CN102162364A - 煤矿井下重介浅槽选煤布置方法 - Google Patents

煤矿井下重介浅槽选煤布置方法 Download PDF

Info

Publication number
CN102162364A
CN102162364A CN2011100740873A CN201110074087A CN102162364A CN 102162364 A CN102162364 A CN 102162364A CN 2011100740873 A CN2011100740873 A CN 2011100740873A CN 201110074087 A CN201110074087 A CN 201110074087A CN 102162364 A CN102162364 A CN 102162364A
Authority
CN
China
Prior art keywords
coal
tunnel
dense
gangue
roadway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011100740873A
Other languages
English (en)
Other versions
CN102162364B (zh
Inventor
任立民
秦文露
葛怀峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG XINYANG ENERGY CO Ltd
Original Assignee
SHANDONG XINYANG ENERGY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG XINYANG ENERGY CO Ltd filed Critical SHANDONG XINYANG ENERGY CO Ltd
Priority to CN 201110074087 priority Critical patent/CN102162364B/zh
Publication of CN102162364A publication Critical patent/CN102162364A/zh
Application granted granted Critical
Publication of CN102162364B publication Critical patent/CN102162364B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种煤矿井下重介浅槽选煤布置方法,它首先在煤仓与采区岩层中开拓矸石仓;在煤仓与矸石仓之间开拓第一贯通巷道;从矸石仓开始向平行于采区运输巷道的采空区方向开拓第二贯通巷道;然后再开拓第三贯巷道与采区运输巷道贯通;在第一贯通巷道内安装布置煤矸重介浅槽分选机,在第二贯通巷道内安装布置煤泥水处理系统和矸石破碎系统,在第三贯通巷道内安装布置矸石储存及充填系统。本发明将适于地面安装使用的煤矸重介浅槽机及煤泥水处理系统应用布置到井下,从而解决了矸石全部不上井的问题,将原产矸石和分选矸石全部回填到采空区,解决了煤矿地面矸石山污染问题。

Description

煤矿井下重介浅槽选煤布置方法
技术领域
本发明涉及煤炭分选技术领域。
背景技术
目前,煤矿地下采出的煤炭需提升到地面,由地面分选厂进行分选,包括原煤分级、产品脱介(选矸)及介质回收和煤泥水处理三大工艺。该工艺生产系统设备布置庞大、繁杂。因此,煤矸重介浅槽分选机在市面上问世。该机可用于分选煤炭、矸石,分选粒度13~150mm。该机具有结构紧凑、分选粒度高、占地面积小和操作方便等优点。可用于大型选煤厂的排矸,代替人工选矸等。
目前,煤矿采用中下矸石回填技术,即掘进巷道产生的矸石在井下直接充填到采空区,不再提到地面,节省了提升运输环节和净化了地面环境。但提升到地面的煤炭分选出的矸石,仍占据地面污染环境,如充填到采空区,还需再运到井下,十分不便。最好的方式是将煤炭在井下直接分选,分选的矸石直接回填到采空区。原有的煤炭分选工艺由于设备庞大,不可能搬移到地下生产。新回进的煤矸重介浅槽分选机由于结构紧凑占地面小,功能先进等优点,完全可以搬移到井下使用。从而解决分选矸石不上井直接充填到采空区的问题。
发明内容
本发明的目的是为解决煤矸重介浅槽分选机在井下工作的问题,提出一种煤矿井下重介浅槽选煤布置方法。
上述的布置方法是:
第一步:在正在开采的采区运输巷道内建筑煤仓,或利用现有已建好的煤仓,并在同一水平面相距50m之内的采区岩层中开拓矸石仓;
第二步:将煤仓与矸石仓之间开拓第一贯通巷道,巷道断面以满足安装煤矸重介浅槽分选机的尺寸要求;
第三步:从矸石仓开始向平行于采区运输巷道的采空区方向开拓第二贯通巷道,开拓长度至便于安装矸石设备的区域,然后再开拓第三贯巷道与采区运输巷道贯通;至此形成一个由采区运输巷道、第一、二、三贯通巷道组成的“口”字形地下通道;
第四步:在第一贯通巷道内安装布置煤矸重介浅槽分选机,在第二贯通巷道内安装布置煤泥水处理系统和矸石破碎系统,在第三贯通巷道内安装布置矸石储存及充填系统。
本发明将适于地面安装使用的煤矸重介浅槽机及煤泥水处理系统应用布置到井下,从而解决了矸石全部不上井的问题,将原产矸石和分选矸石全部回填到采空区,解决了煤矿地面矸石山污染问题;而煤炭在井下直接分选,减少了地面工业广场的布置,节省了多个运输环节,减少了精煤的生产成本。
附图说明
图1是本发明实施例的布置图。
图中:1-运输巷道,2-煤仓,3-煤矸重介浅槽分选机,4-矸石仓,5-煤泥水处理系统,6-第二贯通巷道,7-矸石破碎系统,8-第三贯通巷道,9-矸石储存及充填系统,10-第一贯通巷道。
具体实施方式
下面以煤矿二采区为例结合图1进一步说明技术方案,某煤矿二采区现开采一、七层煤炭,二采区内已建成运输巷道和煤仓,根据技术要求,将原地面的煤炭分选系统移至井下,以便利用分选的矸石回填采空区。根据上述现有情况,实施布骤如下:
第一步:在与现有煤仓2同一水平面相距50m之内的采区岩层中开拓矸石仓4;
第二步:将煤仓2与矸石仓4之间开拓第一贯通巷道10,巷道断面以满足安装煤矸重介浅槽分选机3的尺寸要求;
第三步:从矸石仓4开始向平行于采区运输巷道1的采空区方向开拓第二贯通巷道6,开拓长度至便于安装矸石设备的区域,然后再开拓第三贯巷道8与采区运输巷道10贯通;至此形成一个由采区运输巷道1、第一贯通巷道10、第二贯通巷道6、第三贯通巷道8组成的“口”字形地下通道;
第四步:在第一贯通巷道10内安装布置煤矸重介浅槽分选机3,在第二贯通巷道6内安装布置煤泥水处理系统5和矸石破碎系统7,在第三贯通巷道8内安装布置矸石储存及充填系统9。

Claims (1)

1.一种煤矿井下重介浅槽选煤布置方法,其特征在于,步骤如下:
第一步:在正在开采的采区运输巷道内建筑煤仓,或利用现有已建好的煤仓,并在同一水平面相距50m之内的采区岩层中开拓矸石仓;
第二步:将煤仓与矸石仓之间开拓第一贯通巷道,巷道断面以满足安装煤矸重介浅槽分选机的尺寸要求;
第三步:从矸石仓开始向平行于采区运输巷道的采空区方向开拓第二贯通巷道,开拓长度至便于安装矸石设备的区域,然后再开拓第三贯巷道与采区运输巷道贯通;至此形成一个由采区运输巷道、第一贯通巷道、第二贯通巷道和第三贯通巷道组成的口字形地下通道;
第四步:在第一贯通巷道内安装布置煤矸重介浅槽分选机,在第二贯通巷道内安装布置煤泥水处理系统和矸石破碎系统,在第三贯通巷道内安装布置矸石储存及充填系统。
CN 201110074087 2011-03-21 2011-03-21 煤矿井下重介浅槽选煤布置方法 Expired - Fee Related CN102162364B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110074087 CN102162364B (zh) 2011-03-21 2011-03-21 煤矿井下重介浅槽选煤布置方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110074087 CN102162364B (zh) 2011-03-21 2011-03-21 煤矿井下重介浅槽选煤布置方法

Publications (2)

Publication Number Publication Date
CN102162364A true CN102162364A (zh) 2011-08-24
CN102162364B CN102162364B (zh) 2012-12-12

Family

ID=44463786

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110074087 Expired - Fee Related CN102162364B (zh) 2011-03-21 2011-03-21 煤矿井下重介浅槽选煤布置方法

Country Status (1)

Country Link
CN (1) CN102162364B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518447A (zh) * 2011-11-17 2012-06-27 山东盛泉矿业有限公司 一种防治巷道底鼓的巷道布置方法
CN104033153A (zh) * 2014-06-25 2014-09-10 中国矿业大学 一种煤矿井下采选充一体化方法
CN105983478A (zh) * 2015-02-03 2016-10-05 山东泰山能源有限责任公司翟镇煤矿 井下煤矸分选系统及煤矸分选方法
CN107127051A (zh) * 2017-05-16 2017-09-05 中煤能源研究院有限责任公司 一种井下选煤生产方法及系统
CN109209379A (zh) * 2018-09-30 2019-01-15 中国矿业大学 一种矿山采选充+x开采模式
CN109209380A (zh) * 2018-09-30 2019-01-15 中国矿业大学 一种矿山采选充控开采方法
CN109516145A (zh) * 2019-01-03 2019-03-26 淮南矿业(集团)有限责任公司 接力式煤仓系统

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB682981A (en) * 1950-04-03 1952-11-19 Markham & Company Ltd An improved method for forming packs between the floor and the roof of a mine
DE3216896C1 (de) * 1982-05-06 1983-11-24 Schaum-Chemie Wilhelm Bauer GmbH & Co KG, 4300 Essen Verfahren zum Sichern des Bruchfelds von untertägigen Grubenräumen gegen Selbstentzündungsbrände
US4726712A (en) * 1984-04-11 1988-02-23 Bergwerksverband Gmbh Method of pipeline filling the interstices of controlled caving areas
CN1782326A (zh) * 2004-12-03 2006-06-07 河北金牛能源股份有限公司 煤矿井下矸石处理方法
CN1807843A (zh) * 2005-01-19 2006-07-26 新汶矿业集团汶南煤矿有限责任公司 矸石充填采空区的方法
CN1936271A (zh) * 2006-08-21 2007-03-28 山东盛泉矿业有限公司 煤矿矸石充填无煤柱开采工作面采空区的方法
CN101392659A (zh) * 2008-08-05 2009-03-25 山东华恒矿业有限公司 井下矸石直接利用的方法
CN101482005A (zh) * 2009-02-02 2009-07-15 河南理工大学 井下毛煤排矸及矿井水处理联合工艺
CN101775985A (zh) * 2010-02-10 2010-07-14 东北大学 一种深埋铁矿产资源地下采、选一体化系统
CN201671655U (zh) * 2010-06-04 2010-12-15 新汶矿业集团有限责任公司孙村煤矿 井下煤和矸石分时运输充填系统
CN101967993A (zh) * 2010-09-30 2011-02-09 江苏中机矿山设备有限公司 一种井下矸石分选充填系统及方法

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB682981A (en) * 1950-04-03 1952-11-19 Markham & Company Ltd An improved method for forming packs between the floor and the roof of a mine
DE3216896C1 (de) * 1982-05-06 1983-11-24 Schaum-Chemie Wilhelm Bauer GmbH & Co KG, 4300 Essen Verfahren zum Sichern des Bruchfelds von untertägigen Grubenräumen gegen Selbstentzündungsbrände
US4726712A (en) * 1984-04-11 1988-02-23 Bergwerksverband Gmbh Method of pipeline filling the interstices of controlled caving areas
CN1782326A (zh) * 2004-12-03 2006-06-07 河北金牛能源股份有限公司 煤矿井下矸石处理方法
CN1807843A (zh) * 2005-01-19 2006-07-26 新汶矿业集团汶南煤矿有限责任公司 矸石充填采空区的方法
CN1936271A (zh) * 2006-08-21 2007-03-28 山东盛泉矿业有限公司 煤矿矸石充填无煤柱开采工作面采空区的方法
CN101392659A (zh) * 2008-08-05 2009-03-25 山东华恒矿业有限公司 井下矸石直接利用的方法
CN101482005A (zh) * 2009-02-02 2009-07-15 河南理工大学 井下毛煤排矸及矿井水处理联合工艺
CN101775985A (zh) * 2010-02-10 2010-07-14 东北大学 一种深埋铁矿产资源地下采、选一体化系统
CN201671655U (zh) * 2010-06-04 2010-12-15 新汶矿业集团有限责任公司孙村煤矿 井下煤和矸石分时运输充填系统
CN101967993A (zh) * 2010-09-30 2011-02-09 江苏中机矿山设备有限公司 一种井下矸石分选充填系统及方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨俊利: "发展煤矿井下选煤技术与装备的思考", 《选煤技术》, no. 1, 25 February 2010 (2010-02-25) *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518447A (zh) * 2011-11-17 2012-06-27 山东盛泉矿业有限公司 一种防治巷道底鼓的巷道布置方法
CN102518447B (zh) * 2011-11-17 2014-07-30 山东盛泉矿业有限公司 一种防治巷道底鼓的巷道布置方法
CN104033153A (zh) * 2014-06-25 2014-09-10 中国矿业大学 一种煤矿井下采选充一体化方法
CN105983478A (zh) * 2015-02-03 2016-10-05 山东泰山能源有限责任公司翟镇煤矿 井下煤矸分选系统及煤矸分选方法
CN107127051A (zh) * 2017-05-16 2017-09-05 中煤能源研究院有限责任公司 一种井下选煤生产方法及系统
CN109209379A (zh) * 2018-09-30 2019-01-15 中国矿业大学 一种矿山采选充+x开采模式
CN109209380A (zh) * 2018-09-30 2019-01-15 中国矿业大学 一种矿山采选充控开采方法
CN109516145A (zh) * 2019-01-03 2019-03-26 淮南矿业(集团)有限责任公司 接力式煤仓系统
CN109516145B (zh) * 2019-01-03 2024-03-19 淮南矿业(集团)有限责任公司 接力式煤仓系统

Also Published As

Publication number Publication date
CN102162364B (zh) 2012-12-12

Similar Documents

Publication Publication Date Title
CN102162364B (zh) 煤矿井下重介浅槽选煤布置方法
CN107893658B (zh) 强地压环境下极厚大矿体阶段空场嗣后充填采矿方法
CN101967993B (zh) 一种井下矸石分选充填系统及方法
CN102704934B (zh) 适于大型地下矿山开采的嗣后充填采矿方法
CN101775985B (zh) 一种深埋铁矿产资源地下采、选一体化系统
AU2014223133B2 (en) Method and apparatus for underground separation, conveyance and fill-up of coal and coal gangues
AU2014223132B2 (en) Method and device for using gangue aboveground to backfill mine goaf
AU2018204736B2 (en) A Method for Mining and Processing of an Ore
CN103480482B (zh) 槽选工艺煤矿井下排矸系统
CN104790956A (zh) 遥控掘进机巷道式或综采放顶煤开采端帮煤工艺
CN203905953U (zh) 一种硬岩快速掘进机
CN105298496A (zh) 设置预留工作面煤柱的全采全充采煤方法
CN109458181A (zh) 一种金属矿沿走向一次采全高的充填采矿方法
CN102128051A (zh) 一种煤矿井下矸石充填采空区的方法
AU2018378009A1 (en) Mine field layout method suitable for fluidized mining of coal resources
CN112796829A (zh) 一种综放面冒落区井下原矸充填系统及充填方法
CN201857994U (zh) 一种井下矸石分选充填系统
CN204746555U (zh) 一种煤矿井下双洗选系统
CN1952349A (zh) 利用矸石置换村庄下压煤的开采方法
CN108331580B (zh) 一种清洁高效的采煤方法
Kamp Backfilling on gold mines of the Gold Fields group
CN109184784B (zh) 基于减轻采煤塌陷程度的综采煤矸石同步充填系统及方法
CN102444418B (zh) 用于巷道充填的装置
CN104948227A (zh) 一种煤矿井下洗选工艺双系统布置方法
CN112403647B (zh) 一种井下转载点智能干选系统布置方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121212

Termination date: 20150321

EXPY Termination of patent right or utility model