CN102208222B - Control method and system thereof of nuclear power plant operation - Google Patents

Control method and system thereof of nuclear power plant operation Download PDF

Info

Publication number
CN102208222B
CN102208222B CN2011100771797A CN201110077179A CN102208222B CN 102208222 B CN102208222 B CN 102208222B CN 2011100771797 A CN2011100771797 A CN 2011100771797A CN 201110077179 A CN201110077179 A CN 201110077179A CN 102208222 B CN102208222 B CN 102208222B
Authority
CN
China
Prior art keywords
task
module
allocation criteria
subtask
power plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2011100771797A
Other languages
Chinese (zh)
Other versions
CN102208222A (en
Inventor
邹杰
于正龙
张建波
谭珂
史觊
程波
张刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China General Nuclear Power Corp
China Nuclear Power Engineering Co Ltd
Original Assignee
China General Nuclear Power Corp
China Nuclear Power Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China General Nuclear Power Corp, China Nuclear Power Engineering Co Ltd filed Critical China General Nuclear Power Corp
Priority to CN2011100771797A priority Critical patent/CN102208222B/en
Publication of CN102208222A publication Critical patent/CN102208222A/en
Application granted granted Critical
Publication of CN102208222B publication Critical patent/CN102208222B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)
  • Testing And Monitoring For Control Systems (AREA)
  • Safety Devices In Control Systems (AREA)

Abstract

The invention discloses a control method and a system thereof of nuclear power plant operation. The method comprises the following steps of: S1, executing the task decomposition to generate at least two sub tasks; S2, judging whether each sub task meets a predetermined termination rule, if so, executing the step S3, otherwise, continuously executing the step S1; S3, determining a basic task information flow and a task processing requirement required for the operation according to each sub task obtained from the step S2; S4, analyzing the task in the basic task information flow; S5, distributing the final sub task to a relative execution terminal in a task execution task according to a task analysis result; S6, judging whether the task distribution meets a predetermined distribution rule, if not, returning to the step S5, otherwise, using a master control room to control the relative execution terminal in the task execution system to respectively execute the distributed task. The control method and system can be used for efficiently and rationally distributing the task so as to guarantee the integrality and effectiveness of the control room-related task.

Description

Control method and the system thereof of the operation of a kind of nuclear power plant
Technical field
The present invention relates to the nuclear power plant control room design field, relate in particular to control method and the system thereof of a kind of nuclear power plant operation.
Background technology
The main target of nuclear power plant control room is to realize that power plant moves under its all operations and accident conditions safe and effectively.For realizing the above-mentioned target of pulpit, and meet security doctrine, usability principles and Human Engineering principle, the demand of pulpit task analysis and task being distributed according to statutory standard GB/T13630-92 " design of Control Room of Nuclear Power Plant " and EJ/T1143-2002 " Control Room of Nuclear Power Plant design function analyze with distribute ", task that must be performed to nuclear power station is analyzed also reasonable distribution to operator and machine.
The availability objective of corresponding nuclear power station operation and the analysis requirement of security target, can choose the operating condition that can cover as follows analyzed various tasks and be analyzed, to guarantee the completeness and efficiency of pulpit task analysis and distribution.Wherein, the analysis of availability task is chosen to accidental conditions, be specially: a) unit normally starts; B) unit is normally stopped transport; C) firm power operation; D) Steam Generator in Load Follow.Accident operating conditions is chosen in analysis to the security task, is specially: a) loss of-coolant accident (LOCA) (Loss of Coolant Accident, LOCA); B) steam generator tube rupture accident (Steam Generator Tube Rupture, SGTR); C) Main steam line break accident (Main Steam Line Break, MSLB); D) main feed water pipe road fracture accident (Feed Water Line Break, FWLB); E) loss of off-site power accident.
But, in prior art, do not have a kind of can be intelligently, all sidedly, the method and system of analysis task and then allocating task reasonably, and need to rely on the main control room staff to utilize multiple independently software to carry out the task distribution, not only take time and effort and affect efficiency, and consider not comprehensive, cause task to be distributed reasonable not, thereby affected the control ability of pulpit to nuclear power plant's operation.
Summary of the invention
The technical problem to be solved in the present invention is, distribute the defects such as the efficiency caused is low, unreasonable distribution for relying on manpower and multiple stand alone software to carry out task in prior art, a kind of control method and system thereof of considering comprehensively, distributing the operation of reasonable and efficient nuclear power plant is provided.
The technical solution adopted for the present invention to solve the technical problems is:
The control method of a kind of nuclear power plant operation is provided, comprises:
S1, the decomposition of executing the task, generate at least two subtasks;
S2, judge whether each described subtask meets default termination rules, if execution step S3, if not, continue execution step S1;
S3, according to the subtasks at different levels that obtain in step S2, determine basic task information flow and the task processing requirements that operation is required;
S4, described basic task information flow is carried out to task analysis, described task analysis comprises determines various control informations and the execution information relevant to task;
S5, according to the result of described task analysis, the relevant execution terminal in task execution system is distributed to in final subtask;
S6, judge that task is distributed and whether meet default allocation criteria, if not, return to step S5; If main control room is controlled the task that relevant execution terminal in described task execution system is carried out respectively distribution.
In the control method of nuclear power plant of the present invention operation, described termination rules comprises following at least one:
Described subtask has nothing to do with main control room or is no longer control task;
Individual feature, parameter and/or controller can be controlled in described subtask;
Described subtask no longer comprises subtask.
In the control method of nuclear power plant of the present invention operation, during Task-decomposing, will move general assignment and be decomposed into availability task and security task first.
In the control method of nuclear power plant of the present invention operation, described task analysis also comprises following at least one:
Identical subtask is merged;
The subtask of realizing correlation function is combined as to a kind of combined task.
In the control method of nuclear power plant of the present invention operation, described allocation criteria comprises following at least one:
Determine the allocation criteria which kind of assigns the task to and carry out terminal according to task characteristic, described execution terminal comprises operator and machine;
Determine and take the remote allocation criteria of still controlling on the spot of manually controlling according to objective condition;
Carry out the allocation criteria of task distribution according to the safety requirements under accident conditions;
Carry out the allocation criteria of task distribution according to the information block based on function.
The present invention also provides the control system of a kind of nuclear power plant operation, comprising:
The Task-decomposing module, for the decomposition of executing the task, generate at least two subtasks;
Stop judge module, for judging each described subtask, whether meet default termination rules, and when not meeting, indicate described Task-decomposing module to continue to decompose described subtask;
The dealing with information flow module, determine for the subtasks at different levels according to receiving from described termination judge module basic task information flow and the task processing requirements that operation is required;
The task analysis module, for described basic task information flow is carried out to task analysis, described task analysis comprises determines various control informations and the execution information relevant to task;
The task distribution module, distribute to final subtask the relevant execution terminal of task execution system for the analysis result according to described task analysis module output;
Distribute judge module, for the task of judging described task distribution module, distribute whether meet default allocation criteria, if do not meet and indicate described task distribution module to redistribute described task; If satisfied indicate main control room to control the task that relevant execution terminal in described task execution system is carried out respectively distribution.
In the control system of nuclear power plant of the present invention operation, also comprise that termination rules memory module and termination rules arrange module,
Described termination rules memory module is for storing termination rules, and described termination rules comprises following at least one: described subtask has nothing to do with described main control room or is no longer control task; Individual feature, parameter and/or controller can be controlled in described subtask; Described subtask no longer comprises subtask;
Described termination rules arranges module for from described termination rules memory module, selecting at least one termination rules to send described termination judge module to, also for operate the new termination rules of generation according to the user, is stored in described termination rules memory module.
In the control system of nuclear power plant of the present invention operation, described Task-decomposing module, when Task-decomposing first, will be moved general assignment and be decomposed into availability task and security task.
In the control system of nuclear power plant of the present invention operation, described task analysis module is for following at least one:
Identical subtask is merged;
The subtask of realizing correlation function is combined as to a kind of combined task.
In the control system of nuclear power plant of the present invention operation, also comprise that allocation criteria memory module and allocation criteria arrange module,
Described allocation criteria memory module is for the storage allocation criterion, and described allocation criteria comprises following at least one: determine the allocation criteria which kind of assigns the task to and carry out terminal according to task characteristic, described execution terminal comprises operator and machine; Determine and take the remote allocation criteria of still controlling on the spot of manually controlling according to objective condition; Carry out the allocation criteria of task distribution according to the safety requirements under accident conditions; Carry out the allocation criteria of task distribution according to the information block based on function;
Described allocation criteria arranges module for from described allocation criteria memory module, selecting at least one allocation criteria to send described distribution judge module to, also for operate the new allocation criteria of generation according to the user, is stored in described allocation criteria memory module.
The control method of a kind of nuclear power plant of the present invention operation and the beneficial effect of system thereof are: by the Task-decomposing based on termination rules and the task based on allocation criteria, distribute, and in conjunction with task analysis, realization efficiently, reasonably task is distributed, guarantee the completeness and efficiency of the task that pulpit relates to, improved the control ability of main control room to nuclear power plant's operation.
The accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described, in accompanying drawing:
Fig. 1 is the process flow diagram of the control method that nuclear power plant moves according to an embodiment of the invention;
Fig. 2 is the process flow diagram of Task-decomposing algorithm according to an embodiment of the invention;
Fig. 3 is the process flow diagram of the genetic algorithm that task is distributed according to an embodiment of the invention;
Fig. 4 is the structural representation of the control system that nuclear power plant moves according to an embodiment of the invention;
Fig. 5 is the structural representation of the control system that nuclear power plant moves in accordance with another embodiment of the present invention.
Embodiment
In order to make purpose of the present invention, technical scheme and advantage clearer, below in conjunction with drawings and Examples, the present invention is further elaborated.Should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not intended to limit the present invention.
Various embodiment of the present invention provides the control method of a kind of nuclear power plant operation.At first will move general assignment and be decomposed into availability task (controlled generating) and security task (preventing radioactivity release), the operation general assignment is that the main target (realizing power plant safety and effectively operation under its all operations and accident conditions) according to nuclear power plant is determined.Then availability task and security task are decomposed into respectively at least two subtasks, and judge whether each subtask meets default termination rules, if do not meet, do not continue to decompose this subtask until meet termination rules (being that corresponding task can not be decomposed again).Wherein, termination rules comprises following at least one: this subtask has nothing to do with main control room or is no longer control task; Individual task, parameter and/or controller can be controlled in this subtask; This subtask no longer comprises subtask.Next determine that for the subtasks at different levels that meet termination rules power plant moves required basic task information flow and task processing requirements.
Then, the basic task information flow is carried out to task analysis, determine various control informations and the execution information relevant to task, and carry out the task distribution according to the result of task analysis.Wherein task analysis at least comprises with the next item down: identical subtask is merged; The subtask of realizing correlation function is combined as to a kind of combined task.Next judge task distributes whether meet default allocation criteria, if do not meet this task of redistributing, until meet.Wherein, allocation criteria comprises following at least one: determine the allocation criteria which kind of assigns the task to and carry out terminal according to task characteristic; Determine and take the remote allocation criteria of still controlling on the spot of manually controlling according to objective condition; Carry out the allocation criteria of task distribution according to the safety requirements under accident conditions; Carry out the allocation criteria of task distribution according to the information block based on function.
Fig. 1 is the process flow diagram of the control method that nuclear power plant moves according to an embodiment of the invention.In the present embodiment, at first the control method of nuclear power plant's operation performs step S1 after starting.In step S1, the decomposition of executing the task, generate at least two subtasks.Because the present invention carries out task analysis and distribution mainly for the pulpit of nuclear power station, therefore can at first the general assignment of nuclear power station operation (being that An full ﹑ effectively generates electricity and the protection public avoids radiation hazard) be decomposed into to availability task (controlled generating) and security task (preventing radioactivity release).In decomposable process, can also determine the whole power plant task relevant with main control room for each subtask, only to controlling inter-related task, decomposed.
In step S2, judge whether each subtask meets default termination rules.According to the Standard andRegulation of nuclear power station, the termination rules of the Task-decomposing that the present invention is default comprises following at least one:
A) task is irrelevant with main control room, and for example control and complete on the spot, or this task is no longer a control task, but such as the tasks such as maintenance to equipment;
B) reached the degree that can control individual feature, parameter, controller;
C) this task no longer comprises subtask, such as this task, is simple mechanical action etc.
But the present invention is not limited to this, and can comprise the termination rules of any appropriate, as long as it is complete, independently that this termination rules makes the task of the required bottom reached of Task-decomposing, or can realize, and important hierarchical structure is clear and definite getting final product.
If there is the subtask that does not meet termination rules, S1 is continued respectively to perform step in the subtask that these is not met to termination rules.The rest may be inferred, until all subtasks all meet termination rules, and until the task of the bottom is complete and independently, or can realize, and important hierarchical structure is clear and definite, meets this standard and just can stop decomposing.
If all subtasks all meet termination rules, perform step S3.In step S3, determine according to subtasks at different levels basic task information flow and the task processing requirements that operation is required, for example set up system task model tree or other topological structure, mean subtasks at different levels and mutual relationship thereof.
In step S4, the basic task information flow is carried out to task analysis, comprise and determine various control informations and the execution information relevant to task.Wherein, task analysis can comprise following at least one, and comprises the analysis sequence of any appropriate:
A) determine the back-up system relevant with Given task, comprise process system, power supply, source of the gas etc.;
B) analyze as completing Given task, need the parameter that monitors and/or monitor which means power plant's state, such as: temperature, pressure, valve location etc.;
C) if Given task can not correctly be carried out, there is which other task to substitute;
D) operation that completes this task is automatically completed or manually completed by operator by machine;
E), if automatically control, need to carry out which backup manual and control;
F) no matter automatically still manually, operator will exercise supervision to some parameter, and which these parameters are, where are placed in;
G) if which equipment manual operation (backup manual that comprises automatic control is controlled) needs, where be placed in, in which kind of state just can finish the work;
H), if operation steps needs operator to carry out the senior thought processing, need to decide control action how to carry out by which parameter;
I) identical subtask is merged;
J) subtask that will realize correlation function is combined as a kind of combined task.
Whether, when task analysis is carried out in each subtask, can also differentiate and determine that whether this task is relevant to pulpit, be control task, in order to carry out subsequent allocations.
In step S5, according to the result of above-mentioned task analysis, carry out the task distribution.Task is divided timing, need to consider respectively the ability of operator and blind controller system.The task of for example, distributing to operator can be divided into three classes: carry out control task, to the supervision of automatic system and carry out the senior thought processing.According to factors such as the accuracy of the burden weight of this three generic task, requirement, response times, in the scope that does not exceed operator's ability, reasonably distributed.Again for example, while considering the processing power of blind controller system, the functional requirement that at first will stipulate system and equipment, then according to the requirement of operation task regulation man-machine interface, finally determine all technical, as the quantity of system and equipment, response time, degree of accuracy, Human Engineering requirement etc.
In step S6, judge whether above-mentioned task distribution meets default allocation criteria.Default allocation criteria can comprise following at least one:
Criterion 1: according to the characteristic of task, assign the task to operator or the criterion of machine in Table 1.
The task allocation criteria of table 1 operator and machine
Figure GDA00003207288800071
1) operator's ability
In the nuclear power station design, the task of operator's burden comprises following three kinds: manually carry out a control task; The supervision automatic system is carried out control task; Carry out the senior thought processing.
2) processing power of instrument control system
Nuclear power station protection and controlling of task are mainly completed by the instrument control system, and this just requires to distribute to the control task (having considered the interaction with operator) of machine and processing (information and control) ability of instrument control system adapts.In the instrument control system, need to consider automatically control and manually control, its processing power comprises quantity, response time and the accuracy requirement for system or equipment, and the requirement of Human Engineering standard and Human Engineering standard are determined man machine interface's requirement to each base part.
Criterion 2: according to objective condition, take the remote manually task allocation criteria that control is still controlled on the spot in Table 2.
The remote task allocation criteria with manually controlling on the spot of table 2
Figure GDA00003207288800081
Table 2 is only one embodiment of the present of invention, wherein only enumerated the part situation, but the present invention is not limited to this, and can comprise that any appropriate ground judgement takes the remote standard of manually controlling or controlling on the spot, as long as follow following general principle: requiring summary responses and obvious consequence being arranged of task is by manually having controlled at a distance.
Criterion 3: the safety requirements under accident conditions comprises the explanation of emergency operation rules.
Another source of task allocation criteria is the safety requirements under accident conditions.Criterion 3 is defined as follows: the quick operation response task that accident conditions lower-pilot person has little time to be intervened must be distributed to machine, for important safe operation, except the task that automatic control is arranged, also must be provided with the manual control task of redundancy, supplementing while in order to conduct, automatically controlling inefficacy.
Criterion 4: information block.
According to controlling-show comprehensive principle, the various information that are applicable to operator are divided into groups by function, be divided into one group taking each to operate required information, so that for operator provides an integrated information system in its limit of power, rather than by the information source grouping.
If exist the task of not meeting allocation criteria to distribute, return to step S5 and redistribute the task that these do not meet allocation criteria, until distributing, all tasks all meet allocation criteria.
All meet allocation criteria if all tasks are distributed, the task assigning process finishes so.The relevant execution terminal of main control room in can the control task executive system carried out respectively the task of distribution.For example, the operator and the instrument control equipment that are assigned with task will be carried out task separately as requested, thereby reach the operation general objective.
Fig. 2 is the process flow diagram of task analysis algorithm according to an embodiment of the invention.In the present embodiment, the task analysis algorithm starts from step 201.
In step 201, the operation general assignment of nuclear power station is decomposed into to availability task (controlled generating) and security task (preventing from discharging radioactivity to environment).
Specifically, can carry out detailed Task-decomposing according to following task to pulpit:
A) availability task
1) making power plant reach the Power operation state, is for example 15% rated power from the cold shut operating mode to the band minimum load;
2) control the core steam supply under various normal operating modes, for example firm power operation---be stabilized in a certain power level operation in 15%~100% rated power scope, load-following operation---from 15% rated power load up to 100% rated power, from 100% rated power load down to 15% rated power;
3) steam-energy is converted to electric energy;
4) cold-refueling, comprise from 15% rated power to cold shut and the work in every that reloads;
B) security task
Safe task is to prevent that radioactivity release is in environment, and nuclear power station is provided with three road barriers in design, i.e. fuel can, reactor coolant loop border and containment.Under accident conditions, as long as three road barriers keep integrality, just can complete safe task.The key safety task that therefore, to the decomposition of security task, just need to keep three road barrier integrities from those.The key safety task comprises following six: remain subcritical; Maintain Core cooling; The maintaining heat trap; Maintain the integrality on reactor coolant loop border; Maintain the integrality of containment; Maintain the charging capacity of Main Coolant.
In order to guarantee the execution of above safe task in various accident conditionses, nuclear power station designs different systems or some has operated these tasks, and the present invention is these systems or Operation Definition more further task.Normally play a role under the accident conditions that these systems can be discussed in the present invention, will carry out certain operation or also need some subsystem supports system, the task that the present invention is these operations and subsystem definition more lower one deck.The decomposition that deepens continuously like this, until each operation for executing the task carried out.
In step 202, respectively availability task and security task are decomposed into to subtask layer by layer, and differentiate necessary subtask, determine the whole power plant task relevant with pulpit.
In step 203, the Task-decomposing termination rules is set, and pulpit inter-related task definite in step 202 is confirmed one by one by termination rules, the task of meeting termination rules stops decomposing, and the task of not meeting termination rules continues to get back in step 202 decomposes again.In the present embodiment, it can be from one or more with reference to selecting the described default termination rules of figure 1 that termination rules is set, and can also be to reset other termination rules.
In step 204, according to the task (needn't decomposing again of task) of decomposing fully in step 203, determine that power plant moves needed basic task information flow and task processing requirements.
Fig. 3 is the process flow diagram of the genetic algorithm that task is distributed according to an embodiment of the invention.In the present embodiment, the genetic algorithm that task is distributed starts from step 301.
In step 301, the information flow that the task analysis algorithm is determined carries out task analysis, differentiates and determines which information belongs to control task, and task analysis comprises determines various control informations and the execution information relevant to task.When carrying out task analysis, except analyzing correlation parameter, task, demand for control, can also be merged or be combined identical or inter-related task, to simplify control operation.
For example, in order to realize the operation of power plant, such as processing of accident conditions etc., need to carry out several tasks simultaneously.When carrying out task analysis, different high-level tasks can decomposite identical low level task, so just can merge " like terms "; The function that also has some tasks to realize is correlated with, and can, they appropriate combination, as a unit, be just that a kind of combined task is processed.So just can organize the information in various sources by certain actuating range, be convenient to operator and obtain relatively complete information in limited space.The embodiment of putting specific to pulpit man-machine interface and the dish tablecloth, be exactly on computer workstation, and the information that has been a certain task is put together; On back-up disk, the relative centralized arrangement of the equipment (comprising the equipment such as display instrument, registering instrument, controller) that has been a certain task.This strategy can be made a response operator fast, is also the foundation of parameter marshalling and equipment layout marshalling.
In step 302, by the control task identified in step 301, distribute to operator and machine has gone.When task is distributed, need to consider respectively the ability of operator and blind controller system, assign the task to suitable executor.In addition, when task is distributed, allocation criteria that can be default according at least one, for example according to task characteristic determine assign the task to which kind of carry out terminal (for example operator or machine) allocation criteria, according to objective condition determine take remote manually control the allocation criteria still controlled on the spot, according to the safety requirements under accident conditions carry out the task distribution allocation criteria, carry out at least one in the allocation criteria of task distribution according to the information block based on function.
In step 303, setting will be as the allocation criteria of basis for estimation, and in the present embodiment, it can be from one or more with reference to selecting the described default allocation criteria of figure 1 that allocation criteria is set, and can also be to reset other allocation criteria.The allocation criteria arranged in this step can be the allocation criteria from any appropriate different in step 302.For example, in step 302, based on reference to the described criterion 1 of figure 1, carrying out allocating task, in step 303, based on judging that with reference to the described criterion 2 of figure 1, criterion 3 and criterion 4 task is distributed, whether meet the demands respectively.
In step 304, judge according to the allocation criteria arranged in step 302 that task is distributed and whether meet the requirements, meet allocation criteria and distribute with regard to terminated task, do not meet allocation criteria and just continue to return step 302 and again reallocate, until meet allocation criteria.
In step 305, the distribution of finishing the work, the relevant execution terminal (for example operator and machine) of main control in can the control task executive system carried out being assigned with separately of the task of carrying out respectively.
Fig. 4 is the structural representation of the control system that nuclear power plant moves according to an embodiment of the invention.In the present embodiment, the control system of nuclear power plant's operation comprises Task-decomposing module 40, termination judge module 41, the dealing with information flow module 42, task analysis module 43, task distribution module 44 and distributes judge module 45.
Task-decomposing module 40, for the decomposition of executing the task, generate at least two subtasks.For example, when Task-decomposing first, Task-decomposing module 40 can be moved power plant general assignment and be decomposed into availability task and security task.
Stop judge module 41, for judging Task-decomposing module 40, decompose each subtask obtained and whether meet default termination rules.When existing at least one subtask not meet termination rules, termination judge module 41 can also be indicated Task-decomposing module 40 to continue to decompose these and do not met the subtask of termination rules.
The termination rules of default Task-decomposing comprises following at least one:
A) task is irrelevant with main control room, and for example control and complete on the spot, or this task is no longer a control task, but such as the tasks such as maintenance to equipment;
B) reached the degree that can control individual feature, parameter, controller;
C) this task no longer comprises subtask, such as this task, is simple mechanical action etc.
But the present invention is not limited to this, and can comprise the termination rules of any appropriate, as long as it is complete, independently that this termination rules makes the task of the required bottom reached of Task-decomposing, or can realize, and important hierarchical structure is clear and definite getting final product.
Stop judge module 41 and can also pass to the dealing with information flow module 42 in order to further process by meeting termination rules (decomposing fully) subtask.
The dealing with information flow module 42, for required basic task information flow and the task processing requirements of the definite operation in subtasks at different levels according to receiving from stopping judge module 41.For example, the dealing with information flow module 42 can be set up system task model tree or other topological structure, means subtasks at different levels and mutual relationship thereof.
Task analysis module 43, for from the dealing with information flow module 42, receiving basic task information flow and task processing requirements thereof, and carry out task analysis for the basic task information flow, comprises and determine various control informations and the execution information relevant to task.Task analysis can comprise following at least one, and comprises the analysis sequence of any appropriate:
A) determine the back-up system relevant with Given task, comprise process system, power supply, source of the gas etc.;
B) analyze as completing Given task, need the parameter that monitors and/or monitor which means power plant's state, such as: temperature, pressure, valve location etc.;
C) if Given task can not correctly be carried out, there is which other task to substitute;
D) operation that completes this task is automatically completed or manually completed by operator by machine;
E), if automatically control, need to carry out which backup manual and control;
F) no matter automatically still manually, operator will exercise supervision to some parameter, and which these parameters are, where are placed in;
G) if which equipment manual operation (backup manual that comprises automatic control is controlled) needs, where be placed in, in which kind of state just can finish the work;
H), if operation steps needs operator to carry out the senior thought processing, need to decide control action how to carry out by which parameter;
I) identical subtask is merged;
J) subtask that will realize correlation function is combined as a kind of combined task.
Whether, when task analysis is carried out in each subtask, task analysis module 43 can also differentiate and determine that whether this task is relevant to pulpit, be control task, in order to carry out subsequent allocations.
Task distribution module 44, carry out the task distribution for the analysis result according to 43 outputs of task analysis module.Task distribution module 44 can be carried out allocating task according to the ability of operator and blind controller system.The task of for example, distributing to operator can be divided into three classes: carry out control task, to the supervision of automatic system and carry out the senior thought processing.According to factors such as the accuracy of the burden weight of this three generic task, requirement, response times, in the scope that does not exceed operator's ability, reasonably distributed.Again for example, during according to the processing power allocating task of blind controller system, at first task distribution module 44 will stipulate the functional requirement of system and equipment, then stipulate the requirement of man-machine interface according to operation task, finally determine all technical, as quantity, response time, degree of accuracy and the Human Engineering requirement etc. of system and equipment.
Distribute judge module 45, for the task of judging task distribution module 44, distribute whether meet default allocation criteria, if do not meet and indicate task distribution module 44 to redistribute the task that these do not meet allocation criteria.Default allocation criteria can comprise following at least one: according to task characteristic, determine and assign the task to operator or the allocation criteria of machine; Determine and take the remote allocation criteria of still controlling on the spot of manually controlling according to objective condition; Carry out the allocation criteria of task distribution according to the safety requirements under accident conditions; Carry out the allocation criteria of task distribution according to the information block based on function.These criterions are concrete with reference to the description to Fig. 1.If meet allocation criteria, indicate so the relevant execution terminal in main control room control task executive system to carry out respectively being assigned with separately of task.
In the course of the work, at first Task-decomposing module 40 is moved power plant general assignment and is decomposed into availability task and security task, then respectively availability task and security task respectively is decomposed into at least two subtasks.Stop judge module 41 and judge whether each subtask that in Task-decomposing module 40, decomposition obtains meets default termination rules.When existing at least one subtask not meet termination rules, these do not meet the subtask of termination rules to stop judge module 41 indication Task-decomposing modules 40 continuation decomposition, until all subtasks all meet termination rules.Simultaneously, stopping judge module 41 will meet termination rules (decomposing fully) subtask and pass to the dealing with information flow module 42.The dealing with information flow module 42 is according to required basic task information flow and the task processing requirements of the definite operation in subtasks at different levels received from stopping judge module 41.
Then, task analysis module 43 receives basic task information flow and task processing requirements thereof from the dealing with information flow module 42, and carries out task analysis for the basic task information flow, comprises and determines various control informations and the execution information relevant to task.Task distribution module 44 is carried out the task distribution according to the analysis result of task analysis module 43 outputs.Task distribution module 44 can be carried out allocating task according to the ability of operator and blind controller system.Distribute judge module 45 can judge the task of task distribution module 44 distributes whether meet default allocation criteria, if do not meet and indicate task distribution module 44 to redistribute the task that these do not meet allocation criteria.All meet allocation criteria if all tasks are distributed, task has assigned so, can indicate the relevant execution terminal in main control room control task executive system to start to carry out the task of distributing.
Fig. 5 is the structural representation of task control system in accordance with another embodiment of the present invention.In the present embodiment, task control system comprises Task-decomposing module 40, termination judge module 41, the dealing with information flow module 42, task analysis module 43, task distribution module 44, distributes judge module 45, termination rules memory module 46, termination rules module 47, allocation criteria memory module 48 and allocation criteria to be set module 49 is set.Wherein, termination rules memory module 46, termination rules arrange module 47, allocation criteria memory module 48 and allocation criteria module 49 is set are optional modules, in other embodiments of the invention, can comprise respectively these modules or its combination in any.
Termination rules memory module 46, for storing termination rules.Termination rules comprises following at least one: subtask has nothing to do with main control room or is no longer control task; Individual feature, parameter and/or controller can be controlled in subtask; Subtask no longer comprises subtask.Can the default termination rules of storage vendor in termination rules memory module 46, also can store by termination rules the termination rules that module 47 arranges is set.Termination rules memory module 46 can be integrated in and stop in judge module 41, can be also independent circuit or software/hardware module.
Termination rules arranges module 47, for from termination rules memory module 46, selecting at least one termination rules to send to, stops judge module 41 so that as basis for estimation.Termination rules arranges module 47 and also for operate the new termination rules of generation according to the user, is stored in termination rules memory module 46 or sends termination judge module 41 to as basis for estimation.
Allocation criteria memory module 48, for the storage allocation criterion.Allocation criteria comprises following at least one: according to task characteristic, determine and assign the task to operator or the allocation criteria of machine; Determine and take the remote allocation criteria of still controlling on the spot of manually controlling according to objective condition; Carry out the allocation criteria of task distribution according to the safety requirements under accident conditions; Carry out the allocation criteria of task distribution according to the information block based on function.Can the default termination rules of storage vendor in allocation criteria memory module 48, also can store by allocation criteria the termination rules that module 49 arranges is set.Allocation criteria memory module 48 can be integrated in distributes in judge module 45, can be also independent circuit or software/hardware module.
Allocation criteria arranges module 49, for from, in allocation criteria memory module 48, select at least one allocation criteria to send to and distribute judge module 45 so that as basis for estimation.Allocation criteria arranges module 49 and also for operate the new allocation criteria of generation according to the user, is stored in allocation criteria memory module 48 or sends distribution judge module 45 to as basis for estimation.
In the course of the work, at first Task-decomposing module 40 is moved power plant general assignment and is decomposed into availability task and security task, then respectively availability task and security task respectively is decomposed into at least two subtasks.Termination judge module 41 judges whether each subtask that in Task-decomposing module 40, decomposition obtains meets storage in termination rules memory module 46 or termination rules that module 47 settings are set by termination rules.When existing at least one subtask not meet termination rules, these do not meet the subtask of termination rules to stop judge module 41 indication Task-decomposing modules 40 continuation decomposition, until all subtasks all meet termination rules.Simultaneously, stopping judge module 41 will meet termination rules (decomposing fully) subtask and pass to the dealing with information flow module 42.The dealing with information flow module 42 is according to required basic task information flow and the task processing requirements of the definite operation in subtasks at different levels received from stopping judge module 41.
Then, task analysis module 43 receives basic task information flow and task processing requirements thereof from the dealing with information flow module 42, and carries out task analysis for the basic task information flow, determines various control informations and the execution information relevant to task.Task distribution module 44 is carried out the task distribution according to the analysis result of task analysis module 43 outputs.Task distribution module 44 can be carried out allocating task according to the ability of operator and blind controller system.Task distribution module 44 can also be carried out the task distribution according to one or more allocation criteria of storage in allocation criteria memory module 48.Distribute judge module 45 can judge whether the task distribution of task distribution module 44 meets storage in allocation criteria memory module 48 or other allocation criteria that the module setting is set by allocation criteria.Note, the allocation criteria of distributing judge module 45 to use with task distribution module 44 is different.Do not meet selected allocation criteria if task is distributed, distribute judge module 45 indication task distribution module 44 to redistribute the task that these do not meet allocation criteria.All meet allocation criteria if all tasks are distributed, task has assigned so, distributes judge module 45 can indicate the relevant execution terminal in main control room control task executive system to start to carry out the task of distributing.
The present invention mainly provides a kind of control method and system thereof of the nuclear power plant's operation based on nuclear power plant control room, after the task that need complete for pulpit is analyzed, determine control task, then reasonable distribution goes to carry out to operator and machine, and sets up the system task model tree by computer system, definition termination rules, rule of iteration (repeatedly decomposing), pass through genetic algorithm, finish the work and share out the work, improved efficiency and rationality that task is distributed, saved human and material resources.Not only guaranteed the task that pulpit relates to completeness and efficiency (task analysis of nuclear power station with only distribute pointer for pulpit, because the task that nuclear power station need complete is carried out and is completed by pulpit), can also concentrate reasonably and arrange back-up disk, accelerate operator's reaction velocity and emergency processing speed.
Although the present invention describes by specific embodiment, art technology operator person it should be understood that without departing from the present invention, can also carry out various conversion and be equal to alternative the present invention.In addition, for particular condition or material, can make various modifications to the present invention, and not depart from the scope of the present invention.Therefore, the present invention is not limited to disclosed specific embodiment, and should comprise the whole embodiments that fall in the claims in the present invention scope.

Claims (10)

1. the control method of nuclear power plant's operation, is characterized in that, comprising:
S1, the decomposition of executing the task, generate at least two subtasks;
S2, judge whether each described subtask meets default termination rules, if execution step S3, if not, continue execution step S1;
S3, according to the subtasks at different levels that obtain in step S2, determine basic task information flow and the task processing requirements that operation is required;
S4, described basic task information flow is carried out to task analysis, described task analysis comprises determines various control informations and the execution information relevant to task;
S5, according to the result of described task analysis, the relevant execution terminal in task execution system is distributed to in final subtask;
S6, judge that task is distributed and whether meet default allocation criteria, if not, return to step S5; If main control room is controlled the task that relevant execution terminal in described task execution system is carried out respectively distribution.
2. the control method of nuclear power plant according to claim 1 operation, is characterized in that, described termination rules comprises following at least one:
Described subtask has nothing to do with main control room or is no longer control task;
Individual feature, parameter and/or controller can be controlled in described subtask;
Described subtask no longer comprises subtask.
3. the control method of nuclear power plant according to claim 1 operation, is characterized in that, during Task-decomposing, will move general assignment and be decomposed into availability task and security task first.
4. the control method of nuclear power plant according to claim 1 operation, is characterized in that, described task analysis also comprises following at least one:
Identical subtask is merged;
The subtask of realizing correlation function is combined as to a kind of combined task.
5. the control method of nuclear power plant according to claim 1 operation, is characterized in that, described allocation criteria comprises following at least one:
Determine the allocation criteria which kind of assigns the task to and carry out terminal according to task characteristic, described execution terminal comprises operator and machine;
Determine and take the remote allocation criteria of still controlling on the spot of manually controlling according to objective condition;
Carry out the allocation criteria of task distribution according to the safety requirements under accident conditions;
Carry out the allocation criteria of task distribution according to the information block based on function.
6. the control system of nuclear power plant's operation, is characterized in that, comprising:
The Task-decomposing module, for the decomposition of executing the task, generate at least two subtasks;
Stop judge module, for judging each described subtask, whether meet default termination rules, and when not meeting, indicate described Task-decomposing module to continue to decompose described subtask;
The dealing with information flow module, determine for the subtasks at different levels according to receiving from described termination judge module basic task information flow and the task processing requirements that operation is required;
The task analysis module, for described basic task information flow is carried out to task analysis, described task analysis comprises determines various control informations and the execution information relevant to task;
The task distribution module, distribute to final subtask the relevant execution terminal of task execution system for the analysis result according to described task analysis module output;
Distribute judge module, for the task of judging described task distribution module, distribute whether meet default allocation criteria, if do not meet and indicate described task distribution module to redistribute described task; If satisfied indicate main control room to control the task that relevant execution terminal in described task execution system is carried out respectively distribution.
7. the control system of nuclear power plant according to claim 6 operation, is characterized in that, also comprises that termination rules memory module and termination rules arrange module,
Described termination rules memory module is for storing termination rules, and described termination rules comprises following at least one: described subtask has nothing to do with described main control room or is no longer control task; Individual feature, parameter and/or controller can be controlled in described subtask; Described subtask no longer comprises subtask ;described termination rules arranges module for from described termination rules memory module, selecting at least one termination rules to send described termination judge module to, also for operate the new termination rules of generation according to the user, is stored in described termination rules memory module.
8. the control system of nuclear power plant according to claim 6 operation, is characterized in that, described Task-decomposing module, when Task-decomposing first, will be moved general assignment and be decomposed into availability task and security task.
9. the control system of nuclear power plant according to claim 6 operation, is characterized in that, described task analysis module is for following at least one:
Identical subtask is merged;
The subtask of realizing correlation function is combined as to a kind of combined task.
10. the control system of nuclear power plant according to claim 6 operation, is characterized in that, also comprises that allocation criteria memory module and allocation criteria arrange module,
Described allocation criteria memory module is for the storage allocation criterion, and described allocation criteria comprises following at least one: determine the allocation criteria which kind of assigns the task to and carry out terminal according to task characteristic, described execution terminal comprises operator and machine; Determine and take the remote allocation criteria of still controlling on the spot of manually controlling according to objective condition; Carry out the allocation criteria of task distribution according to the safety requirements under accident conditions; Carry out the allocation criteria of task distribution according to the information block based on function;
Described allocation criteria arranges module for from described allocation criteria memory module, selecting at least one allocation criteria to send described distribution judge module to, also for operate the new allocation criteria of generation according to the user, is stored in described allocation criteria memory module.
CN2011100771797A 2011-03-29 2011-03-29 Control method and system thereof of nuclear power plant operation Active CN102208222B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100771797A CN102208222B (en) 2011-03-29 2011-03-29 Control method and system thereof of nuclear power plant operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100771797A CN102208222B (en) 2011-03-29 2011-03-29 Control method and system thereof of nuclear power plant operation

Publications (2)

Publication Number Publication Date
CN102208222A CN102208222A (en) 2011-10-05
CN102208222B true CN102208222B (en) 2013-09-11

Family

ID=44697012

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100771797A Active CN102208222B (en) 2011-03-29 2011-03-29 Control method and system thereof of nuclear power plant operation

Country Status (1)

Country Link
CN (1) CN102208222B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103165207B (en) * 2011-12-13 2015-12-09 中广核工程有限公司 Be applicable to sequence control method and the system of nuclear power station
CN102902591B (en) * 2012-09-04 2015-03-11 深圳市宏电技术股份有限公司 Task execution method of not long on-line terminal and not long on-line terminal
CN104240781B (en) * 2013-11-07 2017-02-15 中广核工程有限公司 Signal distribution method and signal distribution system of digital instrument control system (DCS) of nuclear power plant
CN103699441B (en) * 2013-12-05 2017-07-18 深圳先进技术研究院 The MapReduce report task executing method of task based access control granularity
CN109659053B (en) * 2018-11-01 2022-01-14 中国核电工程有限公司 Task analysis method for operation strategy development
CN110533308B (en) * 2019-08-16 2022-05-17 中国核电工程有限公司 Establishment method and availability evaluation method of process system availability database
CN111222739B (en) * 2019-10-22 2023-08-25 岭澳核电有限公司 Nuclear power station task allocation method and nuclear power station task allocation system
CN112117018B (en) * 2020-08-26 2023-12-22 中国核电工程有限公司 Comprehensive function analysis method for man-machine interface design of nuclear power plant control room

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0349166A2 (en) * 1988-06-29 1990-01-03 Westinghouse Electric Corporation A system and method for monitoring procedure execution
CN101169738A (en) * 2007-11-28 2008-04-30 电子科技大学 Self-adaptive media content creative objective assignment method
CN101645036A (en) * 2009-09-11 2010-02-10 兰雨晴 Method for automatically distributing test tasks based on capability level of test executor
CN101847222A (en) * 2009-05-06 2010-09-29 中广核工程有限公司 Human factor management system of nuclear power plant and method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0349166A2 (en) * 1988-06-29 1990-01-03 Westinghouse Electric Corporation A system and method for monitoring procedure execution
CN101169738A (en) * 2007-11-28 2008-04-30 电子科技大学 Self-adaptive media content creative objective assignment method
CN101847222A (en) * 2009-05-06 2010-09-29 中广核工程有限公司 Human factor management system of nuclear power plant and method
CN101645036A (en) * 2009-09-11 2010-02-10 兰雨晴 Method for automatically distributing test tasks based on capability level of test executor

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑明光,徐济鋆,宁忠和,陈浩.核电厂先进主控制室功能分析和功能分配.《核动力工程》.2001,第22卷(第2期),全文. *

Also Published As

Publication number Publication date
CN102208222A (en) 2011-10-05

Similar Documents

Publication Publication Date Title
CN102208222B (en) Control method and system thereof of nuclear power plant operation
Zhang et al. Adjustable robust power dispatch with combined wind-storage system and carbon capture power plants under low-carbon economy
US20060190139A1 (en) System and method for managing utility consumption
CN102130503A (en) Multi-agent system-based distribution network self-healing control method
CN108701497B (en) Multi-modular power equipment with off-grid power supply
CN108369825B (en) Multi-modular electric power installation with a dedicated electric network
CN111900729B (en) Method and device for optimizing and adjusting source-grid-load interaction daily plan of regional power grid
CN107390087A (en) Platform is supported in a kind of power network repairing operation
Wu Accelerating NCUC via binary variable-based locally ideal formulation and dynamic global cuts
CN114056161A (en) Charging pile ordered charging system and control method
Grey et al. Unified solution of security-constrained unit commitment problem using a linear programming methodology
CN109213108A (en) A kind of nuclear power station operator runs auxiliary support system and method
Jia et al. A design of human–machine interface for the two-modular high-temperature gas-cooled reactor nuclear power plant
Wang et al. Risk monitor riskangel for risk-informed applications in nuclear power plants
CN106026178B (en) A kind of more distributed generation resources self-discipline electricity-generating control methods in region and device
Qianqian et al. Operation of shared systems via a common control system in a multi-modular plant
Mazzini et al. Methodology of the source term estimation for DEMO reactor
EP2839473B1 (en) Control room for nuclear power plant
Ezzati et al. Security-constrained unit commitment based on hybrid benders decomposition and mixed integer non-linear programming
CN113515831A (en) Energy scheduling method and device, electronic equipment and storage medium
CN109606182B (en) Method for realizing bidirectional electric energy scheduling of electric automobile
CN106329731A (en) Substation model interaction and management device
van Houtte et al. A functional approach for managing ITER operations
Peschon et al. Long-term power system expansion planning by dynamic programming and production cost simulation
CN110717261B (en) Method applied to timing sequence planning design in new generation APS architecture

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 518023 No. 69 Shennan Middle Road, Shenzhen, Guangdong, Futian District

Co-patentee after: CHINA GENERAL NUCLEAR POWER Corp.

Patentee after: CHINA NUCLEAR POWER ENGINEERING Co.,Ltd.

Address before: 518023 No. 69 Shennan Middle Road, Shenzhen, Guangdong, Futian District

Co-patentee before: CHINA GUANGDONG NUCLEAR POWER GROUP Co.,Ltd.

Patentee before: CHINA NUCLEAR POWER ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder