CN102127899A - System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof - Google Patents

System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof Download PDF

Info

Publication number
CN102127899A
CN102127899A CN2011100280738A CN201110028073A CN102127899A CN 102127899 A CN102127899 A CN 102127899A CN 2011100280738 A CN2011100280738 A CN 2011100280738A CN 201110028073 A CN201110028073 A CN 201110028073A CN 102127899 A CN102127899 A CN 102127899A
Authority
CN
China
Prior art keywords
lifting
sliding
box girder
steel box
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011100280738A
Other languages
Chinese (zh)
Other versions
CN102127899B (en
Inventor
王晓敬
黄中华
秦顺全
张金杯
夏邦军
许佳平
陈亚强
魏焕堂
钱云龙
张建红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
2nd Engineering Co Ltd of MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
2nd Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC, 2nd Engineering Co Ltd of MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN2011100280738A priority Critical patent/CN102127899B/en
Publication of CN102127899A publication Critical patent/CN102127899A/en
Application granted granted Critical
Publication of CN102127899B publication Critical patent/CN102127899B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the technical field of bridge construction, and discloses a system for lifting and sliding a large-tonnage steel box girder in a land area and a shoal area and a construction method thereof. The method comprises the following steps of: 1, arranging a lifting system beside a pier adjacent to a waterway, and arranging a sliding system below the lifting system and on a land side; 2, conveying a steel box girder section to a lifting position from the waterway, and lifting the steel box girder section by using a lifting device; 3, drawing a lifting transverse beam by using a jack and a steel stranded wire which are arranged on a lifting longitudinal beam to ensure that the lifting transverse beam, together with the lifting device and the steel box girder section, slides to a position above a sliding platform along the lifting longitudinal beam; 4, descending the steel box girder section to the sliding platform by using the lifting device; and 5, sliding the steel box girder section to a design position along a sliding track by using drawing equipment and arranging in position. The problem that a large floating crane is limited by the water level of a river channel and influenced by tide is solved, the construction period of a single steel box girder section is shortened, and work efficiency is improved; meanwhile, the steel box girder section can be arranged in the shoal area and the land area.

Description

Lifting and sliding system of large-tonnage steel box girder in land area and shoal area and construction method
Technical Field
The invention relates to the technical field of bridge construction, in particular to a lifting and sliding system of a large-tonnage steel box girder in a land area and a shoal area and a construction method thereof. The lifting device is suitable for lifting and longitudinally moving a large-scale lifting station arranged at a bridge site to a designed position by utilizing the large-scale lifting station when a large-tonnage steel box girder is prefabricated by a factory and transported to the bridge site through a water path, and the steel box girder is arranged in place, so that the integral lifting of steel box girder sections is realized.
Background
In the existing bridge construction, large-tonnage steel box girders are generally processed and manufactured in factories and transported to a construction site through a waterway, and a large-scale floating crane is used for hoisting and mounting.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: a lifting system and a construction method of a large-tonnage steel box girder in a land area and a shoal area are provided to overcome the defect that the practical range of the prior art is limited.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows:
a lifting system of a large-tonnage steel box girder in land areas and shoal areas comprises two parts: hoisting system and system that slides:
the hoisting system comprises: the lifting system is arranged beside a pier of the navigation channel; running gear, including: the device comprises a slideway, a jack, a steel strand, a polytetrafluoroethylene sliding plate and a walking base; a lifting longitudinal beam is placed on the top surface of the lifting support, a lifting cross beam is installed on the lifting longitudinal beam, a walking base is installed on the bottom surface of the lifting cross beam, a jack is arranged on the lifting longitudinal beam, a steel strand penetrates through the jack, the steel strand is anchored on the walking base and used for dragging the lifting cross beam and the steel box girder segment to walk, a slide way is arranged between the walking base and the lifting longitudinal beam, and a polytetrafluoroethylene sliding plate is placed between the two moving surfaces during walking in order to reduce the frictional resistance during the movement between the slide way and the walking base;
the sliding system comprises a sliding support, a sliding track and traction equipment, the traction equipment is arranged on the side close to the design position of the steel box girder, and the traction equipment is used for dragging and sliding the steel box girder segment to the design position to be installed in place; the sliding system is arranged below and behind the hoisting system and close to the land side, and is used for supporting, transposing and moving the steel box girder segments.
The lifting support is composed of a left triangular inclined supporting leg and a right triangular inclined supporting leg, the supporting legs are supported on the top surface of the bearing platform through steel pipe piles and are connected with a connecting piece embedded in the pier body in a welding mode, and therefore the requirement for stability of the support is met.
The lifting beam adopts a double-layer multi-row Bailey beam set.
The lifting device adopts two continuous lifting jack systems, steel strands are anchored through an anchorage device, a computer is used for centrally controlling a hydraulic system, a lifting jack piston is driven to extend and contract, the steel strands and a member are driven to ascend and descend, and integral synchronous lifting and descending of a large member are realized.
The sliding support is at least two rows of steel pipe piles arranged according to the design span, the sliding support is positioned near the pier, and the top of the pipe pile is connected with the tower body embedded part by using a pipe pile connection system, so that the stability of the sliding support is enhanced. The sliding track adopts steel or channel steel, and a Bailey beam group consisting of at least three Bailey beams is a supporting structure of the sliding track.
The traction equipment adopts two winches.
The invention also provides a construction method of the large-tonnage steel box girder in the land area and the shoal area, which comprises the following steps:
firstly, installing a hoisting system beside a pier position of an adjacent channel, and arranging a sliding system below the hoisting system and on a land side, wherein the hoisting system comprises a lifting support, a lifting longitudinal beam, a lifting cross beam, a hoisting device and a traveling device, and the sliding system comprises a sliding support, a sliding track and traction equipment;
transporting the steel box girder segments to a lifting position through a water path, and lifting the steel box girder segments by using a lifting device and enabling the steel box girder segments to be higher than the top surface of a sliding platform of the sliding system;
thirdly, starting the traveling device, and dragging the traveling base by using a jack and a steel strand arranged on the lifting longitudinal beam to enable the lifting cross beam, the lifting device and the steel box girder segment to move to the position above the sliding platform along the slide way and then stop;
fourthly, the steel box girder segment is dropped onto the sliding platform by the hoisting device;
and fifthly, sliding the steel box girder segment to a designed position along a sliding track on the sliding platform by utilizing a traction device arranged on the sliding platform, and installing the steel box girder segment in place.
The invention has the advantages that: the invention has low requirement on the water level of the channel, the beam-transporting ship can return to the sea after the steel box girder segment is lifted, and the steel box girder segment can be slid to the shoal land far away from the channel by the winch traction equipment, thereby solving the problems that the large-scale floating crane is limited by the water level of the river and affected by tide, shortening the construction period of the single-section steel box girder, improving the work efficiency, and simultaneously realizing the lifting installation of the steel box girder segment at the shoal and the land.
Drawings
FIG. 1 is a schematic diagram of the overall arrangement of a steel box girder segment hoisting system and a sliding platform.
FIG. 2 is a schematic diagram of a steel box girder segment hoisting system and a side elevation arrangement of a sliding platform.
Description of the components: 1 steel box girder segment section, 2 promote the support, 3 promote the longeron, 4 promote the crossbeam, 5 hoisting accessory, 6 promote the hoist, 7 jacks, 8 slides, 9 support that slides, 10 tracks that slide, 11 traction equipment, 12 steel strand wires, 13 walk the capable base.
Detailed Description
The present invention is further described with reference to the following drawings and specific examples so that those skilled in the art can better understand the present invention and can practice the present invention, but the examples are not intended to limit the present invention.
As shown in fig. 1 and 2, the invention relates to a lifting system of a large-tonnage steel box girder in land areas and shoals, which comprises two parts: a hoisting system and a sliding platform of the steel box girder segment;
hoist and mount system includes: the lifting device comprises a lifting support 2, a lifting longitudinal beam 3, a lifting cross beam 4, a lifting device 5 and a walking device; the hoisting system is arranged beside a pier of the navigation channel, and excavates a riverbed at the position of the lifting support to meet the requirement of transportation and parking of the steel box girder segment. Running gear, including: the device comprises a walking base 13, a slideway 8, a jack 7, a steel strand 12 and a tetrafluoro sliding plate, wherein a walking device is arranged on a lifting longitudinal beam 5 and connected with a lifting cross beam 4; a hoisting device 5 is mounted above the lifting beam 4.
The sliding platform comprises a sliding support 9, a sliding track 10 and a traction device 11, wherein the traction device 11 is arranged on the side close to the design position of the steel box girder, and the traction device 11 is used for dragging and sliding the steel box girder segment to the design position to be installed in place.
Referring to fig. 1 and 2, the construction method of the large-tonnage steel box girder in the land area and the shoal area comprises the following specific steps: when a bridge bearing platform and a tower column close to a river channel lifting position are constructed, embedded parts of a lifting support and a sliding platform are embedded, the lifting support 2 is assembled beside a pier, a lifting longitudinal beam 3 is arranged on the lifting support 2, a lifting jack 7 of a traveling device, a steel strand 12, a slideway 8 and other parts and a lifting cross beam 4 are arranged on the lifting longitudinal beam 3, the slideway is in contact with a traveling base 13 at the bottom of the lifting cross beam 4, a polytetrafluoroethylene sliding plate is placed between two contact surfaces during traveling, and the steel strand 12 and the lifting cross beam 4 are connected and anchored; the hoisting device 5 is arranged on the hoisting cross beam 4, two hoisting devices are arranged, two-point hoisting is adopted, namely two continuous hoisting jack systems are adopted, the steel strand is anchored through an anchorage device, a hydraulic system is controlled in a centralized manner by a computer, a piston of the hoisting jack is driven to extend and retract, the steel strand and the member are driven to ascend and descend, and integral synchronous hoisting and descending of the large member are realized. Meanwhile, a sliding support 9 is assembled below the lifting system and on the side close to the land area, a sliding track 10 is laid on the sliding support 9, and a traction device 11 is installed on the side of the side pier of the steel box girder. During construction, when the steel box girder segment 1 is conveyed to the lower part of a lifting system through a water path, the lifting sling 6 and the lifting device 5 synchronously operate to lift the steel box girder segment 1 to the position where the bottom surface of the steel box girder is higher than the top surface of a sliding platform and then stop, two jacks 7 arranged on the lifting longitudinal beam 3 are started, the lifting beam 4 is pulled through a steel strand 12, so that the lifting beam 4, the lifting device 5 and the steel box girder segment 1 are together moved to the position above the sliding platform along a slide rail 8, the steel box girder segment 1 is placed onto the sliding platform, a traction device 11 arranged on the sliding platform is adopted, and the steel box girder segment 1 is pulled to be moved to a designed position along a sliding rail 10 to be installed in place.
The above-mentioned embodiments are merely preferred embodiments for fully illustrating the present invention, and the scope of the present invention is not limited thereto. The equivalent substitution or change made by the technical personnel in the technical field on the basis of the invention is all within the protection scope of the invention.

Claims (7)

1. A lifting and sliding system of a large-tonnage steel box girder in land areas and shoal areas is characterized by comprising a hoisting system and a sliding system; wherein,
the hoisting system comprises a hoisting support, a hoisting longitudinal beam, a hoisting cross beam, a hoisting device and a traveling device, and is arranged beside a pier of the navigation channel; the lifting support is composed of a left triangular inclined supporting leg and a right triangular inclined supporting leg, the supporting legs are supported on a pier bearing platform and are welded and connected with a connecting piece embedded in advance on a pier body, a group of lifting longitudinal beams are arranged on the top of each supporting leg along the bridge span direction, the length of each lifting longitudinal beam is suitable for enabling a steel box girder segment to travel to the position above a sliding platform of a sliding system, a set of traveling device is arranged on each group of lifting longitudinal beams, and each traveling device comprises a slide way, a jack, a steel strand, a tetrafluoro sliding plate and a traveling base; the lifting cross beam is arranged on a walking base on the lifting longitudinal beam and is temporarily locked, a jack is arranged on the lifting longitudinal beam, a steel strand penetrates through the jack, the steel strand is anchored on the walking base and is used for dragging the lifting cross beam and a steel box girder segment to walk, a slideway is arranged between the walking base and the lifting longitudinal beam, the slideway adopts a steel rail, and a polytetrafluoroethylene sliding plate is arranged between two moving surfaces during walking in order to reduce the friction resistance during moving;
the sliding system comprises a sliding support, a sliding track and traction equipment, is arranged at the lower rear part of the hoisting system, is arranged along the whole length of the side span of a land area, and is used for supporting, transposing and moving the steel box girder segment; the sliding support is a bearing structure of the whole sliding system and is arranged along the axle line of the bridge according to the designed span, and the sliding track is fixed on the support; the traction equipment is arranged on the side of the side pier at the design position of the steel box girder, and the traction equipment pulls the steel box girder segment to slide to the design position along the sliding track to be installed in place.
2. The system of claim 1, wherein the lifting support comprises at least four steel pipe piles, and the steel pipe piles are supported on the top surface of the bearing platform and connected with pier columns to meet the stability requirement of the support.
3. The system of claim 1, wherein the lifting beam is a double-layer multi-row beret beam set.
4. The lifting and sliding system of the large-tonnage steel box girder in the land area and the shoal area as claimed in claim 1, wherein the sliding support is at least two rows of steel pipe piles arranged according to a designed span, the sliding track adopts steel or channel steel, and a Bailey beam group consisting of at least three Bailey beams is a supporting structure of the sliding track.
5. The system of claim 1, wherein the traction device comprises two winches.
6. The system of claim 1, wherein the hoisting device comprises two continuous hoisting jack systems, the steel strand is anchored by anchors, the hydraulic system is centrally controlled by a computer, the piston of the hoisting jack is driven to extend and retract, the steel strand and the member are driven to ascend and descend, and the integral synchronous ascending and descending of the large member are realized.
7. A construction method of a large-tonnage steel box girder in a land area and a shoal area is characterized by comprising the following steps:
firstly, installing a hoisting system beside a pier position of an adjacent channel, and arranging a sliding system below the hoisting system and on a land side, wherein the hoisting system comprises a lifting support, a lifting longitudinal beam, a lifting cross beam, a hoisting device and a traveling device, and the sliding system comprises a sliding support, a sliding track and traction equipment;
transporting the steel box girder segments to a lifting position through a water path, and lifting the steel box girder segments by using a lifting device and enabling the steel box girder segments to be higher than the top surface of a sliding platform of the sliding system;
thirdly, starting the traveling device, and dragging the lifting beam by using a jack and a steel strand arranged on the lifting longitudinal beam to enable the lifting beam to slide to the upper part of the sliding platform along the lifting longitudinal beam together with the lifting device and the steel box girder segment, and then stopping moving;
fourthly, the steel box girder segment is dropped onto the sliding platform by the hoisting device;
and fifthly, sliding the steel box girder segment to a designed position along a sliding track on the sliding platform by utilizing a traction device arranged on the sliding platform, and installing the steel box girder segment in place.
CN2011100280738A 2010-12-30 2011-01-26 System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof Active CN102127899B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100280738A CN102127899B (en) 2010-12-30 2011-01-26 System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201010624514 2010-12-30
CN201010624514.6 2010-12-30
CN2011100280738A CN102127899B (en) 2010-12-30 2011-01-26 System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof

Publications (2)

Publication Number Publication Date
CN102127899A true CN102127899A (en) 2011-07-20
CN102127899B CN102127899B (en) 2012-07-04

Family

ID=44266153

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100280738A Active CN102127899B (en) 2010-12-30 2011-01-26 System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof

Country Status (1)

Country Link
CN (1) CN102127899B (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660923A (en) * 2012-05-25 2012-09-12 中交三航局第三工程有限公司 Assembly construction process of prefabricated 40m T-beam in intertidal zone of open sea
CN102808522A (en) * 2012-08-22 2012-12-05 上海通用金属结构工程有限公司 Overall sliding equipment applicable to ultra-large span frame structure
CN103334381A (en) * 2013-06-25 2013-10-02 宁波市政工程建设集团股份有限公司 Full-bracket track-bogie bearing and moving device and construction method for installing steel box girders
CN103741720A (en) * 2013-11-29 2014-04-23 中交第二航务工程局有限公司 Reinforcement cage hanging system
CN105350459A (en) * 2015-11-20 2016-02-24 中建交通建设集团有限公司 Large steel beam gliding device and construction method thereof
CN105568866A (en) * 2015-12-31 2016-05-11 中铁二十局集团第六工程有限公司 Incremental launching construction method for large-span steel box girder spanning constructed road
CN104646995B (en) * 2015-02-16 2016-11-16 中交一航局第一工程有限公司 A kind of phytal zone quick positioning installation apparatus of barrier board and installation method
CN109607248A (en) * 2018-11-28 2019-04-12 四川路桥华东建设有限责任公司 A kind of applicable tidal waters large-scale component sliding unloading construction method
CN109680618A (en) * 2019-01-28 2019-04-26 中铁重工有限公司 Steel box-girder entirety fall girder apparatus and its fall beam method
CN109734003A (en) * 2019-01-31 2019-05-10 中铁广州工程局集团桥梁工程有限公司 A kind of cantilever loop wheel machine and the loop wheel machine front end cantilever installation method of going to river based on it
CN110965478A (en) * 2019-12-27 2020-04-07 中交二公局第二工程有限公司 Lifting beam and beam moving integrated support mechanism
CN112249940A (en) * 2020-08-04 2021-01-22 中交二公局第二工程有限公司 Hydraulic lifting and positioning system of cable-stayed bridge deck crane
CN112252194A (en) * 2020-10-30 2021-01-22 中铁大桥局武汉桥梁特种技术有限公司 Bridge lifting device, transformation system and transformation construction method
CN113152294A (en) * 2021-04-19 2021-07-23 浙江中天恒筑钢构有限公司 Three-dimensionally adjustable large-scale component conveying platform device and construction method
CN114108466A (en) * 2021-10-12 2022-03-01 中铁广州工程局集团有限公司 Segmental beam prefabrication site and method for carrying segmental beam in wharf
CN114671265A (en) * 2022-04-13 2022-06-28 中交路桥华南工程有限公司 Intelligent weight shifting device
CN114775432A (en) * 2022-04-13 2022-07-22 中交路桥建设有限公司 Assembling support of large-tonnage reinforced concrete combined cross beam of cable-stayed bridge cable tower
WO2023005126A1 (en) * 2021-07-30 2023-02-02 中铁十九局集团第五工程有限公司 Steel box girder lifting and transporting frame system and construction method therefor

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1103701A (en) * 1994-02-25 1995-06-14 铁道建筑研究设计院 Bridge span erecting machine
AU2003259614A1 (en) * 2002-10-31 2004-05-20 Bridge & Marine Engineering Pty. Ltd. System Facilitating Positioning Elongate Superstructures on Substructures
CN201058968Y (en) * 2007-06-26 2008-05-14 中铁一局集团有限公司新运工程公司 Electric track type sliding beam apparatus for erection of railway bridge
CN201087323Y (en) * 2007-09-11 2008-07-16 中铁二局股份有限公司 Mobile integral construction platform

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1103701A (en) * 1994-02-25 1995-06-14 铁道建筑研究设计院 Bridge span erecting machine
AU2003259614A1 (en) * 2002-10-31 2004-05-20 Bridge & Marine Engineering Pty. Ltd. System Facilitating Positioning Elongate Superstructures on Substructures
CN201058968Y (en) * 2007-06-26 2008-05-14 中铁一局集团有限公司新运工程公司 Electric track type sliding beam apparatus for erection of railway bridge
CN201087323Y (en) * 2007-09-11 2008-07-16 中铁二局股份有限公司 Mobile integral construction platform

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660923A (en) * 2012-05-25 2012-09-12 中交三航局第三工程有限公司 Assembly construction process of prefabricated 40m T-beam in intertidal zone of open sea
CN102808522A (en) * 2012-08-22 2012-12-05 上海通用金属结构工程有限公司 Overall sliding equipment applicable to ultra-large span frame structure
CN102808522B (en) * 2012-08-22 2015-06-10 上海通用金属结构工程有限公司 Overall sliding equipment applicable to ultra-large span frame structure
CN103334381A (en) * 2013-06-25 2013-10-02 宁波市政工程建设集团股份有限公司 Full-bracket track-bogie bearing and moving device and construction method for installing steel box girders
CN103334381B (en) * 2013-06-25 2015-01-07 宁波市政工程建设集团股份有限公司 Full-bracket track-bogie bearing and moving device and construction method for installing steel box girders
CN103741720A (en) * 2013-11-29 2014-04-23 中交第二航务工程局有限公司 Reinforcement cage hanging system
CN103741720B (en) * 2013-11-29 2015-10-28 中交第二航务工程局有限公司 A kind of reinforcing cage suspension
CN104646995B (en) * 2015-02-16 2016-11-16 中交一航局第一工程有限公司 A kind of phytal zone quick positioning installation apparatus of barrier board and installation method
CN105350459A (en) * 2015-11-20 2016-02-24 中建交通建设集团有限公司 Large steel beam gliding device and construction method thereof
CN105350459B (en) * 2015-11-20 2017-03-22 中建交通建设集团有限公司 Large steel beam gliding device and construction method thereof
CN105568866A (en) * 2015-12-31 2016-05-11 中铁二十局集团第六工程有限公司 Incremental launching construction method for large-span steel box girder spanning constructed road
CN105568866B (en) * 2015-12-31 2017-06-23 中铁二十局集团第六工程有限公司 Across the large-span steel box beam push construction method of existing road
CN109607248A (en) * 2018-11-28 2019-04-12 四川路桥华东建设有限责任公司 A kind of applicable tidal waters large-scale component sliding unloading construction method
CN109680618A (en) * 2019-01-28 2019-04-26 中铁重工有限公司 Steel box-girder entirety fall girder apparatus and its fall beam method
CN109734003A (en) * 2019-01-31 2019-05-10 中铁广州工程局集团桥梁工程有限公司 A kind of cantilever loop wheel machine and the loop wheel machine front end cantilever installation method of going to river based on it
CN110965478A (en) * 2019-12-27 2020-04-07 中交二公局第二工程有限公司 Lifting beam and beam moving integrated support mechanism
CN112249940A (en) * 2020-08-04 2021-01-22 中交二公局第二工程有限公司 Hydraulic lifting and positioning system of cable-stayed bridge deck crane
CN112252194A (en) * 2020-10-30 2021-01-22 中铁大桥局武汉桥梁特种技术有限公司 Bridge lifting device, transformation system and transformation construction method
CN113152294A (en) * 2021-04-19 2021-07-23 浙江中天恒筑钢构有限公司 Three-dimensionally adjustable large-scale component conveying platform device and construction method
CN113152294B (en) * 2021-04-19 2022-03-22 浙江中天恒筑钢构有限公司 Method for hoisting overwater bridge by using large-scale component conveying platform device
WO2023005126A1 (en) * 2021-07-30 2023-02-02 中铁十九局集团第五工程有限公司 Steel box girder lifting and transporting frame system and construction method therefor
CN114108466A (en) * 2021-10-12 2022-03-01 中铁广州工程局集团有限公司 Segmental beam prefabrication site and method for carrying segmental beam in wharf
CN114108466B (en) * 2021-10-12 2023-12-12 中铁广州工程局集团有限公司 Segmental beam prefabrication site and method for carrying segmental beams on wharf
CN114775432A (en) * 2022-04-13 2022-07-22 中交路桥建设有限公司 Assembling support of large-tonnage reinforced concrete combined cross beam of cable-stayed bridge cable tower
CN114671265A (en) * 2022-04-13 2022-06-28 中交路桥华南工程有限公司 Intelligent weight shifting device
CN114671265B (en) * 2022-04-13 2023-10-20 中交路桥华南工程有限公司 Intelligent weight shifting device
CN114775432B (en) * 2022-04-13 2024-04-19 中交路桥建设有限公司 Splicing bracket of large-tonnage steel-concrete combined beam of cable-stayed bridge cable tower

Also Published As

Publication number Publication date
CN102127899B (en) 2012-07-04

Similar Documents

Publication Publication Date Title
CN102127899B (en) System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof
CN201077721Y (en) Gantry crane with falling girder
CN105274942B (en) Large-span continuous steel truss girder Multipoint synchronous automatic cycle replaces piston shoes pushing tow system and its construction method
CN101736699B (en) Accurate positioning method of sliding of full-support frame steel box girder
CN102337736B (en) Installation process of upper module on offshore oil platform
KR101193608B1 (en) Beam launcher anchorage system for constructing bridge
CN103541308A (en) Variable cross-section cantilever bridge box girder self-locking synchronization pushing system and construction method
CN112900281B (en) Complicated curve beam upward jacking construction device and method
CN111172882A (en) Beam section transportation method for assembling bridge girder cantilever
CN102720432A (en) Self-propelled underground boring jumbo
CN101806053B (en) Integral installation method of cantilever beams of self lifting type well drilling platform
CN113026563B (en) Suspension bridge high-low displacement girder trestle girder hoisting facility and construction method thereof
CN100354477C (en) Swing-construction method for mounting dual-hoist at land-shoul beam section for steel box girder suspension bridge
CN102433844A (en) Cantilever beam hoisting system of trestle and construction system and method for erecting prefabricated beam of bridge deck
CN202369933U (en) Trestle bridge cantilever beam lifting system and bridge surface precast beam erecting construction system
CN113279335A (en) Device and method for mounting large-tonnage and wide-width steel box girder across mountain ridge
CN116497760B (en) Installation method of gravity type caisson wharf precast beam slab bridge girder erection machine
CN111350135B (en) Large-span steel truss girder floating towing frame facility construction method
CN216892057U (en) Large-span steel-concrete composite beam bridge steel box girder section floats and holds in palm top and pushes away construction system
CN201647844U (en) Beam lifting station without abutments
CN201292509Y (en) Suspension bridge main girder construction segment conveying facilities
CN204551280U (en) Bridge subsection hanging apparatus
CN207619857U (en) Bailey beam erection crane horizontal sliding device
CN106012854A (en) Transportation equipment for prefabricated viaduct plates
CN214271728U (en) Integral lifting type steel trestle for navigation hole

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant