CN102140921A CN2011100783510A CN201110078351A CN102140921A CN 102140921 A CN102140921 A CN 102140921A CN 2011100783510 A CN2011100783510 A CN 2011100783510A CN 201110078351 A CN201110078351 A CN 201110078351A CN 102140921 A CN102140921 A CN 102140921A
Authority
CN
China
Prior art keywords
splash guard
layer
secondary lining
concrete
novel tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100783510A
Other languages
Chinese (zh)
Inventor
罗彦斌
陈建勋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN2011100783510A priority Critical patent/CN102140921A/en
Publication of CN102140921A publication Critical patent/CN102140921A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a novel tunnel waterproof structure, which can prevent a waterproof plate from being damaged and the back being voided, and does not influence the thickness of secondary lining concrete. The novel tunnel waterproof structure comprises a sprayed concrete layer and a secondary lining concrete layer; the waterproof plate is arranged between the sprayed concrete layer and the secondary lining concrete layer; and a filler layer is arranged between the waterproof plate and the sprayed concrete layer.

Description

The novel tunnel waterproof construction
One, technical field:
The present invention relates to a kind of buildings waterproof structure, especially relate to a kind of novel tunnel waterproof construction.
Two, background technology:
In the background technology, the supporting and protection structure in tunnel adopts composite lining usually, and separation layer (splash guard) promptly is set between supporting in the early stage and the secondary lining.From point of theory, this composite lining form of structure can be ended the water resistance in the country rock beyond splash guard effectively, guarantees that tunnel lining is water-tight, does not seep water.Yet, in the work progress, be difficult to guarantee tunnel preliminary bracing section rule, smooth-going at the scene, often because rough surface layer causes splash guard breakage and back generation to be come to nothing.Splash guard will lose water-proof function, and coming to nothing of splash guard back can form natural water space in case appearance is damaged.The immediate cause that these all can become tunnel lining percolating water has a strong impact on workmanship, and operation brings potential safety hazard to the tunnel.
Three, summary of the invention:
The present invention provides a kind of novel tunnel waterproof construction in order to solve the weak point in the above-mentioned background technology, and it can avoid splash guard breakage and back to come to nothing, and does not influence the concrete thickness of secondary lining.
For achieving the above object, the technical solution used in the present invention is:
A kind of novel tunnel waterproof construction comprises shotcrete layer and secondary lining layer of concrete, it is characterized in that: be provided with splash guard between shotcrete layer and secondary lining layer of concrete, be provided with packing layer between splash guard and the shotcrete layer.
Compared with prior art, the advantage and the effect that have of the present invention is as follows:
The present invention can not only effectively avoid splash guard to break, and makes splash guard and sprayed mortar closely connected, avoids the splash guard back to come to nothing, and does not influence the concrete thickness of secondary lining, thereby makes that the waterproof effect of composite lining is given full play to.
Four, description of drawings:
Fig. 1 is a structural representation of the present invention;
Fig. 2 is construction process figure of the present invention.
Among the figure, 1-shotcrete layer, 2-splash guard, 3-secondary lining layer of concrete, 4-packing layer.
Five, the specific embodiment:
Referring to Fig. 1, the present invention includes shotcrete layer 1 and secondary lining layer of concrete 3, between shotcrete layer 1 and lining concrete layer 3, be provided with splash guard 2, be provided with packing layer 4 between splash guard 2 and the shotcrete layer 1.Referring to Fig. 2, during actual fabrication, pressure injection has the filler of cementing agent effect between the jog of pneumatically placed concrete and splash guard, form packing layer, splash guard can be arranged on the level and smooth preliminary bracing surface, tunnel, then lateral irrigation is annotated lining concrete within it, realizes having the high-durability tunnel water proofing structure of " do not hinder concrete filling, and the water proof structure closely connected with concrete ".Concrete steps are: be width that the splash guard of 1.5m is processed into wide 6.0m(long span earlier) splash guard.Along the periphery of traveling formwork chassis splash guard is launched then, and good in the fixed-site of regulation, between splash guard and sprayed mortar, pour into the filler of backfill then.At last, side form is built the secondary lining concrete outside splash guard.Adopt pressure injection equipment respectively the curing compound that solidifies of force feed and accelerating admixture to the pressure injection place, mix the back on abutment wall top, left tunnel right side, haunch and vault 5 places are provided with the pressure injection pipe, pressure injection successively from bottom to top.
The present invention has following characteristics:
1, improve water proofing property:
1.5m width waterproof plank factory process is become wide 6.0m(long span) move into, reduced the field Welding operation; The setting of packing layer has reduced the outstanding breakage to splash guard of rock bolt head; Study for a second time courses one has flunked simple and convenient after the splash guard breakage.And splash guard and sprayed mortar are closely connected, can really play the effect of waterproof barrier.
2, improve the concrete quality of secondary lining:
Sprayed mortar and secondary lining concrete are fully isolated, and guarantee that the secondary lining concrete is not subjected to that country rock is phreatic to be influenced.And the traveling formwork chassis can strictly be controlled the preliminary bracing profiled outline, guarantees that the secondary lining concrete thickness is even, and meets design requirement.Simultaneously, the packing layer in the secondary lining concrete and the splash guard outside is closely connected, forms overall structure.
3, reduce cost:
The quality of reduction splash guard because not torn and puncture to wait, splash guard influences, even also can satisfy the requirement of waterproof; Position for the sprayed mortar surface irregularity does not need to repair, and has saved the construction operation time.The waterproof requirement that can adapt to simultaneously, different situations (full section, half section etc.).
4, reduce the load of operating environment, surrounding enviroment:
Splash guard can adopt manpower or machinery to lay, and operation intensity is low; In the construction, can recover the groundwater table of tunnel perimeter.

Claims (1)

1. novel tunnel waterproof construction, comprise shotcrete layer (1) and secondary lining layer of concrete (3), it is characterized in that: between shotcrete layer (1) and secondary lining layer of concrete (3), be provided with splash guard (2), be provided with packing layer (4) between splash guard (2) and the shotcrete layer (1).
CN2011100783510A 2011-03-30 2011-03-30 Novel tunnel waterproof structure Pending CN102140921A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100783510A CN102140921A (en) 2011-03-30 2011-03-30 Novel tunnel waterproof structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100783510A CN102140921A (en) 2011-03-30 2011-03-30 Novel tunnel waterproof structure

Publications (1)

Publication Number Publication Date
CN102140921A true CN102140921A (en) 2011-08-03

Family

ID=44408687

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100783510A Pending CN102140921A (en) 2011-03-30 2011-03-30 Novel tunnel waterproof structure

Country Status (1)

Country Link
CN (1) CN102140921A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587939A (en) * 2012-03-22 2012-07-18 山东华联矿业股份有限公司 Waterproof board isolation re-spraying management method for water leakage of underground mine
CN104763448A (en) * 2013-07-04 2015-07-08 浙江海洋学院 Lining supporting device with improved structure
CN108331601A (en) * 2018-03-06 2018-07-27 中铁十六局集团第工程有限公司 A kind of anti-device that comes to nothing of tunnel-liner
CN109209450A (en) * 2018-10-30 2019-01-15 中铁十局集团第五工程有限公司 Full section of tunnel splash guard spreads hanging hang structure in corrosive formation
CN114320359A (en) * 2021-12-10 2022-04-12 中国一冶集团有限公司 Method for processing large and deep non-filler karst cave above tunnel arch

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101260809A (en) * 2008-04-18 2008-09-10 中铁一局集团有限公司 Back surface stuck AB fastener self-adhering -type water-proof board construction process
CN101614129A (en) * 2009-08-10 2009-12-30 招商局重庆交通科研设计院有限公司 The job practices of tunnel waterproof and water drainage system
JP2010024667A (en) * 2008-07-17 2010-02-04 Kfc Ltd Tunnel waterproof structure and construction method for the same
CN201407056Y (en) * 2009-05-19 2010-02-17 中铁第四勘察设计院集团有限公司 Completely closed waterproof composite lining structure bearing medium water pressure
CN201407053Y (en) * 2009-05-22 2010-02-17 中铁第一勘察设计院集团有限公司 Support and waterproof structure for metro tunnel of tunnel boring machine construction
CN201496072U (en) * 2009-08-31 2010-06-02 中铁第四勘察设计院集团有限公司 Fully-closed water-proof composite lining structure capable of adjusting water pressure
CN201982111U (en) * 2011-03-30 2011-09-21 长安大学 Novel tunnel water-proof structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101260809A (en) * 2008-04-18 2008-09-10 中铁一局集团有限公司 Back surface stuck AB fastener self-adhering -type water-proof board construction process
JP2010024667A (en) * 2008-07-17 2010-02-04 Kfc Ltd Tunnel waterproof structure and construction method for the same
CN201407056Y (en) * 2009-05-19 2010-02-17 中铁第四勘察设计院集团有限公司 Completely closed waterproof composite lining structure bearing medium water pressure
CN201407053Y (en) * 2009-05-22 2010-02-17 中铁第一勘察设计院集团有限公司 Support and waterproof structure for metro tunnel of tunnel boring machine construction
CN101614129A (en) * 2009-08-10 2009-12-30 招商局重庆交通科研设计院有限公司 The job practices of tunnel waterproof and water drainage system
CN201496072U (en) * 2009-08-31 2010-06-02 中铁第四勘察设计院集团有限公司 Fully-closed water-proof composite lining structure capable of adjusting water pressure
CN201982111U (en) * 2011-03-30 2011-09-21 长安大学 Novel tunnel water-proof structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587939A (en) * 2012-03-22 2012-07-18 山东华联矿业股份有限公司 Waterproof board isolation re-spraying management method for water leakage of underground mine
CN102587939B (en) * 2012-03-22 2014-10-15 山东华联矿业股份有限公司 Waterproof board isolation re-spraying management method for water leakage of underground mine
CN104763448A (en) * 2013-07-04 2015-07-08 浙江海洋学院 Lining supporting device with improved structure
CN108331601A (en) * 2018-03-06 2018-07-27 中铁十六局集团第工程有限公司 A kind of anti-device that comes to nothing of tunnel-liner
CN109209450A (en) * 2018-10-30 2019-01-15 中铁十局集团第五工程有限公司 Full section of tunnel splash guard spreads hanging hang structure in corrosive formation
CN114320359A (en) * 2021-12-10 2022-04-12 中国一冶集团有限公司 Method for processing large and deep non-filler karst cave above tunnel arch

Similar Documents

Publication Publication Date Title
CN104963689A (en) Three-step seven-procedure excavation method for tunnel
CN104895089B (en) Basement floor and the construction method of the cooperative permanent support system of support pile
CN103953114B (en) Steel frame-reinforced masonry shear wall combinative structure and construction method thereof
CN102140921A (en) Novel tunnel waterproof structure
CN105421810B (en) Prefabricated wallboard reinforced masonry structure and construction method thereof
CN102251606A (en) Outer partition wall built by adopting light concrete partition wall boards and construction method thereof
CN103088830A (en) Construction method for composite outer wall structure of ultra-deep basement
CN108798059A (en) A kind of old masonry seismic reinforcing structure and construction method
CN204849820U (en) Unilateral formwork of shaped steel combination
CN104818728A (en) Permanent supporting system with basement floor and supporting piles capable of working together
CN102002950B (en) Liquid division slip casting reinforcing method for subsurface structure construction joints
CN105369826A (en) Basement bearing platform side mold construction method
CN202851009U (en) Tunnel buffering multilayer waterproof-drainage structure
CN101498136A (en) After-pouring strips structure with high underground water level
CN203546759U (en) Plugging structure for post-cast strip of underground building
CN102852530A (en) Tunnel buffering multilayered water-discharging-preventing structure and construction method
CN203685208U (en) End-shaping steel template for double-lining trolley for tunnel
CN101469559B (en) Composite heat insulating walling and mounting method thereof
CN201982111U (en) Novel tunnel water-proof structure
CN104594389A (en) Post-cast strip external wall plugging structure with elastic water stoppers
CN202347534U (en) Force transferring structure between foundation ditch support pile and basement outer wall
CN204676533U (en) A kind of soil-nail wall support system based on the recyclable technique of assembling
CN205000360U (en) Basement structure with waterproof structure
CN112012761B (en) Construction method of anti-disturbance double-arch tunnel structure
CN104153361B (en) Prestressed concrete pipe pile underground pile connection construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20110803