Prior art keywords
test
rank
hard disk
module
testing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201010148566.0A
Other languages
Chinese (zh)
Other versions
CN102222517A (en
Inventor
陈兴平
张晓文
陈万福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunda Computer Technology Kunshan Co Ltd
Mitac International Corp
Original Assignee
Kunda Computer Technology Kunshan Co Ltd
Mitac International Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunda Computer Technology Kunshan Co Ltd, Mitac International Corp filed Critical Kunda Computer Technology Kunshan Co Ltd
Priority to CN201010148566.0A priority Critical patent/CN102222517B/en
Publication of CN102222517A publication Critical patent/CN102222517A/en
Application granted granted Critical
Publication of CN102222517B publication Critical patent/CN102222517B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The invention discloses a cluster harddisk automation test method and a cluster harddisk automation test system; a cluster harddisk is tested by a zero-step scheduling module, a first-step monitoring module and a second-step test module which are structurized in a three-step way; the cluster harddisk test system comprises a test server and a test work station, and the test scheduling is carried out to the harddisk by the modules with three-step structuralization, so as to carry out function test under different rotating speeds of a fan and generate an analysis result and a report, thus achieving the purposes of reducing labor time and test errors.

Description

Gather together hard disk automated testing method and system thereof
[technical field]
The invention relates to one gather together hard disk automated testing method and system thereof, relate to especially a kind of the have method of the structurized hard disk automatic test of gathering together of three-layered and the hard disk automatization test system of gathering together that uses the method to form.
[background technology]
The data-interface of hard disc of computer is mainly ATA (Advanced Technology Attachment) or SATA (Serial Advanced Technology Attachment) and SCSI (small computer system interface Small Computer System Interface or SAS, Serial Attached SCSI), in the time that computing machine is loaded onto hard disk, should use the test of carrying out hard disk corresponding to the instrument of data-interface, for example, use SCSI testing tool to test SCSI hard disk.
SCSI released in early days in the 1980's, within 1986, become standard and use till today, storage device as hard drives in, SCSI hard disk widely workstation level personal computer and server uses, because its rotating speed is fast, and it is lower to take CPU calculation resources when data transmission.Scsi interface is by setting unique digital address, or title SCSI ID, distinguishes all devices.All devices in SCSI bus, all must set in advance SCSI ID (normally see through wire jumper, or change-over switch).When computing machine is loaded onto SCSI bus, just need to test each device on these SCSI, for example carry out the test events such as reading speed, spot speed, random access time, average reading speed and CPU usage.For example, SCSI hard drives (hereinafter to be referred as SCSI hard disk) manufacture more will be through the test of maximum import and export (IO) ability (speed), reaction time and CPU usage etc. under difference self temperature and environment temperature before dispatching from the factory; The data-interface that other are different, also has similar testing requirement.
For another example, if when SCSI hard disk is arranged (array SCSI HD) with array, fan rotation can cause the frame of SCSI hard disk array to produce vibrations, therefore, SCSI hard disk needs first under different rotation speeds of the fan, to carry out the rotation vibration test (Rotational Vibration test) of hard disk in frame, under the frame vibrations that caused in fan rotation (and rotation of other adjacent hard disk) with the mechanism design of guaranteeing frame, still can allow the access usefulness of hard disk within zone of reasonableness; In the time of test, must use rotation speed of the fan model (fan speed pattern) to test each SCSI hard disk, (test loop) is quite complicated for test loop, and what spend is chronic.More, if SCSI hard disk during with the arrangement of gathering together (Clustered SCSI HD), operating personnel's operating difficulties degree is more grown up with multiple.
In prior art, as disclosing US2008/0074107, U.S. Patent Publication No. discloses use button controller, test to select that hard disk array is selected to hard disk, but this test needs more manually sequentially test.And for example Taiwan patent 495085 is to disclosing the method for disk array test, as Fig. 1, for multiple disks (81a, 81b, 81c ... 81n) be connected to control circuit substrate 83 via bus winding displacement, be connected to computer system 82 by control circuit substrate 83, the control circuit of control circuit substrate 83 can detect disk function (containing temperature height, each disk quality, signal whether normal etc.), to increase the convenience in assembling.For other advanced application, as Fig. 1 and Fig. 2, be provided with multiple test procedures (821a, 821b, 821c in computer system 82 ... 821n), via bus winding displacement to disk (81a, 81b, 81c ... 81n) detect; But these method of testing all need to by operating personnel respectively selected disc driver test, monitoring and record, be still the work of suitable labor intensive.
For taking in the detection of robotization, Taiwan patent I230857 discloses and uses high-order operating system with automatic test motherboard, as Fig. 3, server 911 is equipped with high-order operating system, high-order operating system contains various test procedures and batch file, server 911 is connected in computing machine 912 to be measured via multiplexer 921, and motherboard 9121 to be measured is installed in computing machine 912 to be measured, and each computing machine 912 to be measured has a floppy disk 9122, hard disk 9123 and a network card 9124.When operation, select motherboard 9121 test events to be measured by operating personnel, after having tested, test result is delivered to server stores.This method of testing can be carried out once man-to-man test to computing machine 912 motherboards 9121 out of the ordinary by high-order operating system, if but the test repeatedly that is applied to hard disk array still needs a large amount of artificial.Taiwan patent I303765 discloses and uses multiple impact dampers reception of magnetic disc array detection temporary disk array detection data respectively, then selects one of them impact damper by outlet selector, and detection data transmission is carried out to record to computing machine; Though but this kind of method can be processed once the test of multiple hard disks, for the test of multiple patterns repeatedly, needs the impact damper of more times, though there is the part of minimizing artificial, impact damper and the hardware of volume are online, more aobvious complexity.
As previously mentioned, in the time carrying out array hard disk test, especially in the frame of server, be equiped with the hard disk of gathering together, in the time gathering together hard disk test, (test loop) is quite complicated for test loop, therefore as how automated execution test plan (testing plan), automatically detection record, and further produce analytical statement, for urgently required.
[summary of the invention]
Because above-mentioned prior art problem, one of fundamental purpose of the present invention is exactly that the one hard disk automated testing method of gathering together is being provided, and solves the test difficulty of the hard disk of gathering together with three-layered structuring; The method, by the three-layered structuring of the 0th rank arranging module, the 1st rank monitoring module and the 2nd rank test module, is tested the hard disk of gathering together, and it comprises the following step:
S1: set the 0th rank arranging module, layout hard disk test matrix (testing matrix), this test matrix includes test loop (testing loop) and test scheduling (testing schedule);
S2: the 0th rank arranging module, according to test matrix, drives the 1st rank monitoring module to carry out this test matrix;
S3: the 1st rank monitoring module starts the 2nd rank test module, carries out hard disk function test, and this functional test can be SCSI tool box (SCSI Toolbox) test or I/O test (IO testing) at SCSI hard disk; For the SCSI hard disk of gathering together, further can carry out functional test under with different rotation speeds of the fan at the fan of the each SCSI hard disk of frame;
S4: whether the 1st rank monitoring module monitoring the 2nd rank test module, complete the hard disk function test of gathering together;
S5: if complete functional test,, by the data of the 1st rank monitoring module acquisition the 2nd rank test module test screen picture, data are sent to the 0th rank arranging module, data are write archives by the 0th rank arranging module; Wherein, the test screen picture that the data of test screen picture produce including but not limited to the test screen picture of the 2nd rank test module or the testing software of use;
S6: repeat S3 to S5 until all hard disks of gathering together are complete according to test matrix;
S7: the data that the 0th rank analytical statement module transmits the 1st rank monitoring module complete archives, and these archives are analyzed;
S8: the result of analyzing is produced listing file by the 0th rank analytical statement module, exports this listing file.
Another fundamental purpose of the present invention is exactly that the one hard disk automated system of gathering together is being provided, and this system comprises: one or more measurement unit, a testing server and the testing workstation of being subject to; Wherein be subject to measurement unit to can be the fan (fan) of small computer system interface (SCSI) hard disk and frame (rack); Wherein, testing server is equiped with the 0th rank arranging module, and testing workstation is equiped with the 1st rank monitoring module and the 2nd rank test module; Testing workstation is connected with testing server, can receive the 0th rank arranging module fill order of this testing server, and can carry out the 1st rank monitoring module, the 1st rank test module can be monitored the 2nd rank test module, and the result of the 1st rank monitoring module is sent to this testing server storage; Testing workstation is connected with being subject to measurement unit, can carry out the 2nd rank test module to being subject to measurement unit to carry out functional test.
Further object of the present invention is exactly that the one hard disk automated system of gathering together is being provided, and the testing server of this system includes the 0th rank arranging module, in order to setting harddisk test scheduling; Testing server further comprises the 0th rank analytical statement module, in order to by functional test information, analyzes and make form.
Another object of the present invention is exactly that the one hard disk automated system of gathering together is being provided, the testing workstation of this system is installed the 1st rank monitoring module, further include graphical user interface gui software program, this gui software program can be AutoIT software program, can utilize gui software program to control the 2nd rank test module, and result or the screen-picture of the 2nd rank test module test are captured to relevant information.
Another object of the present invention is exactly that the one hard disk automated system of gathering together is being provided, and the testing workstation of this system is installed the 2nd rank test module, at least comprises: I/O test software programs or test kit any; For the SCSI hard disk of gathering together, wherein I/O test software programs can be Iometer software program, so that SCSI hard disk is carried out to I/O test.
From the above, according to the present invention gather together hard disk automated testing method and system thereof, it can have one or more following advantage:
(1) this hard disk automated testing method of gathering together has the structurized method of testing of three-layered, can be to being subject to measurement unit test scheduling planning, supervision and control fechtable test result and test according to test scheduling, more can the result of test be produced and be analyzed and form, reach and reduce labor hour and reduce the target that test errors occurs with automatic test.
(2) this hard disk automatization test system of gathering together has testing server and testing workstation, be equiped with the 0th rank arranging module, the 1st rank test module, the 2nd rank test module, can be to the hard disk of gather together (or array), automatically carry out different rotation speed of the fan circulation I/O tests or test kit test, reach and reduce labor hour and reduce the target that test errors occurs.
For object of the present invention, structural attitude and function thereof are had to further understanding, hereby coordinate accompanying drawing to be described in detail as follows:
[accompanying drawing explanation]
Fig. 1 is existing hard disk test system schematic diagram;
Fig. 2 is the piece solution figure of existing hard disk test system;
Fig. 3 is the measurement system diagram of existing automated computer motherboard;
Fig. 4 is the present invention's hard disk automatization test system schematic diagram of gathering together;
Fig. 5 is the gather together piece solution figure of hard disk automatization test system the first embodiment of the present invention;
Fig. 6 is the gather together process flow diagram of hard disk automatization test system the first embodiment of the present invention;
Fig. 7 is the gather together piece solution figure of hard disk automatization test system the second embodiment of the present invention;
Fig. 8 is the gather together process flow diagram of hard disk automatization test system the second embodiment of the present invention;
Fig. 9 is the gather together process flow diagram of hard disk automatization test system circulation of the present invention;
Figure 10 is the present invention's hard disk automated testing method process flow diagram of gathering together; And
Figure 11 is that the present invention's hard disk automatization test system of gathering together uses the screen-picture example figure of IO testing software and the scope example of acquisition screen-picture data.
[embodiment]
Refer to Fig. 4, it is the present invention's hard disk automatization test system schematic diagram of gathering together.In figure, the hard disk automatization test system 1 of gathering together, comprise: one or several measurement unit that is subject to, several measurement units that are subject to are arranged with array, be subject to the kind of measurement unit 21a~21n at least to comprise hard disk 21a~21n, also can comprise fan 24a~24n, hard disk 21a~21n and fan 24a~24n are installed in frame 22 (rack), on hard disk 21a~21n, there is disk output/inbound port 23a~23n (I/O port), disk output/inbound port 23a~23n uses winding displacement (bus) to be connected, and be connected on control interface circuit 18, another fan 24a~24n is also connected in and controls on interface circuit 18, one testing server 31, has screen 33 and can show various information and test pictures, and testing server 31 is equiped with the 0th rank arranging module 34 (not showing in figure is upper), one testing workstation 11, be equiped with the 1st rank monitoring module 14 (not showing in figure is upper) and the 2nd rank test module 15 (not showing in figure is upper), the first defeated in/out port 12 of testing workstation 11 is used winding displacement to be connected with control interface circuit 18, the mode of its connection is not limited, and also can use IP communication connection etc., testing workstation 11 is used winding displacement to be connected with the defeated in/out port 32 of testing server 31 via the second defeated in/out port 13, and the mode of its connection is not limited, and also can use IP communication connection etc.Wherein, testing workstation 11 is provided with media (not showing in figure is upper) that can storage data, as internal memory, hard disk or disk etc., in order to store the data data of result of test.
For different application, testing server 31 can connect one or a plurality of testing workstation 11, by testing server 31, one or a plurality of testing workstation 11 is carried out to one or more groups test, is to use widely.
The test mode of different pieces of information interface or testing tool difference, below only take small computer system interface (SCSI) hard disk as explanation, but not as limit.In the time being used in the small computer system interface of gathering together (SCSI) hard disk test, as Fig. 4, the hard disk automatization test system 1 of gathering together, comprise: one or several measurement unit that is subject to, several measurement units that are subject to are that array is arranged, and are subject to the kind of measurement unit 21a~21n to comprise SCSI hard disk 21a~21n, and fan 24a~24n, SCSI hard disk 21a~21n and fan 24a~24n are installed in frame 22 (rack), utilize testing server 31 and testing workstation 11 to test
Refer to Figure 10, it is the hard disk automated testing method process flow diagram of gathering together of the present invention, and the structurized method of testing of its three-layered is:
Step S1: set the 0th rank arranging module 34, layout hard disk 21a~21n test matrix, this test matrix includes test loop and test scheduling, the SCSI hard disk test of gathering together if be applied to, test matrix is as table one and table two;
Table one: SCSI hard disk IO (Iometer) functional test matrix
SCSI a SCSI b SCSI c SCSI d
Fan a on
Fan b on
Fan c on
Fan d on
Fan a~d on
Table two: SCSI hard disk tool box (Toolbox) test matrix
SCSI a SCSI b SCSI c SCSI d
Fan a~d on
Fan a~d speed 100% 100% 100% 100%
Fan a~d speed 80% 80% 80% 80%
Fan a~d speed 60% 60% 60% 60%
Step S2: the 0th rank arranging module 34, according to test matrix, drives the 1st rank monitoring module 14 to carry out this test matrix;
Step S3: the 1st rank monitoring module 14 starts the 2nd rank test module 15, the test of execution hard disk function, this functional test can be test kit (if SCSI hard disk uses SCSI tool box (SCSI Toolbox)) test or uses I/O test software programs 16; Further can under different rotation speeds of the fan, (for example adjust fan 24a~24n) and carry out functional test;
Whether step S4: the 1st rank monitoring module 14 is monitored the 2nd rank test module 15, complete hard disk 21a~21n functional test;
Step S5: if complete functional test, utilized data and/or the test result of gui software program acquisition the 2nd rank test module 15 test screen pictures by the 1st rank monitoring module 14, data are sent to the 0th rank arranging module 34; Data are write archives by the 0th rank arranging module 34, as notepaper archives (note pad); The data of acquisition are not limited with the mode that writes archives;
Step S6: repeat S3 to S5 until all hard disk 21a~21n are complete according to test matrix.
Further, the hard disk automated testing method of gathering together of the present invention can increase the following step again:
Step S7: the data that the 0th rank analytical statement module 35 transmits the 1st rank monitoring module 14 complete notepaper archives, and these notepaper archives are analyzed;
Step S8: the result of analyzing is produced listing file by the 0th rank analytical statement module 35, exports this listing file.
< the first embodiment >
This first embodiment is the present invention's hard disk automatization test system of gathering together, be applied to the SCSI hard disk automatic test of gathering together of small computer system interface (SCSI), figure is as Fig. 5 for piece solution, the 0th rank arranging module 34 of testing server 31 can be sent test instruction according to test scheduling, the 1st rank monitoring module 14 of testing workstation 11 can receive the fill order of testing server 31, and can carry out the 1st rank monitoring module 14, the 1st rank monitoring module 14 sends and is specifically subject to measurement unit (SCSI hard disk 21a~21n) test instruction, drive the 2nd rank test module 15 of testing workstation 11, in the 2nd rank test module 15, there is IO test software programs 16, can be to being subject to measurement unit (SCSI hard disk 21a~21n) to carry out IO functional test, in the present embodiment, IO test software programs 16 is used Iometer software program, its test event and picture be as Figure 11, and whether test result can show I/O speed, read data rate, I/O average reaction time, maximum reaction time, CPU usage and test etc.
The 1st rank test module 14 can be monitored the 2nd rank test module 15, and the result that the 1st rank monitoring module 14 is monitored is sent to testing server 31.At the present embodiment, the 1st rank monitoring module 14 that testing workstation 11 is installed includes gui software program, at the present embodiment, gui software program is used AutoIT software program, the screen-picture data that AutoIT software program fechtable Iometer software program is carried out, whether the data of acquisition data as shown in Figure 11 square frame, as the numbering of SCSI hard disk, I/O speed numerical value, read data rate numerical value, I/O average reaction time numerical value, maximum reaction time numerical value, CPU usage numerical value and tested etc.
Wherein, Iometer software program is issued on February 17th, 1998 by Intel Corporation and Intel Developers Forum (IDF), can be to the system amount of commenting single or that gather together.
Wherein, AutoIT software program is free common program, can be in order to write and to generate the shell script with similar BASIC, can be used for carrying out automatic operation in window GUI (user interface graphical user interface) window, utilize AutoIT software program can be used in combination that simulation thump, mouse move and window/control operation etc. realized automatically working.
The step S1 as described in Figure 10 of SCSI hard disk automated testing method that the present embodiment uses is to step S6, at this repeated description no longer.The present embodiment test flow chart is as Fig. 6, starting, test (square 401) is front, first first plan by the 0th rank arranging module 34 test matrix (square 402) that is subject to measurement unit 21a~21n, this test matrix includes condition, the circulation of test and the scheduling of test of test, starting after test (square 401), start the 0th rank arranging module 34 (square 403), carry out test loop (square 411) and the program (square 412) of carrying out each SCSI hard disk by the 1st rank monitoring module 14, and drive the 2nd rank test module 15, the 2nd rank test module 15 is carried out test software programs (square 421) (as Iometer), the to be measured measurement unit 21a~21n that is subject to is carried out respectively to functional test (square 422a~422n), whether the 1st rank monitoring module 14 monitoring are completed by the test loop of measurement unit 21a~21n (square 423a~423n), and carry out gui software program (square 413) (the present embodiment uses AutoIT software program) by the 1st rank monitoring module 14, the numerical value in acquisition Iometer screen-picture particular data district, and be sent in the data file of testing server 31 (square 414), complete test (square 404).
< the second embodiment >
The present embodiment is another embodiment of hard disk automatization test system of gathering together of the present invention, be applied to the SCSI hard disk automatic test of gathering together of small computer system interface (SCSI), figure is as Fig. 7 for piece solution, testing server 31 is equiped with the 0th rank arranging module 34 and the 0th rank analytical statement module 35, the 0th rank arranging module 34 can be sent test instruction according to test scheduling, the 1st rank monitoring module 14 of testing workstation 11 can receive the fill order of testing server 31, and can carry out the 1st rank monitoring module 14, the 1st rank monitoring module 14 sends and is specifically subject to measurement unit (SCSI hard disk 21a~21n and fan 24a~24n) test instruction, drive the 2nd rank test module 15 of testing workstation 11, in the 2nd rank test module 15, there are IO test software programs 16a~16n and SCSI toolkit programs 17a~17n (not showing in figure is upper), can be to being subject to measurement unit (SCSI hard disk 21a~21n and fan 24a~24n) to carry out the IO functional test under different rotation speeds of the fan, in the present embodiment, IO test software programs 16a~16n uses Iometer software program, its test event and picture be as Figure 11, and whether test result can show I/O speed, read data rate, I/O average reaction time, maximum reaction time, CPU usage and test etc.
The 1st rank test module 14 can be monitored the 2nd rank test module 15, and the result that the 1st rank monitoring module 14 is monitored is sent to testing server 31.At the present embodiment, the 1st rank monitoring module 14 that testing workstation 11 is installed includes gui software program, at the present embodiment, gui software program is used AutoIT software program 141, the screen-picture data that AutoIT software program fechtable Iometer software program is carried out, the data of acquisition data as shown in Figure 11 square frame.
The step S1 as described in Figure 10 of SCSI hard disk automated testing method that the present embodiment uses is to step S8, at this repeated description no longer.Test flow chart is as Fig. 8, starting, test (square 501) is front, first first plan by the 0th rank arranging module 34 test matrix (square 502) that is subject to measurement unit 21a~21n, this test matrix includes condition, the circulation of test and the scheduling of test of test; Starting after test (square 501), start the 0th rank arranging module 34 (square 503), carry out test loop (square 511) and the program (square 512) of carrying out each SCSI hard disk by the 1st rank monitoring module 14, and drive the 2nd rank test module 15; the 2nd rank test module 15 is carried out test software programs 16a~16n (the present embodiment uses Iometer) and test software programs 17a~17n (the present embodiment uses SCSI tool box) (not showing in figure is upper) (square 521a~521n), the to be measured measurement unit (SCSI hard disk 21a~21n and fan 24a~24n) that is subject to is carried out to functional test (square 522a~522n) simultaneously, the 1st rank monitoring module 14 monitoring are subject to the test loop of measurement unit (SCSI hard disk 21a~21n and fan 24a~24n) whether to complete (square 523a~523n), and carry out user interface gui software program (square 513) (the present embodiment uses AutoIT software program) by the 1st rank monitoring module 14, the numerical value in acquisition Iometer screen-picture particular data district, and be sent in the data file of testing server 31 (square 514), be subject to the functional test results analysis of measurement unit (SCSI hard disk 21a~21n and fan 24a~24n) and produce form (square 504) by the 0th rank analytical statement module 35 again, complete test (square 505).
The test plan of the present embodiment and test loop illustrate as Fig. 9, in figure, test starts after (square 701), whether the notepaper archives (note pad) that first check SCSI toolkit programs, test condition (test scheduling), IO test software programs and the instruction of control rotation speed of the fan there is (square 702), have any not exist during if above-mentioned, stop carrying out (square 721), while all existence if above-mentioned, prepare deposit data folder (square 703) in testing server 31; At the 0th rank test arranging module 34 setting rotating speed of fan (square 704), this can preset in notepaper archives, and sets up rotation speed of the fan matrix to be tested (square 705); Select rotation speed of the fan test condition (square 706 and square 707) and select screen-picture picking point (the present embodiment is selected screen-picture picking point on AutoIT software program, as Figure 11) in the 1st rank monitoring module 14; Start to carry out the test (square 710~square 718) of fan 24a under test condition~24n rotation and SCSI hard disk 21a~21n, this group has been tested the data of rear access screen-picture acquisition and has been stopped the SCSI hard disk test (square 719) of this group; Selected the test (square 709) of next group SCSI hard disk 21a~21n by test plan, until whole tests of this condition complete, carry out the test rotation speed of the fan (square 706) of next group; Until all having tested rear replacement returns the rotation speed of the fan of former setting (square 720).
The test (square 710~square 718) of SCSI hard disk 21a~21n is described as follows: first first start SCSI toolkit programs (square 710); Whole measurement units (SCSI hard disk 21a~21n) that is subject to is all chosen to (square 711); Cancelled by measurement unit (SCSI hard disk 21a~21n and fan 24a~24n one of them) to select (deselect) (square 712 to what testing, remove to select the measurement unit that is subject in current test), form except all test environments in the state of running up of all hard disks testing hard disk just; Set required test parameter, start to carry out the test (square 713 and square 714) of SCSI toolkit programs; After SCSI toolkit programs has been tested, start IO test software programs (square 715), select test topology (testing topology) (square 716) by IO test software programs (the present embodiment uses Iometer), select SCSI hard disk (21a~21n) (square 717) to be tested by test scheduling; Carry out IO test software programs test (square 718).

Claims (15)

1. the hard disk automated testing method of gathering together, by the three-layered structuring of one the 0th rank arranging module, one the 1st rank monitoring module and one the 2nd rank test module, tests the hard disk of gathering together, and it is characterized in that, it comprises the following step:
S1: set the 0th rank arranging module, a test matrix of layout hard disk;
S2: make the 0th rank arranging module according to this test matrix, drive the 1st rank monitoring module to carry out functional status corresponding in this test matrix;
S3: make the 1st rank monitoring module start the 2nd rank test module, carry out the functional test of hard disk;
S4: make the 1st rank monitoring module monitor the 2nd rank test module, whether complete the functional test of hard disk;
S5: if complete functional test, captured the data of the 2nd rank test module test screen picture by the 1st rank monitoring module, data are sent to the 0th rank arranging module, data are write archives by the 0th rank arranging module; And
S6: repeat S3 to S5 until all hard disks are complete according to this test matrix.
2. the hard disk automated testing method of gathering together as claimed in claim 1, further comprises one the 0th rank analytical statement module, it is characterized in that, after step S6 completes, further comprises:
S7: the data that the 0th rank analytical statement module transmits the 1st rank monitoring module, analyze and produce a listing file, export this listing file.
3. the hard disk automated testing method of gathering together as claimed in claim 1, is characterized in that, the 2nd rank test module of step S3 is carried out the functional test of hard disk, at least comprises: any test or its combined test of I/O test, test kit test.
4. the hard disk automatization test system of gathering together, is characterized in that, it comprises:
The one or more measurement unit that is subject to, this is subject to the kind of measurement unit at least to comprise hard disk;
One testing server, is equiped with one the 0th rank arranging module; And
One testing workstation, is equiped with one the 1st rank monitoring module and one the 2nd rank test module; This testing workstation is connected with this testing server, in order to receive the 0th rank arranging module fill order of this testing server, and in order to carry out the 1st rank monitoring module, the 1st rank monitoring module is in order to monitor the 2nd rank test module, and the monitored results of the 1st rank monitoring module is sent to this testing server; This testing workstation is connected by measurement unit again with this, be subject to measurement unit to carry out functional test in order to carry out the 2nd rank test module to this.
5. the hard disk automatization test system of gathering together as claimed in claim 4, is characterized in that, the 0th rank arranging module that this testing server is installed, includes a hard disk test scheduling.
6. the hard disk automatization test system of gathering together as claimed in claim 4, is characterized in that, the 1st rank monitoring module that this testing workstation is installed in order to capture the functional test information of the 2nd rank test module, and is sent to this testing server.
7. the hard disk automatization test system of gathering together as claimed in claim 4, it is characterized in that, this testing server further includes one the 0th rank analytical statement module, and the functional test information transmitting in order to collect this testing workstation, analyzes and make a form.
8. the hard disk automatization test system of gathering together as claimed in claim 4, is characterized in that, the 1st rank monitoring module that this testing workstation is installed includes a user interface software program.
9. the hard disk automatization test system of gathering together as claimed in claim 4, is characterized in that, the 2nd rank test module that this testing workstation is installed at least comprises: an I/O test software programs or a test kit.
10. the hard disk automatization test system of gathering together as claimed in claim 4, is characterized in that, this is subject to the kind of measurement unit further to comprise a fan, rotates with this fan of the 2nd rank test module control, carries out the functional test of hard disk to adjust this rotation speed of the fan.
The 11. hard disk automatization test systems of gathering together as claimed in claim 10, is characterized in that, the 0th rank arranging module that testing server is installed includes the scheduling of the rotation speed of the fan test of a hard disk function test and a hard disk.
The 12. hard disk automatization test systems of gathering together as claimed in claim 10, is characterized in that, the 1st rank monitoring module that this testing workstation is installed in order to capture the functional test information of the 2nd rank test module, and is sent to this testing server.
The 13. hard disk automatization test systems of gathering together as claimed in claim 10, it is characterized in that, this testing server further comprises one the 0th rank analytical statement module, and the functional test information transmitting in order to collect this testing workstation, analyzes and make a form.
The 14. hard disk automatization test systems of gathering together as claimed in claim 10, is characterized in that, the 1st rank monitoring module that this testing workstation is installed includes a user interface software program.
The 15. hard disk automatization test systems of gathering together as claimed in claim 10, is characterized in that, this testing workstation is installed the 2nd rank test module and at least comprised: an I/O test software programs or a test kit.
CN201010148566.0A 2010-04-16 2010-04-16 Cluster harddisk automation test method and system Expired - Fee Related CN102222517B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010148566.0A CN102222517B (en) 2010-04-16 2010-04-16 Cluster harddisk automation test method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010148566.0A CN102222517B (en) 2010-04-16 2010-04-16 Cluster harddisk automation test method and system

Publications (2)

Publication Number Publication Date
CN102222517A CN102222517A (en) 2011-10-19
CN102222517B true CN102222517B (en) 2014-06-11

Family

ID=44779048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010148566.0A Expired - Fee Related CN102222517B (en) 2010-04-16 2010-04-16 Cluster harddisk automation test method and system

Country Status (1)

Country Link
CN (1) CN102222517B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9501766B2 (en) 2012-06-29 2016-11-22 International Business Machines Corporation Generating a storage drive qualification test plan
CN104484254A (en) * 2014-12-30 2015-04-01 浪潮电子信息产业股份有限公司 Method for testing influence of internal vibration of high-density cabinet on I/O (Input/Output) performance
CN107832176A (en) * 2017-11-16 2018-03-23 郑州云海信息技术有限公司 Hard disk pressure automatic test approach and system under a kind of Windows
CN109614306A (en) * 2018-12-12 2019-04-12 广东浪潮大数据研究有限公司 Hard disk performance detection method, device, equipment and computer readable storage medium

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2321751A4 (en) * 2008-07-07 2014-03-05 Quali Systems Ltd System and method for automatic hardware and software sequencing of computer-aided design (cad) functionality testing

Also Published As

Publication number Publication date
CN102222517A (en) 2011-10-19

Similar Documents

Publication Publication Date Title
CN102568522B (en) The method of testing of hard disk performance and device
US6915466B2 (en) Method and system for multi-user channel allocation for a multi-channel analyzer
US10929260B2 (en) Traffic capture and debugging tools for identifying root causes of device failure during automated testing
EP2843537B1 (en) Method and systems for simulating a workload of a storage system
CN104331373A (en) Monkey test system and method
TWI566090B (en) Debugging firmware / software to produce tracking systems and methods, recording media and computer program products
EP2686771B1 (en) Usability testing
CN107066370A (en) A kind of automatic monitoring and the instrument and method for collecting faulty hard disk daily record
CN104518924A (en) Automatic testing and result comparison method and system
CN102222517B (en) Cluster harddisk automation test method and system
CN105074671A (en) Method and system for detecting concurrency programming errors in kernel modules and device drivers
CN105223889A (en) A kind of method being applicable to the automatic monitoring PMC RAID card daily record of producing line
CN102087855A (en) Rotating vibration test system and method of storage equipment
CN107015896B (en) Embedded equipment CPU and peripheral state real-time monitoring method and system thereof
CN103699474A (en) Storage equipment monitoring system and method
CN103593271A (en) Method and device for chip tracking debugging of system on chip
CN104298583A (en) Mainboard management system and method based on baseboard management controller
US11620176B2 (en) Visualization system for debug or performance analysis of SOC systems
CN111274078A (en) Method, system and device for testing performance of hard disk
CN101776915A (en) Cross-platform station automatic monitoring system testing method based on concurrency simulating tools
CN115525490A (en) Memory eye pattern testing method, hardware debugging equipment and storage medium
US7380054B2 (en) Storage of fault and position data in nonvolatile memory on system components
Lyu et al. Hyrax:{Fail-in-Place} Server Operation in Cloud Platforms
TW201128388A (en) Automatic testing method for clustered hard disks and system thereof
CN106708445B (en) Link selecting method and device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140611

Termination date: 20160416

CF01 Termination of patent right due to non-payment of annual fee