CN102108873A - High-polymer grouting method for rapidly disposing percolating water in tunnel - Google Patents

High-polymer grouting method for rapidly disposing percolating water in tunnel Download PDF

Info

Publication number
CN102108873A
CN102108873A CN 200910227697 CN200910227697A CN102108873A CN 102108873 A CN102108873 A CN 102108873A CN 200910227697 CN200910227697 CN 200910227697 CN 200910227697 A CN200910227697 A CN 200910227697A CN 102108873 A CN102108873 A CN 102108873A
Authority
CN
China
Prior art keywords
tunnel
high polymer
water
percolating water
percolating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200910227697
Other languages
Chinese (zh)
Other versions
CN102108873B (en
Inventor
王复明
钟燕辉
石明生
张蓓
许建强
Original Assignee
ZHENGZHOU YOUTE INFRASTRUCTURE ENGINEERING MAINTAINANCE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHENGZHOU YOUTE INFRASTRUCTURE ENGINEERING MAINTAINANCE Co Ltd filed Critical ZHENGZHOU YOUTE INFRASTRUCTURE ENGINEERING MAINTAINANCE Co Ltd
Priority to CN 200910227697 priority Critical patent/CN102108873B/en
Publication of CN102108873A publication Critical patent/CN102108873A/en
Application granted granted Critical
Publication of CN102108873B publication Critical patent/CN102108873B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a high-polymer grouting method for rapidly disposing percolating water in a tunnel. Aiming at the problem of the percolating water in the tunnel, the high-polymer grouting method comprises the following steps: high-polymer materials are injected to water percolating positions, rapidly swell in size after reaction and are solidified to rapidly fill and plug gaps of the water percolating positions, thus achieving the purpose of rapidly disposing the defect of the percolating water in the tunnel. Compared with the traditional tunnel defect disposing method, the high-polymer grouting technology developed in the invention for rapidly disposing the defect of the percolating water in a tunnel has the advantages of good disposal effect, quickness in construction, no requirement of maintenance, strong pertinence, good controllability and the like. The high-polymer grouting method is obviously creative in the aspects of technological principle and construction method, provides a novel approach to rapid, durable, economic and practical tunnel maintenance, is successfully applied to the defect disposal of the percolating water in the tunnel, shows great economic and social benefits and has broad development and application prospects.

Description

Tunnel percolating water is punished the high polymer grouting method fast
Technical field
The invention belongs to the tunnel maintenance maintenance technique, relate in particular to the tunnel percolating water high polymer grouting technology of punishment fast.
Background technology
At present in part highway and railway tunnel that China has built or built, owing to reasons such as design and constructions, in various degree exist various diseases, comparatively commonly leak, tunnel lining is come to nothing behind etc.When the tunnel passes or close water bearing ground, constantly be subjected to phreatic osmosis, as the waterproof and the drainage imperfection of lining cutting, underground water will be invaded the tunnel, and tunnel percolating water disease takes place.Tunnel percolating water is stable to the tunnel, facility, traffic safety, surface structures and tunnel ambient water environment produce many harmful effects even threat in the hole, influence internal construction and ancillary facility, reduce application life, will jeopardize the operation security of tunnel and underground construction when serious.The origin cause of formation of therefore correct these diseases of understanding is also utilized mature technology and new material, and efficient, convenient, good all kinds of diseases of regulation are safely guaranteed the durable, unimpeded of operation tunnel, seem particularly important.
Construction of tunnel percolating water form mainly shows as three kinds of forms, and the seepage of seepage promptly, the seepage of seam and face can be divided into slowly again according to the seepage speed and to ooze, ooze soon, to leak and water burst.Therefore, the principle that will specifically treat as the case may be of the percolating water disease in tunnel is handled.For tunnel infiltration several improvement technology commonly used ways such as surperficial shutoff, shallow bore hole slip casting, chemical grouting and pipe laying ejectment are arranged in the engineering at present, other engineering solution is all extended from this several method basically.The subject matter that exists is as follows:
(1) when the processing infiltration is not too serious, no matter take which kind of method, all be to paste, to block up, such processing mode has just solved seepage problem in appearance from the tunnel, the crack of lining cutting and lining cutting back may exist in the problem of coming to nothing and not be resolved, after a period of time, the seepage problem in tunnel can reappear again.
(2) though and traditional grouting method can play the effect that shutoff crack and filling are come to nothing to a certain extent, but be limited by the performance of material, after slip casting a period of time, material meeting solidification shrinkage, the tunnel comes to nothing and can reappear, and this hides some dangers for for later seepage problem recurrence.
(3) improvement method construction technology is complicated, and the implementation of each scheme all needed than the long engineering time, and this can comparatively seriously influence the construction or the normal operation generation in tunnel, and can't carry out shutoff fully for more serious big issue.
(4) because water response class high polymer material after meeting water chemical reaction could take place, under the bigger or big water burst situation of hydraulic pressure, be difficult to prove effective
Therefore, press for a kind of fast waterproof blocking method of exploitation and come the treating tunnel water leakage disease.
Non-aqueous reaction class high polymer grouting technology is the foundation rapid reinforcement technology that new development is in recent years got up.This technology is by injection many component high polymers material in ground, utilizes the characteristic that volume expands and solidifies rapidly behind the high polymer material generation chemical reaction, reaches consolidated subsoil, fills the purpose of coming to nothing or promoting the floor.At present, non-aqueous reaction class high polymer grouting technology is mainly used in the ground stabilization and the road maintenance of industry and civilian construction.At present domestic exploitation about tunnel percolating water disease punishment high polymer technology still is in the starting developing stage, and existing research is confined to water response class high polymer material mostly.Dispose non-aqueous reaction class high polymer grouting technology about the tunnel seepage and do not see relevant report.
Summary of the invention
The object of the invention is the punishment problem at tunnel percolating water disease, develops a kind of new non-aqueous reaction class high polymer grouting method, for percolating water disease punishment in tunnel provides advanced, efficient, economic, practical technical measures.
The present invention is achieved by the following technical solutions:
A kind of tunnel percolating water is punished the high polymer grouting method fast, leakage problem at the tunnel, to percolating water position injection high polymer material, the rapid expansion curing of volume after material reacts, shutoff is filled in space, percolating water position, tunnel rapidly, thereby reach the purpose of quick treating tunnel water leakage disease.
Basic construction technology is:
(1) bore injected hole at a certain distance in the percolating water position, hole depth is determined according to tunnel surrounding and liner structure situation;
(2) Grouting Pipe under in injected hole for big water burst mouth, is set up geotechnological cloth bag;
(3) inject high polymer material by Grouting Pipe to the percolating water position, high polymer material reacts rapidly, and volume expansion is solidified, and fills the space, the shutoff infiltration.
When partial points or slit infiltration, concrete implementation step is:
(1) bores injected hole.At percolating water position, tunnel, at the infiltration point, or bore injected hole with a determining deviation along the infiltration slit, hole depth is according to the structures shape of lining cutting or country rock, and boring is wanted and can be connected with penetrating passage;
(2) Grouting Pipe under.Grouting Pipe under in injected hole, Grouting Pipe can be PPR pipe or metal tube;
(3) carry out high polymer grouting.Inject high polymer material by Grouting Pipe to lining cutting or country rock seepage part, high polymer material generation chemical reaction, expansion curing is filled percolating water space and cavity rapidly, thus quick blocking percolating water.
When sweat, concrete implementation step is:
(1) bores injected hole.On infiltration face, bore injected hole according to vertical and horizontal with a determining deviation, hole depth is according to the structures shape of lining cutting or country rock;
(2) Grouting Pipe under.Grouting Pipe under in injected hole, Grouting Pipe are PPR pipe or metal tube;
(3) carry out high polymer grouting.Inject high polymer material by Grouting Pipe to the percolating water position, high polymer material generation chemical reaction, expansion curing is filled percolating water space and cavity rapidly, thus quick blocking percolating water.
When big water burst, concrete implementation step is:
(1) with hoop geotechnological cloth bag openend is fixed on hollow steel pipe one end;
(2) with adhesive tape or cord geotechnological cloth bag is bundled into strip;
(3) hold the hollow steel pipe other end, the geotechnological cloth bag of tying up put into the water burst mouth, put into again simultaneously one not with the Grouting Pipe of geotechnological cloth bag at the water burst mouth, Grouting Pipe is put into the water burst mouth degree of depth will exceed geotechnological cloth bag;
(4) inject the multicomponent high polymer material by hollow steel pipe in geotechnological cloth bag, high polymer material expands rapidly in geotechnological cloth bag and solidifies, thus quick blocking water burst mouth;
(5) again by not with the Grouting Pipe of geotechnological cloth bag, inject the multicomponent high polymer material in the water burst passage, high polymer material expands rapidly in the water burst passage and solidifies, thus quick blocking water burst passage.
The diameter of described geotechnological cloth bag and length can produce plurality of specifications according to the design of issue concrete condition; The hollow metal tube diameter is generally 1.6cm, can be fixed according to requirement of engineering, and length is fixed according to requirement of engineering; According to the diameter of steel pipe and geotechnological cloth bag, can select the hoop of different size for use.
Compare with traditional tunnel defect punishment technology, the tunnel percolating water disease punishment high polymer grouting technology of the present invention's exploitation has following advantage:
(1) punishment is effective.The high polymer material reaction of injection is fast, good endurance, and water resistance is good, and has elasticity preferably;
(2) quick construction does not need health.Material is injected the intensity that can form in back 15 minutes more than 90%, the traffic of can letting pass.Compare with traditional tunnel defect punishment method, the high polymer grouting technology of the present invention's exploitation can be saved the duration more than 70%;
(3) with strong points, controllability is good.The characteristic that volume expands voluntarily behind the patent utilization high polymer material generation chemical reaction of the present invention, reach fill come to nothing, purpose such as shutoff infiltration, and its density and intensity can be regulated and control according to requirement of engineering after the material cured.Therefore, compare with traditional mud jacking method, the high polymer grouting technology of the present invention's exploitation has better targeted and controllability.
In sum, the tunnel percolating water disease high polymer grouting technology of punishing fast of the present invention's exploitation is compared with traditional tunnel defect punishment method, all has obvious innovation aspect know-why and the job practices, started quick, durable, economic, practical tunnel maintenance new way, and be successfully applied to the percolating water disease punishment in tunnel, demonstrate huge economic and social benefits and wide development and application prospect.
Description of drawings
Fig. 1 geotechnique cloth bag is fixed in hollow steel pipe one end schematic diagram;
Fig. 2 geotechnique cloth bag is bundled into the strip schematic diagram;
Geotechnological cloth bag that Fig. 3 will tie up and Grouting Pipe are put into water burst mouth schematic diagram;
Fig. 4 high polymer sealing slip casting shutoff water burst mouth construction schematic diagram;
Water burst passage construction schematic diagram is filled in Fig. 5 high polymer sealing slip casting.
The specific embodiment
Embodiment: the tunnel percolating water of the present invention's exploitation is punished the high polymer grouting method fast, leakage problem at the tunnel, to percolating water position injection high polymer material, the rapid expansion curing of volume after material reacts, shutoff is filled in space, percolating water position, tunnel rapidly, thereby reach the purpose of quick treating tunnel water leakage disease;
Basic construction technology is:
(1) bore injected hole at a certain distance in the percolating water position, hole depth is determined according to tunnel surrounding and liner structure situation;
(2) Grouting Pipe under in injected hole for big water burst mouth, is set up geotechnological cloth bag;
(3) inject high polymer material by Grouting Pipe to the percolating water position, high polymer material reacts rapidly, and volume expansion is solidified, and fills the space, the shutoff infiltration.
Concrete constructure scheme has following several:
(1) when partial points or slit infiltration, concrete implementation step is:
(1) bores injected hole; At percolating water position, tunnel, at the infiltration point, or bore injected hole with a determining deviation along the infiltration slit, hole depth is according to the structures shape of lining cutting or country rock, and boring is wanted and can be connected with penetrating passage;
(2) Grouting Pipe under; Grouting Pipe under in injected hole, Grouting Pipe can be PPR pipe or metal tube;
(3) carry out high polymer grouting; Inject high polymer material by Grouting Pipe to lining cutting or country rock seepage part, high polymer material generation chemical reaction, expansion curing is filled percolating water space and cavity rapidly, thus quick blocking percolating water.
(2) when sweat, concrete implementation step is:
(1) bores injected hole; On infiltration face, bore injected hole according to vertical and horizontal with a determining deviation, hole depth is according to the structures shape of lining cutting or country rock;
(2) Grouting Pipe under; Grouting Pipe under in injected hole, Grouting Pipe are PPR pipe or metal tube;
(3) carry out high polymer grouting; Inject high polymer material by Grouting Pipe to the percolating water position, high polymer material generation chemical reaction, expansion curing is filled percolating water space and cavity rapidly, thus quick blocking percolating water.
(3) when big water burst, concrete implementation step is:
(1) with hoop 2 geotechnological cloth bag 3 openends is fixed on hollow steel pipe 1 one ends, as shown in Figure 1;
(2) with adhesive tape or cord 4 geotechnological cloth bag 3 is bundled into strip, as shown in Figure 2;
(3) hold hollow steel pipe 1 other end, the geotechnological cloth bag of tying up 3 put into water burst mouth 7, put into again simultaneously one not with the Grouting Pipe 5 of geotechnological cloth bag at water burst mouth 7, Grouting Pipe 5 is put into water burst mouth 7 degree of depth will exceed geotechnological cloth bag 3, as shown in Figure 3;
(4) in geotechnological cloth bag 3, inject multicomponent high polymer material 9 by hollow steel pipe 1, high polymer material 9 expands rapidly in geotechnological cloth bag 3 and solidifies, and water burst 6 is along with the expansion of high polymer material 9 in the geotechnological cloth bag 3, and flow is decreased to gradually and stops, thereby quick blocking water burst mouth 7, as shown in Figure 4;
(5) again by not with the Grouting Pipe 5 of geotechnological cloth bag, inject multicomponent high polymer material 9 in the water burst passage, high polymer material 9 expands rapidly in the water burst passage and solidifies, thus quick blocking water burst passage, and reinforce the country rock 8 that seeps water, as shown in Figure 5.
The diameter of above-mentioned geotechnological cloth bag 3 and length can produce plurality of specifications according to the design of issue concrete condition; Hollow steel pipe 1 diameter and length are decided according to requirement of engineering; According to the diameter of hollow steel pipe 1 and geotechnological cloth bag 3, can select the hoop 2 of different size for use.

Claims (4)

1. a tunnel percolating water is punished the high polymer grouting method fast, it is characterized in that: at the leakage problem in tunnel, to percolating water position injection high polymer material, the rapid expansion curing of volume after material reacts, shutoff is filled in space, percolating water position, tunnel rapidly, thereby reach the purpose of quick treating tunnel water leakage disease;
Basic construction technology is:
(1) bore injected hole at a certain distance in the percolating water position, hole depth is determined according to tunnel surrounding and liner structure situation;
(2) Grouting Pipe under in injected hole for big water burst mouth, is set up geotechnological cloth bag;
(3) inject high polymer material by Grouting Pipe to the percolating water position, high polymer material reacts rapidly, and volume expansion is solidified, and fills the space, the shutoff infiltration.
2. tunnel according to claim 1 percolating water is punished the high polymer grouting method fast, it is characterized in that: when partial points or slit infiltration, concrete implementation step is:
(1) bore injected hole: at percolating water position, tunnel, at the infiltration point, or bore injected hole along the infiltration slit with a determining deviation, hole depth is according to the structures shape of lining cutting or country rock, and boring is wanted and can be connected with penetrating passage;
(2) Grouting Pipe under: Grouting Pipe under in injected hole, Grouting Pipe can be PPR pipe or metal tube;
(3) carry out high polymer grouting: inject high polymer material by Grouting Pipe to lining cutting or country rock seepage part, high polymer material generation chemical reaction, expansion curing is filled percolating water space and cavity rapidly, thus quick blocking percolating water.
3. tunnel according to claim 1 percolating water is punished the high polymer grouting method fast, it is characterized in that: when sweat, concrete implementation step is:
(1) bore injected hole: on infiltration face, bore injected hole according to vertical and horizontal with a determining deviation, hole depth is according to the structures shape of lining cutting or country rock;
(2) Grouting Pipe under: Grouting Pipe under in injected hole, Grouting Pipe are PPR pipe or metal tube;
(3) carry out high polymer grouting: inject high polymer material by Grouting Pipe to the percolating water position, high polymer material generation chemical reaction, expansion curing is filled percolating water space and cavity rapidly, thus quick blocking percolating water.
4. tunnel according to claim 1 percolating water is punished the high polymer grouting method fast, it is characterized in that: when big water burst, concrete implementation step is:
(1) with hoop geotechnological cloth bag openend is fixed on hollow steel pipe one end;
(2) with adhesive tape or cord geotechnological cloth bag is bundled into strip;
(3) hold the hollow steel pipe other end, the geotechnological cloth bag of tying up put into the water burst mouth, put into again simultaneously one not with the Grouting Pipe of geotechnological cloth bag at the water burst mouth, Grouting Pipe is put into the water burst mouth degree of depth will exceed geotechnological cloth bag;
(4) inject the multicomponent high polymer material by hollow steel pipe in geotechnological cloth bag, high polymer material expands rapidly in geotechnological cloth bag and solidifies, thus quick blocking water burst passway;
(5) again by not with the Grouting Pipe of geotechnological cloth bag, inject the multicomponent high polymer material in the water burst passage, high polymer material expands rapidly in the water burst passage and solidifies, thus quick blocking water burst passage.
CN 200910227697 2009-12-29 2009-12-29 High-polymer grouting method for rapidly disposing percolating water in tunnel Active CN102108873B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910227697 CN102108873B (en) 2009-12-29 2009-12-29 High-polymer grouting method for rapidly disposing percolating water in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910227697 CN102108873B (en) 2009-12-29 2009-12-29 High-polymer grouting method for rapidly disposing percolating water in tunnel

Publications (2)

Publication Number Publication Date
CN102108873A true CN102108873A (en) 2011-06-29
CN102108873B CN102108873B (en) 2013-11-06

Family

ID=44173144

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910227697 Active CN102108873B (en) 2009-12-29 2009-12-29 High-polymer grouting method for rapidly disposing percolating water in tunnel

Country Status (1)

Country Link
CN (1) CN102108873B (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536270A (en) * 2011-12-29 2012-07-04 中铁十六局集团北京轨道交通工程建设有限公司 Tunnel seepage protection method for soft soil stratum by existing shield method
CN102877865A (en) * 2012-09-10 2013-01-16 刘清洁 Construction method for treating underground gob or cavity
CN103215960A (en) * 2013-04-11 2013-07-24 河南博特工程防护有限公司 Grouting method for high polymer vertical support system
CN103215952A (en) * 2013-04-11 2013-07-24 河南博特工程防护有限公司 High polymer anchoring grouting method
CN103821544A (en) * 2014-02-28 2014-05-28 山东大学 Tunnel and underground engineering high-pressure high-flow-rate sudden surging water control method
CN103967036A (en) * 2014-05-07 2014-08-06 中国水电顾问集团华东勘测设计研究院有限公司 Pile and sleeve grouting connecting structure for offshore wind power generation and construction method thereof
CN104033164A (en) * 2014-05-26 2014-09-10 江苏鼎泰工程材料有限公司 Method for solving disengagement and water seepage of internal arch of tunnel
CN104033165A (en) * 2014-05-26 2014-09-10 江苏鼎泰工程材料有限公司 Repairing method and grout for tunnel defects
CN104500108A (en) * 2014-12-11 2015-04-08 中铁十九局集团有限公司 Tunnel foundation water return point processing method
CN104631478A (en) * 2015-02-16 2015-05-20 中交一航局第一工程有限公司 Method and device for quick blockage of piping in deep foundation pit
CN104775412A (en) * 2015-03-25 2015-07-15 广州建恒机电设备安装有限公司 Stratum reinforcement PSC construction method
CN108951708A (en) * 2018-06-26 2018-12-07 山东大学 A kind of used in Underground Engineering Lining leakage comprehensive treatment method for water
CN110805052A (en) * 2019-10-31 2020-02-18 中国二十二冶集团有限公司 Comprehensive treatment method for sudden surge of ultra-deep foundation pit
CN111140264A (en) * 2020-04-02 2020-05-12 中铁工程设计咨询集团有限公司 Method for treating water leakage of cracks of tunnel concrete lining structure
CN111749198A (en) * 2020-05-30 2020-10-09 郑州安源工程技术有限公司 Channel slab underwater grouting stabilizing and lifting method
CN114108545A (en) * 2021-12-01 2022-03-01 姜泽南 Segmented-bundling-type plugging machine for piping emergency rescue
CN114525760A (en) * 2022-01-22 2022-05-24 郑州大学 Portable high polymer gushing water plugging device and method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1017366B (en) * 1988-12-05 1992-07-08 铁道部山海关桥梁工厂 Construction technology of preventing and controlling seepage in buildings
CN1469012A (en) * 2002-07-19 2004-01-21 岩 李 Serial motor for fasting treating piping, sandy soil liquefaction and leakage of underwater structure
CN1546842A (en) * 2003-12-11 2004-11-17 广州市泰利斯固结补强工程有限公司 Construction method of leakage waterstop for shield tunnel concrete structure segments
JP4902255B2 (en) * 2006-04-21 2012-03-21 株式会社イーテック Modified asphalt composition for waterproof / waterproof material and method for producing the same

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536270A (en) * 2011-12-29 2012-07-04 中铁十六局集团北京轨道交通工程建设有限公司 Tunnel seepage protection method for soft soil stratum by existing shield method
CN102877865A (en) * 2012-09-10 2013-01-16 刘清洁 Construction method for treating underground gob or cavity
CN103215960B (en) * 2013-04-11 2015-06-24 郑州安源工程技术有限公司 Grouting method for high polymer vertical support system
CN103215960A (en) * 2013-04-11 2013-07-24 河南博特工程防护有限公司 Grouting method for high polymer vertical support system
CN103215952A (en) * 2013-04-11 2013-07-24 河南博特工程防护有限公司 High polymer anchoring grouting method
CN103821544A (en) * 2014-02-28 2014-05-28 山东大学 Tunnel and underground engineering high-pressure high-flow-rate sudden surging water control method
CN103821544B (en) * 2014-02-28 2016-04-06 山东大学 Tunneling and underground engineering high-pressure high-flow is dashed forward Water outburst treatment method
CN103967036A (en) * 2014-05-07 2014-08-06 中国水电顾问集团华东勘测设计研究院有限公司 Pile and sleeve grouting connecting structure for offshore wind power generation and construction method thereof
CN104033164A (en) * 2014-05-26 2014-09-10 江苏鼎泰工程材料有限公司 Method for solving disengagement and water seepage of internal arch of tunnel
CN104033165A (en) * 2014-05-26 2014-09-10 江苏鼎泰工程材料有限公司 Repairing method and grout for tunnel defects
CN104033164B (en) * 2014-05-26 2016-07-06 江苏鼎泰工程材料有限公司 Come to nothing and the harmful method repaired that seeps water to what encircle in tunnel
CN105888692A (en) * 2014-05-26 2016-08-24 江苏鼎泰工程材料有限公司 Method for repairing tunnel inner arch
CN104033165B (en) * 2014-05-26 2016-08-31 江苏鼎泰工程材料有限公司 Tunnel defect restorative procedure and reparation slurry
CN104500108A (en) * 2014-12-11 2015-04-08 中铁十九局集团有限公司 Tunnel foundation water return point processing method
CN104631478A (en) * 2015-02-16 2015-05-20 中交一航局第一工程有限公司 Method and device for quick blockage of piping in deep foundation pit
CN104775412A (en) * 2015-03-25 2015-07-15 广州建恒机电设备安装有限公司 Stratum reinforcement PSC construction method
CN108951708B (en) * 2018-06-26 2020-12-18 山东大学 Comprehensive treatment method for underground engineering lining water leakage
CN108951708A (en) * 2018-06-26 2018-12-07 山东大学 A kind of used in Underground Engineering Lining leakage comprehensive treatment method for water
CN110805052A (en) * 2019-10-31 2020-02-18 中国二十二冶集团有限公司 Comprehensive treatment method for sudden surge of ultra-deep foundation pit
CN111140264A (en) * 2020-04-02 2020-05-12 中铁工程设计咨询集团有限公司 Method for treating water leakage of cracks of tunnel concrete lining structure
CN111749198A (en) * 2020-05-30 2020-10-09 郑州安源工程技术有限公司 Channel slab underwater grouting stabilizing and lifting method
CN114108545A (en) * 2021-12-01 2022-03-01 姜泽南 Segmented-bundling-type plugging machine for piping emergency rescue
CN114108545B (en) * 2021-12-01 2023-08-08 重庆艺锦陶瓷有限公司 Plugging machine for sectional closing type piping emergency
CN114525760A (en) * 2022-01-22 2022-05-24 郑州大学 Portable high polymer gushing water plugging device and method
CN114525760B (en) * 2022-01-22 2024-05-28 郑州大学 Portable high polymer gushing water plugging device and method

Also Published As

Publication number Publication date
CN102108873B (en) 2013-11-06

Similar Documents

Publication Publication Date Title
CN102108873B (en) High-polymer grouting method for rapidly disposing percolating water in tunnel
US20140314497A1 (en) Polymer grouting method for constructing gravel pile
CN104328782A (en) Expansive pouring device and method for governing railway roadbed sedimentation and deformation
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN103031836A (en) Method for quickly building road on new reclamation sludge foundation
CN203488189U (en) Tunnel structure for emptying renovation
CN102080381B (en) Method for managing landslip of side slope landslide for transformer substation
CN111395263B (en) Leakage treatment method for roller compacted concrete dam body
CN105673025A (en) Underground engineering loess tunnel ground surface settlement control construction process
CN105178285A (en) Method for widening grouting reinforcement and seepage and blockage prevention range of rock and soil
CN103388338A (en) Novel rapid water stopping and soil mass improving method
CN109236367A (en) A kind of tunnel structure and its frozen construction method with antiseepage drain function
CN105064335A (en) Ultrahigh pressure rotary jet grouting method suitable for sandy cobble stratum shield end well reinforcement
CN107012861B (en) A kind of discrete material core expansive concrete stake and its construction method
CN105731978A (en) Grouting slurry for reinforcing tunnel face of jacking culvert of fine-sand layer and grouting method
CN103912290B (en) Grouting method used for vibration isolating and denoising outside subway tunnel segments
CN105254195B (en) A kind of Waste tire regeneration concrete composite material and complex and its construction method
CN204716253U (en) Circular major diameter diversion tunnel structure
CN108914911A (en) A kind of stratum prestress advanced excavation stability control method
CN206753653U (en) A kind of tunnel solution cavity and Groundwater Comprehensive administer construction
CN112983454A (en) Reverse recovery construction method for jacking pipe
CN110485405B (en) Reinforcing system and reinforcing method for soft soil foundation
CN105221158B (en) Shield export & import notes dual slurry construction method
CN106939619A (en) A kind of anti-vibration for underground engineering disturbs the leak stopping reinforcement means of voids and pits
CN102052081A (en) High polymer grouting technology for treating tunnel void and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: HENAN BOTE ENGINEERING PROTECTION CO., LTD.

Free format text: FORMER OWNER: ZHENGZHOU YOUTE FOUNDATION ENGINEERING MAINTENANCE CO., LTD.

Effective date: 20130618

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 450016 ZHENGZHOU, HENAN PROVINCE TO: 450000 ZHENGZHOU, HENAN PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20130618

Address after: Bamboo high tech Development Zone in Henan Province, Zhengzhou City, 450000 street, No. 100 and No. 10 Liyuan Sheng Yuan Building 1 unit 8

Applicant after: Henan Bote Engineering Protection Co., Ltd.

Address before: 450016 A6 villa Green, No. 1369 East navigation road, Zhengzhou economic and Technological Development Zone, Zhengzhou, Henan

Applicant before: Zhengzhou Youte Infrastructure Engineering Maintainance Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160607

Address after: 450000 Zhengzhou province Jinshui District, Henan Cultural Road, building 48, building 39, No. 33

Patentee after: Wang Fuming

Address before: Bamboo high tech Development Zone in Henan Province, Zhengzhou City, 450000 street, No. 100 and No. 10 Liyuan Sheng Yuan Building 1 unit 8

Patentee before: Henan Bote Engineering Protection Co., Ltd.