CN102277879B - Construction protection method for existing foundation with over crossing railway bridge - Google Patents

Construction protection method for existing foundation with over crossing railway bridge Download PDF

Info

Publication number
CN102277879B
CN102277879B CN 201110116699 CN201110116699A CN102277879B CN 102277879 B CN102277879 B CN 102277879B CN 201110116699 CN201110116699 CN 201110116699 CN 201110116699 A CN201110116699 A CN 201110116699A CN 102277879 B CN102277879 B CN 102277879B
Authority
CN
China
Prior art keywords
steel pipe
construction
existing railway
pile
protection method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110116699
Other languages
Chinese (zh)
Other versions
CN102277879A (en
Inventor
雷兵
周伟
韩立峰
李长白
谷付堂
张波
费才章
陈林峰
麻小军
金海忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cr7bg No1 Engineering Co Ltd
First Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
Cr7bg No1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cr7bg No1 Engineering Co Ltd filed Critical Cr7bg No1 Engineering Co Ltd
Priority to CN 201110116699 priority Critical patent/CN102277879B/en
Publication of CN102277879A publication Critical patent/CN102277879A/en
Application granted granted Critical
Publication of CN102277879B publication Critical patent/CN102277879B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a construction protection method for an existing foundation with an over crossing railway bridge. The method comprises the following steps of: 1, reinforcing an existing railway ballast bed, blocking ballast aggregate with a baffle plate, and punching a baffle plate side into a subgrade with a steel bar or a steel pipe so as to stabilize the baffle plate; 2, drilling a plurality of arranging holes on lava and boulder stones of a pier cushion cap and a gantry pier cushion cap foundation pit positioned on one side of a railway bed; 3, washing holes; 4, inserting a steel pipe protection pile into each hole to form a cement mortar steel pipe pile protection wall; 5, washing holes; 6, injecting cement mortar: injecting cement mortar into steel pipes and gaps between steel pipes and holes from the pipe bottom of each steel pipe protection pile; and 7, performing receiving inspection. Due to the adoption of the method, the construction technical problem of high protection construction difficulty of the existing railway subgrade under the geological conditions of lava and boulder stone is solved effectively, and the aims of realizing low construction protection cost on the existing railway bridge foundation, easiness for construction, high construction efficiency, short construction period and low safety risk are fulfilled.

Description

Upper spanning existing railway Bridge Foundation construction protection method
Technical field
The invention belongs to road and bridge construction method and technology field, what relate generally to is a kind of upper spanning existing railway Bridge Foundation construction protection method.
Background technology
Along with the development of high-speed railway, speedway, corresponding newly built railway, highway crossing existing railway are can hardly be avoided thereupon.Cross on a lot of the existing railway bridge pier from existing railway too close to, before excavation bridge pier base and cushion cap foundation, must carry out construction safety protection to the existing railway roadbed of corresponding site.Construction safety protection method commonly used is by the hand excavated pile protection and squeezes into rail pile or the steel pipe pile protection at present.The protection of employing hand excavated pile need to strengthen the button rail to existing railway, and button rail spended time is longer, and is very large to existing railway operation interference, can have a strong impact on the duration, and not only cost is high, and security risk is very large; Adopt the protection of rail pile or steel pipe pile, running into lava and boulder geological conditions, when pile driver is difficult to rail pile or steel pipe pile laid, still need to after manually excavating the hole, steel pipe pile be inserted in the hole, bring great inconvenience to construction, not only have a strong impact on construction speed, and cost is high, potential safety hazard is large.
Summary of the invention
The present invention is directed to above-mentioned deficiency of the prior art, a kind of upper spanning existing railway Bridge Foundation construction protection method is provided, effectively solved the large construction technology difficult problem of existing railway subgrade protection difficulty of construction under lava and boulder geological conditions, reach make spanning existing railway Bridge Foundation construction protection cost low, be easy to construct, efficiency of construction height, short construction period, purpose that security risk is low.
For achieving the above object, the present invention adopts following technical scheme: a kind of upper spanning existing railway Bridge Foundation construction protection method may further comprise the steps:
The first step: the existing railway railway roadbed is reinforced, with baffle plate ballast aggregate is blocked, the baffle plate side is squeezed into reinforcing bar or steel pipe and is stablized baffle plate in the roadbed;
Second step: boring is positioned at pier cushion cap and transom pier cushion cap foundation ditch that water bores a plurality of aligned apertures on the lava of railway bed one side and the boulder geology;
The 3rd step: hole flushing;
The 4th step: in each hole, insert a steel pipe fender pile, form cement mortar steel pipe pile protecting wall;
The 5th step: hole flushing;
The 6th step: injected water cement mortar, cementing mortar in steel pipe and the space in steel pipe and hole at the bottom of the pipe of each steel pipe fender pile;
The 7th step: check and accept.
The drilling technique that the present invention processes the karst of maturation is initiative for upper spanning existing railway Bridge Foundation construction protection, has effectively solved the large construction technology difficult problem of existing railway subgrade protection difficulty of construction under lava and boulder geological conditions.Make that spanning existing railway Bridge Foundation construction protection cost is low, to be easy to construction, efficiency of construction height, short construction period, security risk low, guarantee in upper spanning existing railway bridge pier base, bearing platform construction process, especially the safety of existing railway operation and engineering construction in the upper spanning existing railway bridge pier base under lava and boulder geological conditions, the bearing platform construction process.
Description of drawings
Fig. 1 is the schematic diagram of upper spanning existing railway Bridge Foundation construction protection method flow process;
Fig. 2 is spanning existing railway cushion cap fender pile general layout schematic diagram on the newly built railway Line for Passenger Transportation grand bridge;
Fig. 3 is pier cushion cap fender pile layout schematic diagram;
Fig. 4 is pier cushion cap elevational schematic view;
Fig. 5 is transom pier cushion cap fender pile layout schematic diagram;
Fig. 6 is the transom pier elevational schematic view.
Among the figure: 1, steel pipe fender pile; 2, pier cushion cap; 3, existing railway roadbed; 4, existing railway uplink and downlink center line; 5, pile foundation; 6, transom pier cushion cap; 7, special line for passenger trains grand bridge; 8, existing railway operation line.
The specific embodiment
Technical scheme of the present invention is described in further detail.
Shown in Fig. 2-6: a kind of upper spanning existing railway Bridge Foundation construction protection method, the special line for passenger trains grand bridge 7 of constructing comprises two transom pier cushion caps 6 crossing over existing railway operation line 8 and the bridge pier that lays respectively at existing railway uplink and downlink center line 4 one sides, pier cushion cap 2 and transom pier cushion cap 6 outsides are 2.94 meters from the beeline of existing railway uplink and downlink center line 4, and spanning existing railway Bridge Foundation construction protection method may further comprise the steps on this:
As shown in Figure 1:
The first step: the existing railway railway roadbed is reinforced, with baffle plate ballast aggregate is blocked, the baffle plate side is squeezed into reinforcing bar or steel pipe and is stablized baffle plate in the roadbed.
Second step: boring, be positioned on the lava of railway bed one side and the boulder geology water at the cushion cap foundation ditch and hole to projected depth, water bores when holing, in the railway outside, hold borer drill rod with two wire rope, the other end is fixed on the earth anchor, and angle is 45 between wire rope and ground 0, affect the existing railway operation to prevent that rig from tilting or collapsing.
For guaranteeing pier cushion cap 2 and transom pier cushion cap 6 excavation safety, pier cushion cap 2 design heights are three meters, adopt dark 6 meters Ф 10.8 ㎝ * 1 pair of existing railway roadbed 3 of 1 ㎝ steel pipe fender pile to protect; Transom pier cushion cap 6 design heights are 2.5 meters, adopt dark 5 meters Ф 10.8 ㎝ * 1 pair of existing railway roadbed 3 of 1 ㎝ steel pipe fender pile to protect.For forming cement mortar steel pipe pile protecting wall, need to arrange and bore a plurality of holes, the spacing between each hole is 25cm.Be to guarantee the stable of existing railway operation security and existing railway roadbed 3, steel pipe fender pile 1 routinely dig a drilling construction every three.
The 3rd step: hole flushing.At the bottom of the Grouting Pipe patchhole, at the bottom of the hole, up clean the duct with clear water, the water that emits in the hole becomes and stops to clean after clear.
The 4th step: the steel pipe fender pile is inserted in the hole, just form cement mortar steel pipe pile protecting wall behind steel pipe fender pile 1 of insertion in each hole, when fender pile was constructed, the existing railway main points were gone slowly, by train speed limit 45Km/h.Since from existing railway line too close to, during construction, personnel and machinery will be strictly on guard against especially and invade limit.
The 5th step: hole flushing.At the bottom of the Grouting Pipe patchhole, at the bottom of the hole, up clean the duct with clear water, emit in the hole
After becoming clearly, water stops to clean.
The 6th step: injected water cement mortar
With cement: sand is that the cement mortar of 1:1 match ratio is injected in Ф 10.8 ㎝ * 1 ㎝ steel pipe and the space in steel pipe and hole, the filling space, and 1 slip casting of steel pipe fender pile is notes upwards from the pipe end.
The 7th step: acceptance(check), carry out the front protection of construction for bridge pier base 5, bearing platform construction and prepare.
The above; it only is preferred embodiment of the present invention; be not that the present invention is imposed any restrictions, every any simple modification, change and equivalent structure of above embodiment being done according to the technology of the present invention essence changes, and all still belongs in the protection domain of technical solution of the present invention.

Claims (4)

1. go up spanning existing railway Bridge Foundation construction protection method for one kind, it is characterized in that: described upper spanning existing railway Bridge Foundation construction protection method may further comprise the steps:
The first step: the existing railway railway roadbed is reinforced, with baffle plate ballast aggregate is blocked, the baffle plate side is squeezed into reinforcing bar or steel pipe and is stablized baffle plate in the roadbed;
Second step: boring is positioned at pier cushion cap foundation ditch that water bores a plurality of aligned apertures on the lava of railway bed one side and the boulder geology;
The 3rd step: hole flushing;
The 4th step: in each hole, insert a steel pipe fender pile, form cement mortar steel pipe pile protecting wall;
The 5th step: hole flushing;
The 6th step: injected water cement mortar, cementing mortar in steel pipe and the space in steel pipe and hole at the bottom of the pipe of each steel pipe fender pile;
The 7th step: check and accept.
2. upper spanning existing railway Bridge Foundation construction protection method according to claim 1, it is characterized in that: the spacing between each hole of described a plurality of aligned apertures is 25cm.
3. upper spanning existing railway Bridge Foundation construction protection method according to claim 1 is characterized in that: described steel pipe fender pile is dark 6 meters Ф 10.8 ㎝ * 1 ㎝ steel pipe or dark 5 meters Ф 10.8 ㎝ * 1 ㎝ steel pipe.
4. upper spanning existing railway Bridge Foundation construction protection method according to claim 1, it is characterized in that: described steel pipe fender pile is by digging a drilling construction every three.
CN 201110116699 2011-05-06 2011-05-06 Construction protection method for existing foundation with over crossing railway bridge Active CN102277879B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110116699 CN102277879B (en) 2011-05-06 2011-05-06 Construction protection method for existing foundation with over crossing railway bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110116699 CN102277879B (en) 2011-05-06 2011-05-06 Construction protection method for existing foundation with over crossing railway bridge

Publications (2)

Publication Number Publication Date
CN102277879A CN102277879A (en) 2011-12-14
CN102277879B true CN102277879B (en) 2013-03-13

Family

ID=45103581

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110116699 Active CN102277879B (en) 2011-05-06 2011-05-06 Construction protection method for existing foundation with over crossing railway bridge

Country Status (1)

Country Link
CN (1) CN102277879B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102888795A (en) * 2012-10-25 2013-01-23 中铁十九局集团有限公司 Karst roadbed grouting process
CN109629590A (en) * 2017-10-09 2019-04-16 上海宝冶集团有限公司 The construction method of Rock Region building pile foundation cushion cap

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050097478A (en) * 2005-09-15 2005-10-07 김혜영 Process for constructing underground structures
CN101838968A (en) * 2010-05-19 2010-09-22 中铁二十局集团有限公司 Double track bridge construction process crossing existing railway operational lines
CN101963061A (en) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 Construction method for underground box culvert of existing railway line

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050097478A (en) * 2005-09-15 2005-10-07 김혜영 Process for constructing underground structures
CN101838968A (en) * 2010-05-19 2010-09-22 中铁二十局集团有限公司 Double track bridge construction process crossing existing railway operational lines
CN101963061A (en) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 Construction method for underground box culvert of existing railway line

Also Published As

Publication number Publication date
CN102277879A (en) 2011-12-14

Similar Documents

Publication Publication Date Title
CN102392458B (en) Piling beam cofferdam construction method used for bare rock foundation construction in water
CN102352590A (en) Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN113565525A (en) Construction protection system and construction method for newly-built shield tunnel super-close ultra-shallow buried upper-span existing tunnel
CN108755698B (en) Construction method for steep slope loose accumulation body large inclined rock surface foundation
CN107524141B (en) Construction method of cast-in-situ bored pile of rock soil foundation
CN113174961B (en) Foundation pit slope supporting method
CN107083771A (en) A kind of drilling construction method of artificial digging pile
CN108049393A (en) For the attached building enclosure construction technology in subway station under the conditions of rich water thick sand bed
CN102966356A (en) Method for controlling upward flotation and deformation of liquefiable ground operating tunnel under action of earthquake
CN107142926A (en) The supratectal steel trestle steel-pipe pile antiscour construction method of shallow water riverbed thickness erratic boulder
CN101838957B (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN110735436A (en) cutting rock slope reinforced structure
CN109989407B (en) Roadbed pile tube curtain supporting structure behind newly-added two-line platform of railway
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
KR100683589B1 (en) Amethod for solidification of railroad bridge and public works-connection part
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN205576896U (en) That can effectively reduce engineering cost takes steel reinforcement cage construction hole stake
JP4990206B2 (en) Structure of underground structure and its construction method
CN102277879B (en) Construction protection method for existing foundation with over crossing railway bridge
CN205576957U (en) Stake end pilework
CN210946536U (en) Protective structure of small dangerous rock falling stone
CN111733827A (en) Station yard deep foundation pit protection construction method under adjacent high-speed rail complex environment silt geology
JP2019015100A (en) Removing method of earth retaining wall
CN218060412U (en) Utility tunnel enclosure wall construction structures
CN207633225U (en) The small spacing abutment constructing structure of neighbouring running railway line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Lei Bing

Inventor after: Jin Haizhong

Inventor after: Zhou Wei

Inventor after: Han Lifeng

Inventor after: Li Changbai

Inventor after: Gu Futang

Inventor after: Zhang Bo

Inventor after: Fei Caizhang

Inventor after: Chen Linfeng

Inventor after: Ma Xiaojun

Inventor before: Lei Bing

Inventor before: Zhou Wei

Inventor before: Gu Futang

Inventor before: Li Changbai

Inventor before: Zhang Bo

Inventor before: Fei Caizhang

Inventor before: Chen Linfeng

Inventor before: Ma Xiaojun

Inventor before: Jin Haizhong

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LEI BING ZHOU WEI GU FUTANG LI CHANGBAI ZHANG BO FEI CAIZHANG CHEN LINFENGMA XIAOJUN JIN HAIZHONG TO: LEI BING ZHOU WEI HAN LIFENG LI CHANGBAI GU FUTANG ZHANG BO FEI CAIZHANG CHEN LINFENG MA XIAOJUN JIN HAIZHONG

C14 Grant of patent or utility model
GR01 Patent grant