CN102119261A - Mining system - Google Patents

Mining system Download PDF

Info

Publication number
CN102119261A
CN102119261A CN2009801312794A CN200980131279A CN102119261A CN 102119261 A CN102119261 A CN 102119261A CN 2009801312794 A CN2009801312794 A CN 2009801312794A CN 200980131279 A CN200980131279 A CN 200980131279A CN 102119261 A CN102119261 A CN 102119261A
Authority
CN
China
Prior art keywords
ore
hole
conveyer
mine
mobile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2009801312794A
Other languages
Chinese (zh)
Inventor
科利特·阿莫斯
约翰·克拉伦斯·博克斯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Technological Resources Pty Ltd
Original Assignee
Technological Resources Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2008904109A external-priority patent/AU2008904109A0/en
Application filed by Technological Resources Pty Ltd filed Critical Technological Resources Pty Ltd
Publication of CN102119261A publication Critical patent/CN102119261A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/26Methods of surface mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C47/00Machines for obtaining or the removal of materials in open-pit mines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Disintegrating Or Milling (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

A method of mining ore in a mine pit (3) and a mine are disclosed. The method comprises drilling and blasting ore in a bench (19) of ore within the mine pit and collecting ore blasted from the bench from a floor (5) of the mine pit using at least one mobile excavation machine (11). The method also comprises delivering ore that has been collected by the mobile excavation machine to at least one mobile-in-pit crusher (41), and transporting crushed ore to outside the pit on at least one ladder conveyor (23) that extends up the wall of the pit.

Description

Mining system
Technical field
The present invention relates to exploit the ore that comprises precious metal.
But the present invention exclusively relates to the exploitation iron ore particularly anything but.
Background technology
Traditional strip mining transformation of iron ore comprises: the boring and the part of explosion ore body progressively make and can pick up ore by forklift or other excavator that is fit to, and ore is transmitted from the hole on haulage truck.The a series of steps of known use are exploited the iron ore of bulk, make it possible to carry out simultaneously in the hole multiple recovery activity.At first to the pattern of step boring with formation " explosion " hole, described step can be that for example 40-200m is long, 20-100m is dark and 10-15m is high, and comprises ore and/or other material of thousands of metric tons.For example analyze the material that is removed during the process of shot hole getting out by chemical analysis, with determine on average whether ore is that (a) is high-grade, (b) inferior grade or (c) waste material.Boundary between the upper-lower hierarchy depends on series of factors, and can change between the mine and in the different piece at mine.The explosive that use is prepared in the bulk goods preparation truck of particular design comes the step of explosion ore, this explosive is normally based on ANFO (ammonium nitrate/fuel oil), and this bulk goods preparation truck can adjust the density of explosive before loading shot hole downwards.The material that explosion goes out is picked up with the native vehicle of moving of excavator form, and this excavator for example is cord forklift, diesel oil hydraulic crawler excavator or front-end loader, and the material that goes out of explosion is placed in the haulage vehicle such as truck, and sends away from the pit.Determine ore is handled outside the pit according to grade.For example, abandoned mine is used as mine fills, and low grade ore is stored or is used for mixing with high-grade ore, and high-grade ore further handled as required, to form vendible product.
Summary of the invention
The present invention is the instead of production method of said method.
Exploitation method of the present invention can be as the unique method of exploiting in the pit or as one of several exploitation methods in the pit.
According to the present invention, provide a kind of in the pit method of exploitated ore, comprise step:
(a) boring and explosion ore in the ore step in the pit;
(b) using at least one to move excavator to collect the ore that goes out from bench blasting from the work plane in pit;
(c) ore of will be being collected by mobile excavator is delivered at least one and moves crushing engine in the hole, and is the ore that overall dimensions reduces with ore reduction; And
(d) at least one the ladder type conveyer that extends on the wall in hole, the ore of fragmentation is sent to the outside in hole.
Mobile excavator can have the form of cord forklift, diesel oil hydraulic crawler excavator or front-end loader, or is used for collecting from the hole work plane any machine that other is fit to of the ore of being exploited.
The step of described method (c) can comprise: move the ore that the transmission of flexible delivery machine has been collected by mobile excavator in the pit at least one, and on conveyer, send ore from excavator, and ore is delivered to crushing engine in the hole, and is the ore that overall dimensions reduces ore reduction.
Term " mobile flexible delivery machine " is understood that to represent conveyer at this, this conveyer is that move and flexible, and can move through the work plane in pit with linear and nonlinear mode, and can when moving through the hole work plane, continue operation.
Term " mobile flexible delivery machine " does not comprise that the person in the extraction industry is the conveyer of " can be shifted " or " removable " conveyer, as mentioned above." can be shifted " or " removable " conveyer is the conveyer that can reorientate in mine after finishing period of exploitation.In other words, conveyer is being what not move on the following meaning: its can move continuously with for example continuous service with when conveyer transmits ore and mobile excavator or other mobile apparatus go forward side by side.
Usually, mobile flexible delivery machine must satisfy three basic demands any one or a plurality of, promptly (a) moves fully, when carrying hands-operation and transmitting ore, to go forward side by side with the mobile excavator that is associated or other mobile apparatus, (b) when carrying hands-operation and transmitting ore, allow moving of lateral flexibility, and for example can in the work plane of hole, move up and down the nearly step of 400mm, and (c) when carrying hands-operation and transmitting ore, allow extending longitudinally and contraction.
Mobile flexible delivery machine can be the type of describing in Michael Pietsch Australian Patent 767395 under one's name.Being disclosed in this and incorporating in this Australian Patent by cross reference.
Described method can comprise: move in the pit at least one and keep and ore that the feedway transmission has been collected by mobile excavator, and via move keep and feedway to mobile flexible delivery machine transmission ore.
Described method can comprise: transmit ore via the crushing engine of a plurality of flexible moving conveyors in the hole.
The interior crushing engine in hole can be close to the ore after the explosion, to minimize to the travel distance of crushing engine.
About this point, crushing engine can be the mobile crushing machine in the hole, and described method can comprise: the change in response to the position of the hole degree of depth that increases and/or recovery activity comes constantly around pit mobile crushing machine.
Described method can comprise: with in ore at least one haulage truck in the pit of fragmentation in cheat crushing engine be sent to the ladder type conveyer.
Described method can comprise: the ore of fragmentation is moved on the main line conveyer at least one of extending along the part of hole work plane crushing engine is sent to the ladder type conveyer in cheat.
Term " mobile main line conveyer " is understood that to represent that at this person in extraction industry is the conveyer of " can be shifted " or " removable " conveyer." can be shifted " or " removable " conveyer is the conveyer that can reorientate in mine after finishing period of exploitation.In other words, conveyer is being what not move on the following meaning: its can move continuously with for example continuous service with when conveyer transmits ore and mobile apparatus go forward side by side.Conveyer can be periodically moves on reposition displacement or the meaning that moves at it.
Mobile main line conveyer can be located on the hole work plane in the lower area in hole.
Mobile main line conveyer can be followed linear path or nonlinear path.
Described method can comprise: adjust mobile main line conveyer periodically in response to the reduction of hole work plane constantly.
Crushing engine can be close to ladder type conveyer location in the hole.
In this case, described method can comprise: the ore of will be being collected by mobile excavator is delivered at least one and moves the main line conveyer, described at least one move the position of the ore of main line conveyer after the contiguous explosion and extend to crushing engine in the hole along the part of hole work plane.
In addition, in this case, described method can comprise: the ore of (a) will be collecting by mobile excavator be delivered to ore after the contiguous explosion at least one move the flexible delivery machine; (b) along mobile flexible delivery machine ore is sent to the main line conveyer; And (c) along the main line conveyer with ore be sent to the hole in crushing engine.
Term " ladder type conveyer " is understood that to represent the ore from the pit directly can be sent to from the hole work plane conveyer on the wall in pit as used herein, and its mesospore is the precipitous wall that with respect to the horizontal plane becomes at least 20 ° angle.
The wall in pit can with respect to the horizontal plane be at least 30 °, is at least 65 ° in many cases.
The hole wall can be 20m at least, and 40m at least normally.
The ladder type conveyer can be the single conveyer from the hole work plane to the edge in hole, and extend on the wall of hole, and, promptly do not have ore unloaded and be loaded onto on the lower end of continuous part of conveyer at the upper end of the part of conveyer not along the branchpoint of the length of conveyer.
The ladder type conveyer can extend on the wall of hole, and does not turn to.
Described method can comprise: the ladder type conveyer is extended in the general reduction in response to the hole work plane.
Described method can comprise: the ore that will be sent to the fragmentation on the wall in hole along the ladder type conveyer is transferred at least one main conveyor, and along main conveyor ore is sent to processing factory and/or discharge point.
Step (d) can comprise: the ore of fragmentation is sent to the outside in hole at least two ladder type conveyers, described at least two ladder type conveyers extend on the wall in hole; And, the ore of fragmentation is transferred on the main conveyor via the independent branchpoint of each ladder type conveyer.
Main conveyor can be positioned on the edge in hole usually or be positioned at around the base portion of the local physical features in hole, and follows its physical features.
Main conveyor can receive ore from the more than one part in hole or from a series of holes.
According to the present invention, a kind of mine also is provided, described mine comprises: at least one hole, described at least one hole have hole work plane and hole wall, and described hole wall limits at least a portion in hole; At least one moves excavator, is used to be collected in the hole the ore from bench blasting; At least one moves crushing engine in the hole, and being used for ore reduction is the ore that overall dimensions reduces; And, at least one ladder type conveyer, described at least one ladder type conveyer extends on the wall in hole, is used for transmitting broken ore from the hole.
Mine can be included at least one the flexible moving conveyor in the hole, is used for transmitting ore from excavator, and ore is delivered to crushing engine in the hole.
Usually, mobile flexible delivery machine must satisfy three basic demands any one or a plurality of, promptly (a) moves fully, when carrying hands-operation and transmitting ore, to go forward side by side with the mobile excavator that is associated or other mobile apparatus, (b) when carrying hands-operation and transmitting ore, allow moving of lateral flexibility, and for example can in the work plane of hole, move up and down the nearly step of 400mm, and (c) when carrying hands-operation and transmitting ore, allow extending longitudinally and contraction.
Mine can comprise that at least one moves the main line conveyer, and its part along the hole work plane is extended, and is used for ore is transmitted at least a portion of the distance from mobile excavator to the ladder type conveyer.
Crushing engine can be close to the recovery activity in mine in the hole, to minimize to the travel distance of crushing engine.
Crushing engine can be the mobile crushing machine in the hole.
Crushing engine can be close to ladder type conveyer location in the hole.
In this case, mine can comprise that at least one moves the main line conveyer, and its part along the hole work plane is extended, at least a portion of the distance of crushing engine in being used for transmitting ore from mobile excavator to the hole.
In addition, in this case, mine can be included in the pit at least one move the flexible delivery machine, the ore that is used for being exploited transmits to mobile main line conveyer from mobile excavator.
The hole wall can be precipitous wall, promptly with respect to the horizontal plane is at least 20 °, is more generally as at least 30 °, is at least 65 ° in many cases.
The hole wall is a 20m height at least, and 40m height at least normally.
The ladder type conveyer can be the single conveyer from the hole work plane to the edge in pit, and extend on the wall of hole, and, promptly do not have ore unloaded and be loaded onto on the lower end of continuous part of conveyer at the upper end of the part of conveyer not along the branchpoint of the length of conveyer.
The ladder type conveyer can extend on the wall of hole, and does not turn to.
Mine can be included in the main conveyor of the outside in hole, be used for exploit and/or collected ore is sent to processing factory or discharge point from the hole.
Can have at least two ladder type conveyers, it extends on the wall in hole, is used for the ore of fragmentation is transferred to main conveyor.
Can there be the independent branchpoint that is used for each ladder type conveyer.
The mine can comprise a plurality of holes and at least one main conveyor of outside in hole, be used for exploit and/or collected ore is sent to processing factory or discharge point from the hole.
Mine can be the iron ore mine.
Description of drawings
Only the present invention is described now by the exemplary reference accompanying drawing, in the accompanying drawings:
Fig. 1 illustrates according to a plurality of embodiment of the method for exploitation iron ore of the present invention with according to the schematic diagram of the layout in the pit of a plurality of embodiment of mine of the present invention; And
Fig. 2 illustrates according to a plurality of other embodiment of the method for exploitation iron ore of the present invention with according to the schematic diagram of the layout in the pit of a plurality of other embodiment of mine of the present invention.
The specific embodiment
The following description of two accompanying drawings is under the background of exploitation iron ore.Be appreciated that to the invention is not restricted to exploit iron ore, and expand to other ore of exploitation.
Be appreciated that also in the mine layout shown in two accompanying drawings be schematically, and be intended to represent the mine layout with unusual general meaning.
In two accompanying drawings, use identical Reference numeral to describe identical feature.
With reference to figure 1, totally limited by rib 7 at least in part by label 3 signs and pit with hole work plane 5.Only for convenience, rib 7 is shown as relative straight wall, and the invention is not restricted to this layout.Hole work plane 5 can be at a horizontal plane place.Alternatively, as shown in the figure, hole work plane 5 is on a plurality of horizontal planes, and these a plurality of horizontal planes form a series of steps, and these a series of steps can separate each other or interconnect by slope 33.
Each rib 7 can comprise a series of steps or a continuous wall.
Pit 5 comprises two steps 19, described two steps 19 are moved 51 one-tenth piece ground borings of auger and explosion, described for example is that 40m is long, 20m is dark, 10m is high usually, and comprise 8,000 tonne ore, and described two steps 19 produce the ore of explosion on the getting out of a predicament or an embarrassing situation of work plane 5 of hole.The ore of explosion changes from the boulder to the fines in size.
A plurality of mobile excavators 11 are collected the ore of explosion from hole work plane 5.Mobile excavator 11 can be the machine of any suitable type.For example, mobile excavator 11 can have the form of cord forklift, diesel oil hydraulic crawler excavator or front-end loader.
Can remote control or control at the mobile excavator 11 (and miscellaneous equipment) shown in Fig. 1 by the operator on machine.In either case, usually, the mobile route of the mobile excavator 11 in pit 3 (with miscellaneous equipment) is consistent with production program.
Moving excavator 11 a group shown in Fig. 1 directly transfers to collected ore in the hole on the crushing engine 41.Mobile crushing machine 41 is reduced to suitable size with the size of ore, with material processed and the processing that is used for the downstream." A " discerns this option by the letter in Fig. 1.
Perhaps the ore of fragmentation crushing engine 41 in cheat is sent to ladder type conveyer 23, promptly " can be shifted " or the conveyer of " removable " by mobile main line conveyer 27 or by truck 37.
In the accompanying drawings another organized mobile excavator 11 collected ore transferred on the mobile flexible delivery machine 13, and conveyer 13 is sent to ore the mobile feed system 15 of the front end that is positioned at mobile main line conveyer 27, and conveyer 27 is sent to ore crushing engine 41 in the hole of contiguous ladder type conveyer 23.Discern this option by letter " B " in the drawings.
Shown in the figure another organized mobile excavator 11 ore of collecting directly transferred on the mobile feed system 15 that is positioned at mobile main line conveyer 27 front ends, and conveyer 27 is sent to ore crushing engine 41 in the hole of contiguous ladder type conveyer 23." C " discerns this option by the letter in Fig. 1.
Crushing engine 41 can be any suitable type in the hole.
Mobile feed system 15 can be loading bin or any feed system that other is fit to.
Mobile flexible delivery machine 13 can be any suitable type.For example, mobile flexible delivery machine 13 can be as being made by International Conveying Systems International and as described in the Michael Pietsch Australian Patent 767395 under one's name.
Mobile main line conveyer 27 can be any suitable type.For example, mobile main line conveyer 27 can be with such as the identical design of the mobile flexible delivery machine making by International Conveying Systems International and in Australian Patent 767395, describe 13, but with more static mode operation.
Mobile flexible delivery machine 13 and mobile main line conveyer 27 make it possible to reduce to being used for 3 dependences that transmit the truck of the ore of being exploited from the pit.This is the benefit aspect running cost, particularly in big dark pit, in this big dark pit, from the production zone to the crushing engine and the travel distance and the time of other treatment facility can be very big.
Ladder type conveyer 23 is arranged to ore directly is sent on the wall 7.The ladder type conveyer can be in the permanent position of sidewall 7, maybe can be mounted for moving along the length of sidewall 7.Under latter event, main line conveyer 27 is arranged to be shifted or is removable, or can be extended the change with the position that adapts to ladder type conveyer 23 in addition.In both cases, when the hole degree of depth increased, ladder type conveyer 23 can stretch on length.
Ladder type conveyer 23 can be any suitable conveyer.For example, ladder type conveyer 23 can be the type of being made and being described in Michael Pietsch Australian Patent 767395 under one's name by International Conveying Systems International.
Ladder type conveyer 23 is transferred to the ore of fragmentation on the convey assembly 29 via independent branchpoint 61,3 edge extends this convey assembly 29 along the pit, and the different part in interconnect a series of holes and/or same hole, and ore is sent to treating stations such as crushing engine.
Convey assembly 29 can be that being convenient to ore separation is two types of handling stream, wherein be transmitted and be used for handling, and be sent to such as another stream of abandoned mine and store heap and be used for subsequently as packing material at crushing engine such as a stream of high-grade ore.
Should be noted that in the layout shown in Fig. 1 and only represent a part of cheating, and the exploitation method that the repeated reference accompanying drawing is described in the other parts in hole 3.Also can be following situation: in the different piece in hole 3, use other exploitation method.Under any circumstance, the ore of being exploited is transmitted via ladder type conveyer 23 from mine, and is delivered to convey assembly 29.
As mentioned above, Fig. 2 illustrates according to a plurality of other embodiment of the method for exploitation iron ore of the present invention with according to the schematic diagram of the layout in the pit of a plurality of other embodiment of mine of the present invention.
With reference to figure 2, usually limited by rib 7 at least in part by label 3 signs and pit with hole work plane 5.Only for convenience, rib 7 is shown as relative straight wall, and the invention is not restricted to this layout.Hole work plane 5 can be at a horizontal plane place.Alternatively, as shown in the figure, hole work plane 5 is on a plurality of horizontal planes, and these a plurality of horizontal planes form a series of steps, and these a series of steps can separate each other or interconnect by the slope (not shown).
Each rib 7 can comprise a series of steps or a continuous wall.
Comprise two steps 19 in the pit shown in Fig. 25, described two steps 19 are moved 51 one-tenth piece ground borings of auger and explosion, and described for example is that 40m is long, 20m is dark, 10m is high usually, and comprises 8,000 tonne ore, and described two steps 19 produce the ore of explosion.The ore of explosion changes from the boulder to the fines in size.
A plurality of mobile excavators 11 are collected the ore of explosion from hole work plane 5.Mobile excavator 11 can be the machine of any suitable type.For example, mobile excavator 11 can have the form of cord forklift, diesel oil hydraulic crawler excavator or front-end loader.
Mobile excavator 11 (and miscellaneous equipment) can remote control or is controlled by the operator on machine.In either case, usually, the mobile route of the surperficial excavator 11 in pit 3 (with miscellaneous equipment) is consistent with production program.
Moving excavator 11 a group shown in Fig. 2 directly transfers to the ore of being exploited on the mobile flexible delivery machine 13.
Organizing mobile excavator 11 at shown in Fig. 2 another shifts collected ore via the mobile feed system 15 that is positioned at conveyer 13 front ends.
Mobile feed system 15 can be loading bin or any feed system that other is fit to.
Mobile flexible delivery machine 13 makes it possible to not use the trucies as the main selection that is used for the ore that 3 transmission are exploited from the pit to operate mineral.This is the benefit aspect running cost, particularly in big dark pit, in this big dark pit, from the production zone to the crushing engine and the travel distance and the time of other treatment facility can be very big.
Mobile flexible delivery machine 13 can be any suitable type.For example, mobile flexible delivery machine 13 can be as being made by International Conveying Systems International and as described in the Australian Patent 767395.
Collected ore is sent to the mobile crushing machine 41 that is positioned on the work plane 5 of hole via the mobile flexible delivery machine 13 in pit 5.Mobile crushing machine 41 reduces to suitable size with the size of ore, with material processed and the processing that is used for the downstream.
Mobile crushing machine 41 can be any suitable type.
The ore of the fragmentation that is produced by mobile crushing machine 41: perhaps (a) directly is sent to ladder type conveyer 23, and this ladder type conveyer 23 is arranged to the ore of fragmentation is sent on the rib 7 from pit 3; Perhaps (b) is sent to inward trunk conveyer 27, and this inward trunk conveyer 27 is sent to ladder type conveyer 23 along 5 extensions of hole work plane and with ore.
Ladder type conveyer 23 can be in the permanent position of sidewall 7, maybe can be mounted for moving along the length of sidewall 7.Under latter event, main line conveyer 27 is arranged to removable, or can be extended the change with the position that adapts to ladder type conveyer 23 in addition.In both cases, when the hole degree of depth increased, ladder type conveyer 23 can stretch on length.
Ladder type conveyer 23 can be any suitable conveyer.For example, ladder type conveyer 23 can be the type of being made and being described in Michael Pietsch Australian Patent 767395 under one's name by International Conveying Systems International.
Ladder type conveyer 23 is transferred to the ore of fragmentation on the convey assembly 29 via independent branchpoint 61,3 edge extends this convey assembly 29 along the pit, and the different part in interconnect a series of holes and/or same hole, and ore is sent to treating stations such as crushing engine.
Convey assembly 29 can be that being convenient to ore separation is two types of handling stream, wherein be transmitted and be used for handling, and be sent to such as another stream of abandoned mine and store heap and be used for subsequently as packing material at crushing engine such as a stream of high-grade ore.
Should be noted that in the layout shown in Fig. 2 and only represent a part of cheating, and the exploitation method that the repeated reference accompanying drawing is described in the other parts in hole 3.Also can be following situation: in the different piece in hole 3, use other exploitation method.Under any circumstance, the ore of being exploited is transmitted via ladder type conveyer 23 from mine, and is delivered to convey assembly 29.
Can under situation without departing from the spirit and scope of the present invention, carry out many modifications for the method for in accompanying drawing and foregoing, summarizing of the present invention.

Claims (28)

1. the method for an exploitated ore in the pit comprises the steps:
(a) boring and explosion ore in the ore step in described pit;
(b) using at least one to move excavator to collect the ore that goes out from described bench blasting from the work plane in described pit;
(c) ore that will have been collected by described mobile excavator is delivered at least one and moves crushing engine in the hole, and being used for ore reduction is the ore that overall dimensions reduces; And
(d) at least one the ladder type conveyer that extends on the wall in described hole, the ore of fragmentation is sent to the outside in described hole.
2. method according to claim 1, wherein, step (c) comprising: move the ore that the transmission of flexible delivery machine has been collected by described mobile excavator in described pit at least one, and on described conveyer, leave described excavator ground and transmit ore, and ore is delivered to crushing engine in the described hole, and is the ore that overall dimensions reduces ore reduction.
3. method according to claim 2, wherein, described mobile flexible delivery machine satisfy following three basic demands any one or a plurality of, that is: (a) can move fully, to go forward side by side with the mobile excavator that is associated or other mobile apparatus at described conveying hands-operation with when transmitting ore; (b) allow lateral flexibility to move at described conveying hands-operation with when transmitting ore, and for example can in the work plane of hole, move up or down the nearly step of 400mm; And (c) permission extending longitudinally and contraction in described conveying hands-operation and transmission ore.
4. according to claim 2 or the described method of claim 3, comprise: at least one that the ore of being collected by described mobile excavator is delivered in described pit moves maintenance and feedway, and via described mobile maintenance and feedway ore is delivered to described mobile flexible delivery machine.
5. according to each described method in the aforementioned claim, wherein, crushing engine is positioned to the ore after the contiguous explosion in the described hole, so that minimize to the travel distance of described crushing engine.
6. method according to claim 5, wherein, crushing engine is the mobile crushing machine in the described hole, and described method comprises: the change in response to the position that increases the hole degree of depth and/or recovery activity to move described crushing engine around described pit every now and then.
7. according to each described method in the aforementioned claim, comprising: with in ore at least one haulage truck in described pit of fragmentation in the described hole crushing engine be sent to described ladder type conveyer.
8. according to each described method in the claim 1 to 6, comprising: the ore of fragmentation is moved on the main line conveyer at least one of extending along the part of hole work plane crushing engine is sent to described ladder type conveyer in the described hole.
9. according to each described method in the claim 1 to 4, wherein, crushing engine is positioned to contiguous described ladder type conveyer in the described hole.
10. method according to claim 9, comprise: the ore of will be being collected by described mobile excavator is delivered at least one and moves the main line conveyer, described at least one move the position of the ore of main line conveyer after the contiguous explosion and extend to crushing engine in the described hole along the part of hole work plane.
11. method according to claim 10 comprises: the ore of (a) will be collecting by described mobile excavator be delivered to ore location after the contiguous explosion at least one move the flexible delivery machine; (b) ore is sent at least one the main line conveyer that extends to crushing engine in the described hole along the part of hole work plane along described mobile flexible delivery machine; And (c) ore is sent to crushing engine in the described hole along described main line conveyer.
12. according to each described method in the aforementioned claim, comprise: the ore that will be sent to the fragmentation on the wall in described hole along described ladder type conveyer is transferred at least one main conveyor, and along described main conveyor ore is sent to processing factory and/or discharge point.
13. method according to claim 12, wherein, step (d) comprising: the ore of fragmentation is sent to the outside in described hole at least two ladder type conveyers, described at least two ladder type conveyers extend on the wall in described hole; And the ore of fragmentation is transferred to described main conveyor via the independent branchpoint that is used for each ladder type conveyer.
14. a mine, described mine comprises: at least one hole, described at least one hole have hole work plane and hole wall, and described hole wall limits at least a portion in described hole; At least one moves excavator, is used for collecting from the ore of the bench blasting in described hole; At least one moves crushing engine in the hole, and being used for ore reduction is the ore that overall dimensions reduces; At least one ladder type conveyer, described at least one ladder type conveyer extends on the wall in described hole, is used for transmitting broken ore from described hole.
15. mine according to claim 14 is included at least one the flexible moving conveyor in the described hole, is used to leave described excavator ground and transmits ore and ore is delivered to crushing engine in the described hole.
16. mine according to claim 15, wherein, described mobile flexible delivery machine satisfy following three basic demands any one or a plurality of, that is: (a) can move fully, to go forward side by side with the mobile excavator that is associated or other mobile apparatus at described conveying hands-operation with when transmitting ore; (b) allow lateral flexibility to move at described conveying hands-operation with when transmitting ore, and for example can in the work plane of hole, move up or down the nearly step of 400mm; And (c) permission extending longitudinally and contraction in described conveying hands-operation and transmission ore.
17. according to each described mine in the claim 14 to 16, comprise that at least one moves the main line conveyer, described at least one move the main line conveyer and extend along the part of hole work plane, be used for the ore after the explosion is transmitted at least a portion from described mobile excavator to the distance of described ladder type conveyer.
18. according to each described mine in the claim 14 to 17, wherein, crushing engine is positioned to contiguous recovery activity in described mine in the described hole, so that minimize to the travel distance of described crushing engine.
19. mine according to claim 18, wherein, crushing engine is the mobile crushing machine in the described hole.
20. according to each described mine in the claim 14 to 19, wherein, crushing engine is positioned to contiguous described ladder type conveyer in the described hole.
21. mine according to claim 20, at least one that is included in the pit moves the flexible delivery machine, at least a portion of the distance of crushing engine in the ore that is used for exploiting transmits from described mobile excavator to described hole.
22. according to each described mine in the claim 14 to 21, wherein, described hole wall is precipitous wall, promptly with respect to the horizontal plane is at least 20 °, more typically is at least 30 °, is at least 65 ° in many cases.
23. according to each described mine in the claim 14 to 22, wherein, described hole wall is a 20m height at least, and 40m height at least typically.
24. according to each described mine in the claim 14 to 23, wherein, described ladder type conveyer is the single conveyer from the hole work plane to the edge in pit, and extend on the wall of described hole, and, promptly do not have ore unloaded and be loaded onto on the lower end of continuous part of described conveyer at the upper end of the part of described conveyer not along the branchpoint of the length of described conveyer.
25. according to each described mine in the claim 14 to 24, be included in the main conveyor of the outside in described hole, be used for the ore of exploitation and/or collection is sent to processing factory or discharge point from described hole.
26. according to each described mine in the claim 14 to 25, comprise a plurality of holes and at least one main conveyor of the outside in described hole, described at least one main conveyor is used for exploitation and/or the ore collected are sent to processing factory or discharge point from described hole.
27. according to claim 25 or the described mine of claim 26, wherein, have at least two ladder type conveyers, described at least two ladder type conveyers extend on the wall in described hole, are used for the ore of fragmentation is transferred to described main conveyor.
28. wherein, there is the independent branchpoint that is used for each ladder type conveyer in mine according to claim 27.
CN2009801312794A 2008-08-11 2009-08-11 Mining system Pending CN102119261A (en)

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
AU2008904109 2008-08-11
AU2008904109A AU2008904109A0 (en) 2008-08-11 Mining System
AU2008904111 2008-08-11
AU2008904111A AU2008904111A0 (en) 2008-08-11 Mining System
PCT/AU2009/001025 WO2010017582A1 (en) 2008-08-11 2009-08-11 Mining system

Publications (1)

Publication Number Publication Date
CN102119261A true CN102119261A (en) 2011-07-06

Family

ID=41668572

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009801312794A Pending CN102119261A (en) 2008-08-11 2009-08-11 Mining system

Country Status (8)

Country Link
US (1) US20110175429A1 (en)
CN (1) CN102119261A (en)
AU (1) AU2009281697A1 (en)
BR (1) BRPI0917528A2 (en)
CA (1) CA2733640A1 (en)
CL (1) CL2011000312A1 (en)
WO (1) WO2010017582A1 (en)
ZA (1) ZA201101049B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106801605A (en) * 2017-02-08 2017-06-06 王杨 A kind of mining mining machines equipment

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EA021860B1 (en) * 2012-09-10 2015-09-30 Кабир Емам Назар Абдул Method for development of gravel deposits in mudflow and flood dangerous areas
BR102015010652B1 (en) * 2015-05-11 2019-11-19 Vale S/A open pit iron ore mining method
CN105386767B (en) * 2015-12-10 2017-09-15 华北理工大学 A kind of barnyard avalanche mixed mining hangs the mining methods of side
CN107100626A (en) * 2017-07-11 2017-08-29 朱鸿 Monomer movement type complete equipment semi-continuousmining technology system
GB201718881D0 (en) * 2017-11-15 2017-12-27 Anglo American Services (Uk) Ltd A method for mining and processing of an ore
CN110285872B (en) * 2019-06-28 2024-05-31 三一重机有限公司 Weighing device, material conveying equipment and material conveying system
CN115749784B (en) * 2022-11-09 2023-08-11 文山麻栗坡紫金钨业集团有限公司 Continuous drilling device for mining

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1980634A (en) * 1932-11-14 1934-11-13 Link Belt Co Method for building levees
US4103972A (en) * 1973-12-03 1978-08-01 Kochanowsky Boris J Open pit mine
US4150852A (en) * 1977-05-18 1979-04-24 Mccoy Charles M Method of strip mining
JPS5423001A (en) * 1977-07-22 1979-02-21 Mitsubishi Mining & Cement Co Opencut mining method and apparatus
US4609097A (en) * 1983-08-17 1986-09-02 Continental Conveyor And Equipment Company, Inc. High angle conveyor
US4842130A (en) * 1984-11-13 1989-06-27 D M Enterprises Inc. Belt bender
DE3430642A1 (en) * 1984-08-21 1986-03-06 O & K Orenstein & Koppel Ag, 1000 Berlin TRAVELABLE SLOPE LIFT
GB8423420D0 (en) * 1984-09-17 1984-10-24 Doyle G H Excavator with cutting wheel assembly
US4765461A (en) * 1985-05-23 1988-08-23 Minenco Pty. Limited Mobile elevator conveyor
US5154489A (en) * 1991-02-15 1992-10-13 Exxon Coal Usa, Inc. Inclined surface mining method
US5427439A (en) * 1994-06-14 1995-06-27 Atlantic Richfield Company Surface mining conveyor system
DE19901287C2 (en) * 1999-01-15 2003-10-16 Man Takraf Foerdertechnik Gmbh Deck belt conveyors
AUPQ401299A0 (en) * 1999-11-12 1999-12-09 Pietsch, Michael Continous haulage system
CA2526336C (en) * 2005-11-09 2013-09-17 Suncor Energy Inc. Method and apparatus for oil sands ore mining

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106801605A (en) * 2017-02-08 2017-06-06 王杨 A kind of mining mining machines equipment

Also Published As

Publication number Publication date
ZA201101049B (en) 2012-02-29
WO2010017582A1 (en) 2010-02-18
CA2733640A1 (en) 2010-02-18
US20110175429A1 (en) 2011-07-21
AU2009281697A1 (en) 2010-02-18
BRPI0917528A2 (en) 2018-05-29
CL2011000312A1 (en) 2011-07-15

Similar Documents

Publication Publication Date Title
CN102119261A (en) Mining system
CA2745066C (en) Continuous mining
CN104033153A (en) Coal mine underground mining, dress and filling integral method
CN102966355A (en) Method for creating internal dumping conditions of strip mine
AU2014202712C1 (en) Ore removal production line, twin ramps and ground support installation method
CN112427326A (en) Intelligent gangue selecting and backfilling process and gangue selecting and backfilling device for underground coal mine
CN107676096B (en) Continuous mining system and mining process for ferrous metallurgy open-pit mine
CN113329824A (en) Material conveyor, system and method for material movement
CN111322073A (en) Combined mine exploitation system based on vertical shaft and adhesive tape inclined shaft
CN102119260A (en) Mining system
Marinin et al. Blasting preparation for selective mining of complex structured ore deposition
CN102777184B (en) The mining system in mine and method
RU2394158C1 (en) Procedure for open pit development of mineral deposits
Schimm et al. Wirtgen Surface Miner–The First Link of a Simple Extraction and Materials Handling Chain in “Medium Hard”-Rock
AU2009208123A1 (en) Mining system
CN207229102U (en) A kind of semicontinuous mining system of opencut
Egerton Presidential address: The mechanisation of UG2 mining in the Bushveld Complex
CA1064528A (en) Open pit mine
CN212027787U (en) Combined mine exploitation system based on vertical shaft and adhesive tape inclined shaft
CN112377249B (en) Fully-mechanized top coal caving working face goaf gangue filling system and method
CA1252484A (en) Mining method and apparatus
Tadayon Mansouri et al. A feasibility study of waste transportation through existing underground excavations in open pit Angouran mine
Parra et al. Qualitative Review of Alternative Transport Systems for Open Pit Mines
CN1776197A (en) Method for treating large blocks during mining transportation
WO2024031130A1 (en) Underground mining

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110706