CN102196047A - Electricity collection terminal function tester - Google Patents

Electricity collection terminal function tester Download PDF

Info

Publication number
CN102196047A
CN102196047A CN2011101207829A CN201110120782A CN102196047A CN 102196047 A CN102196047 A CN 102196047A CN 2011101207829 A CN2011101207829 A CN 2011101207829A CN 201110120782 A CN201110120782 A CN 201110120782A CN 102196047 A CN102196047 A CN 102196047A
Authority
CN
China
Prior art keywords
electricity
collection terminal
function tester
computer
centralizer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101207829A
Other languages
Chinese (zh)
Inventor
王震
张辉
张淑杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Fushun Power Supply Co of Liaoning Electric Power Co Ltd
Original Assignee
Fushun Power Supply Co of Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fushun Power Supply Co of Liaoning Electric Power Co Ltd filed Critical Fushun Power Supply Co of Liaoning Electric Power Co Ltd
Priority to CN2011101207829A priority Critical patent/CN102196047A/en
Publication of CN102196047A publication Critical patent/CN102196047A/en
Priority to PCT/CN2011/001902 priority patent/WO2012151730A1/en
Priority to AU2011367734A priority patent/AU2011367734B2/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q9/00Arrangements in telecontrol or telemetry systems for selectively calling a substation from a main station, in which substation desired apparatus is selected for applying a control signal thereto or for obtaining measured values therefrom
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q2209/00Arrangements in telecontrol or telemetry systems
    • H04Q2209/30Arrangements in telecontrol or telemetry systems using a wired architecture
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q2209/00Arrangements in telecontrol or telemetry systems
    • H04Q2209/60Arrangements in telecontrol or telemetry systems for transmitting utility meters data, i.e. transmission of data from the reader of the utility meter
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q2209/00Arrangements in telecontrol or telemetry systems
    • H04Q2209/80Arrangements in the sub-station, i.e. sensing device
    • H04Q2209/88Providing power supply at the sub-station

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Telephonic Communication Services (AREA)
  • Arrangements For Transmission Of Measured Signals (AREA)

Abstract

The invention relates to an electricity collection terminal function tester which is especially suitable for the electricity collection and maintenance of a power system. The electricity collection terminal function tester is structurally characterized in that a power supply is connected with an electric shock protector; an AC (alternating current) converter, a switch, a computer, a printer and an electricity centralizer are respectively connected with the electric shock protector; both the AC converter and the electricity centralizer are connected with a watt-hour meter protocol simulator; the switch is respectively connected with the electricity centralizer and the computer; and the electricity centralizer and the computer are respectively connected with a telephone set. According to the communication protocol specification of the electricity collection terminal and the support condition of a testing terminal to a plurality of communication manners and communication protocols, the electricity collection terminal function tester can be used for verifying the correctness of the flow, analyzing and processing the feedback information of the collection terminal to form an integral terminal testing report, assisting test operators to test the function of the electricity collection terminal and also has a certain fault analysis effect.

Description

Electric quantity acquisition termination function tester
Technical field
The present invention relates to a kind of functional tester, relate in particular to a kind of electric quantity acquisition termination function tester, be particularly useful for electric power system electric quantity acquisition and maintenance.
Background technology
The electric quantity acquisition terminal is the basic equipment of electrical energy metering automated system, in the electrical energy metering acquisition system, bear the effect of forming a connecting link, be responsible for gathering, handle, store the various data on the ammeter, adopt various means of communications, stipulations by agreement provide data to main website, and it is to guarantee that electric quantity data is complete, basic accurately.Along with the expansion of electric energy metering system scale, need to insert a plurality of acquisition terminal equipment and kilowatt-hour meter usually.Though the stipulations of each device fabrication producer all support DL/T645 and IEC60870 ?5 ?102 stipulations because these stipulations are a framework, concrete details is not stipulated; And in specific implementation process, each implements producer and Utilities Electric Co. expands it respectively, causes differing greatly on the realization details, and stipulations also often have ambiguity on understanding, cause each producer's stipulations incompatible, often insert electric quantity collector and bring very big difficulty to kilowatt-hour meter.
Summary of the invention
The present invention is directed to above-mentioned problems of the prior art, a kind of electric quantity acquisition termination function tester is provided, and it is incompatible to have solved in the prior art stipulations, is difficult to multiple kilowatt-hour meter is inserted the problem of electric quantity collector, and the present invention improved operating efficiency, and is easy to maintenance.
Technical scheme of the present invention is as follows:
Power supply links to each other with earth leakage protector, and earth leakage protector links to each other with AC converter, switch, computer, printer and electric weight concentrator respectively; AC converter all links to each other with kilowatt-hour meter stipulations simulator with the electric weight concentrator; Switch links to each other with computer with the electric weight concentrator respectively; Electric weight concentrator and computer are connected with telephone set respectively.
Described switch is the network switch.
Described electric weight concentrator links to each other with kilowatt-hour meter stipulations simulator by 485 interfaces.
Described power supply is 220 volts of AC power.
Advantageous effect of the present invention is as follows:
1, the present invention is according to generated energy acquisition terminal communication stipulations standard, the test terminal is to the support situation of multiple communication mode and communication protocol, the correctness of checking flow process, and the feedback information of acquisition terminal carried out analyzing and processing, form complete terminal test report, help the tester that the function of generated energy acquisition terminal is tested and assessed, also have certain accident analysis effect simultaneously.
2, the present invention carries out omnibearing function, flow testing analysis to terminal, in early days under the simulated environment for terminal provides detection means, in time find terminal defective, fault, thereby play the effect of shortening the engineering construction time and using manpower and material resources sparingly.
3, powerful, flexible operation, attended operation are convenient, are applicable to electric power system electric power system electric quantity acquisition and maintenance, have the prospect of using widely.
Description of drawings
Fig. 1 is a structural representation block diagram of the present invention.
Embodiment
The present invention in conjunction with specific embodiments, is described in detail as follows with reference to accompanying drawing.
Embodiment
220 volts of AC power link to each other with earth leakage protector, and earth leakage protector links to each other with AC converter, the network switch, notebook computer, printer and electric weight concentrator respectively; AC converter all links to each other with kilowatt-hour meter stipulations simulator with the electric weight concentrator, and the electric weight concentrator links to each other with kilowatt-hour meter stipulations simulator by 485 interfaces; The network switch links to each other with notebook computer with the electric weight concentrator respectively; Electric weight concentrator and notebook computer are connected with telephone set respectively.
Serial ports special line, dial telephone, TCP/IP network are supported to adopt in the test terminal.The invention provides the various communication interfaces mode, realize the real-time Transmission or the timing extraction stored record of Monitoring Data, Industrial Ethernet interface and the communication of distant place quality of power supply administrative center can be passed through, also the S232C/RS485 interface can be passed through, with GPRS mode and distant place communication.
The present invention can monitor the communication packet of uplink and downlink in real time, and can preserve, print message
Data in the uplink message are resolved, and can preserve, print.And the explain information of outgoing message.
The essential information (testing time, ERTU parameter, communications parameter) of this test of statistics and test command were carried out information (command type and parameter, execution result, error statistics etc.) after the present invention supported to test and finishes, the output test report provides test report output and printing function.
The present invention is except that having the monitoring of kilowatt-hour meter and collector and on the spot the writing function, can also distant place electric quantity acquisition center communication, with realize real-time power quality data on send, accept a distant place calling, parameter etc. is set.In the communication interface configuration of device, 100M is provided Ethernet interface, support ICP/IP protocol (comprising File Transfer Protocol).Except that the ether network interface, conventional RS232 and RS485 interface also is provided, can GPRS mode and distant place communication.
Protection scope of the present invention is as the criterion with claim, not limited by specific embodiment.

Claims (4)

1. electric quantity acquisition termination function tester is characterized in that power supply links to each other with earth leakage protector, and earth leakage protector links to each other with AC converter, switch, computer, printer and electric weight concentrator respectively; AC converter all links to each other with kilowatt-hour meter stipulations simulator with the electric weight concentrator; Switch links to each other with computer with the electric weight concentrator respectively; Electric weight concentrator and computer are connected with telephone set respectively.
2. electric quantity acquisition termination function tester according to claim 1 is characterized in that described switch is the network switch.
3. electric quantity acquisition termination function tester according to claim 1 is characterized in that described electric weight concentrator links to each other with kilowatt-hour meter stipulations simulator by 485 interfaces.
4. electric quantity acquisition termination function tester according to claim 1 is characterized in that described power supply is 220 volts of AC power.
CN2011101207829A 2011-05-11 2011-05-11 Electricity collection terminal function tester Pending CN102196047A (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN2011101207829A CN102196047A (en) 2011-05-11 2011-05-11 Electricity collection terminal function tester
PCT/CN2011/001902 WO2012151730A1 (en) 2011-05-11 2011-11-14 Electric quantity collection terminal function tester
AU2011367734A AU2011367734B2 (en) 2011-05-11 2011-11-14 Electric quantity collection terminal function tester

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101207829A CN102196047A (en) 2011-05-11 2011-05-11 Electricity collection terminal function tester

Publications (1)

Publication Number Publication Date
CN102196047A true CN102196047A (en) 2011-09-21

Family

ID=44603413

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101207829A Pending CN102196047A (en) 2011-05-11 2011-05-11 Electricity collection terminal function tester

Country Status (3)

Country Link
CN (1) CN102196047A (en)
AU (1) AU2011367734B2 (en)
WO (1) WO2012151730A1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012151730A1 (en) * 2011-05-11 2012-11-15 辽宁省电力有限公司 Electric quantity collection terminal function tester
CN103311830A (en) * 2013-05-30 2013-09-18 国家电网公司 Substation automation system debugging device
CN104407239A (en) * 2014-10-23 2015-03-11 国网重庆市电力公司电力科学研究院 Electricity information acquisition terminal modular electromagnetic compatibility integrated test apparatus
CN104683150A (en) * 2015-02-10 2015-06-03 河北省电力勘测设计研究院 1,000 kV process-level network structure for ultrahigh-voltage transformer substation
CN105510867A (en) * 2015-11-27 2016-04-20 中国南方电网有限责任公司超高压输电公司 Power plant and substation electric quantity acquisition device-based testing system and method
CN109462524A (en) * 2018-12-11 2019-03-12 国网湖北省电力有限公司 A kind of intelligent power acquisition terminal detection device and detection method
CN110672940A (en) * 2019-09-20 2020-01-10 扬州市职业大学(扬州市广播电视大学) Distribution automation integration testing arrangement
CN110763295A (en) * 2019-11-08 2020-02-07 杭州先锋电子技术股份有限公司 Remote intelligent collector and working method thereof

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103529289B (en) * 2013-11-06 2016-09-28 江苏大唐国际吕四港发电有限责任公司 Use the coulomb collection system of communication manager
CN103809151B (en) * 2014-02-19 2016-05-04 青岛乾程科技股份有限公司 A kind of multi-epitope parameter Lookup protocol and checkout gear
CN105206035A (en) * 2015-09-21 2015-12-30 国网上海市电力公司 Automatic detecting system and method for collection terminal functions

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101231320A (en) * 2008-01-31 2008-07-30 湖北省电力试验研究院 Undervoltage collection copy system detecting device based on virtual electric energy meter module
CN101546472A (en) * 2009-04-29 2009-09-30 安徽省电力公司芜湖供电公司 Integrated universal simulation test system and implement method for electric network scheduling and electric quantity collection
CN201440156U (en) * 2009-07-02 2010-04-21 北京市电力公司 Testing device for electric energy collecting terminal
CN202066957U (en) * 2011-05-11 2011-12-07 辽宁省电力有限公司抚顺供电公司 Function tester for electric quantity collection terminal

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2884656Y (en) * 2006-01-25 2007-03-28 福建省电力试验研究院 Simulator for testing power loading management terminal communication
CN100495041C (en) * 2008-06-12 2009-06-03 江苏中电科技有限公司 Remote automatic centralized control monitoring meter reading system
CN102196047A (en) * 2011-05-11 2011-09-21 辽宁省电力有限公司抚顺供电公司 Electricity collection terminal function tester

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101231320A (en) * 2008-01-31 2008-07-30 湖北省电力试验研究院 Undervoltage collection copy system detecting device based on virtual electric energy meter module
CN101546472A (en) * 2009-04-29 2009-09-30 安徽省电力公司芜湖供电公司 Integrated universal simulation test system and implement method for electric network scheduling and electric quantity collection
CN201440156U (en) * 2009-07-02 2010-04-21 北京市电力公司 Testing device for electric energy collecting terminal
CN202066957U (en) * 2011-05-11 2011-12-07 辽宁省电力有限公司抚顺供电公司 Function tester for electric quantity collection terminal

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周孔均: "电能表与采集终端通信测试系统的设计", 《电测与仪表》 *
葛洪健,等: "电能计量采集装置通信规约测试平台的研究与应用", 《中国电力教育》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012151730A1 (en) * 2011-05-11 2012-11-15 辽宁省电力有限公司 Electric quantity collection terminal function tester
CN103311830A (en) * 2013-05-30 2013-09-18 国家电网公司 Substation automation system debugging device
CN103311830B (en) * 2013-05-30 2016-07-06 国家电网公司 Electric substation automation system debugging apparatus
CN104407239A (en) * 2014-10-23 2015-03-11 国网重庆市电力公司电力科学研究院 Electricity information acquisition terminal modular electromagnetic compatibility integrated test apparatus
CN104407239B (en) * 2014-10-23 2017-07-04 国网重庆市电力公司电力科学研究院 A kind of power information acquisition terminal modular electromagnetic compatibility comprehensive test device
CN104683150A (en) * 2015-02-10 2015-06-03 河北省电力勘测设计研究院 1,000 kV process-level network structure for ultrahigh-voltage transformer substation
CN105510867A (en) * 2015-11-27 2016-04-20 中国南方电网有限责任公司超高压输电公司 Power plant and substation electric quantity acquisition device-based testing system and method
CN109462524A (en) * 2018-12-11 2019-03-12 国网湖北省电力有限公司 A kind of intelligent power acquisition terminal detection device and detection method
CN110672940A (en) * 2019-09-20 2020-01-10 扬州市职业大学(扬州市广播电视大学) Distribution automation integration testing arrangement
CN110672940B (en) * 2019-09-20 2022-03-25 扬州市职业大学(扬州市广播电视大学) Distribution automation integration testing arrangement
CN110763295A (en) * 2019-11-08 2020-02-07 杭州先锋电子技术股份有限公司 Remote intelligent collector and working method thereof
CN110763295B (en) * 2019-11-08 2021-04-02 杭州先锋电子技术股份有限公司 Remote intelligent collector and working method thereof

Also Published As

Publication number Publication date
WO2012151730A1 (en) 2012-11-15
AU2011367734B2 (en) 2016-01-28
AU2011367734A1 (en) 2013-11-28

Similar Documents

Publication Publication Date Title
CN102196047A (en) Electricity collection terminal function tester
CN102361346B (en) Master station full-digital scene testing method of power distribution automation system
CN106556765B (en) The test method and RTDS emulator of distributed distribution automation system
CN204515048U (en) Digital transformer substation intelligent tester
CN103076520A (en) Dynamic analogue simulation detection platform and analogue simulation method for secondary system of intelligent substation
CN203069709U (en) Intelligent transformer station relay protection device detector based on DDRTS
CN102118282A (en) Communication protocol consistency detection method and system
CN103761854A (en) Testing and debugging system for low-voltage meter concentrated reading district
CN107832183B (en) Service system-based acquisition and maintenance integrated training and checking device
CN103107914A (en) Detection method and detection system for remote power acquisition terminal
CN102724006A (en) Rapid self-checking system and method of satellite comprehensive testing system
CN105548948A (en) Device and method for testing digitalization electric energy metering system
CN103344883A (en) Simulation testing device and method achieving cable fault simulation through wireless network
CN110492907A (en) The method and device of archives is established for ammeter
CN105388416A (en) Intelligent substation relay protection remote test system
CN110932406B (en) Remote signaling information checking method and device for intelligent substation scheduling master station
CN101814964A (en) Simulation system of carrier concentrator
CN104267283A (en) Platform and method for testing process layer to spacer layer of digital substation
CN114390374B (en) Broadband micropower multi-network comprehensive test system of electricity consumption information acquisition system
CN101799504B (en) Method for testing influence of distortion data on relay protection device
CN105785170A (en) Intelligent transformer substation oriented data flow panoramic displaying device and intelligent transformer substation oriented data flow panoramic displaying method
CN203909606U (en) Test system for distribution automation system
CN104660662A (en) Advanced meter reading infrastructure field surveying system
CN108093039B (en) Method for processing sleeping electric meter based on national network Q/GDW3761 protocol
CN202066957U (en) Function tester for electric quantity collection terminal

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20120919

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20120919

Address after: 113008 West Xinfu Road, Liaoning, Fushun, No. 13

Applicant after: Fushun Power Supply Company of Liaoning Electric Power Co., Ltd.

Applicant after: State Grid Corporation of China

Address before: 113008 West Xinfu Road, Liaoning, Fushun, No. 13

Applicant before: Fushun Power Supply Company of Liaoning Electric Power Co., Ltd.

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20110921