CN102189388A - Manufacture method of door module of integral vehicle main model checking fixture - Google Patents
Manufacture method of door module of integral vehicle main model checking fixture Download PDFInfo
- Publication number
- CN102189388A CN102189388A CN2011100706976A CN201110070697A CN102189388A CN 102189388 A CN102189388 A CN 102189388A CN 2011100706976 A CN2011100706976 A CN 2011100706976A CN 201110070697 A CN201110070697 A CN 201110070697A CN 102189388 A CN102189388 A CN 102189388A
- Authority
- CN
- China
- Prior art keywords
- workpiece
- door module
- car load
- master cast
- load master
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Automobile Manufacture Line, Endless Track Vehicle, Trailer (AREA)
Abstract
The invention discloses a manufacture method of a door module of an integral vehicle main model checking fixture. The manufacturing method approximately comprises the following steps of: carrying out rough machining on an aluminum alloy blank, then carrying out aging treatment, renovating a corresponding machining reference platform, semifinishing, then carrying out aging treatment, finishing, measuring by using a three-coordinate measuring machine, renovating the corresponding machining reference platform, secondarily finishing, and assembling a workpiece. The method has the advantages of effectively eliminating precision influence of machining deformation to final products through multiple aging treatment and renovation on the machining reference platform, ensuring that the final product reaches the requirement for strength by using the aluminum alloy material with reliable strength, and manufacturing the door module of the integral vehicle main model checking fixture according with requirements for strength and precision.
Description
Technical field
The present invention relates to a kind of manufacture method of car load master cast cubing, be specifically related to a kind of manufacture method of car load master cast cubing door module.
Background technology
The car load master cast is test stage and a quality control tools indispensable in the Hyundai Motor industry, because the instrument that the conduct of car load master cast cubing itself detects, it need reach the requirement that accuracy is good, intensity is high, to adapt to concrete applied environment.In the car load master cast, door module is because its design feature and institute's application site particularity, need have good structural strength and precision as assurance, but in the existing manufacturing processing method, often the problem of machining deformation amount is paid attention to deficiency, or do not adopt effective technical scheme but to address this problem, cause the intensity and the precision of final products can not reach the index that requires in advance, form defect ware, waste resource and manpower, production efficiency is low.
Summary of the invention
Be to solve the deficiencies in the prior art, the object of the present invention is to provide a kind ofly to have the manufacture method of the car load master cast cubing door module of satisfactory hardness and precision by the car load master cast cubing door module that makes that successfully manages the machining deformation problem.
In order to realize above-mentioned target, the present invention adopts following technical scheme:
The manufacture method of car load master cast cubing door module is characterized in that, comprises the steps:
A, the aluminium alloy blank is carried out roughing, form the rough-wrought product of the workpiece of forming car load master cast cubing door module, and the rough-wrought product of above-mentioned workpiece is carried out Ageing Treatment;
B, on the rough-wrought product of above-mentioned workpiece the trimming corresponding machining benchmark platform;
C, the rough-wrought product of above-mentioned workpiece is carried out semifinishing, the control processing capacity keeps certain allowance, forms the semifinishing product of workpiece;
D, the semifinishing product of workpiece is carried out Ageing Treatment;
E, the semifinishing product of workpiece is carried out the intensely processed products that fine finishining forms workpiece, and keep certain allowance;
F, utilize three coordinate measuring machine to measure to the profile and the machining benchmark platform of the intensely processed products of workpiece;
G, according to the concrete condition of the measurement result among the step f, carry out secondary fine finishining, profile is met the requirements, form the workpiece of required composition car load master cast cubing door module;
The workpiece of h, the above-mentioned composition car load master cast cubing door module of assembling forms car load master cast cubing door module.
The manufacture method of aforesaid car load master cast cubing door module is characterized in that, the workpiece of above-mentioned composition car load master cast cubing door module comprises door skin and inner plate of car door.
The manufacture method of aforesaid car load master cast cubing door module is characterized in that, above-mentioned steps a, b, c, g all use the CNC machining center to the processing that hockets of the tow sides of workpiece.
The manufacture method of aforesaid car load master cast cubing door module, it is characterized in that, in above-mentioned steps a, roughing and Ageing Treatment hocket at twice, carry out double-edged roughing for the first time, and 5 millimeters surpluses are respectively stayed on the two sides, carried out natural aging treatment then 168 hours, carry out the double-edged roughing second time after the natural aging treatment, 3 millimeters surpluses are respectively stayed on the two sides, carry out artificial aging then and handle; Carry out in the roughing at the tow sides to above-mentioned aluminium alloy blank, tow sides are all reserved the position of machining benchmark platform, in addition, also will remain for the locating platform that lifts and support in advance.
The manufacture method of aforesaid car load master cast cubing door module is characterized in that, during semifinishing, the locating platform that is used to lift and support continues to keep, and controls the processing capacity of every cutter during processing in carrying out step c, and tow sides all keep 1 millimeter surplus.
The manufacture method of aforesaid car load master cast cubing door module is characterized in that the Ageing Treatment among the above-mentioned steps d is the natrual ageing in thermostatic chamber, and the time of natrual ageing is 72 hours, and the temperature range of thermostatic chamber temperature is 20 to 25 degrees centigrade.
The manufacture method of aforesaid car load master cast cubing door module, it is characterized in that, in above-mentioned steps e, carry out the preceding machining benchmark platform finishing of fine finishining earlier, remove again and be used to the locating platform that lifts and support, carry out fine finishining, when carrying out fine finishining, remove the machining benchmark platform machining benchmark is transformed on the measuring basis hole that workpiece itself design has, the control processing capacity finally keeps 0.3 millimeter surplus.
The manufacture method of aforesaid car load master cast cubing door module, it is characterized in that, in above-mentioned steps g, if it is even to detect surplus among the step f, then the wherein one side of the semifinishing product of workpiece is carried out being refined to the second time desired profile, no longer keep surplus and the locating platform that is used to lift and support, and replace locating platform at the above-mentioned original position adhering resin material that is used to the locating platform that lifts and support that has been removed, the resin material of bonding is processed made it identical with the machining benchmark podium level; If it is inhomogeneous to detect surplus among the step f, then according to concrete error condition, 0.3 millimeter the surplus biasing allowance that utilizes reverse side to reserve carries out adequate compensation, carries out secondary fine finishining again.
The manufacture method of aforesaid car load master cast cubing door module is characterized in that, the material that the aluminium alloy blank uses is 6 series alloys materials.
Usefulness of the present invention is: the Ageing Treatment by repeatedly and to the trimming of machining benchmark platform, effectively eliminated the precision influence of machining deformation to final products, the while working strength is aluminum alloy materials reliably, make final products can reach requirement of strength, produce the satisfactory car load master cast of hardness and precision cubing door module.
Description of drawings
Fig. 1 is the schematic block diagram of the step of manufacturing flow process of car load master cast cubing door module of the present invention.
The specific embodiment
Below in conjunction with the drawings and specific embodiments the present invention is done concrete introduction.
Fig. 1 is the schematic block diagram of the step of manufacturing flow process of car load master cast cubing door module of the present invention.
With reference to Fig. 1, the manufacture method of car load master cast cubing door module of the present invention mainly comprises following step:
Step a: the aluminium alloy blank is carried out roughing, form the rough-wrought product of the workpiece of forming car load master cast cubing door module, and the rough-wrought product of above-mentioned workpiece is carried out Ageing Treatment.So-called roughing is exactly on the basis that keeps certain allowance, process according in advance design primary structure on the aluminium alloy blank with the CNC machining center in advance workpiece, and process the platform structure that being used to of needing in the subsequent step locate, support, lift accordingly, what need explanation here is that the platform structure that is used for locating, support, lifting is not exist at final product, but only be for the follow-up easy to process and intermediate structure of design, removal that can be in good time in follow-up procedure of processing.
As preferred version, the workpiece of the composition car load master cast cubing door module in of the present invention comprises door skin and car internal hilar plate.Below do not have specified otherwise, the workpiece of indication all describes as embodiment with door skin and car internal hilar plate.
In addition, below to the processing of workpiece, be meant and use the CNC machining center the processing that hockets of the tow sides of workpiece.
As a kind of preferred version, roughing and Ageing Treatment among the step a hocket at twice, carry out for the first time double-edged roughing, 5 millimeters surpluses are respectively stayed on the two sides, carried out natural aging treatment then 168 hours, carry out the double-edged roughing second time after the natural aging treatment, 3 millimeters surpluses are respectively stayed on the two sides, carry out artificial aging then and handle; Carry out in the roughing at the tow sides to the aluminium alloy blank, tow sides are all reserved the position of machining benchmark platform, and in addition, the locating platform that is used to lift and support also will be reserved.Described machining benchmark platform is meant the platform of the lathe tool processing dead-center position that is used for definite CNC machining center, and described locating platform is to be used for the follow-up man-hour that adds, in order not influence the structure of workpiece itself, some is suitable for the sufficient platform structure of surplus that stressed part processes at workpiece.
Artificial aging among the step a adopts following technical scheme: in temperature is that insulation was placed 6-10 hour in 180 degrees centigrade of (± 5 degrees centigrade) aging furnaces.
Step b: the corresponding machining benchmark platform of trimming on the rough-wrought product of workpiece.Because during the artificial aging in step a is handled, because the stress that roughing produces obtains discharging, and then processing deformation makes moderate progress, and the machining benchmark platform of processing among the step a may change, and therefore needs the corresponding machining benchmark platform of trimming.
Step c: the rough-wrought product to workpiece carries out semifinishing, and the control processing capacity keeps certain allowance, forms the semifinishing product of workpiece.So-called semifinishing is meant and further reduces allowance on rough machined basis, still keeps such as intermediate structures such as locating platforms simultaneously.
As a kind of preferred version, during semifinishing, the locating platform that is used to lift and support continues to keep, and controls the processing capacity of every cutter during processing in carrying out step c, and tow sides all keep 1 millimeter surplus.
Steps d: the semifinishing product to workpiece carries out Ageing Treatment.
As a kind of preferred version, the Ageing Treatment in the steps d is the natrual ageing in thermostatic chamber, and the time of natrual ageing is 72 hours, and the temperature range of thermostatic chamber temperature is 20 to 25 degrees centigrade, and as a kind of preferred version, temperature can be selected 22 degrees centigrade.
Step e: the semifinishing product to workpiece carries out the intensely processed products that fine finishining forms workpiece, and keeps certain allowance.
As preferred version, in step e, carry out the preceding machining benchmark platform finishing of fine finishining earlier, remove again and be used to the locating platform that lifts and support, carry out fine finishining, when carrying out fine finishining, remove the machining benchmark platform machining benchmark is transformed on the measuring basis hole that workpiece design itself has, control processing capacity, finally keep 0.3 millimeter surplus.
Herein, why carry out again the machining benchmark platform is revised, its reason as hereinbefore, promptly Zhi Qian step has been carried out Ageing Treatment, variation has taken place in the machining benchmark platform, in order to guarantee the accurately machined precision among the step e, so repair the machining benchmark platform again.
Step f: profile and machining benchmark platform to the intensely processed products of workpiece utilize three coordinate measuring machine (Coordinate Measuring Machining is abbreviated as CMM) to measure.
Step g: according to the concrete condition of the measurement result among the step f, carry out secondary fine finishining, profile is met the requirements, form the workpiece of required composition car load master cast cubing door module.
Allowance and intermediate structure are promptly no longer preserved in so-called secondary fine finishining, directly are machined to profile according to designing requirement.
In step g, if it is even to detect surplus among the step f, then the wherein one side of the semifinishing product of workpiece is carried out being refined to second time desired profile, no longer keep surplus and be used to the locating platform that lifts and support; For adding, reverse side still has the part that can support or lift man-hour, replace locating platform at the above-mentioned original position adhering resin material that is used to the locating platform that lifts and support that has been removed, the resin material of bonding is processed made it identical with the machining benchmark level.If it is inhomogeneous to detect surplus among the step f, then according to concrete error condition, 0.3 millimeter the surplus biasing allowance that utilizes reverse side to reserve carries out adequate compensation, carries out secondary fine finishining again.
After finishing final secondary fine finishining, remove the resin material that replaces locating platform, finish workpiece and finally process, form final products.Promptly meet door skin and inner plate of car door that precision and hardness require as previously mentioned.
Step h: assemble the workpiece of above-mentioned composition car load master cast cubing door module, form car load master cast cubing door module.
The workpiece that is about to final molding in the step g is assembled into whole car owner's model cubing door module, particularly is exactly that door skin and inner plate of car door assembling are become unified car load master cast cubing door module with regard to aforesaid preferred version, finishes whole manufacturing process.
In addition, as preferred version, the material that the aluminium alloy blank uses is that the material that workpiece uses is 6 series alloys materials.6 series alloys materials draw intensity can reach 265 MPas (Mpa), and the aluminium alloy tensile strength of technology use before has only 205 MPas (Mpa).
The foregoing description does not limit the present invention in any form, and all employings are equal to the technical scheme that mode obtained of replacement or equivalent transformation, all drop in protection scope of the present invention.
Claims (9)
1. the manufacture method of car load master cast cubing door module is characterized in that, comprises the steps:
A, the aluminium alloy blank is carried out roughing, form the rough-wrought product of the workpiece of forming car load master cast cubing door module, and the rough-wrought product of above-mentioned workpiece is carried out Ageing Treatment;
B, on the rough-wrought product of above-mentioned workpiece the trimming corresponding machining benchmark platform;
C, the rough-wrought product of above-mentioned workpiece is carried out semifinishing, the control processing capacity keeps certain allowance, forms the semifinishing product of workpiece;
D, the semifinishing product of workpiece is carried out Ageing Treatment;
E, the semifinishing product of workpiece is carried out the intensely processed products that fine finishining forms workpiece, and keep certain allowance;
F, utilize three coordinate measuring machine to measure to the profile and the machining benchmark platform of the intensely processed products of workpiece;
G, according to the concrete condition of the measurement result among the step f, carry out secondary fine finishining, profile is met the requirements, form the workpiece of required composition car load master cast cubing door module;
The workpiece of h, the above-mentioned composition car load master cast cubing door module of assembling forms car load master cast cubing door module.
2. the manufacture method of car load master cast cubing door module according to claim 1 is characterized in that, the workpiece of above-mentioned composition car load master cast cubing door module comprises door skin and inner plate of car door.
3. the manufacture method of car load master cast cubing door module according to claim 2 is characterized in that, above-mentioned steps a, b, c, g all use the CNC machining center to the processing that hockets of the tow sides of workpiece.
4. the manufacture method of car load master cast cubing door module according to claim 3, it is characterized in that, in above-mentioned steps a, roughing and Ageing Treatment hocket at twice, carry out double-edged roughing for the first time, and 5 millimeters surpluses are respectively stayed on the two sides, carried out natural aging treatment then 168 hours, carry out the double-edged roughing second time after the natural aging treatment, 3 millimeters surpluses are respectively stayed on the two sides, carry out artificial aging then and handle; Carry out in the roughing at the tow sides to above-mentioned aluminium alloy blank, tow sides are all reserved the position of machining benchmark platform, in addition, also will remain for the locating platform that lifts and support in advance.
5. the manufacture method of car load master cast cubing door module according to claim 4, it is characterized in that during semifinishing, the locating platform that is used to lift and support continues to keep in carrying out step c, control the processing capacity of every cutter during processing, tow sides all keep 1 millimeter surplus.
6. the manufacture method of car load master cast cubing door module according to claim 5, it is characterized in that, Ageing Treatment among the above-mentioned steps d is the natrual ageing in thermostatic chamber, and the time of natrual ageing is 72 hours, and the temperature range of thermostatic chamber temperature is 20 to 25 degrees centigrade.
7. the manufacture method of car load master cast cubing door module according to claim 6, it is characterized in that, in above-mentioned steps e, carry out the preceding machining benchmark platform finishing of fine finishining earlier, remove again and be used to the locating platform that lifts and support, carry out fine finishining, when carrying out fine finishining, remove the machining benchmark platform machining benchmark is transformed on the measuring basis hole that workpiece itself design has, the control processing capacity finally keeps 0.3 millimeter surplus.
8. the manufacture method of car load master cast cubing door module according to claim 7, it is characterized in that, in above-mentioned steps g, if it is even to detect surplus among the step f, then the wherein one side of the semifinishing product of workpiece is carried out being refined to the second time desired profile, no longer keep surplus and the locating platform that is used to lift and support, and replace locating platform at the above-mentioned original position adhering resin material that is used to the locating platform that lifts and support that has been removed, the resin material of bonding is processed made it identical with the machining benchmark podium level; If it is inhomogeneous to detect surplus among the step f, then according to concrete error condition, 0.3 millimeter the surplus biasing allowance that utilizes reverse side to reserve carries out adequate compensation, carries out secondary fine finishining again.
9. according to the manufacture method of the described car load master cast of claim 1 to 8 cubing door module, it is characterized in that the material that the aluminium alloy blank uses is 6 series alloys materials.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110070697 CN102189388B (en) | 2011-03-23 | 2011-03-23 | Manufacture method of door module of integral vehicle main model checking fixture |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110070697 CN102189388B (en) | 2011-03-23 | 2011-03-23 | Manufacture method of door module of integral vehicle main model checking fixture |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102189388A true CN102189388A (en) | 2011-09-21 |
CN102189388B CN102189388B (en) | 2013-02-06 |
Family
ID=44598727
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110070697 Expired - Fee Related CN102189388B (en) | 2011-03-23 | 2011-03-23 | Manufacture method of door module of integral vehicle main model checking fixture |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102189388B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102699647A (en) * | 2012-05-17 | 2012-10-03 | 宁波富信模胚有限公司 | Method for processing bi-color mold blank |
CN104374247A (en) * | 2014-10-20 | 2015-02-25 | 湖南湖大艾盛汽车技术开发有限公司 | Modularization detection device for automobile engine cover |
CN107030458A (en) * | 2017-06-02 | 2017-08-11 | 苏州市零点精密模具有限公司 | A kind of processing method of shearing die |
CN107122525A (en) * | 2017-03-31 | 2017-09-01 | 上汽通用五菱汽车股份有限公司 | Inner plate of car door three-dimensional modeling method |
CN107414437A (en) * | 2017-08-18 | 2017-12-01 | 苏州沃思诺自动化科技有限公司 | A kind of folded loft cutting process method |
CN110026739A (en) * | 2019-04-16 | 2019-07-19 | 贵州航天风华精密设备有限公司 | A kind of processing method of the aluminium alloy thin-walled discoid part of T4 |
CN112008341A (en) * | 2020-08-28 | 2020-12-01 | 成都凯迪精工科技有限责任公司 | Method for improving machining quality of wing-shaped part |
CN113070651A (en) * | 2021-03-26 | 2021-07-06 | 中国船舶重工集团公司第七二五研究所 | Machining process method of large titanium and titanium alloy curved surface component |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101476539A (en) * | 2008-12-05 | 2009-07-08 | 武汉重工铸锻有限责任公司 | Manufacturing process of wind-power principal shaft product and its special integral forming device |
CN201514175U (en) * | 2009-04-08 | 2010-06-23 | 上海通用汽车有限公司 | Vehicle door module of total vehicle interior trim detecting device |
CN101856784A (en) * | 2010-06-01 | 2010-10-13 | 辽宁忠旺集团有限公司 | Machining process of train body profile mold |
-
2011
- 2011-03-23 CN CN 201110070697 patent/CN102189388B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101476539A (en) * | 2008-12-05 | 2009-07-08 | 武汉重工铸锻有限责任公司 | Manufacturing process of wind-power principal shaft product and its special integral forming device |
CN201514175U (en) * | 2009-04-08 | 2010-06-23 | 上海通用汽车有限公司 | Vehicle door module of total vehicle interior trim detecting device |
CN101856784A (en) * | 2010-06-01 | 2010-10-13 | 辽宁忠旺集团有限公司 | Machining process of train body profile mold |
Non-Patent Citations (1)
Title |
---|
孔啸等: "面向汽车匹配主模型检具的大型薄壁件制造工艺", 《模具工业》, vol. 35, no. 7, 31 December 2009 (2009-12-31), pages 59 - 64 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102699647A (en) * | 2012-05-17 | 2012-10-03 | 宁波富信模胚有限公司 | Method for processing bi-color mold blank |
CN102699647B (en) * | 2012-05-17 | 2014-07-16 | 宁波富信模胚有限公司 | Method for processing bi-color mold blank |
CN104374247A (en) * | 2014-10-20 | 2015-02-25 | 湖南湖大艾盛汽车技术开发有限公司 | Modularization detection device for automobile engine cover |
CN107122525A (en) * | 2017-03-31 | 2017-09-01 | 上汽通用五菱汽车股份有限公司 | Inner plate of car door three-dimensional modeling method |
CN107030458A (en) * | 2017-06-02 | 2017-08-11 | 苏州市零点精密模具有限公司 | A kind of processing method of shearing die |
CN107414437A (en) * | 2017-08-18 | 2017-12-01 | 苏州沃思诺自动化科技有限公司 | A kind of folded loft cutting process method |
CN110026739A (en) * | 2019-04-16 | 2019-07-19 | 贵州航天风华精密设备有限公司 | A kind of processing method of the aluminium alloy thin-walled discoid part of T4 |
CN112008341A (en) * | 2020-08-28 | 2020-12-01 | 成都凯迪精工科技有限责任公司 | Method for improving machining quality of wing-shaped part |
CN112008341B (en) * | 2020-08-28 | 2022-05-13 | 成都凯迪精工科技有限责任公司 | Method for improving machining quality of wing-shaped part |
CN113070651A (en) * | 2021-03-26 | 2021-07-06 | 中国船舶重工集团公司第七二五研究所 | Machining process method of large titanium and titanium alloy curved surface component |
Also Published As
Publication number | Publication date |
---|---|
CN102189388B (en) | 2013-02-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102189388B (en) | Manufacture method of door module of integral vehicle main model checking fixture | |
Klocke et al. | Technological and economical assessment of alternative process chains for blisk manufacture | |
Huang et al. | Robotic grinding and polishing for turbine-vane overhaul | |
US20100164424A1 (en) | Tool compensation system and method for computer numerical control machine | |
Dieste et al. | Automatic grinding and polishing using spherical robot | |
US9817393B2 (en) | Adaptive machining of components | |
CN104439884A (en) | Mould three-dimensional rapid forming and repairing method based on reverse engineering | |
CN102886640A (en) | Method for machining thin-wall aluminum alloy part | |
Wang et al. | Improving the machining accuracy of thin-walled parts by online measuring and allowance compensation | |
CN105094052A (en) | Numerical control machine tool and automatic precision correction method | |
CN104808581A (en) | Compensation processing method for complicated face-type curved surface manufacture | |
CN109277883A (en) | Superelevation strength titanium alloy roughness prediction technique based on Cutting Parameters weight | |
CN103831579A (en) | Machining method of complex casting with non-circular cross section | |
Pop et al. | Improving product quality by implementing ISO/TS 16949 | |
CN104801935A (en) | Method for processing aircraft aluminum alloy special-shaped cabin | |
CN106584027B (en) | A kind of process improving closed thin-wall rotation-type part evenness of wall thickness | |
Zuo et al. | Integrated geometric error compensation of machining processes on CNC machine tool | |
Boivie et al. | Development of a hybrid manufacturing cell; integration of additive manufacturing with CNC machining | |
CN109692990A (en) | A kind of band damping platform rotor blade processing method | |
US10852709B2 (en) | Machine tool certification for part specific working volume | |
JP2733877B2 (en) | Method of documenting material removal when machining pre-contoured workpieces | |
CN102922232B (en) | Machining process for non-standard clamp components | |
Zheng et al. | Study of distortion on milled thin-wall aluminum parts influenced by initial residual stress and toolpath strategy | |
Postnov et al. | Theoretical and experimental stress-strain analysis of machining gas turbine engine parts made of the high energy structural efficiency alloy | |
CN113681247A (en) | Machining method of turbine type part |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP01 | Change in the name or title of a patent holder |
Address after: Kunshan City, Suzhou City, Jiangsu Province, Zhangpu town 215321 Jujin Road No. 286 Patentee after: If yu seized Limited by Share Ltd Address before: Kunshan City, Suzhou City, Jiangsu Province, Zhangpu town 215321 Jujin Road No. 286 Patentee before: Kunshan Royal Gauge Industry Co., Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130206 Termination date: 20190323 |