water-mill drilling construction process for Karst terrain
CA2818859A1 (en) Annulus ring hole drill
CN105887820A (en) Circular arc socket herringbone pile manufacturing equipment
CN105821837A (en) Circular-arc insertion combination T-shaped pile manufacturing facility
CN116220546A (en) Construction method for combining super-thick hard rock condition large-diameter long piles into holes
CN103088832B (en) Annular type impact method for digging rock at bottom of drilled pile shaft
CN104695961A (en) Stone exploiting method
CN103924928B (en) The fit structure of the bit Integrated and anchor cable of rotary jet grouting and construction method thereof
CN102628268A (en) Cyclone pile
CN105887842A (en) Arc-locking crossed retaining pile manufacturing equipment
CN116181224A (en) Construction method of multi-layer oversized karst cave rock-socketed pile foundation in complex karst area
CN204457773U (en) A kind of device for quarrying stone
CN113605899A (en) Tunnel excavation method based on hydraulic impact crushing and static crushing
CN114198015A (en) Down-the-hole hammer-rotary drilling combined hole forming method for hard rock pile
CN114075923A (en) Combined drill bit of hydraulic down-the-hole hammer secant pile
CN105672304A (en) Inserting equipment for triangular piles and T-shaped piles
CN105586904A (en) Arc engaging equipment for T piles and rectangular piles
CN210738456U (en) Down-the-hole hammer device for drilling hard rock stratum
CN103375136A (en) Downhole hydraulic cutting saw of pile driver
CN204782740U (en) Combined type rig
CN216194693U (en) Multi-nozzle multi-angle combined high-pressure jet grouting construction equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111214