CN102249158B - Hoisting construction method of dual crane rail large-tonnage device - Google Patents

Hoisting construction method of dual crane rail large-tonnage device Download PDF

Info

Publication number
CN102249158B
CN102249158B CN 201110195611 CN201110195611A CN102249158B CN 102249158 B CN102249158 B CN 102249158B CN 201110195611 CN201110195611 CN 201110195611 CN 201110195611 A CN201110195611 A CN 201110195611A CN 102249158 B CN102249158 B CN 102249158B
Authority
CN
China
Prior art keywords
equipment
place
tower
base
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110195611
Other languages
Chinese (zh)
Other versions
CN102249158A (en
Inventor
葛加君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Province No.1 Water Conservancy & Electric Power Construction Group Holdings Co., Ltd.
Original Assignee
葛加君
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 葛加君 filed Critical 葛加君
Priority to CN 201110195611 priority Critical patent/CN102249158B/en
Publication of CN102249158A publication Critical patent/CN102249158A/en
Application granted granted Critical
Publication of CN102249158B publication Critical patent/CN102249158B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a hoisting construction method of a dual crane rail large-tonnage device, comprising the steps of: on three-dimensional wall surfaces entering floors drawn up to enter by the device, reserving door openings, paving steel rails, processing tower crane bases, putting tower cranes and collocated facilities in place, transporting needed hoisting devices to the site, tying and hooking the devices, trying hanging, hoisting, withdrawing the tower cranes and the like. The invention has the advantages of high safety coefficient, fast hoisting speed, low cost and advanced technologies.

Description

Double-rail large-tonnage equipment hoisting construction method
Technical field
The present invention relates to a kind of large-tonnage equipment hoisting construction method.
Background technology
In recent years, fast development along with industrial economy, land resources day is becoming tight, industrial premises is more and more heavier to multilayer, high-rise development, its mechanical body weight, its large-tonnage equipment is installed and has been brought a technical difficult problem, say in some sense, because large-tonnage mechanical equipment hoisting difficulty is large, hoists to extend to industrial factory building and brought restraining factors.
Summary of the invention
The object of the present invention is to provide a kind of safety factor high, lifting speed is fast, the double-rail large-tonnage equipment hoisting construction method that cost is low.
Technical solution of the present invention is:
A kind of double-rail large-tonnage equipment hoisting construction method is characterized in that: comprise the following steps:
(1) draft the three-dimensional metope of the floor that enters at equipment, reserve door opening, door opening adds 20% above coefficient by equipment external form plan area to be reserved, after reserving at portal mouth week embedding subsides plank or rubber pad;
(2) steel rail laying, rail will be drafted laying floor face road and clear up before laying, and choice structure stake and Equipment Foundations are established the traction anchor point on the steel rail laying route of drafting, and track adopts channel steel type; After channel-section steel is laid, place mat solid drawn pipe rolling bar, the thick sheeting caps of place mat 15mm on the solid drawn pipe rolling bar is finished rail place mat operation again;
(3) process in the tower crane base, adds the weight of equipment of hanging according to tower machine own wt and add tower machine own wt and 50% of the weight of equipment sum of hanging again, and calculates the substantially required bearing capacity of tower crane, carries out the base according to the required bearing capacity in base and process; The base processing mode adopts cement concrete base, composite earth base or steel plate base;
(4) crane machine and allocation of facility are in place, and be according to configuration requirement that two tower machines and configuration are comprehensively in place, in place after, carry out sky machine running tentative, operation freely, test passes is stand-by;
(5) when weather fine, wind-force<4 grade are transported to the scene with required hanging device;
(6) equipment colligation fishhook, mechanical equipment adopt three-dimensional positive lifting in when lifting, when equipment when falling to encircle, carry out colligation with steel rope, the pulling force of its steel rope is 2 times of necessary 〉=equipment gravity after tested; Use the intersecting parallels colligation during colligation, and at four criss-cross places, the amount of establishing suspension ring;
(7) jointly carry out the equipment examination with two tower machines and hang, repeatedly try to hang more than 2 times, examination is hung and highly is 3m;
(8) after hanging successfully by twice examination, lift to the flooring equipment place that enters, when hanging device enters floor, a tower machine pine hook, change by the bottle gouard moved by hands that arranges in the floor of place and equipment is drawn in floor and be placed on the preprepared track sheeting caps, then another tower machine also breaks off relations;
(9) equipment after winching to flooring moves away equipment, in order to provide the lifting place to carry out the lifting of next device;
(10) the tower machine is withdrawn from, and after equipment hoisting is finished, the tower machine is connect hook and flexible position instrument is dismantled comprehensively, cleans vanning, and complete machine is withdrawn from, and to former tower machine base residue, greasy dirt is cleared up, and restores to the original state.
Safety factor of the present invention is high, and lifting speed is fast, and cost is low, advanced technology.
The invention will be further described below in conjunction with embodiment.
The specific embodiment
A kind of double-rail large-tonnage equipment hoisting construction method comprises the following steps:
(1) draft the three-dimensional metope of the floor that enters at equipment, reserve door opening, door opening adds 20% above coefficient by equipment external form plan area to be reserved, after reserving at portal mouth week embedding subsides plank or rubber pad;
(2) steel rail laying, rail will be drafted laying floor face road and clear up before laying, and choice structure stake and Equipment Foundations are established the traction anchor point on the steel rail laying route of drafting, and track adopts channel steel type; After channel-section steel is laid, place mat solid drawn pipe rolling bar, the thick sheeting caps of place mat 15mm on the solid drawn pipe rolling bar is finished rail place mat operation again;
(3) process in the tower crane base, adds the weight of equipment of hanging according to tower machine own wt and add tower machine own wt and 50% of the weight of equipment sum of hanging again, and calculates the substantially required bearing capacity of tower crane, carries out the base according to the required bearing capacity in base and process; The base processing mode adopts cement concrete base, composite earth base or steel plate base;
(4) crane machine and allocation of facility are in place, and be according to configuration requirement that two tower machines and configuration are comprehensively in place, in place after, carry out sky machine running tentative, operation freely, test passes is stand-by;
(5) when weather fine, wind-force<4 grade are transported to the scene with required hanging device;
(6) equipment colligation fishhook, mechanical equipment adopt three-dimensional positive lifting in when lifting, when equipment when falling to encircle, carry out colligation with steel rope, the pulling force of its steel rope is 2 times of necessary 〉=equipment gravity after tested; Use the intersecting parallels colligation during colligation, and at four criss-cross places, the amount of establishing suspension ring;
(7) jointly carry out the equipment examination with two tower machines and hang, repeatedly try to hang more than 2 times, examination is hung and highly is 3m;
(8) after hanging successfully by twice examination, lift to the flooring equipment place that enters, when hanging device enters floor, a tower machine pine hook, change by the bottle gouard moved by hands that arranges in the floor of place and equipment is drawn in floor and be placed on the preprepared track sheeting caps, then another tower machine also breaks off relations;
(9) equipment after winching to flooring moves away equipment, in order to provide the lifting place to carry out the lifting of next device;
(10) the tower machine is withdrawn from, and after equipment hoisting is finished, the tower machine is connect hook and flexible position instrument is dismantled comprehensively, cleans vanning, and complete machine is withdrawn from, and to former tower machine base residue, greasy dirt is cleared up, and restores to the original state.

Claims (1)

1. a double-rail large-tonnage equipment hoisting construction method is characterized in that: comprise the following steps:
(1) draft the three-dimensional metope of the floor that enters at equipment, reserve door opening, door opening adds 20% above coefficient by equipment external form plan area to be reserved, after reserving at portal mouth week embedding subsides plank or rubber pad;
(2) steel rail laying, rail will be drafted laying floor face road and clear up before laying, and the choice structure stake reaches and establishes the traction anchor point in Equipment Foundations on the steel rail laying route of drafting, and track adopts channel steel type; After channel-section steel is laid, place mat solid drawn pipe rolling bar, the thick sheeting caps of place mat 15mm on the solid drawn pipe rolling bar is finished rail place mat operation again;
(3) process in the tower crane base, adds the weight of equipment of hanging according to tower machine own wt and add tower machine own wt and 50% of the weight of equipment sum of hanging again, and calculates the substantially required bearing capacity of tower crane, carries out the base according to the required bearing capacity in base and process; The base processing mode adopts cement concrete base, composite earth base or steel plate base;
(4) tower crane and allocation of facility are in place, and be according to configuration requirement that two tower machines and configuration are comprehensively in place, in place after, carry out sky machine running tentative, operation freely, test passes is stand-by;
(5) when weather fine, wind-force<4 grade are transported to the scene with required hanging device;
(6) equipment colligation fishhook, mechanical equipment adopt three-dimensional positive lifting in when lifting, when equipment when falling to encircle, carry out colligation with steel rope, the pulling force of its steel rope is 2 times of necessary 〉=equipment gravity after tested; Use the intersecting parallels colligation during colligation, and at four criss-cross places, the amount of establishing suspension ring;
(7) jointly carry out the equipment examination with two tower machines and hang, repeatedly try to hang more than 2 times, examination is hung and highly is 3m;
(8) after hanging successfully by twice examination, lift to the flooring equipment place that enters, when hanging device enters floor, a tower machine pine hook, change by the bottle gouard moved by hands that arranges in the floor of place and equipment is drawn in floor and be placed on the preprepared track sheeting caps, then another tower machine also breaks off relations;
(9) equipment after winching to flooring moves away equipment, in order to provide the lifting place to carry out the lifting of next device;
(10) the tower machine is withdrawn from, and after equipment hoisting is finished, the tower machine is connect hook and flexible position instrument is dismantled comprehensively, cleans vanning, and complete machine is withdrawn from, and to former tower machine base residue, greasy dirt is cleared up, and restores to the original state.
CN 201110195611 2011-07-13 2011-07-13 Hoisting construction method of dual crane rail large-tonnage device Active CN102249158B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110195611 CN102249158B (en) 2011-07-13 2011-07-13 Hoisting construction method of dual crane rail large-tonnage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110195611 CN102249158B (en) 2011-07-13 2011-07-13 Hoisting construction method of dual crane rail large-tonnage device

Publications (2)

Publication Number Publication Date
CN102249158A CN102249158A (en) 2011-11-23
CN102249158B true CN102249158B (en) 2013-01-02

Family

ID=44976801

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110195611 Active CN102249158B (en) 2011-07-13 2011-07-13 Hoisting construction method of dual crane rail large-tonnage device

Country Status (1)

Country Link
CN (1) CN102249158B (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08135196A (en) * 1994-11-02 1996-05-28 Takenaka Komuten Co Ltd Exterior wall material fitting method and device therefor
KR100716454B1 (en) * 2006-06-26 2007-05-10 삼성물산 주식회사 Multiple curtain walls hoisting device and curtain wall establishing method using thereof
CN101476287B (en) * 2008-11-26 2010-10-06 中铁二局股份有限公司 Construction method for carrying large box girder by tire type portal jib crane
CN102071646A (en) * 2010-12-31 2011-05-25 中铁大桥局集团第四工程有限公司 Large-tonnage box girder sea system and construction method

Also Published As

Publication number Publication date
CN102249158A (en) 2011-11-23

Similar Documents

Publication Publication Date Title
CN205955236U (en) Container formula of taking pulley platform of unloading of encorbelmenting
CN102139832B (en) Gantry crane device with lengthways and transverse traveling functions and hoisting method
CN106006425B (en) A kind of high-rise building ground machine room lower large scale equipment hoisting transportation method
CN101476287B (en) Construction method for carrying large box girder by tire type portal jib crane
CN107700719A (en) A kind of hanging method of high-rise building glass curtain wall
CN107990051A (en) It is a kind of to lift auxiliary device in place and method for jacking pipe joints
CN102190249B (en) Method for hoisting equipment positioned at bottom of multilayer frame platform
CN106948604A (en) The irregular alien invasion glass curtain wall positioning apparatus of high-rise building and construction method
CN102602834B (en) Platform-free lifting method and system of installing large rectangular devices to high-rise buildings
CN102587284B (en) Independent derrick mast and beam plate mounting method
CN102530721A (en) Anti-typhoon method for portal crane and special equipment thereof
CN205061252U (en) Lower string in a perpendicular conveyor system of material of mould platform
CN107503365A (en) Super High elevator high and big die plate installation engineering method
CN102249158B (en) Hoisting construction method of dual crane rail large-tonnage device
CN101122115B (en) Construction method for tower crane shift
CN107476263A (en) A kind of construction method of prestressed pier anchor cable
CN205061257U (en) Material transports lifting platform perpendicularly
CN108675116B (en) Construction method of PC (polycarbonate) component
CN102807178A (en) Chamfered hanging basket device with slide rail
CN203682931U (en) Wharf building crane
CN206693641U (en) The irregular alien invasion glass curtain wall positioning apparatus of high-rise building
CN214942249U (en) Novel indoor wall construction device
CN205934730U (en) Installation device of wave form steel web
CN105253793B (en) Construction method for traction transporting and hoisting of zinc pot in zinc plating workshop
CN206273951U (en) The hoisting apparatus of attachment type raise scaffold

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: HANGZHOU ZEDA CIVIL ENGINEERING CONSULTING CO., LT

Free format text: FORMER OWNER: GE JIAJUN

Effective date: 20130609

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 226400 NANTONG, JIANGSU PROVINCE TO: 310016 HANGZHOU, ZHEJIANG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20130609

Address after: 209, room 3, building 193, 310016 sailing Road, Hangzhou, Zhejiang, Jianggan District

Patentee after: Hangzhou Zeda Civil Engineering Consulting Co., Ltd.

Address before: Rudong County, Jiangsu province 226400 Nantong juegang Taishan Road East Development Building 1002

Patentee before: Ge Jiajun

ASS Succession or assignment of patent right

Owner name: ZHEJIANG NO.1 WATER CONSERVANCY + ELECTRIC POWER C

Free format text: FORMER OWNER: HANGZHOU ZEDA CIVIL ENGINEERING CONSULTING CO., LTD.

Effective date: 20131118

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 310016 HANGZHOU, ZHEJIANG PROVINCE TO: 310051 HANGZHOU, ZHEJIANG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20131118

Address after: 310051, Zhejiang, Hangzhou province Binjiang District Province Hydropower District

Patentee after: Zhejiang Province No.1 Water Conservancy & Electric Power Construction Group Holdings Co., Ltd.

Address before: 209, room 3, building 193, 310016 sailing Road, Hangzhou, Zhejiang, Jianggan District

Patentee before: Hangzhou Zeda Civil Engineering Consulting Co., Ltd.